You are on page 1of 53

CIVIL AVIATION AUTHORITY, BANGLADESH

Expansion of Osmani International Airport,Sylhet (1st Phase)


Sub-soil Investigation Implementation Proposal

Authored By:

Reviewed By:

Approved By:

BEIJING URBAN CONSTRUCTION GROUP CO., LTD

December 2020
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

TABLE OF CONTENT

Ⅰ. Project overview......................................................................................................1

1. Project introduction........................................................................................... 1

2. Scope andcontent of the investigation.............................................................. 1

Ⅱ. Investigation basis................................................................................................... 2

1. Documents for investigation basis..................................................................... 2

2. Specifications and standards of investigation basis........................................... 3

Ⅲ. Investigation objectives and tasks.......................................................................... 5

Ⅳ. Investigation implementation organization planning............................................ 7

1. Project organization and management ............................................................7

2. Investigation personnel...................................................................................... 8

3. Equipment and instruments...............................................................................9

4. Establishment and management of geotechnical Laboratory......................... 10

Ⅴ. Investigation description and implementation plan............................................11

1. Investigation process........................................................................................11

2. Brief description of the site..............................................................................12

3. Investigation implementation plan.................................................................. 13

Ⅵ. Results submission................................................................................................ 35

1. Ground Investigation Report............................................................................36

2. Geotechnical Design Report.............................................................................37

Ⅶ. Quality assurance measures................................................................................. 38

1. Quality objectives.............................................................................................38

2. Quality assurance system.................................................................................38

3. Quality assurance measures............................................................................ 39

Ⅷ. Investigation programme...................................................................................... 41

Ⅸ. Environmental protection objectives................................................................... 41

Attachments.................................................................................................................42

Attachment 1. Proposed Ground Investigation Plan..................................................42


SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Attachment 2. List of Boreholes..................................................................................42

Attachment 3. Bar Chat of Investigation Schedule.....................................................42


SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Ⅰ. Project overview
1. Project introduction

Project Name: Expansion of Osmani International Airport,Sylhet (1st Phase)

Project Location: Sylhet, Bangladesh

Employer: Civil Aviation Authority of Bangladesh (CAAB)

Contractor: Beijing Urban Construction Group Co., Ltd (BUCG)

Osmani International Airport is located in the Sylhet area of Northeast

Bangladesh. The location of proposed site is shown in Figure 1-1, and the domestic

flights of Dhaka-Sylhet are carried out by CAAB, the runway of existing airport is

45 meters wide and 3,125 meters long. The airport expansion project is carried out

to meet the flight needs of the international flights for airport, passenger terminal,

passenger parking apron, taxiway, and other infrastructure.

Figure 1-1 Location of the proposed site


2. Scope and content of the investigation

According to the contract signed between CAAB and BUCG, the content of the

investigation includes the International Passenger Terminal building, control tower,

administrative building, cargo building, the maintenance building, the utility station,

page 1 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

the Apron, taxiway etc. The specific information on each building is shown in the

table below:
Information list of proposed buildings and structures Table 1-1
Main parameters Foundation type
No. Name of buildings
(Floor, Height, Aera) to be adopted

1 Passenger Terminal Building 3 floors,16.55m,34,919 m2 Pile foundation

2 Cargo Building 2 floors,12.00m,6,892 m2 Pile foundation

Operation Building With


3 9 floors,43.20m,2,772 m2 Pile foundation
Control Tower
Rescue And Fire Fighting
4 2 floors,9.42m,2,415 m2 Pile foundation
Station

5 Administrative Building 2 floors,8.70m,1,395 m2 Pile foundation

6 Utility Station 1 floors,7.50m,1,800 m2 Pile foundation

7 Maintenance Building 1 floors,6.50m,606 m2 Pile foundation

8 AFL Station (CCR Room) 1 floors,6.00m,667m2 Pile foundation

9 Cargo Annex Building 4 floors,6.60m,1,827 m2 Pile foundation

Sewage & Water Treatment


10 1 floors,830 m2 Pile foundation
Plant
Natural
11 Taxiways 108,389 m2
foundation
Natural
12 International Apron 76,242 m2
foundation
Natural
13 Parking Lot 29,707 m2
foundation

Ⅱ. Investigation basis
The investigation basis is mainly composed of two parts. One part is the

bidding documents and attachments provided by CAAB, the other part is relevant

standards and specifications implemented in the industry.

1. Documents for investigation basis

☆ Report: Geotechnical Investigation For Osmani Airport December 2018,

heerim

page 2 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

☆ Topographical Survey Report On Osmani International Airport (Oia),

Sylhet December 2018

☆ Design Report of Osmani International Airport, December 2018, heerim

☆ Design Report of Osmani International Airport, December 2018

☆ Section-1: Instruction to tenderers (ITT)

☆ Section-2: Tender Data Sheet (TDS)

☆ Section-3: General Condition of Contract (GCC)

☆ Section-4: Particular Conditions of Contract (PCC)

☆ Section-5: Tender and Contract Forms

☆ Section-6: Bill of Quantities

☆ Section-7: General Specification

☆ Section-8: Particular Specification (Civil Works)

☆ Section-8: Particular Specification (Building Work)

☆ Section-8: Particular Specification (Electro-Mechanical Works)

☆ Section-8 : Particular Specification (Communication & Security System)

☆ Section-8: Particular Specification (Fuel Hydrant System)

☆ Section-9: Drawings

2. Specifications and standards of investigation basis

☆ EM1110-1-1804 US Army Corps of Engineers ENGINEER MANUAL

Geotechnical Investigations.

☆ ASTM D420-18 Standard Guide for Site Characterization for Engineering

Design and Construction Purposes.

☆ ASTM D2113-14 Standard Practice for Rock Core Drilling and Sampling

of Rock for Site Exploration.

☆ ASTM D4220/D4220M-14 Standard Practices for Preserving and

Transporting Soil Samples.

☆ ASTM D2487-17 Standard Practice for Classification of Soils for

Engineering Purposes(Unified Soil Classification System).

page 3 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

☆ ASTM D2488-17 Standard Practice for Description and Identification of

Soils (Visual-Manual Procedures).

☆ ASTM D1586/D1586M-18 Standard Test Method for Standard Penetration

Test (SPT) and Split-Barrel Sampling of Soils.

☆ ASTM D1587/D1587M-15 Standard Practice for Thin-Walled Tube

Sampling of Fine-Grained Soils for Geotechnical Purposes.

☆ ASTM D7400-19 Standard Test Methods for Downhole Seismic Testing.

☆ ASTM D2216-19 Standard Test Methods for Laboratory Determination of

Water (Moisture) Content of Soil and Rock by Mass.

☆ ASTM D2937-17 Standard Test Method For Density Of Soil In Place By

The Drive-Cylinder Method.

☆ ASTM D854-14 Standard Test Methods for Specific Gravity of Soil Solids

by Water Pycnometer.

☆ ASTM D4318-17 Standard Test Methods for Liquid Limit, Plastic Limit,

and Plasticity Index of Soils.

☆ ASTM D6913/D6913M-17 Standard Test Methods for Particle-Size

Distribution (Gradation) of Soils Using Sieve Analysis.

☆ ASTM D7928-17 Standard Test Method for Particle-Size Distribution

(Gradation) of Fine-Grained Soils Using the Sedimentation (Hydrometer) Analysis.

☆ ASTM D2435/D2435M-11 Standard Test Methods for One-Dimensional

Consolidation Properties of Soils Using Incremental Loading.

☆ ASTM D2850-15 Standard Test Method for Unconsolidated-Undrained

Triaxial Compression Test on Cohesive Soils.

