: DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
Project Title Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq
Contract No FGP/C-07
AT STA.54+000~STA.61+000
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 1 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
CONTENTS
1. Purpose..........................................................................................................................................4
2. Mock-up date and location...........................................................................................................4
3. Attendees........................................................................................................................................5
4. Equipment.....................................................................................................................................5
5. Material..........................................................................................................................................5
6. Sample & Field Test Plan.............................................................................................................6
7. Mock-up Test.................................................................................................................................7
8. Result of Existing Soil Test.........................................................................................................13
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 2 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
FIGURE OF CONTENTS
TABLE OF CONTENTS
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 3 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
1. Purpose
The purpose of Mock-up of Trafficability Layer is as followings:
1) Determination of the height of the trafficability layer(for trafficability of 60 ton dump
trailer) and the optimal Roller compaction count through mock-up testing with approved
materials that meet the Requirement by Material Specification And Employer’s
Requirements-Volume 2 as per point 4.3.2 of Section 2 : Roads specifications
2) It is possible to calculate the thickness of the trafficability layer to withstand earthmoving
heavy equipments like dump trailer.
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 4 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
3. Attendees
1) Client
2) Supervision Consultant
3) Construction Contractor
① Project Manager
② Site Engineer
③ Construction Manager
④ QA/QC Manager
4. Equipment
Below equipment will be used in this mock-up test.
< Table 1> Equipment list
Item Spec Quantity Remark
Excavator 2.3 m3 1 Loading
Wheel Loader 4m3 1 Loading
Roller 18.5ton 1 Compaction
Water Truck 20KL 1 watering
Dump Trailer 60ton 1 Transportation
Dozer 38.5ton 1 pushing
5. Material
1) Material Type
The materials to be used during the mock-up test will use Silty Sandy Soil that meet the
approved material specifications.
2) Material Source
- Quantities
: 118,800 m3
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 5 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
: 180,000 m3
- Pond : 27m x 0.7m x 4,500m x 2 = 170,100 m3
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 6 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
7. Mock-up Test
2) Sequence for Determination of trafficability layer height and optimal number of roller
counts(Purpose 1)
The following sequence as shown to determine the height of trafficability and the optimal
number of compactions. The sequence below shows the types of tests and location to be
performed in each of the three section. The levels indicated in Fig4 are before compaction.
After the compaction by 13%, i.e, 0.6m, 0.9m and 1.2m.(loose material thickness 0.68m,
1.02m, 1.36m)
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 7 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
- Sequence 2: Compaction with vibration and test each section (60cm Height Layer)
- Sequence 3: Compaction with vibration and test each section (90cm height Layer)
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 8 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
Note : The test will be executed on demand at different level in the thickness(body) of the level
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 9 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
- Sequence 4: Compaction with vibration and test each section (1.2m Height Layer)
Note : The test will be executed on demand at different level in the thickness(body) of the level
- Summary of number of tests
Description SECTION 1(H=0.6m) SECTION2(H=0.9m) SECTION3(H=1.2m) NRI
1.Check elevation No. 1 1 1 Survey
2.Trafficability test No. 1 1 1 Survey
Phase 1
3.Field CBR No. 2 2 2 Test
(Top layer)
4.Field Density No. 2 2 2 Test
5.Plate Load Test No. 2 2 2 Test
1.Check elevation No. - 1 2 Survey
Phase 2
2.Field CBR No. - 2 4 Test
(Deep test)
3.Field Density No. - 2 4 Test
SUM 8 13 18
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 10 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
③ Watering
Water Tank will pour proper water for the better compaction.
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 11 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
④ Compaction
Layer will be compacted by Vibration Roller.
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 12 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000
Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 13 of 13