SCHEDULE
BOQ from BOQ review by
Strategy (Refer of Nature of Budget Consultants PH & C&B
S.No. W.O package distribution Remarks Floating of tender PO/WO issue Work Start Lead Period Tender Float Date BOQ Drawing
legend below) Contracto Work (Rs. in Cr.)
rs
Stormwater drain
1 External Infra Works DO 4 Civil 18.43 5/Feb/21 10/Feb/21 15/Feb/21 17/Mar/21 1/Apr/21 95 12/Dec/20 9/Dec/20 24/Nov/20 RMC - Supply
added
19 Compound Wall DO 2 Infra 6.50 17/Feb/21 24/Feb/21 3/Mar/21 2/Apr/21 2/May/21 lead time 30 days 95 28/Dec/20 25/Dec/20 10/Dec/20 -
3 Civil Works (STP; UGS & OHT; Club House; OWC etc.,) DO 1 Civil 9.39 11/Feb/21 18/Feb/21 25/Feb/21 16/Apr/21 1/May/21 95 11/Jan/21 8/Jan/21 24/Dec/20
4 Infra MEP Works DO 4 Services 13.72 11/Feb/21 18/Feb/21 25/Feb/21 16/Apr/21 1/May/21 95 11/Jan/21 8/Jan/21 24/Dec/20 - -
7 LT & HT Cable ITC - DO 1 Services 2.88 27/Feb/21 6/Mar/21 13/Mar/21 2/May/21 1/Jun/21 lead time 30 days 95 27/Jan/21 24/Jan/21 9/Jan/21
24 Hardscape Works DO 4 Infra 8.50 13/Apr/21 20/Apr/21 27/Apr/21 16/Jun/21 1/Jul/21 95 13/Mar/21 10/Mar/21 23/Feb/21
2 Pre Cast Concrete Materials - Pavers, Kerbs, Saucer Drain ITC - DO 1 Civil 3.67 4/May/21 11/May/21 18/May/21 2/Jul/21 1/Aug/21 95 29/Mar/21 26/Mar/21 11/Mar/21 Balance
10 HT Panels & RMU ITC - DO 1 Services 0.80 30/Apr/21 7/May/21 14/May/21 3/Jul/21 1/Sep/21 lead time 60 days 95 30/Mar/21 27/Mar/21 12/Mar/21 2.37
14 Street Lights & Poles ITC - DO 1 Services 1.41 30/Apr/21 7/May/21 14/May/21 3/Jul/21 1/Sep/21 lead time 60 days 95 30/Mar/21 27/Mar/21 12/Mar/21
13 Landscape Light Fixtures ITC - DO 1 Services 0.04 30/Apr/21 7/May/21 14/May/21 3/Jul/21 1/Sep/21 lead time 60 days 95 30/Mar/21 27/Mar/21 12/Mar/21
This is our Outside
26 Lake Rejuvenation DO 1 Amenity 5.05 14/May/21 21/May/21 28/May/21 17/Jul/21 1/Aug/21 95 13/Apr/21 10/Apr/21 26/Mar/21
boundary works
26 Cart Track Road DO Amenity 1.86 14/May/21 21/May/21 28/May/21 17/Jul/21 1/Aug/21 95 13/Apr/21 10/Apr/21 26/Mar/21
9 LT Panel ITC - DO 1 Services 2.88 20/Apr/21 27/Apr/21 4/May/21 2/Aug/21 1/Sep/21 lead time 30 days 95 29/Apr/21 26/Apr/21 11/Apr/21
16 Landscape Irrigation Works DO 1 Services 0.89 30/May/21 6/Jun/21 13/Jun/21 2/Aug/21 1/Sep/21 lead time 30 days 95 29/Apr/21 26/Apr/21 11/Apr/21
22 Plants, Trees, Creepers, Climbers, Shrubs - Supply ITC - DO 1 Infra 1.78 30/May/21 6/Jun/21 13/Jun/21 2/Aug/21 1/Sep/21 lead time 30 days 95 29/Apr/21 26/Apr/21 11/Apr/21
20 Afforestation DO 1 Amenity 2.36 14/Jun/21 21/Jun/21 28/Jun/21 17/Aug/21 1/Sep/21 95 14/May/21 11/May/21 26/Apr/21