☆ ASTM D4767-11 Standard Test Method for Consolidated Undrained

Triaxial Compression Test for Cohesive Soils.

☆ ASTM D2166 /D2166M-16 Standard Test Method for Unconfined

Compressive Strength of Cohesive Soil.

☆ ASTM D2974-14 Standard Test Methods for Moisture, Ash, and Organic

page 4 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Matter of Peat and Other Organic Soils.

☆ ASTM D698-12 Standard Test Methods for Laboratory Compaction of Soil

Standard Effort.

☆ CBR ASTM D1883-16 Standard Test Method for California Bearing Ratio

(CBR) of Laboratory-Compacted Soils.

☆ FEMA450 NEHRP Recommended Provisions for Seismic Regulations for

New Buildings and Other Structures.

☆ ASTM D511-14 Standard Test Methods for Calcium and Magnesium In

Water.

☆ ASTM D516-16 Standard Test Method for Sulfate Ion in Water.

☆ ASTM D1293-18 Standard Test Methods for pH of Water.

☆ ASTM D4972-19 Standard Test Methods for pH of Soils.

☆ ASTM D512-12 Standard Test Methods for Chloride Ion In Water.

☆ ASTM C1580-15 Standard Test Method for Water-Soluble Sulfate in Soil.

☆ ASTMD1126-17 Standard Test Methods for Hardness in Water.

☆ ASTMD1068-15 Standard Test Methods for Iron in Water.

☆ IBC2018 International Building Code.

☆ ASCE20-96 Standard Guidelines For The Design And Installation Of Pile

Foundations.

☆Bangladesh National Building Code

Ⅲ. Investigation objectives and tasks


The objective of this investigation is to carry out necessary Sub-Soil

Investigation for each building and structure according to the instructions and

requirements of CAAB or consulting engineer before the construction begins.

Through drilling, in-situ test, laboratory geotechnical test and other means, the

engineering geological conditions of the site shall be found out, and the process

characteristics of various rock and earth mass shall be analyzed and evaluated.

According to the result of investigation, the original foundation design shall be

page 5 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

rechecked to ensure the safety, rationality and applicability. The main tasks shall be

as follows:

(1) Find out the causes, types, distribution range, development trend and harm

grade of adverse geological phenomena, and make sure that they are consistent with

the conditions given in the original design report;

(2) Find out whether there are buried objects unfavorable to the project in the

site, such as buried river channels, ditches, tombs, boulders and others;

(3) Find out the classification, structure, thickness, slope and engineering

characteristics of each layer of rock and soil within the scope of the building in

detail. Provide and evaluate the stability and bearing capacity of the foundation, and

check and compare it with the original design report to determine its rationality and

applicability;

(4) According to the single building (structure) or building (structure) group,

propose the detailed Sub-Soil data and geotechnical parameters required by the

design; Make evaluation on the Sub-Soil of the building foundation; and put forward

recheck opinions on the foundation type, foundation form, bearing layer, foundation

buried depth, foundation treatment, engineering precipitation as well as prevention

and control of adverse geological effects proposed in the original design;

(5) Find out the distribution depth, range, and characteristics of soft soil, and

provide the permeability parameters of corresponding layers. Determine the possible

changes of subsoil and groundwater during the construction and use of buildings and

their impact on the project, and recheck the prevention and control measures and

suggestions of the original design;

(6) Propose the corrosion evaluation of water, soil and underground minerals

to building materials and metals, and propose the anti-floating water level;

(7) Analyze the rationality and applicability of the foundation type, foundation

pit excavation and bracing and dewatering scheme in the original design report.

Provide the calculation parameters of foundation deformation for buildings that need

page 6 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

settlement calculation, so as to predict the settlement, differential settlement or

overall inclination of buildings and give corresponding prevention and control

suggestions;

(8) Provide the geotechnical parameters required for pile foundation design,

and determine the bearing capacity of every single pile; Recheck whether the type,

length, and construction method of pile proposed in the original design report can

meet the load and deformation requirements of upper structures.

Ⅳ. Investigation implementation organization planning


1. Project organization and management

The investigation project management department of the project is specially

established to ensure the quality and efficiency of the project, and to complete the

objectives of quality, safety, progress, environment, and civilized construction. A

registered geotechnical engineer with sufficient geotechnical investigation

experience is responsible for the project. The project organization is shown in Figure

4-1.

page 7 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Investigation project management


department

Production Management Technical quality HSE General Management


Department Department Department department

Measurement Drilling in-situ test Geotechnical Report


group group group test group preparation
group

Realization of each
objective

Figure 4-1 Project organization chart

During the construction process, the project department shall strictly implement

the approved proposal, and fully accept the supervision of CAAB to ensure the

project quality and construction schedule.

2. Investigation personnel

To ensure the smooth implementation of the project, qualified management

personnel with similar work experience shall be appointed.

The main personnel allocation is shown in the table below:


Main personnel allocation Table 4-1

No. Name Age Gender Specialty Proposed position

Engineering
1 Dai Jinming 50 Male Investigation Project Director
geology

Geotechnical
2 Liu zhewei 29 Male Technical Manager
engineering

page 8 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Geotechnical
3 Li Wentao 35 Male Investigation Manager
engineering
Geotechnical
4 Fan Lipeng 37 Male HSE director and safety supervisor
engineering
Geotechnical
5 Wang Yupei 31 Male Test director
engineering
Geotechnical
6 Zhu Wanli 32 Male Production controller
engineering

3. Equipment and instruments

Through careful analysis of the actual situation, geological conditions and

schedule target of the project, following geotechnical equipment and instruments

shall be used to carry out the required tasks.

List of main instruments and equipment Table 4-2

Name of Machinery or Year of


No. Quantity Remarks
Equipment manufacture

1 Rigs 5 sets 2018 Drilling


2 Electronic balance 1 set 2020
3 Standard sieve 1 set 2020

4 Oven 1 set 2020

5 Consolidation test apparatus 48 sets 2020

6 Direct shear apparatus 1 set 2020


unconfined compressive 2020
7 1 set
strength meter apparatus
8 Triaxial apparatus 2 sets 2020

9 Pipette 1 set 2020

10 Cylinder 1 set 2020

11 GPS-RTK 2 sets 2018


12 Level 1 set 2020
13 Underground pipeline detector 1 set 2018

Adjustment of the investigation equipment shall be made according to the

investigation progress. If the investigation schedule is found delayed, proper number

of investigation equipment and instruments shall be increased timely to ensure the

ultimate realization of the overall construction schedule.

page 9 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

4. Establishment and management of geotechnical Laboratory

4.1 Establishment of laboratory

To improve the operation efficiency of the laboratory, the on-site geotechnical

laboratory is planned to establish in the construction area in Sylhet.

4.2 Laboratory management

Despite the management regulations of the construction area, the following

laboratory management systems shall also be conducted.

① The temperature and humidity as well as shock-proof and dust-proof of test

room shall meet the relevant national regulations.

② The laboratory shall be kept clean and the indoor air shall be fresh and in

circulation.

③In the laboratory, the road shall be clear; the instruments and equipment shall

be placed in order, and the sample shall be placed at the designated place.

④ The non-laboratory personnel shall not enter the laboratory without

permission. Non-test operators of the laboratory shall not operate testing instruments

and equipment. .

⑤ No one shall be allowed to bring anything irrelevant to work into the

laboratory.

⑥ Operation procedures shall be strictly implemented, and it is forbidden to

use instruments and equipment beyond the measurement range and overload. After

the operation, unload immediately. After each test, clean up the equipment and site,

cut off the power immediately.

⑦ All facilities in the laboratory shall be kept by a specially assigned person

and shall not be taken out without permission.

