DELAY ANALYSIS –
ALUMINUM SHUTTERING TECHNOLOGY
GODREJ GARDEN CITY
PROJECT DETAILS
Project Name – GGC, Phase-1, Cluster- Orchard
Number of Buildings – 13
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
PROJECT DETAILS
Project Name – Phase-2, Cluster-Tivoli
Number of Buildings – 06
Built Up area – 4.2 Lakh Sqft Saleable Area – 4.53 Lakh Sqft
• Labour Shortfall
Super Structure 4-Aug-11 17-Oct-12 28-Sep-11 17-Dec-12 15 15 2 2 0 • Delayed payment to Contractor
• Delay in settlement of outstanding issue(Claim)
• Delay in Lift Installation
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Planned Customer
Actual /
Projected
Finish Delay
(Actual finish date - Plan finish date)
Actual / Projected
duration
---- Handover Date
PROJECT DETAILS
Project Name – Phase-3A, Cluster-Eden
Number of Buildings – 15
Built Up area – 12.66 Lakh Sqft Saleable area – 12.66 Lakh Sqft
• Labour Shortfall
Super Structure 8-Aug-11 7-Jul-13 10-Jul-11 17-Jun-13 23 24 -1 -1 0 • Delayed payment to Contractor
• Delay in settlement of outstanding issue(Claim)
• Delay in Lift Installation
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Number of Buildings – 3
Built Up area – 5.53 Lakh Sqft Saleable Area – 6.17 Lakh Sqft
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
PROJECT DETAILS
Project Name – Phase-3C, Cluster-Tivoli
Number of Buildings – 7
Built Up area – 7.9 Lakh Sqft Saleable area – 8.15 Lakh Sqft
• Labour Shortfall
Super Structure 30-Jun-12 3-Jun-14 16-Feb-12 9-Aug-15 23 42 -5 14 19 • Delayed payment to Contractor
• Delay in Lift Installation
• Priority change in 03 towers
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Number of Buildings – 2
Built Up area – 1.5 Lakh Sqft Saleable Area – 1.62 Lakh Sqft
• Labour Shortfall
• Delayed payment to Contractor
Super Structure 16-Jul-12 12-Oct-13 10-Nov-12 26-Aug-14 15 22 4 11 7 • Delay in settlement of
outstanding issue(Claim)
• Delay in Lift Installation
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
DELAY ANALYSIS – FRONTIER
PROJECT DETAILS
Project Name – Frontier
Number of Buildings – 10
Built Up area – 12.96 Lakh Sqft Saleable area – 10.98 Lakh Sqft
Baselin
Baseline Baseline Actual Actual Start finish Net
Activity Actual Start e plan Reasons
start Finish Finish duration delay delay delay
duration
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
DELAY ANALYSIS – PALM GROOVE
PROJECT DETAILS
Project Name – Godrej Palm Grove Phase - 1
Number of Buildings – 5
Built Up area – 6.42 Lakh Sqft Saleable area – 6.42 Lakh Sqft
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
PRAKRITI PHASE2
PROJECT DETAILS
Project Name – Prakriti - Phase-2
Number of Buildings – 4
Built Up area – 6.59 Lakh Sqft Saleable area – 5.68 Lakh Sqft
Activity Baseline Baseline Finish Actual Start Actual Finish Planed Actual Start Finish Net delay Reasons
start duration duration delay delay
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
DELAY ANALYSIS – INFINITY
PROJECT DETAILS
Project Name – INFINITY
Built Up area – 18.04 Lakh Sqft Saleable area – 13.06 Lakh Sqft
Substructure - Footing
30-Apr-16 18-Oct-16 10-May-16 30-Sep-16 6 5 0 -1 -1
to Podium Slab
Internal Gypsum
20-Dec-16 31-Jan-18 30-Dec-16 30-Mar-18 14 15 0 2 2
Plaster
• 01 month Delay in vendor
finalization