21 Softscape Works - Plantation DO 2 Infra 2.94 14/Jun/21 21/Jun/21 28/Jun/21 17/Aug/21 1/Sep/21 95 14/May/21 11/May/21 26/Apr/21
23 Nursery - Set up & Maintenance DO 1 Infra 0.53 14/Jun/21 21/Jun/21 28/Jun/21 17/Aug/21 1/Sep/21 95 14/May/21 11/May/21 26/Apr/21
5 STP (Electro Mechanical Works) DO 1 Services 0.85 30/Jul/21 6/Aug/21 13/Aug/21 2/Oct/21 1/Dec/21 lead time 60 days 95 29/Jun/21 26/Jun/21 11/Jun/21
25 Fabrication Works - Railings, Gazebo etc., DO 1 Infra 0.99 30/Jul/21 6/Aug/21 13/Aug/21 2/Oct/21 1/Nov/21 lead time 30 days 95 29/Jun/21 26/Jun/21 11/Jun/21
Including Supply &
12 Pumps ITC - DO 1 Services 0.45 29/Aug/21 5/Sep/21 12/Sep/21 1/Nov/21 1/Dec/21 lead time 30 days 95 29/Jul/21 26/Jul/21 11/Jul/21
Installation
6 WTP (Electro Mechanical Works) DO 1 Services 0.34 30/Aug/21 6/Sep/21 13/Sep/21 2/Nov/21 1/Jan/22 lead time 60 days 95 30/Jul/21 27/Jul/21 12/Jul/21
34 OWC (Electro Mechanical Works) DO 1 Services 0.12 30/Oct/21 6/Nov/21 13/Nov/21 2/Jan/22 1/Feb/22 lead time 30 days 95 29/Sep/21 26/Sep/21 11/Sep/21
26 Club House - Electrical Works DO 1 Services 4.14 12/Dec/21 19/Dec/21 26/Dec/21 14/Feb/22 1/Mar/22 95 11/Nov/21 8/Nov/21 24/Oct/21
11 DG Supply ITC - DO 1 Services 0.57 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/Apr/22 lead time 30 days 95 27/Nov/21 24/Nov/21 9/Nov/21 - -
External HT Electrical Works including liasoning
15 DO 1 Services 3.20 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/May/22 95 27/Nov/21 24/Nov/21 9/Nov/21
(Including Miscelleneous)
Club House - Swimming pool and Water Bodies Services &
31 DO 1 1.18 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/May/22 lead time 60 days 95 27/Nov/21 24/Nov/21 9/Nov/21
(Including finishes Works) Finishes
32 Club House - CP & Sanitary Fixture Rate Contract 1 Services NA Part of MEP 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/May/22 lead time 60 days 95 27/Nov/21 24/Nov/21 9/Nov/21
44 External Signages DO 1 Amenity 0.25 27/Jan/22 3/Feb/22 10/Feb/22 1/Apr/22 1/May/22 lead time 60 days 95 27/Dec/21 24/Dec/21 9/Dec/21
8 Transformer ITC - DO 1 Services 0.85 19/Dec/21 26/Dec/21 2/Jan/22 2/Apr/22 1/Jun/22 lead time 60 days 95 28/Dec/21 25/Dec/21 10/Dec/21
38 Glazing Works DO 1 Finishes 28/Jan/22 4/Feb/22 11/Feb/22 2/Apr/22 1/Jun/22 lead time 60 days 95 28/Dec/21 25/Dec/21 10/Dec/21
28 Club House - PHE & FAPA Works DO 1 Services 11/Feb/22 18/Feb/22 25/Feb/22 16/Apr/22 1/May/22 95 11/Jan/22 8/Jan/22 24/Dec/21