⑧ The electrical appliances, lines, and various pipelines in the laboratory shall

be inspected and maintained regularly. The maintenance of high-voltage electrical

appliances shall be carried out by certified electricians to ensure the safety of

personnel and equipment.

page 10 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

⑨ Inflammable and dangerous goods shall be strictly kept by a designated

person and in fixed place. Indoor fire fighting equipment shall not be moved at will

in order to ensure emergency use.

⑩ Before off duty, the water, electricity, gas, and doors and windows shall be

checked to eliminate all hidden dangers before leaving.

Ⅴ. Investigation description and implementation plan


1. Investigation process

The investigation process is shown in the figure below.

page 11 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Investigation Planning

Determine the investigation


process
Determine the
Set up investigation Select instruments,
standards and
organization equipment,
documents to be
machines and tools
implemented
Construction preparation

Prepare investigation outline

Prepare operation plan


Implement technical
standards and Work in a suitable
procedures environment
On-site investigation process
control
Collect
topographic and Drilling, sampling, in-situ Equipment
geological data testing maintenance

Process control of interior


field

Geotechnical test indoor Data analysis and chart drawing

Prepare investigation report

Verify / review investigation documents

Printing and binding Delivery

Figure 5-1 Investigation flow chart

2. Brief description of site investigation

The site of this project is located in Sylhet in the northeast, on the alluvial plain,

with flat and open terrain, small undulation, and well-developed vegetation, which

mainly includes the infrastructure in the existing plant.

page 12 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Figure 5-2 Existing roads in the site area


3. Investigation implementation plan

3.1 Investigation methods to be adopted

According to the engineering characteristics and geological conditions of the

site, the current relevant standards, as well as engineering investigation experience,

the following investigation methods shall be adopted.

(1) Drilling

The aims and function of drilling include:

① Find out the formation lithology and the variation of the thickness of the

rock and soil layer within the scope of the investigation site, and find out the nature,

thickness, number of layers, occurrence and spatial distribution of the soft rock and

soil layer;

② Find out the geological structure, distribution limit, and shape of

unfavorable geological phenomena, etc;

③ Analyze and test the rock and soil samples taken in the borehole, and find

out physical and mechanical properties of rock and soil layer;

④ Carry out various in-situ tests by drilling boreholes;

⑤ Find out the type and layer number of groundwater, measure the depth of

water level and take water samples. Analyze the physical and chemical properties of

groundwater, and provide hydrogeological parameters.

page 13 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

The BWQ160 drilling rig is used in this project. The drilling and sampling

methods are under Standard Practice for Rock Core Drilling and Sampling of Rock

for Site Exploration (ASTM D2113).

(2) In-situ test

It is taken to evaluate the site type, as well as soil layer density, bearing

capacity, and soil shear index parameters of the site. Wave velocity test, and standard

penetration test shall be arranged in some boreholes.

(3) Laboratory test

Laboratory tests mainly aims to measure the physical and mechanical

parameters of soil, compress shear index, evaluate the corrosivity of groundwater

and soil, and provide necessary parameters for design and construction. The number

of laboratory tests shall be determined according to the number of on-site samples

and the actual requirements of the project.

Figure 5-3 Soil sample preparation

① Physical test

A. Purpose and content: To obtain physical property indexes of different types

of soil layers of different origin in Quaternary, including natural water content,

page 14 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

natural gravity, natural density, relative density, saturation, plastic limit, liquid limit,

plasticity index, liquid index, void ratio, permeability coefficient, content of organic

matter and other indexes.

B. Method: Physical test shall be implemented according to ASTM D standard

system.

Figure 5-4 Water content sampling Figure5-5 Weighing with scale

② Particle-Size Analysis

A. Purpose and content: To name the sand and determine the distribution of

particle sizes of each layer in the Quaternary.

B. Method: sieving method and hydrometer method.

Figure 5-6 Sieving method Figure 5-7 Hydrometer method

③ Mechanical test

A. Purpose and content: To determine the consolidation compression and shear

property indexes of Quaternary layers, including compression coefficient,

page 15 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

compression modulus, consolidation coefficient, rebound index, shear strength index

(friction angle φ and cohesion value C ), pre-consolidation pressure, and unconfined

compressive strength, etc.

B. Method: Triaxial shear test and direct shear test shall be used for shear

strength; The standard consolidation test shall be used for compression consolidation

test, namely the one-dimensional consolidation compression test.

Figure 5-8 Consolidation test Figure 5-9 Direct shear test

Figure 5-10 Triaxial test

④ Corrosion test

A. Purpose and content: To determine the corrosivity of foundation soil and

groundwater above groundwater, including water quality analysis and soil soluble

salt test.

B. Method: The test shall be carried out according to requirements in the

page 16 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

ASTMD standard system.

Figure 5-11 Water quality analysis test

3.2 Layout principle and workload of exploration points

3.2.1 Layout principle of exploration points

According to the related standards of Bangladesh National Building Code

(2018), ASTM, EM, BS, combined with the site engineering geological features,

project overview, geological background conditions, site conditions, project

characteristics and basic engineering problem, the principles are as follows:

(1) Single building

① Drilling spacing: the drilling spacing depends on the nature and conditions

of the site soil layer as well as the nature and scale of the project. In homogeneous

formation, the drilling spacing shall be within 30-100 meters or more; In very

uneven formation, the drilling spacing shall be 10 meters or less.

② Number of boreholes: for small buildings, the number of exploration points

shall not be less than 3, and the layout of boreholes shall not be located in a straight

line; for multi-story buildings, the number of boreholes shall not be less than 5, and

the boreholes shall be arranged in a shape of plum blossom.

③ Drilling arrangement:

a. The exploration points shall be arranged at the locations where the load and

the building shape vary greatly, and the exploration borehole spacing shall also take

page 17 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

into account the principle of surrounding underground structure outline.

b. The controlling exploration points account for 1/3 ~ 1/2 of the total number

of exploration points.

c. The exploration points of 10 single buildings shall be arranged according to

the above principles, and the average drilling spacing shall be 30 meters.

(2) Taxiway

The boreholes shall be arranged along the center line of the taxiway with a

spacing of 60-76 meters.

(3) Apron

The boreholes shall be arranged according to the square grid with a spacing of

60-75m.

For a detailed layout of exploration points, please refer to Attachment 1

“OSMANI GROUND INVESTIGATION PLAN”.

3.2.2 Exploration point depth design

The drilling depth of the proposed site shall be designed based on related

standards of the Bangladesh National Building Code (2018), ASTM, EM, BS, and

other equivalent standards and specifications.

(1) Single building

General principles:

a. The depth of control exploration borehole exceeds the calculated depth of

foundation deformation.

b. The depth of general exploration borehole can control the main stress layer

of the foundation.

c. The depth of wave velocity test borehole meets the site classification

evaluation.

d. When the drilling boreholes are shared, the drilling depth shall meet the

requirement of the larger depth.

The drilling depth of the project is as follows:

page 18 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Estimate the possible base load according to the similar engineering experience.

Based on the buried depth of the foundation, the number of upper layers, and the

formation of adjacent site, the requirements of deformation checking, single pile

bearing capacity checking, and foundation pit supporting design shall be considered.

(2) Taxiway, apron

Find out the engineering geological conditions along the line and meet the

requirements of “General Specification”. The drilling depth shall not be less than

20m.

Refer to the attached Attachment 1 “OSMANI GROUND INVESTIGATION

PLAN” for a detailed depth layout of exploration points.

3.2.3 Workload

① Drilling: a total of 154 boreholes shall be arranged, and the footage shall be

5495 linear meters.