Flooring & Tiling Work 05-May-17 08-Aug-18 24-Jun-17 09-Apr-19 15 22 2 8 6
• 01 month delay material
procurement
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
DELAY ANALYSIS –
CONVENTIONAL SHUTTERING TECHNOLOGY
DELAY ANALYSIS – PRANA
PROJECT DETAILS
Project Name – PRANA
Number of Buildings – 07
Built Up area –10.17 Lakh Sqft Saleable area – 7.09 Lakh Sqft
Internal Paint - 1st Coat 01-Feb-17 24-Apr-18 25-Jan-18 02-May-19 15 15 12 12 1 • Work yet to be started
Baseline data Activity Name Plan duration ---- Baseline Finish Date
Actual / Finish Delay Actual / Projected Planned Customer
Projected
(Actual finish date - Plan finish date) duration ---- Handover Date
DELAY ANALYSIS –
SYSTEM FORMWORK SHUTTERING TECHNOLOGY
DELAY ANALYSIS – SUMMIT
PROJECT DETAILS
Project Name – SUMMIT
Number of Buildings – 11
Built Up area – 26.13 Lakh Sqft Saleable area – 20.38 Lakh Sqft
Plan Timelines – Ph 1 – Oct 13 to Dec 16 (39 Months) Ph 2 – Jan 14 to Oct 17 (47 Months)
Actual Timelines – Ph 1 – Oct 13 to Aug 17 (47 Months) Ph 2 – Nov 13 to Mar 18(53 Months)
NET DELAY DETAILS – SUMMIT PHASE 1
(Towers D, E, F, G, H)
Baseline
Baseline Baseline Actual Start finish
Activity Actual Start Actual Finish plan Net delay Reasons
start Finish duration delay delay
duration
• Shortage of manpower
External Plaster 05-Dec-15 10-May-16 13-Sep-15 23-Jan-17 5 17 -3 9 11
• Repairing work
• 10 month start Delay (Vitrified & ceramic Tiles)
Flooring & tiling (Approval delay 8.50 month + 1.5 month
03-Nov-14 22-Apr-16 27-Aug-15 30-Mar-17 18 19 10 11 2
Works material procurement time)
• Shortage of manpower
• Delay in external plaster and shortage of
External Painting 23-Apr-16 05-Aug-16 10-May-16 28-Jul-17 3 15 1 12 11
manpower.
Door Frames & • Delay in supply of door frame from vendor
03-Oct-14 22-Apr-16 11-Jan-15 26-Mar-16 19 15 3 -1 -4
Shutters because of quality issue
• 10.50 month start Delay (Approval delay 8
Aluminum door and month + 1.50 month days material procurement
25-Mar-15 16-Jan-16 04-Feb-16 25-Jul-17 10 18 11 19 8
window time) Aluminum Approval Date 19/11/2015
• Shortage of manpower.
SUMMIT PHASE 1 – BAR CHART
Summit Phase-2 16-Jan-14 15-Oct-17 29-Nov-13 30-Mar-18 46 53 -2 6 7 • Start of A & L towers delayed
100 14
100
12 93
12 91 12
11 85
80 10
10 73 78
9 76 10
69
62 68 8 8
8 8
60 7 7 55 58 8
51
52
44
45 5 6
38
40 34 38
4
27 32
25 28 4
20 26
20 22
13 17
1 2
5 12
- - 4 6
- - - -
Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17
In Months
Cumulative outstanding after due date Cumulative Payment Maid after due date
Shortfall as per due date Linear (Shortfall as per due date)
Average slab Cycle in Days ( On time Vs Delay payment Period)
1 30
27.1363636363636
0.9
25
0.8
0.7
20
0.6 16.5909090909091
15.8461538461538 15.9285714285714
15.1666666666667 14.9242424242424
0.5 14.1060606060606 15
12.9166666666667
In Nos
11.8438333333333
11.2142857142857
0.4 10.7745
9 10
0.3
0.2
5
0.1
0 0
0 0
Aug-16
Jan-17
Aug-17
Sep-16
Oct-16
Nov-16
Dec-16
Feb-17
Mar-17
Apr-17
May-17
Jun-17
Jul-17
Sep-17
In Months
50 57
55
42 42 42 50
0.4 43 45 40
42 42
28 28 28
35
30
0.2 14 25 20
12
0
0 0
0
May-17
May-16
Jun-16
Aug-16
Oct-16
Nov-16
Jan-17
Mar-17
Jun-17
Aug-17
Sep-17
Apr-16
Jul-16
Sep-16
Dec-16
Feb-17
Apr-17
Jul-17
On time payment period Delayed Payment period Cummulative Planned Cumulative acheived