Professional Documents
Culture Documents
Table of Contents
1. GENERAL ........................................................................................................................................................................2
1.1 Project Brief.............................................................................................................................................................2
1.2 Purpose ...................................................................................................................................................................3
1.3 Basis for Compilation ..............................................................................................................................................3
1.4 Site planning & Preparation ....................................................................................................................................3
1.5 Plant and Equipment ...............................................................................................................................................4
1.6 Materials..................................................................................................................................................................4
1.7 Organization, Responsibility and Supervision .........................................................................................................5
2. WORK EXECUTTION PROCESS ...................................................................................................................................5
2.1 General Preparations work .....................................................................................................................................5
2.2 Work Methodology ..................................................................................................................................................5
3. SAFETY ASSURANCE MEASURES...............................................................................................................................7
3.1 Overall Goal of The Security Management .............................................................................................................7
3.2 HSE Policy ..............................................................................................................................................................7
3.3 Safety Education Training .......................................................................................................................................7
3.4 Safety Supervision and Inspection ..........................................................................................................................8
3.5 Safety Assurance Measures ...................................................................................................................................8
3.6 Safety and Qualification for Construction ................................................................................................................8
4. ATTACHMENTS ..............................................................................................................................................................8
4.1 Method statement of Special construction plan for roof crane installation & Demolition .........................................8
4.2 Method statement of Material loading platform for MEP equipment........................................................................8
4.3 Shop drawing of Footing for derrick crane at L26 ...................................................................................................8
4.4 Shop drawing of loading platform for loading MEP equipment................................................................................8
1|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
1. GENERAL
1.1 Project Brief
- Project Name: Novotel Phnom Penh Project
- Construction Company:Pasteur Square Co.,Ltd.
- Soil Survey Company:FIRST BUILD ENINEERING CO.,LTD
- Architectural Design Company:SODA(Thailand)
- Structural Design Company:Meinhardt (Thailand)Ltd.
- Main Contractor:China Construction Fourth Engineering Division Corp.Ltd
- Project’s Address:Intersection of Road St.51 corner St. 294, BKK1, Phnom Penh
- Project Basic Information:Total Floor Area 22,768m2, 27 floors, 3 basements, Total height 103.1m, and
Land area 1,756m2. Project contain 3 basement floors; the deepest basement floor(B3) slab’s top level is
-8.45m and -9.45m.
2|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
1.6 Materials
- All materials shall be complied with all requirement in the specifications.
- Only approved material by engineer in the specification and quality control plan shall be used.
- Should be the material nor complied with the requirement of the specification and other pertinent
requirements shall be removed for the site.
4|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
The materials required for executing the work are tabulated below:
Figure 4: Unloading chiller equipments to the ground position, by using mobile crane
Reference
Figure 5: Preparing for hoisting chiller equipments up to L25, by using derrick crane
6|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
- Prior to moving the chillers at site, ensure that the foundation requirements have been done. Foundation
details & requirements for the chillers shall be as per approved shop drawings
- Ensure that the foundation will be able to support the chiller at its full operating weight.
- After ensuring that the foundations for the chillers are satisfactory, shift the chillers by using moving rollers
to its exact location and install.
Reference
Figure 6: Shifting chiller equipments to the installation position, by using moving rollers
7|Page
Novotel Phnom Penh Project Ms of Hoisting MEP Equipments form GF-25F
e. The safety technology should be given before the inspection operation.
3.4 Safety Supervision and Inspection
a. The purpose of the security check is to find unsafe behavior and unsafe state, which is an important method
to eliminate the hidden trouble, implement corrective measures, prevent accident injury and improve
working conditions.
b. The main content of security check is to check the thought, check the management, check the system,
check the scene, check hidden trouble, check the accident treatment.
c. Security checks should be planned, purposeful, prepared, rectification, summary, have to deal with.
4. ATTACHMENTS
4.1 Method statement of Special construction plan for roof crane installation & Demolition
Reference Approval No. NPP/RFA/MS/S-084
4.2 Method statement of Material loading platform for MEP equipment
Reference Approval No. NPP/RFA/MS/S-085
8|Page