It should be noticed that the final drilling depth and workload shall be

determined in combination with the site formation conditions. The investigation

workload is shown in Table 5-1.

② In-situ test: The standard penetration test is required to start from 2.5 to

3.5m below the ground and be conducted at 1.5m interval.

Wave velocity test: This test shall be adopted to determine dynamic parameters,

measure the P-wave velocity curve and S-wave velocity curve and Poisson’s ratio of

different formation; Distinguish site types and obtain shear wave velocity data of the

site. Each single building shall be arranged with 1-2 wave velocity test boreholes, a

total of 19 shall be arranged, and all test depth is less than hole depth.

③ Laboratory test:

a. Conventional test: test of natural water content, natural density, specific

gravity, boundary water content, etc;

b. Standard consolidation test: one-dimensional consolidation test,

pre-consolidation pressure, and primary consolidation coefficient;

page 19 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

c. Shear test: direct shear test, triaxial shear test, cohesion and internal friction

angle of rock and soil;

d. Particle-Size Distribution test: a screening test for sand; clay content test;

e. Organic matter content test: determine the organic matter content and

ignition loss of organic soil;

f. Permeability test: determine the permeability coefficient of rock and soil

layer;

g. Corrosivity test of soil or water: determine the corrosivity of soil and

groundwater in the site to construction materials;


Detailed list of investigation workload Table 5-1
Field exploration workload
Soil sampling standard penetration
Type Total
drilling
Drilling footage (m) 5495 5495

Number of boreholes 154 154

Digging, sampling and in-situ testing


Standard
Type Undisturbed sample Disturbed sample Wave velocity test
penetration test
Quantity 900 pieces 900 pieces 3700 times 19 boreholes

Geotechnical test
Unconfined
Conventional Permeability Particle-Size
Test items Consolidation test compressive
test coefficient Analysis
strength
Number of test 900 pieces 800 pieces 100 pieces 32 pieces 1800 pieces
Brief analysis
Organic matter Soluble salt of
Test items Direct shear Triaxial shear of water
content soil
quality
Number of test 100 pieces 200 pieces 100 pieces 20 group 30 group
Notes:
Referring to Attachment 1 “ OSMANI GROUND INVESTIGATION PLAN” for drilling location;
Referring to Attachment 2 “List of exploration points” for drilling information.
3.3 Survey and set out of Borehole and related measurement

3.3.1 General provisions

(1) The survey personnel shall confirm the coordinates or control points

provided by CAAB, and then adopt GPS-RTK to survey and set out the exploration

page 20 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

points. The serial number of exploration points, drilling depth and drilling type shall

be marked. The technical personnel shall recheck the exploration points and protect

the point marks.

(2) Drilling and borehole setting: according to the list of drilling tasks, the

borehole location shall be photographed on site. If it is necessary to relocate the

borehole, the proposed location shall be reported to CAAB’s on-site engineer for

approval. Check the data of borehole setting after completion.

(3) Before drilling, record the change of elevation of borehole in the log (which

may be caused by machine weight). After drilling, the location and elevation of

drilling borehole shall be re-surveyed in batches. After the re-survey, the “Table of

re-survey results of borehole location” shall be provided.

The borehole location shall be carried out according to the requirements of the

approved proposal. In case of special circumstances, it is requested to report to

CAAB’s on-site engineer immediately. Before drilling each borehole, the technician

must go to the site verify whether the borehole location is accurate. If it is necessary

to relocate the borehole, the proposed location shall be reported to CAAB’s on-site

engineer for approval, the actual borehole location and elevation shall be recorded in

the log. If the borehole location is found to be within the required location range, the

drilling can be started immediately. The borehole orifice is generally calculated from

the original ground. In case of excavation or filling of leveling machine platform,

the elevation discrepancy between the orifice and the original ground orifice after

site leveling shall be noted in the log, and the borehole depth shall be determined

together with CAAB’s on-site engineer.

3.3.2 Borehole location deviation requirements are as follows:

(1) Location error of exploration point: On the land, the location deviation shall

not be greater than 0.1m;

(2) The elevation deviation of ground orifices of exploration points: On the

land, it shall not be greater than 0.01m;

page 21 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

(3) After the exploration is completed, the location and elevation of the

exploration points shall be re-surveyed and recorded.

3.3.3 The process of borehole location survey and setting out

In this project, GPS-RTK is used to survey and set out the borehole location.

The process is as follows:

(1) Inspection of survey instruments: check whether the identification

certificate of GPS-RTK is expired, whether the accuracy of the instrument meets the

needs of the project, and whether all parts of the instrument are complete;

(2) Handover of site control points: before point location survey, BUCG’s

survey engineer shall receive the coordinates and elevation of control points of the

project provided by CAAB, and complete the handover procedures.

(3) Recheck of on-site control points: after the handover of control points,

recheck the control points provided by CAAB with GPS and total station

respectively in order to check whether there is an error and whether the error

accuracy meets the engineering requirements.

(4) Establishment of engineering coordinate system: when the recheck results

of control points meet the engineering requirements, the new coordinate system of

the project shall be built in GPS with setting parameters. And the coordinates shall

be corrected by transforming the parameters.

(5) On-site survey and set out: the coordinate of each survey point shall be

imported into the GPS survey map by computer. Survey and set out the points on

each road, and make temporary marks.

(6) Point recheck: after the completion of the point survey and setting out,

some points shall be selected for recheck. When all of them are qualified, the point

survey and setting out shall be considered as correct.

(7) Point mark: after points location is confirmed, record shall be made timely.

page 22 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Figure 5-12 Survey and setting out exploration points

3.3.4 Elevation survey

GPS is used for the elevation survey,

(1) Survey requirements:

① After the completion of drilling, inform the survey team to measure the

elevation of the orifice in time, so as to prevent the survey accuracy from being

affected by back filling of the borehole;

② At least two leveling points are required. The two points shall be rechecked

mutually before survey, and they shall be adopted only when the accuracy meets the

requirements;

③ During elevation survey, GPS shall be placed at the orifice for at least 1

minute under the fixed solution state, and the elevation data shall be saved after the

elevation data is stable;

④ The preserved elevation data shall be exported in time, and the “Orifice

elevation survey table” shall be filled in.

page 23 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

3.3.5 Survey of underground water level

The water level shall be measured by using a heavy hammer and steel

measuring rope. Before measurement, the steel measuring rope shall be calibrated to

ensure that its error meets requirements of the specification and its calibration is

accurate.

The initial water level and the static water level shall be measured 24 hours

after the drilling of each borehole, the readings shall be measured to centimeters

(cm), and the accuracy shall not be less than ± 2cm.

3.4 Drilling and sampling

3.4.1 Drilling

(1) Field drilling

The BWQ160 drilling rig with 146mm diameter casing and mud protection

alloy drilling tool shall be used for drilling. And the bore diameter of the drilling

shall not be less than 110mm.

After the exploration point is confirmed, the drilling work shall be conducted.

For dry drilling above the groundwater level, the footage per round trip shall not be

greater than 1.5m, and shall not be greater than the length of the core tube. During

the drilling process and shall not be longer than the length of core pipe. All depth

data shall be measured and obtained, and the cumulative allowable error of

measurement is ± 5cm. Other matters not covered herein shall follow the Standard

Practice for Rock Core Drilling and Sampling of Rock for Site Exploration (ASTM

D2113-2014).

The technical requirements are as follows:

① The drilling rig shall be placed stably and reliably. The drilling tool shall be

kept vertical during drilling, and the drilling verticality shall be less than 1%.

② The measurement error range of drilling depth and depth of rock and soil

layer shall be ± 0.05m.