29 Club House - HVAC Works DO 1 Services 27/Feb/22 6/Mar/22 13/Mar/22 2/May/22 1/Jul/22 lead time 60 days 95 27/Jan/22 24/Jan/22 9/Jan/22
Part of Club
36 Tiles - Club House & Hardscape Works Basic Rate 1 Amenity NA 27/Feb/22 6/Mar/22 13/Mar/22 2/May/22 1/Jun/22 lead time 30 days 95 27/Jan/22 24/Jan/22 9/Jan/22
Finishing Cost
37 Granite - Club House & Hardscape Works Basic Rate 1 Amenity 27/Feb/22 6/Mar/22 13/Mar/22 2/May/22 1/Jun/22 lead time 30 days 95 27/Jan/22 24/Jan/22 9/Jan/22
30 Club House - Elevators DO 1 Services 28/Feb/22 7/Mar/22 14/Mar/22 3/May/22 1/Aug/22 lead time 90 days 95 28/Jan/22 25/Jan/22 10/Jan/22
35 Club House Finishes Works (Interior & Exterior) DO 1 Finishes 7.48 14/Mar/22 21/Mar/22 28/Mar/22 17/May/22 1/Jun/22 95 11/Feb/22 8/Feb/22 24/Jan/22
33 Club House - Switches & Sockets Rate Contract 1 Services 29/Apr/22 6/May/22 13/May/22 2/Jul/22 1/Aug/22 lead time 30 days 95 29/Mar/22 26/Mar/22 11/Mar/22
43 Sports Flooring DO 1 Amenity 0.65 Sports amenities 30/Jul/22 6/Aug/22 13/Aug/22 2/Oct/22 1/Nov/22 lead time 30 days 95 29/Jun/22 26/Jun/22 11/Jun/22
42 Kitchen Equipment S - DO 1 Amenity 1.56 31/Jul/22 7/Aug/22 14/Aug/22 3/Oct/22 1/Jan/23 lead time 90 days 95 30/Jun/22 27/Jun/22 12/Jun/22
39 Loose Furniture S - DO 1 Amenity Reserve -only indoor 30/Aug/22 6/Sep/22 13/Sep/22 2/Nov/22 1/Jan/23 lead time 60 days 95 30/Jul/22 27/Jul/22 12/Jul/22
gym available -
40 Gym Equipment S - DO 1 Amenity 30/Aug/22 6/Sep/22 13/Sep/22 2/Nov/22 1/Jan/23 lead time 60 days 95 30/Jul/22 27/Jul/22 12/Jul/22
Hence linked Park
41 Play Equipment DO 1 Amenity As wegym
area are in 30/Aug/22 6/Sep/22 13/Sep/22 2/Nov/22 1/Jan/23 lead time 60 days 95 30/Jul/22 27/Jul/22 12/Jul/22
schematic stage
concrete & Steel is
17 Concrete (RMC) ITC - DO 1 Civil 0.00
part of the packages
18 Reinf. Steel ITC - DO 1 Civil 0.00 given.This will be
Miscellaneous package (Borewells, Survey, Boombarrier, bifurcated later
45 DO 1 Misc. 1.02
UPS, Testing, etc)
TOTAL 56 107.30 0
106.28 106.28
Strategy Options
Direct Order by
1 DO Material Supply
GPL
2 S - DO Direct
List
ITC of Order by
BasicOrder
Direct rate by
GPL (Free
3 ITC - DO items
GPL for respective
Issue
packages
Material) shall be
4 Basic Rate provided, Value
included in the
5 Rate Contract respective package
budget provision
PROJECT : GODREJ - AGROVET PROCUREMENT SCHEDULE
Split / No Budget Final BOQ from BOQ review by Floating of tender PO/WO issue Work Start Remarks
Strategy (Refer Nature of
S.No. W.O package distribution of (Rs. in Remarks Consultants PH & C&B
legend below) Work RMC - Supply
Contracto Cr.)
