You are on page 1of 13

Doc. No.

: DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

Project Title Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq
Contract No FGP/C-07

Employer General Company for Ports of Iraq


Engineer Technital S.p.A
Contractor Daewoo E&C

Method Statement for Trafficability Mock Up Test

AT STA.54+000~STA.61+000

Document No. : DWAU-MS-012


REV DATE REASON FOR ISSUE PREP’D REV’D APR’D

0 25 Sep. 2022 Issue For Approval SH SO GB KONG K.H.Paik

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 1 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

CONTENTS

1. Purpose..........................................................................................................................................4
2. Mock-up date and location...........................................................................................................4
3. Attendees........................................................................................................................................5
4. Equipment.....................................................................................................................................5
5. Material..........................................................................................................................................5
6. Sample & Field Test Plan.............................................................................................................6
7. Mock-up Test.................................................................................................................................7
8. Result of Existing Soil Test.........................................................................................................13

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 2 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

FIGURE OF CONTENTS

<Fig. 1> Location of mockup test...............................................................................................4


<Fig. 2> Cross section of available sandy soil..............................................................................6
<Fig. 3> Layout of the Mockup test............................................................................................7
<Fig. 4> Pouring materials on each Section.................................................................................7
<Fig. 5> Summary of Sequence 2(30cm Height Layer).................................................................8
<Fig. 6> Summary of Sequence 3(60cm height Layer)..................................................................9
<Fig. 7> Summary of Sequence 4(90m Height Layer).................................................................10
<Fig. 8> Construction method (Dumping).................................................................................11
<Fig. 9> Construction method (Pouring and pushing).................................................................11
<Fig. 10> Construction method (Watering)................................................................................11
<Fig. 11> Construction method (Compaction)...........................................................................12

TABLE OF CONTENTS

< Table 1> Equipment list..........................................................................................................5


< Table 2> Number of tests on each Section..............................................................................11

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 3 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

1. Purpose
The purpose of Mock-up of Trafficability Layer is as followings:
1) Determination of the height of the trafficability layer(for trafficability of 60 ton dump
trailer) and the optimal Roller compaction count through mock-up testing with approved
materials that meet the Requirement by Material Specification And Employer’s
Requirements-Volume 2 as per point 4.3.2 of Section 2 : Roads specifications
2) It is possible to calculate the thickness of the trafficability layer to withstand earthmoving
heavy equipments like dump trailer.

2. Mock-up date and location


1) Mock up date :
① STA. 54+000 : 1th Oct to 10th Oct
② STA. 56+500 : As per construction schedule
2) Mock-up location( Accessible points)
① Fourth Mock-up point is the immersed tunnel west (STA. 54+000)
② Fifth Mock-up point is the low water level (STA. 56+500)
③ It has been zoning as below.

<Fig. 1> Location of mockup test

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 4 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

3. Attendees
1) Client
2) Supervision Consultant
3) Construction Contractor
① Project Manager
② Site Engineer
③ Construction Manager
④ QA/QC Manager

4. Equipment
Below equipment will be used in this mock-up test.
< Table 1> Equipment list
Item Spec Quantity Remark
Excavator 2.3 m3 1 Loading
Wheel Loader 4m3 1 Loading
Roller 18.5ton 1 Compaction
Water Truck 20KL 1 watering
Dump Trailer 60ton 1 Transportation
Dozer 38.5ton 1 pushing

5. Material
1) Material Type
The materials to be used during the mock-up test will use Silty Sandy Soil that meet the
approved material specifications.