③ The footage per round trip of discontinuous coring drilling shall not be

page 24 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

greater than 1m in the sand.

④ The core recovery rate shall reach 80% and meet the needs of formation

stratification and description.

⑤ The drilling records shall be true and timely, and shall be filled in section by

section according to the drilling round trip. It is strictly forbidden to record after the

event. Common identification methods can be used for site description, such as

naked-eye identification, hand touching, etc.

⑥ The core of rock and soil shall be arranged in order on the flat ground

which does not affect the drilling construction.

⑦ The initial water level shall be recorded during drilling, and the stable

groundwater level shall be measured 24 hours after the completion of drilling. The

influence of mud in the borehole shall be eliminated in groundwater level

measurement.

⑧ Take photos of all the cores taken out, and take photos after each core box

is filled with rock cores. Colored strip colorimetric cards shall be attached when

taking photos, to identify the core color more accurately.

(2) Site recording

The soil (rock) samples shall be described on time to form detailed field

drilling records. Each column of the drilling record sheet shall be filled in the item

by item according to the drilling round trip. When finding layer change in each

round trip, it shall be filled in separately. Several round trips or several layers shall

not be combined into one record. Field records shall not be transcribed or altered but

can be corrected if necessary. The correction adopts the method of division and

modification, and the original content and the changed content can be identified

after the modification. After the description of each exploration borehole is

completed, the cataloger shall carry out self-inspection according to the core placed,

and sign on the corresponding responsibility column after confirmation.

The contents of drilling records shall be in accordance with Chapter 11 of

page 25 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

ASTM D2113-14, Standard Practice for Rock Core Drilling and Sampling of Rock

for Site Exploration.

(3) Borehole acceptance

The results of single borehole drilling shall include the following contents:

Project name, serial number of borehole, borehole diameter, starting and ending

depth of per round trip, footage per round trip, depth and description of formation

stratification, initial water level and stable water level, sampling depth and sampler

type (including soil (rock) sample type, soil (rock) sample length, serial number,

etc.), and other relevant information.

When drilling to the specified depth, the technical personnel shall check the

drilling depth and analyze the formation. When meeting the final borehole

requirements, the drilling shall be finished.

After all the boreholes are accepted and the stable groundwater level is

measured, the sand shall be used for backfilling.

Figure 5-13 Drilling construction

3.4.2 Sampling

(1) Take an undisturbed soil sample

The undisturbed soil sample location is set according to the drilling boreholes

arranged and the expected stratum conditions. Undisturbed samples shall be taken

from cohesive soil and silt at a depth of 3.0 m starting from 1.0 m below the existing

ground surface. After the undisturbed samples are taken, the standard penetration

page 26 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

distance is 1.5m. The first standard penetration test disturbed samples are not taken,

and the second standard penetration test takes disturbed samples. At the second

sampling location, the standard penetration test and sampling work were carried out

according to the above principles.

After the undisturbed soil sample is taken out, the technician (cataloger) shall

inspect the quality of the soil sample. If it meets the requirements, it shall be

packaged and marked in time; if it does not meet the requirements, it shall be taken

again by the driller. The packaged soil samples shall be properly preserved. All

undisturbed samples shall be sent to the designated laboratory within 24 hours. The

storage time from the soil samples taken to the laboratory before the soil opening

test shall not exceed two weeks.

The undisturbed soil samples shall be taken by different soil samplers

according to different formations, including piston sampler, thin-wall sampler, and

sand sampler. The relevant requirements of ASTM D2113-14 and D1587/D1587-15

shall be strictly implemented in the sampling process.

When undisturbed soil samples need to be taken from a silt stratum or silty clay

layer blows during drilling, piston sampler shall be used to take soil by static

pressure or hammering. The diameter of the soil sample taken shall be 104mm and

the length of the soil sample shall be 200mm.

Figure 5-14 U100 sampling Figure 5-15 U104 sampling


(2) Take disturbed samples

For each standard penetration test(SPT), disturbed samples shall be taken from

page 27 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

the soil samples in the open pipe. Meanwhile, disturbed soil samples shall be taken

from the sand layer in the sampling borehole, and representative sand samples shall

be taken from each borehole according to the layer.

(3) Taking groundwater samples

① Groundwater samples shall be taken from suitable boreholes, private wells,

and other groundwater dew points. Mud is not allowed to be used in drilling in order

to eliminate the influence of mud on water quality;

② Representative channels and rivers shall be selected for surface water

samples, and the sampling depth shall be controlled at 0.3m below the water surface;

③ Plastic bottles shall be used for water container. Before sampling, the

plastic bottles shall be washed first with potassium permanganate solution, then with

pure water, and rinsed with the water sample for more than three times; a space of

10 mm-20 mm shall be left on the top of the plastic bucket when taking water

samples; the quantity of water samples collected shall be 1000 ml-1500 ml/piece;

④ For water samples of corrosive carbon-dioxide, the appropriate amount of

marble powder shall be added to the water samples, so as to prevent the precipitation

of carbon-dioxide after taking out the sample;

⑤ After the water sample is taken, it shall be sealed with wax immediately,

labeled with the water sample, and sent to the laboratory for analysis and test. The

storage time shall not exceed 72 hours.

(4) Investigation of groundwater

According to the engineering requirements, the following hydrogeological

conditions shall be mastered through data collection and investigation;

① The type and occurrence state of groundwater;

② The distribution law of main aquifers;

③ Regional climate data, such as annual precipitation, annual evaporation, and

their changes as well as their impact on groundwater level;

④ The recharge and discharge conditions of groundwater, the recharge and

page 28 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

discharge relationship between surface water and groundwater, and their impact on

groundwater level;

⑤ Groundwater level during the investigation, highest groundwater level, on

records, highest groundwater level in recent 3-5 years, trend of water level variation

and its main influencing factors;

⑥ Whether there are pollution sources of groundwater and surface water, and

the possible pollution degree.

The initial water level and stable water level can be directly measured by

measuring rope in the borehole. The interval time of measuring stable water level

shall be determined according to the permeability of the stratum. It shall not be less

than 0.5h for sandy soil and 8h for silty soil and cohesive soil. The stable water level

shall be measured uniformly after the investigation. Measure the reading to cm with

an accuracy of not less than ± 2cm.

The measurement accuracy of groundwater level shall be defined as ± 2cm,

which refers to the limitation of the total error caused by measuring tools and

observation, so the measuring tools shall be calibrated regularly with a steel ruler.

3.5 In-situ testing

The in-situ test to be used in this investigation include the standard penetration

test (SPT) and wave velocity test.

3.5.1 Standard penetration test

In order to obtain the change of soil compaction along the depth direction and

evaluate the seismic liquefaction, the standard penetration test shall be carried out in

the standard penetration borehole. According to the requirements of Standard Test

Method for Penetration Test and Split-Barrel Sampling of Soils ASTM

D1586/D1586-18, the borehole diameter shall be between 56 mm to 162mm. The

test shall start from 2.5 to 3.5m below the ground, and the test spacing shall be 1.5m.