rs Stormwater drain 5/Feb/21 10/Feb/21 15/Feb/21 17/Mar/21 1/Apr/21 -
1 External Infra Works DO 4 Civil 18.43
added
Pre Cast Concrete Materials - Pavers, Kerbs, Saucer Drain 1 4/May/21 11/May/21 18/May/21 2/Jul/21 1/Aug/21
2 ITC - DO Civil 3.67
3 Civil Works (STP; UGS & OHT; Club House; OWC etc.,) DO 1 Civil 9.39 11/Feb/21 18/Feb/21 25/Feb/21 16/Apr/21 1/May/21 - -
4 Infra MEP Works DO 4 Services 13.72 11/Feb/21 18/Feb/21 25/Feb/21 16/Apr/21 1/May/21
5 STP (Electro Mechanical Works) DO 1 Services 0.85 30/Jul/21 6/Aug/21 13/Aug/21 2/Oct/21 1/Dec/21 lead time 60 days
6 WTP (Electro Mechanical Works) DO 1 Services 0.34 30/Aug/21 6/Sep/21 13/Sep/21 2/Nov/21 1/Jan/22 lead time 60 days Balance
7 LT & HT Cable ITC - DO 1 Services 2.88 27/Feb/21 6/Mar/21 13/Mar/21 2/May/21 1/Jun/21 lead time 30 days 2.37
8 Transformer ITC - DO 1 Services 0.85 19/Dec/21 26/Dec/21 2/Jan/22 2/Apr/22 1/Jun/22 lead time 60 days
9 LT Panel ITC - DO 1 Services 2.88 20/Apr/21 27/Apr/21 4/May/21 2/Aug/21 1/Sep/21 lead time 30 days
10 HT Panels & RMU ITC - DO 1 Services 0.80 30/Apr/21 7/May/21 14/May/21 3/Jul/21 1/Sep/21 lead time 60 days
11 DG Supply ITC - DO 1 Services 0.57 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/Apr/22 lead time 30 days
Including Supply &
12 Pumps ITC - DO 1 Services 0.45 29/Aug/21 5/Sep/21 12/Sep/21 1/Nov/21 1/Dec/21 lead time 30 days
Installation
13 Landscape Light Fixtures ITC - DO 1 Services 0.04 30/Apr/21 7/May/21 14/May/21 3/Jul/21 1/Sep/21 lead time 60 days
14 Street Lights & Poles ITC - DO 1 Services 1.41 30/Apr/21 7/May/21 14/May/21 3/Jul/21 1/Sep/21 lead time 60 days
External HT Electrical Works including liasoning 1 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/May/22
15 (Including Miscelleneous) DO Services 3.20
16 Landscape Irrigation Works DO 1 Services 0.89 schematic stage 30/May/21 6/Jun/21 13/Jun/21 2/Aug/21 1/Sep/21 lead time 30 days
17 Concrete (RMC) ITC - DO 1 Civil - concrete & Steel is
18 Reinf. Steel ITC - DO 1 Civil - part of the packages
19 Compound Wall DO 2 Infra 6.50 given.This will be 17/Feb/21 24/Feb/21 3/Mar/21 2/Apr/21 2/May/21 lead time 30 days
20 Afforestation DO 1 Amenity 2.36 14/Jun/21 21/Jun/21 28/Jun/21 17/Aug/21 1/Sep/21
21 Softscape Works - Plantation DO 2 Infra 2.94 14/Jun/21 21/Jun/21 28/Jun/21 17/Aug/21 1/Sep/21
Plants, Trees, Creepers, Climbers, Shrubs - Supply 1 30/May/21 6/Jun/21 13/Jun/21 2/Aug/21 1/Sep/21 lead time 30 days
22 ITC - DO Infra 1.78
23 Nursery - Set up & Maintenance DO 1 Infra 0.53 14/Jun/21 21/Jun/21 28/Jun/21 17/Aug/21 1/Sep/21
24 Hardscape Works DO 4 Infra 8.50 13/Apr/21 20/Apr/21 27/Apr/21 16/Jun/21 1/Jul/21 - -
25 Fabrication Works - Railings, Gazebo etc., DO 1 Infra 0.99 30/Jul/21 6/Aug/21 13/Aug/21 2/Oct/21 1/Nov/21 lead time 30 days
26 Lake Rejuvenation DO 1 Amenity 5.05 This is our Outside 14/May/21 21/May/21 28/May/21 17/Jul/21 1/Aug/21
26 Cart Track Road DO Amenity 1.86 boundary works 14/May/21 21/May/21 28/May/21 17/Jul/21 1/Aug/21
26 Club House - Electrical Works DO 1 Services 12/Dec/21 19/Dec/21 26/Dec/21 14/Feb/22 1/Mar/22
28 Club House - PHE & FAPA Works DO 1 Services 11/Feb/22 18/Feb/22 25/Feb/22 16/Apr/22 1/May/22
4.14
29 Club House - HVAC Works DO 1 Services 27/Feb/22 6/Mar/22 13/Mar/22 2/May/22 1/Jul/22 lead time 60 days
30 Club House - Elevators DO 1 Services 28/Feb/22 7/Mar/22 14/Mar/22 3/May/22 1/Aug/22 lead time 90 days
