Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F

Table of Contents
1. GENERAL ........................................................................................................................................................................2
1.1 Project Brief.............................................................................................................................................................2
1.2 Purpose ...................................................................................................................................................................3
1.3 Basis for Compilation ..............................................................................................................................................3
1.4 Site planning & Preparation ....................................................................................................................................3
1.5 Plant and Equipment ...............................................................................................................................................4
1.6 Materials..................................................................................................................................................................4
1.7 Organization, Responsibility and Supervision .........................................................................................................5
2. WORK EXECUTTION PROCESS ...................................................................................................................................5
2.1 General Preparations work .....................................................................................................................................5
2.2 Work Methodology ..................................................................................................................................................5
3. SAFETY ASSURANCE MEASURES...............................................................................................................................7
3.1 Overall Goal of The Security Management .............................................................................................................7
3.2 HSE Policy ..............................................................................................................................................................7
3.3 Safety Education Training .......................................................................................................................................7
3.4 Safety Supervision and Inspection ..........................................................................................................................8
3.5 Safety Assurance Measures ...................................................................................................................................8
3.6 Safety and Qualification for Construction ................................................................................................................8
4. ATTACHMENTS ..............................................................................................................................................................8
4.1 Method statement of Special construction plan for roof crane installation & Demolition .........................................8
4.2 Method statement of Material loading platform for MEP equipment........................................................................8
4.3 Shop drawing of Footing for derrick crane at L26 ...................................................................................................8
4.4 Shop drawing of loading platform for loading MEP equipment................................................................................8

1|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
1. GENERAL
1.1 Project Brief
- Project Name: Novotel Phnom Penh Project
- Construction Company:Pasteur Square Co.,Ltd.
- Soil Survey Company:FIRST BUILD ENINEERING CO.,LTD
- Architectural Design Company:SODA(Thailand)
- Structural Design Company:Meinhardt (Thailand)Ltd.
- Main Contractor:China Construction Fourth Engineering Division Corp.Ltd
- Project’s Address:Intersection of Road St.51 corner St. 294, BKK1, Phnom Penh
- Project Basic Information:Total Floor Area 22,768m2, 27 floors, 3 basements, Total height 103.1m, and
Land area 1,756m2. Project contain 3 basement floors; the deepest basement floor(B3) slab’s top level is
-8.45m and -9.45m.

Figure 1: 3D rendering view of the building

2|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F

Figure 2: Site Layout Plan


1.2 Purpose
This method statement describes the details procedure of hoisting and installing, for chiller & MEP equipments.

1.3 Basis for Compilation


No. Basis for Compilation
1 Architectural Drawing for Construction & General Specifications by SODA
2 Structural / MEP Drawing for Construction & General Specifications by Meinhardt
3 GB/T20118-2006 - General Purpose of Wire Rope
5 Technical regulations for the using of construction machinery safety JGJ33-2012
6 Technical code for safety of construction at heights JGJ80-2016
1.4 Site planning & Preparation
- Equipment, tools and other material shall be confined within the working area and designated storage and
parking area.
- Barricading and securing of the construction area as well as the storage and parking area shall be adequate
to prevent entry of unauthorized personnel and to ensure the safety of the worker on site.
- All necessary permits to carry out the work such shall prepared in advance.
- Due to the installed tower crane (TC5610) of the project has the largest hoisting weight is 3T, which is not
enough to meet the hoisting requirements of the chiller equipments. Therefore, the project plans to install
a roof hoisting crane (QTZ80.12) at southeast corner of the 26th floor for hoisting the chiller equipments,
the maximum hoisting weight is 12T with the arm length is 20m and the total load of itself is 15T, the
hoisting machine rated lifting torque 80T·M, Total power consumption 64KW, it can meet the hoisting
requirements of chiller plant for this project.
3|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F

Figure 3: Level 25 - Layout Plan


1.5 Plant and Equipment
The plant and equipment required for executing the woks are list below, but not limited:

Item Plant/Equipment Specification Quantity Remark


1 Derrick crane 15T 1
2 Mobile crane / 1
3 Various steel ropes, hemp ropes / As required
4 Tape measure 5M 2
5 Level machine DZS3-1/AL332 1
6 Walkie talkie / As required
7
8 Spirit level Length 450-500mm As required
9 Plumb bob / As required
10 Moving rollers etc., 10T/12T As required
Note: The project quantity in this plan is only the reference value, for the specific quantity should be based on actual
requirement.

1.6 Materials
- All materials shall be complied with all requirement in the specifications.
- Only approved material by engineer in the specification and quality control plan shall be used.
- Should be the material nor complied with the requirement of the specification and other pertinent
requirements shall be removed for the site.
4|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
The materials required for executing the work are tabulated below:

Item Plant/Equipment Specification Quantity Remark


1 Chiller machine (1583 kWR) Weight 8564kg 2
2 Chiller equipmnets etc., / /
1.7 Organization, Responsibility and Supervision
Item Plan/Equipment Quantity Responsibility
1 Site Engineer 1 To responsible for the day activity
To advise for health & safety aspects in the job as per
2 Safety Officer 1 standard safety requirements prior to start o work daily.
His recommendations will be complied with at all times
3 QC Engineer / Inspector 1 To conduct inspections and monitor the required tests
4 Full-Time security officer As required /
5 Professional sub-con. installer As required To do installation works
6 Crane operator 2 Dispatching equipment components
7 Crane command 2 Safe control of crane operation