The test spacing shall be reduced in the thin soil layer, in order to ensure that the

layer has in-situ test data. For the stratum with the stable spatial distribution and

page 29 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

large thickness in the lower part, the test spacing can be appropriately increased or

controlled according to layer. The main technical requirements are as follows:

(1) The equipment of standard penetration test shall meet the requirements of

table 5-3
Specification requirement for standard penetration test equipment s Table 5-3
Hammer quality (kg) 63.5±1
Hammer
Drop distance (cm) 76±2.5
Length (mm) 457~762
Split-Barrel Sampler Inner diameter (mm) 50.8±1.3-0
Outer diameter (mm) 38.1±1.3-0
Length (mm) 25~50
Pipe boot Edge angle (°) 16~23
Single blade thickness (mm) 2.54±0.25
Rigidity ≥ “a” drill pipe
Drill pipe Diameter (mm) (outer diameter 41.2, inner
diameter 28.5)
Note: the relative bending of drill pipe shall be less than 1 ‰.
(2) The standard penetration test borehole shall be taken by rotary drilling and

keeps the water level in it slightly higher than the groundwater level. When the

borehole wall is unstable, the slurry can be used to protect the wall. When drill to

15cm above the test elevation, remove the residual soil at the bottom of the borehole

and then carry out the test;

(3) The free-drop method with automatic decoupling shall be adopted for

hammering. This method can reduce the friction resistance between the guide rod

and the hammer, so as to avoid eccentricity and lateral shaking during hammering. It

also can maintain the perpendicularity of the connection of the penetrometer, probe

rod and guide rod. The hammering rate shall be less than 30 blows/min;

(4) The penetrometer shall be continuously driven into 45cm in the drawing

and be counted in three sections. The actual hammering numbers shall be recorded

after each 15cm penetration. The cumulative hammering numbers of 30cm in the

last two times is the hammering number N of standard penetration test. The test can

be terminated when any of the following conditions are met.

① The actual hammering number of any 15cm penetration reaches 50;

page 30 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

② The total hammers number reaches 100;

③ After hammering ten times consecutively, the penetrometer does not

penetrate.

When the standard of terminating test is reached without 45 cm penetration, the

actual hammering number of each completed 15 cm penetration and the hammering

number of partial penetration at penetration depth shall be recorded in the borehole

log. For partial penetration, the penetration depth shall be recorded to the nearest

2.5cm.

(5) Sampling requirements of standard penetrometer: lift the standard

penetrometer to the ground and open it. Record the recovery rate or the length of the

sample, describe the composition, color, stratification, and conditions of the soil

sample. Then place one or more samples in a sealed moisture-proof container (tank),

which shall be sealed to prevent evaporation of soil moisture. Label the container

with the project name, serial number of the borehole, sampling depth, and 15cm

hammering number. If there is soil layer change in the sample, separately take

samples from each layer of soil, and record the position of the layer change.

Figure 5-16 Standard penetration test

3.5.2 Wave velocity test

According to the value of shear wave velocity of each rock and soil layer, the

soil type of the site shall be determined; the equivalent shear wave velocity shall be

calculated, judge the site category, and provide various dynamic parameters of rock

page 31 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

and soil.

Figure 5-17 Wave velocity test device


(1) Device composition

① The vibration source and vibration source of shear wave source. The device

is required to be with polarization and be capable of generating dominant SH wave.

And it shall have the vibration source with reversibility, good repetitiveness and

sufficient energy. The method of striking plate shall be adopted this time;

② Three component detector;

③ Signal acquisition analyzer.

(2) Test key points

The technical requirements of the wave velocity test:

① The test borehole shall be vertical;

②The three-component detector shall be fixed at the predetermined depth in

the borehole and attached to the borehole wall;

③ Ground vibration or borehole vibration can be used;

④ The measuring points shall be arranged according to the soil layer, and the

vertical spacing of the measuring points shall be 1 m. The position where layer

changes shall be encrypted, and test them point by point according to the sequence

from bottom to top.

(3) Site layout:

page 32 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

① Boreholes shall be drilled at the designated test site, and the

perpendicularity requirements are the same as those for general exploration

boreholes. The vibration device shall be arranged 1-1.5m away from the orifice. It

testing the borehole inclination, PVC casing shall be set in the borehole. There are

four notches in the casing for inclinometer to move along the notch.

② If the measured soil layer is not thick and hard, or the borehole will not

collapse after the mud wall protection, the drilling rig can be removed before the test,

otherwise, the drilling rig shall be left on the borehole location for standby.

③ If the detector in the borehole does not have a fixed device on the borehole

wall, the drilling rig shall be need for assistance.

(4) Test procedure:

① Switch on the power. The test can be carried out after the tester is normal on

the ground.

② Put the three-component detector into the borehole at the predetermined

depth of the test point. Then the capsule shall be inflated on the ground with a pump

and be expanded to make the three-component detector attach to the hole wall.

③ After striking one end of the vibration plate horizontally with a wooden

hammer or a hammer, the shear wave generated on the surface shall propagates

through the stratum. And the SH signal wave shall be received by the horizontal

detector of the three-component detector in the borehole. The signal shall be sent to

the seismograph through the cable for amplification and recording. The test requires

that the seismograph shall obtain clear recording wave forms for three times. Then

knock the board in the reverse direction until obtain clear wave forms for three times

in the same way. After the test at this SH wave is completed, the steel plate placed

on the surface shall be knocked with a heavy hammer. And the generated P-wave

shall be recorded by the three-component vertical detector in the borehole. It is also

required to obtain clear P-wave wave forms for three times. After the data is saved

correctly, the test of the drilling depth at this point shall be completed.

page 33 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

④ Release gas from the capsule, transfer the three-component detector in the

borehole to the depth of the next test point. Repeat the above test steps until the

drilling depth requirements are met.

⑤ After finishing the whole borehole test, check whether the field test record

is complete.

(5) The following aspects shall be paid attention to in the process of in-situ

survey of soil shear wave velocity

① The main purpose of this investigation is to recheck the basic information

completed before, such as the general stratum structure and overburden thickness.

Therefore, the exploration borehole for measuring the shear wave velocity of the soil

layer may not need to pass through the overburden layer during wave velocity test;

② In the field survey, the borehole of shear wave velocity test shall be selected

as far as possible in the vicinity of the borehole without obstacles affecting the

artificial wave propagation.

③ In the depth range of wave velocity test, if the wall is protected by casing,

the whole process of casing shall be followed up as far as possible to ensure that the

casing is in close contact with the soil layer; if the wall is protected by mud, the

proportion of mud shall be as small as possible;

④ In principle, the data of the wave velocity test shall be collected at the

change layer of formation, and the data shall be collected per meter.

Figure 5-18 Wave velocity test Figure 5-19 Acquisition of wave velocity data

page 34 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

3.6 Geotechnical test

The test method shall comply with the relevant test method standards under

THE ASTM D system. The person in charge of the test shall first check and accept

the rock (soil) samples sent from the construction site. If the label content of the

rock (soil) sample is not complete, or the label is not clear and can not be recognized,

and the serial number and depth of soil sample are inconsistent with the project list,

these samples shall not be accepted until make clear. The drilling team shall take

sample again, or arrange them and send it to the laboratory again.

Before the test, the person in charge of the test shall clarify the requirements,

items and methods of the test to the tester; the test instrument shall be calibrated.

The test director shall check the preparation of the sample to ensure that the sample

meets the specified requirements, and the mechanical property test shall not be

conducted for cracked or squeezed soil. After the preparation of undisturbed soil

samples and disturbed samples that need to maintain natural humidity, they shall be

placed in the soil sample storage box if they can not be tested immediately, .

The person in charge of the test shall check and accept the test results of each

item, and the test shall be conducted again if any abnormality is found. The test

reviewer shall recheck the test results and sign after the check.