Club House - Swimming pool and Water Bodies 1 Services & 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/May/22 lead time 60 days
31 (Including finishes Works) DO 1.18
Finishes
32 Club House - CP & Sanitary Fixture Rate Contract 1 Services 28/Dec/21 4/Jan/22 11/Jan/22 2/Mar/22 1/May/22 lead time 60 days
NA Part of MEP
33 Club House - Switches & Sockets Rate Contract 1 Services 29/Apr/22 6/May/22 13/May/22 2/Jul/22 1/Aug/22 lead time 30 days
34 OWC (Electro Mechanical Works) DO 1 Services 0.12 30/Oct/21 6/Nov/21 13/Nov/21 2/Jan/22 1/Feb/22 lead time 30 days
35 Club House Finishes Works (Interior & Exterior) DO 1 Finishes 7.48 14/Mar/22 21/Mar/22 28/Mar/22 17/May/22 1/Jun/22
36 Tiles - Club House & Hardscape Works Basic Rate 1 Amenity 27/Feb/22 6/Mar/22 13/Mar/22 2/May/22 1/Jun/22 lead time 30 days
37 Granite - Club House & Hardscape Works Basic Rate 1 Amenity Part of Club 27/Feb/22 6/Mar/22 13/Mar/22 2/May/22 1/Jun/22 lead time 30 days
38 Glazing Works DO 1 Finishes Finishing Cost 28/Jan/22 4/Feb/22 11/Feb/22 2/Apr/22 1/Jun/22 lead time 60 days
NA
39 Loose Furniture S - DO 1 Amenity Reserve -only indoor 30/Aug/22 6/Sep/22 13/Sep/22 2/Nov/22 1/Jan/23 lead time 60 days
40 Gym Equipment S - DO 1 Amenity gym available - 30/Aug/22 6/Sep/22 13/Sep/22 2/Nov/22 1/Jan/23 lead time 60 days
41 Play Equipment DO 1 Amenity Hence linked Park 30/Aug/22 6/Sep/22 13/Sep/22 2/Nov/22 1/Jan/23 lead time 60 days
42 Kitchen Equipment S - DO 1 Amenity 1.56 area gym 31/Jul/22 7/Aug/22 14/Aug/22 3/Oct/22 1/Jan/23 lead time 90 days
43 Sports Flooring DO 1 Amenity 0.65 Sports amenities 30/Jul/22 6/Aug/22 13/Aug/22 2/Oct/22 1/Nov/22 lead time 30 days
44 External Signages DO 1 Amenity 0.25 27/Jan/22 3/Feb/22 10/Feb/22 1/Apr/22 1/May/22 lead time 60 days
Miscellaneous package (Borewells, Survey, Boombarrier,
45 DO 1 Misc. 1.02
UPS, Testing, etc)
TOTAL 56 107.30 0
106.28 106.28
Strategy Options
1 DO Direct Order by GPL
2 S - DO Material Supply Direct Order by GPL
3 ITC - DO ITC Direct Order by GPL (Free Issue Material)
4 Basic Rate List of Basic rate items for respective packages shall be provided, Value included
in the respective package budget provision
5 Rate Contract
Godrej Properties Limited
Pre Cast Concrete Materials - Pavers, Kerbs, Labour
1.00 Qty Rate Material Labour Supply Amt Amount
Saucer Drain Amount
Paver - 60mm sqm 18,428.08 885.60 539.10 346.50 9,934,576.68 16,319,905.60
Road Work - M25 cum 6,927.23 6,005.00 3,655.00 2,350.00 15.00 50,000.00 36,000.00 14,000.00 25,319,007.38 540,000.00
STP - detailed BOQ not available MT
UG Sump & OHT cum 720.81 4,352.27 3,390.00 962.27 84.42 50,300.00 36,000.00 14,300.00 2,443,529.67 3,039,175.10
Hardscape Works - -
Yashashwini - M30/M25 163.05 5,450.00 3,650.00 1,800.00 12.50 53,000.00 36,000.00 17,000.00 595,133.74 450,000.00
Sri venki - M30/M25 107.07 5,450.00 3,650.00 1,800.00 6.76 53,000.00 36,000.00 17,000.00 390,799.18 243,397.63
Icon - M30/M25 6.24 5,450.00 3,650.00 1,800.00 1.42 53,000.00 36,000.00 17,000.00 22,773.67 51,246.44
Nandi - M25 235.58 5,450.00 3,650.00 1,800.00 16.32 53,000.00 36,000.00 17,000.00 859,849.64 587,633.08
Club House - M25 958.45 4,865.20 3,650.00 1,215.20 13.77 48,100.00 36,000.00 12,100.00 3,498,348.50 495,816.45
7,875,247.31
Total 147,334,755.47 -
Hardscape Works
Fabrication Works - Railings, Gazebo etc.,