2. WORK EXECUTTION PROCESS


2.1 General Preparations work
- Secure necessary work permit Representative prior to start of work/activity.
- Check foundations and other connection points to confirm locations, orientation elevation and condition.
- Identify the structure members for leave-out (if any) due to installation of equipment and other prerequisite.
- Mobilize all manpower, tools and equipment needed for the job.
- Ensure that the completed foundation with anchor bolts was already checked and its dimensions, levelness,
alignment, top of concrete elevation, surface finish, and others are as per the latest revision of approval
shop drawings.
- Check lifting weight, crane position with capacity of applied crane base on crane specification issued by
manufacturer.
- Make sure there is space and firmed pathway for truck delivery. The suitable truck & crane capacity
should be clarified.
- The plan for unloading and materials storage on the site should be suitable and dry location. Materials
shall be stored in designated areas for each building and clearly identified for their location as per
planning.
- Before unloading materials out of trucks, the access road must be prepared properly for crane and trucks
by term safely load.
- To avoid materials being moved so much on the job site that might cause unexpected damages of paint
or discolor and shapes, they shall be unloaded and arranged close to the designed installation point. The
materials shall be stacked in location according to the building/areas, should be near to the lifting position
adjacent to the area to be installed.
2.2 Work Methodology
- Chillers are normally shipped & dispatched from factory as a hermetically assembled package, factory
piped, wired and tested. All openings except for the water box vent & drain holes are covered or plugged
to prevent contamination during shipment & handling.
- All delivery materials to the site shall be informed to the engineer to have the plan for unloading. Upon
arrival of materials at the storage yard, the materials controller will match delivery notes and shall verify
the consignment.
5|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
- Use appropriate type of vehicles in transporting the units and that they are protected against mechanical
& weather damage.
- Unloading the materials to the ground position onsite area, it can be done by term with using mobile cranes.
Be sure to hook belts to component with the right number of points and position so that the load of the
component itself do not damaged or broken especially the coating/discolor.
- Hoisting the chiller equipments up from the ground position to 25th floor, by using derrick crane (QTZ80.12)
for hoisting, then unloading the material on loading platform.

Figure 4: Unloading chiller equipments to the ground position, by using mobile crane

Reference

Figure 5: Preparing for hoisting chiller equipments up to L25, by using derrick crane

6|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
- Prior to moving the chillers at site, ensure that the foundation requirements have been done. Foundation
details & requirements for the chillers shall be as per approved shop drawings
- Ensure that the foundation will be able to support the chiller at its full operating weight.
- After ensuring that the foundations for the chillers are satisfactory, shift the chillers by using moving rollers
to its exact location and install.

Reference

Figure 6: Shifting chiller equipments to the installation position, by using moving rollers

3. SAFETY ASSURANCE MEASURES


3.1 Overall Goal of The Security Management
The overall goal of the project safety management is to achieve safety and no accident. Specifically:
a. To eliminate any personal casualties
b. To prevent the occurrence of equipment accidents
c. To eliminate the occurrence of fire accidents
d. To avoid other construction projects to affect their own safety
e. Eliminate their own safety impact on other construction projects.

3.2 HSE Policy


a. Safety First Prevention
b. Focus on health protection environment
c. Strengthen the basic Process control
d. Full participation in continuous improvement
e. Under the guidance of HSE policy, we should continuously strengthen the HSE management of production
and operation activities, comprehensively improve the risk control and accident prevention ability, and
strive for the target of 0 accidents, 0 injuries and 0 pollution.

3.3 Safety Education Training


a. The aim of safety education and training is to enhance the consciousness of safety production of each
functional department and post personnel, to master the knowledge of safety production, to prevent unsafe
behavior effectively and to reduce human error, so that the construction is carried out in a safe and
controlled state.
b. Develop project safety training plan. In different stages of testing, the safety training plan should be
formulated in a timely manner.
c. The object of safety training and education is to participate in the project inspection of all personnel
d. The main contents of safety training education are safety management system and safety operation rules.

7|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
e. The safety technology should be given before the inspection operation.
3.4 Safety Supervision and Inspection
a. The purpose of the security check is to find unsafe behavior and unsafe state, which is an important method
to eliminate the hidden trouble, implement corrective measures, prevent accident injury and improve
working conditions.
b. The main content of security check is to check the thought, check the management, check the system,
check the scene, check hidden trouble, check the accident treatment.
c. Security checks should be planned, purposeful, prepared, rectification, summary, have to deal with.

3.5 Safety Assurance Measures


1. Safety precautions:
a. In the testing site to lay signs, for the construction site safety tips, warnings or prohibited signs.
b. All personnel entering the scene must wear a safety helmet, the construction personnel must unify the
attire, the electrician must wear the insulating shoes.
c. To test the site and living in the workplace to be equipped with fire extinguishers.
d. Abide by the safety system of construction site.
e. The detection project in strict accordance with the relevant procedures, to eliminate the unsafe
behavior of people, the unsafe state of things, environmental insecurity factors, the detection of the
operation of the project area set up a clear warning sign.

3.6 Safety and Qualification for Construction


a. Comply with the relevant safety requirements as to site arrangement/layout of equipment/plant, material
stockpile, fabrication/assembly yard, toilet, washing bay, drainage system, office, etc.
b. Qualified construction, coordination, and actively cooperate with the construction staff of the relevant
construction units to ensure normal construction.
c. On-site inspection personnel to keep the clothes neat
d. The equipment should be neatly arranged and kept clean
e. The Office, the lodging place should keep clean, neat and so on.

4. ATTACHMENTS
4.1 Method statement of Special construction plan for roof crane installation & Demolition
Reference Approval No. NPP/RFA/MS/S-084
4.2 Method statement of Material loading platform for MEP equipment
Reference Approval No. NPP/RFA/MS/S-085

4.3 Shop drawing of Footing for derrick crane at L26


Reference Approval No. NPP/RFA/SD/S-201R1

4.4 Shop drawing of loading platform for loading MEP equipment


Reference Approval No. NPP/RFA/SD-202R1

8|Page