Ⅵ. Results submission
The technical director shall organize the technical personnel to sort out, analyze

and calculate the original records, in-situ test data, test final report, chart of wave

velocity test results and others, and to draw various maps, and to prepare Sub-Soil

investigation report according to relevant regulations and standards. All kinds of

results maps, outcome documents and investigation reports shall be checked by the

checker, submitted to the auditor for review, and finally approved by the chief

engineer. After the investigation report is reviewed at three levels, the technical

director shall modify it according to the audit opinions of all levels, and then submit

it to CAAB and BUCG for review after being reconfirmed by all the auditors at all

page 35 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

levels. The main contents of ground Investigation report are as follows:

According to the relevant standards and specifications under the current

American standard system, the final report shall be divided into two parts: Ground

Investigation Report and Geotechnical Design Report. The main contents of each

part are as follows:

1. Ground Investigation Report

1. Project introduction

2. Scope of work

3. Site description

4. Field investigation and in-situ test

5. Laboratory test

6. Site conditions, geological environment, and geological chart information

7. Summary of geological conditions and geological profile

8. Conclusions and recommendations

8.1 Overview

8.1.1 Geotechnical types of foundation

8.1.2 Geotechnical properties

8.2 Groundwater conditions and observation results

8.3 Special topics

8.4 Chemical analysis

9. Reference

Appendix

A Borehole layout and geological profile

B Borehole histogram and core picture

C In-situ test

D Laboratory test

E Relevant information collected

F Chart

page 36 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

2. Geotechnical Design Report

1. Project introduction

1.1 Project description (including equipment description, load standard, and

requirements)

1.2 Scope of work

2. Geology

2.1 Regional geology

2.2 Site geology

3. Geotechnical information collected

4. Investigation procedure

4.1 Investigation process

4.2 Laboratory test

5. Geological conditions

5.1 Topographic map

5.2 Geological map

5.3 Geotechnical characteristics

5.4 Groundwater characteristics

6. Suggestions for foundation

6.1 Foundations Design

6.2 Design parameters of pile foundation

6.3 Estimation of bearing capacity of single pile foundation

6.4 Pile forming possibility analysis

7. Scheme and suggestions of foundation pit excavation and support

8. Earthquake

8.1 Seismicity

8.2 Seismic hazard criteria

8.3 Liquefaction

9. Construction suggestions

page 37 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Attachments

References

Chart

Appendix

A Drill borehole histogram

B Laboratory test results

C Geological information collected

Ⅶ. Quality assurance measures


1. Quality objectives

The investigation quality objectives of the project are: the products shall meet

the requirements of specifications, regulations, and contracts; the data shall be true

and accurate; the report shall be objective, true and fair.

2. Quality assurance system

The project shall form a pyramid quality assurance system with the project

leader as the first responsible person, the project technical director, quality inspector,

on-site technical personnel, and team quality controller as the main responsible

personnel. The diagram of the quality assurance system is shown in the figure below.

page 38 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

Management departmen of investigation project

Technical director
Quality inspector

Production Management Technical quality HSE General management


department department department department

Measurem Drilling In-situ test Geotechni Report


ent group group group cal test preparation
group group

Quality assessment standard

Figure 7-1 Quality assurance system


3. Quality assurance measures

3.1 Training system

(1) Training content

① Relevant local laws and regulations of Bangladesh, relevant provisions of

CAAB, and production management system of the project department;

② Current regulations, specifications, standards, and implementation rules;

③ Job skills and process standards;

④ Safety operation procedures and system training;

(2) Training plan

All construction personnel participating in the project shall receive pre-job

training after entering the construction site; Post-transfer and new entrants shall

receive induction training. Different training shall be carried out for different posts,

and the project management department shall make training plans according to the

company’s requirements.

3.2 Quality management system

page 39 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

(1) Establish quality monitoring system of project

The technical quality Department shall be responsible for organizing inspection

and spot check; the technical supervisor shall monitor the key links; and the quality

supervisor shall be responsible for the specific monitoring work of each link.

(2) Preparation and approval system of technical scheme

All technical schemes shall be subject to second-level audit before

implementation. The investigation technical schemes shall be approved in the order

of “preparation by technical director, approval by the professional chief engineer,

approval by the chief engineer of the institute”.

(3) Joint review system

Before the commencement of the project, the technology and quality

department shall organize the expert advisory group, quality supervisor, professional

leader, and all technical personnel to conduct a joint review of the investigation

outline of the project; raise questions to deepen and refine the technical scheme;

clarify what to do and how to do, especially pointing out the key points and

difficulties. In this way, pre-control work shall be done well, so as to eliminate the

hidden dangers at an early stage.

(4) Technical disclosure system

CAAB shall make technical disclosure to all field operators (captains),

descriptors and testers, so as to make them understand the technical requirements,

process flow, quality standards, safety measures, etc.

(5) Review and approval system of outcome document

The outcome document (investigation report) shall reflect the objective law of

the site area, including complete parameters, sufficient basis, concise words, clear

and beautiful drawings, appropriate and reasonable suggestions and accurate

conclusions.

(6) Quality acceptance system

The central idea of the quality assurance system for geotechnical engineering

page 40 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

investigation of our company is process control, that is, to check and accept the

quality of every link in the investigation, and to control the investigation quality of

the whole project by controlling the quality of each process. Quality acceptance is an

important means of process control.

① After the completion of every single project such as field test of borehole,

the supervisor shall inform relevant personnel for quality acceptance. The site

records shall include the signature and quality evaluation opinions of technical

director, descriptors and quality inspectors.

② For the indoor test, sample specification and test process shall meet the

requirements of specifications and standards. The submitted outcomes require

accurate data and reliable results.

③ The investigation results shall be submitted only after being reviewed and

accepted by the technical director, checker, reviewer, and approval personnel.

Ⅷ. Investigation programme
According to the requirements of the overall project programme, combined

with the characteristics of local engineering projects and site conditions in

Bangladesh, it is planned to obtain approval from CAAB within 36 days from the

submission date of the proposal. The field investigation shall be accomplished

within 90 days. All reports shall be scheduled for submission and approval within

164 days. The whole work of sub-soil investigation shall be completed within 225

days.

For detail information, see the Attachment 3 “Bar Chat of Investigation

Schedule”.

Ⅸ. Environmental protection objectives


The environmental management objectives of the project are as follows:

① Reduce waste; reduce the consumption of resources and energy; reduce and

eliminate the pollutants released to the environment.

page 41 of 42
SUB-SOIL INVESTIGATION IMPLEMENTATION PROPOSAL

② Control the environmental impact caused by raw materials and minimize

the harmful environmental impact during production.

③ The environmental protection indexes of the construction site shall meet the

local standards, and the general environmental pollution accidents shall not occur.

④ Reduce the impact of night noise on the surrounding residents.

⑤ Reduce harmful environmental impact; improve benefits and reduce costs.

⑥ Establish an effective and credible environmental management system

which can identify environmental factors and evaluate major environmental factors.