2) Material Source

- Quantities

1) Required qunantity of trafficability layer

: 118,800 m3

- STA. 54+000 ~ STA. 56+500 : 36m x 0.9m x 2,500m = 81,000 m3

- STA. 56+500 ~ STA. 61+000 : 36m x 0.3m x 3,500m = 37,800 m3

2) Available sandy(existing) soil

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 5 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

: 180,000 m3
- Pond : 27m x 0.7m x 4,500m x 2 = 170,100 m3

- Excavation for overpass = 9,900 m3

- Existing Sandy Soil

<Fig. 2> Cross section of available sandy soil

6. Sample & Field Test Plan


1) Laboratory activities
① Lab testing: Granular materials
- Sieve test, as per BS 1377:Part1, 2
- Modified Proctor curve, as per BS1377:Part 4
2) Field Test
- Field Density Test, as per BS 1377: Part 9
- Field California Bearing Ratio, as per BS 1377: Part 7 and ASTM D4429
- Plate Load Test, as per BS 1377: Part 9
- Check elevation each Section
- Trafficability test by using 60ton dump trailer each Section
3) Quality control
- One NRI for the lab tests on granular materials
- One NRI for the survey(elevation) of each compacted lift of each Section
- One NRI for the survey(elevation) of each Section
- One NRI for the survey(trafficability test) of each Section
- One NRI for the field tests done on a given test elevation and Section

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 6 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

7. Mock-up Test

1) Layout for Construction


The mockup test consists of: Three sections of sandy soil. The three sections of each
material are 0.6m, 0.9m and 1.2m in compacted height and 35m in length.

<Fig. 3> Layout of the Mockup test

2) Sequence for Determination of trafficability layer height and optimal number of roller
counts(Purpose 1)
The following sequence as shown to determine the height of trafficability and the optimal
number of compactions. The sequence below shows the types of tests and location to be
performed in each of the three section. The levels indicated in Fig4 are before compaction.
After the compaction by 13%, i.e, 0.6m, 0.9m and 1.2m.(loose material thickness 0.68m,
1.02m, 1.36m)

- Sequence 1: Pouring materials on each Section

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 7 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

<Fig. 4> Pouring materials on each Section

- Sequence 2: Compaction with vibration and test each section (60cm Height Layer)

<Fig. 5> Summary of Sequence 2(30cm Height Layer)


Note : The test will be executed on demand at different level in the thickness(body) of the level

- Sequence 3: Compaction with vibration and test each section (90cm height Layer)

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 8 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

<Fig. 6> Summary of Sequence 3(60cm height Layer)

Note : The test will be executed on demand at different level in the thickness(body) of the level

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 9 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

- Sequence 4: Compaction with vibration and test each section (1.2m Height Layer)

<Fig. 7> Summary of Sequence 4(90m Height Layer)

Note : The test will be executed on demand at different level in the thickness(body) of the level
- Summary of number of tests
Description SECTION 1(H=0.6m) SECTION2(H=0.9m) SECTION3(H=1.2m) NRI
1.Check elevation No. 1 1 1 Survey
2.Trafficability test No. 1 1 1 Survey
Phase 1
3.Field CBR No. 2 2 2 Test
(Top layer)
4.Field Density No. 2 2 2 Test
5.Plate Load Test No. 2 2 2 Test
1.Check elevation No. - 1 2 Survey
Phase 2
2.Field CBR No. - 2 4 Test
(Deep test)
3.Field Density No. - 2 4 Test
SUM 8 13 18

< Table 2> Number of tests on each Section

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 10 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

3) Construction Method for Mock-up Test


① Dumping
At the stockpile area excavator will load the material to dump truck and this material will be
dumped to mock up area.

<Fig. 8> Construction method (Dumping)

② Pouring out and Pushing


Material will be dumped and it will be pushed by dozer.

<Fig. 9> Construction method (Pouring and pushing)

③ Watering
Water Tank will pour proper water for the better compaction.

<Fig. 10> Construction method (Watering)

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 11 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

④ Compaction
Layer will be compacted by Vibration Roller.

<Fig. 11> Construction method (Compaction)

Construction of the Connecting Road between Al Faw Grand Port and Um Qasr in Iraq Page 12 of 13
Doc. No. : DWAR-MS-012
Rev. No. : 0
Method Statement for Trafficability Mock Up Test AT STA. 54+000~61+000

8. Result of existing soil test

※ Refer to “DWAU-MAR--REV01 Source Approval For Material of existing soil


STA. 56+500~60+000(material for earthwork)”