Attachments

Attachment 1. Proposed Sub-Soil Investigation Plan

Attachment 2. List of Boreholes

Attachment 3. Bar Chart of Investigation Schedule

page 42 of 42
List of Investigation Boreholes
G.I.STATION COORDINATE (m) DEPTH ADDITIONAL
NO. EASTING NORTHING (m) TESTING
BH-001 384620.71 2761460.643 35
BH-002 384649.436 2761448.355 45
BH-003 384628.293 2761442.683 45 DS
BH-004 384600.604 2761439.794 45
BH-005 384638.611 2761423.318 35
BH-006 384685.148 2761431.036 35
BH-007 384702.665 2761409.597 45 DS
BH-008 384730.103 2761411.541 35
BH-009 384774.395 2761408.865 35
BH-010 384791.459 2761401.193 35
BH-011 384776.062 2761387.687 45 DS
BH-012 384759.742 2761375.326 35
BH-013 384776.898 2761367.887 35
BH-014 384655.246 2761391.865 45
BH-015 384683.104 2761379.785 35
BH-016 384710.935 2761367.716 45
BH-017 384643.041 2761363.992 35
BH-018 384670.916 2761351.716 45 DS
BH-019 384698.721 2761339.55 35
BH-020 385480.734 2761673.515 45
BH-021 385507.253 2761661.525 35
BH-022 385534.031 2761650.131 45
BH-023 385560.808 2761638.737 35
BH-024 385470.311 2761649.478 35
BH-025 385497.009 2761637.9 45 DS
BH-026 385523.707 2761626.323 35
BH-027 385550.404 2761614.746 45
BH-028 385088.558 2761120.555 45
BH-029 385105.617 2761113.157 35
BH-030 385080.911 2761102.92 35
BH-031 385098.115 2761095.463 45 DS
BH-032 385072.147 2761082.71 45
BH-033 385089.206 2761075.313 35
BH-034 385128.154 2761115.18 45
BH-035 385153.636 2761104.13 35 DS
BH-036 385179.21 2761093.04 45
BH-037 385204.784 2761081.95 35
BH-038 385230.358 2761070.86 45
BH-039 385119.827 2761096.229 35
BH-040 385145.292 2761085.077 55
BH-041 385170.889 2761073.977 45
BH-042 385196.509 2761062.867 55 DS
BH-043 385222.123 2761051.869 35
BH-044 385111.512 2761077.054 45
BH-045 385137.086 2761065.964 35 DS
BH-046 385162.822 2761054.803 55
BH-047 385188.394 2761043.714 35
BH-048 385213.899 2761032.654 45
BH-049 385103.197 2761057.879 35

第 1 页,共 4 页
List of Investigation Boreholes
G.I.STATION COORDINATE (m) DEPTH ADDITIONAL
NO. EASTING NORTHING (m) TESTING
BH-050 385128.811 2761046.881 45
BH-051 385154.345 2761035.699 35
BH-052 385179.958 2761024.701 45 DS
BH-053 385205.493 2761013.628 35
BH-054 385258.627 2761065.795 45
BH-055 385286.149 2761053.861 35
BH-056 385313.672 2761041.925 45
BH-057 385341.198 2761029.989 35
BH-058 385368.119 2761018.097 45 DS
BH-059 385395.208 2761006.568 35
BH-060 385422.218 2760994.855 45
BH-061 385449.228 2760983.142 35
BH-062 385476.238 2760971.43 45
BH-063 385503.247 2760959.717 35
BH-064 385530.257 2760948.005 45 DS
BH-065 385556.858 2760936.129 35
BH-066 385274.7085 2761090.137 45
BH-067 385324.538 2761068.926 35
BH-068 385253.176 2761053.225 35
BH-069 385280.699 2761041.289 45
BH-070 385308.221 2761029.355 35
BH-071 385330.184 2761004.733 45
BH-072 385357.25 2760993.027 35
BH-073 385384.867 2760981.051 55
BH-074 385411.282 2760969.637 35
BH-075 385438.28 2760957.897 55 DS
BH-076 385465.478 2760946.04 35
BH-077 385492.277 2760934.419 55
BH-078 385519.287 2760922.706 35
BH-079 385546.012 2760911.117 45
BH-080 385365.6925 2761050.94 45
BH-081 385406.8701 2761033.084 35
BH-082 385319.7935 2760980.63 35
BH-083 385346.782 2760968.927 45
BH-084 385372.768 2760957.658 35
BH-085 385400.834 2760945.542 45 DS
BH-086 385427.778 2760933.803 35
BH-087 385454.833 2760922.071 45 DS
BH-088 385481.843 2760910.358 35
BH-089 385508.853 2760898.646 45
BH-090 385535.578 2760887.056 35
BH-091 385309.268 2760954.348 45 DS
BH-092 385335.833 2760943.702 35
BH-093 385363.172 2760931.847 45
BH-094 385390.154 2760920.146 35
BH-095 385416.641 2760908.876 45
BH-096 385443.486 2760896.692 35
BH-097 385470.594 2760884.937 45
BH-098 385497.871 2760873.259 35

第 2 页,共 4 页
List of Investigation Boreholes
G.I.STATION COORDINATE (m) DEPTH ADDITIONAL
NO. EASTING NORTHING (m) TESTING
BH-099 385523.952 2760861.252 45 DS
BH-100 385642.486 2760899.337 60
BH-101 385662.081 2760896.845 70 DS
BH-102 385673.688 2760885.807 60
BH-103 385637.0748 2760886.86 40
BH-104 385653.221 2760877.795 60
BH-105 385666.736 2760871.076 40
BH-106 385608.008 2760879.424 45
BH-107 385633.568 2760870.629 35
BH-108 385658.098 2760860.21 45
BH-109 385601.523 2760864.47 35
BH-110 385626.16 2760853.922 55 DS
BH-111 385649.997 2760842.032 35
BH-112 385671.395 2761270.995 20
BH-113 385646.455 2761214.254 20
BH-114 385278.989 2761290.126 20
BH-115 385348.411 2761260.022 20
BH-116 385399.408 2761242.252 20
BH-117 385440.906 2761224.257 20
BH-118 385482.088 2761206.398 20
BH-119 385531.772 2761184.853 20
BH-120 385597.671 2761156.244 20
BH-121 385657.304 2761130.384 20
BH-122 385716.938 2761104.524 20
BH-123 385776.494 2761078.484 20
BH-124 385836.219 2761052.832 20
BH-125 385895.861 2761026.991 20
BH-126 385955.429 2761000.977 20
BH-127 386026.8879 2760998.941 20
BH-128 386093.8304 2760966.954 20
BH-129 386143.6659 2760926.372 20
BH-130 386039.8383 2761123.458 20
BH-131 386098.1778 2761056.695 20
BH-132 386132.1758 2760993.797 20
BH-133 386176.4421 2760951.145 20
BH-134 386207.7926 2760898.001 20
BH-135 386256.3731 2761018.197 20
BH-136 386246.7201 2760970.405 20
BH-137 385456.5239 2761011.506 45
BH-138 385522.4112 2760982.875 35
BH-139 386186.4679 2760853.3 20
BH-140 386121.9884 2760881.541 20
BH-141 Delete
BH-142 Delete
BH-143 385567.446 2761086.545 20
BH-144 385501.467 2761115.157 20
BH-145 385451.813 2761136.689 20
BH-146 385410.424 2761154.643 20
BH-147 385369.172 2761172.526 20

第 3 页,共 4 页
List of Investigation Boreholes
G.I.STATION COORDINATE (m) DEPTH ADDITIONAL
NO. EASTING NORTHING (m) TESTING
BH-148 385320.208 2761194.093 20
BH-149 385250.338 2761224.057 20
BH-150 385176.6663 2761131.061 20
BH-151 385236.5331 2761150.339 20
BH-152 385323.1133 2761118.271 20
BH-153 385384.007 2761093.047 20
BH-154 385424.895 2761074.509 20
BH-155 385474.384 2761052.703 20
BH-156 385540.364 2761024.092 20

第 4 页,共 4 页
Attachment 3. Bar Chart of Investigation Schedule
Items Plan 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180
Preparation for plan 10 days
(1)Review and Comment by CAAB 5 days
(2)Review and Submission 4 days
(3)Obtain Approval from CAAB 1 days
Geological Survey Work 120 days
(1)Main Equipment Ready 20 days
(2)Verification and Calibration 15 days
(3)Setting Out and Measurement 5 days
(4)Drilling and Testing Outside 70 days
(5)Indoor Testing 80 days
Confirmation of Report 45 days
(1)Preparation and Submission 21 days
(2)Review and Comment by CAAB 7 days
(3)Revision and Submission 14 days
(6)Obtain Approval from CAAB 3 days

You might also like