Contract No. Document No.

EPCC of Water Injection Station


CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

LIFTING PLAN FOR FIBER BALL


FILTER SKID

A 21/02/2020 Issued for Approval Mohammad A. Abdulkareem Seyed Jalal

Rev. Date Description Prepared Checked Approved

1|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

TABLE OFCONTENTS

1. SCOPE ................................................................................................................................................. 3

2. REFERENCES ..................................................................................................................................... 3

3. Prerequisites ........................................................................................................................................ 3

4. Selection of crane ................................................................................................................................. 5

5. Lifting procedure................................................................................................................................... 9

6. Working Process: ............................................................................................................................... 11

7. Details ................................................................................................................................................ 12

8. HSE Requirements ............................................................................................................................. 13

9. Appendix ............................................................................................................................................ 15

2|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

1. SCOPE

This plan describes the hoisting of Fiber ball filter skids for source water treatment unit
to ensure the safety and quality of hoisting activity.

2. REFERENCES

- OSHA1926.1432– 2010“Crane and Derricks in Construction"


- OSHA1926.1400-2012 “Certification and qualification requirements for mechanics,
inspectors, and testers under the Cranes and Derricks in Construction standards”
- OSHA 2236-2002 “Materials Handling and Storage”

3. Prerequisites

3.1- Requirement for Staff


• Construction staff shall pass related training and safety education.
• All the construction operators shall be organized to make the technical
disclosure before construction.
• Hoisting signal between hoisting command and crane, crane driver shall be
clear.
• Riggers involved in lifting work shall have related valid operation certificate.
Crane driver shall be with corresponding qualifications.
• Construction personnel plan

Table 1. Schedule of construction personnel

No. profession Quantity Remarks


1 Commander 1
2 Crane operator 1
3 Rigger 1
4 Banks man 2

3|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

3.2 - Preparation for Tools and Machines


1) The tools are complete, and the numbers meet the requirements of the lifting.
2) Crane shall be inspected, and in a good condition.
3) The lifting slings and shackles shall be with knotted SWL.
4) Make appearance inspection for rigging and lifting tools (Lifting sling, shackles, the
lifting hook and tag line. etc.) before hoisting, and if there is any unqualified, shall be
marked. The unqualified items are forbidden to be used for hoisting.
5) The riggings should be placed in ventilated and dry place, and shall not be heated,
be affected with damp and shall not contact with acid, alkali and another corrosive
medium.
6) Perform non-load test foe the crane before lifting.

3.3- Equipment and Material


1) Hoisting machinery and equipment shall be checked qualified.
2) Construction materials should meet the rigging requirement.

3.4- Technical Documents


1) Technical documents of equipment installation diagram have been issued.
2) Construction scheme has been issued and technical disclosure is completed.

3.5- Weather Condition


1) Measure the wind speed before starting work and observe the weather, wind speed
shall not exceed 10.8 m/s . do not lift when there is bad weather, such heavy fog, snow,
rain and thunderstorm.
2) It is strictly prohibited to perform lifting operation at night.

4|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

4. Selection of crane

To select the suitable crane, the lifting parameter have to be identified and
compared with the parameter table of the crane to ensure that the capacity of the
selected crane is sufficient for the lifting activity.
The load parameter is:
• The Operating radius = 6 meters;
• The boom length = 25.4 meter;
• The boom angle =70º;
• The Skid weight = 13 ton;
• The total weight of the load (weight of the Skid in additional to the
weight of the lifting tools) = 13.3
Comparing the above parameter with the parameter table of 50 Ton crane , the
lifting capacity of crane is 18 tons , the lifting weight of the Skid is 13 tons in
addition to the lifting tools weight 0. 3 tons the total weight of load will be 13.3
tons, which meets the requirements of the lifting activity.
50 tons crane is selected to lift the Fiber ball filter skid of source water treatment unit.

5|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

The crane parameters are as follows:

6|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

Working curve of 50 TON Mobile Crane

7|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

8|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

5. Lifting procedure.
5.1- Before start the lifting activity:
- PTW shall be issued prior to start the lifting activity.
- Discuss the work with Operators, Slinger and other involved parties where JSA
indicates special risks or where a Rigging Study is applicable.
- Regular weather forecasts shall be obtained before hoisting work commences
- The stability and bearing capacity of the soil where a mobile crane installed or
travel on shall be carefully examined and compacted if required.
- The responsible lifting supervisor shall inform HSE Manager prior to
commencing lifting work whenever wind speeds are higher than 10.8 m/s.
- NO ENTRY” warning signs and guard barriers shall be placed around the
hazardous areas (working radius) to restrict unauthorized entry
- Lifting accessories should be clearly marked with the rated capacity.
- Lifting equipment must be visually inspected before use with any defects
being reported immediately.

5.2- Lifting:
- Allocate the selected crane ( 50 ton - Mobile Crane) in the correct
position and make it close to the foundation as max as possible to reduce
the distance between the centre of the crane and the centre of the load,
maximum distance shall be 6 m.
- Ensure that the Boom length used and distance between the center of
the crane and the centre of the load as per the calculation.
- Adjust the hock of the crane at the center of the load when the crane
boom is opened with correct length and angle.
- Adjust the load location according to the radius of the crane, so no
change in the angle and length of the crane boom during the lifting.
- Install the shackles and the lifting belts in the lifting points
- Install the taglines to the load at two points.
- Start the pre-lifting for the load and make the check for the cran,
shackles, lifting belts and the stability of the load.
- During the lifting, the load shall be controlled by using the tag lines.
- Start the rotating for the crane to allocate the load in its position on the
foundation.
- Adjust the orientation of the load by using the taglines.
- Set up the load in its position and ensure that the orientation is correct

9|P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

- Lifting shall be not be commenced unless Lifting Supervisor per


elementarily ensures that the lifting equipment is satisfactorily set up,
and all preparations are completed in accordance with the Work Method
Statements, Risk Assessment and Job Safety Analysis.
- The sketch below shows the crane position, the distance between the
center of the crane and the load:

10 | P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

- Recheck of 50 ton - Mobile Crane


As shown in the figure above the operating radius is about 6 meters, when
check Parameter of 50-ton Mobile Crane; when the operating radius is 6 meters,
the boom length is 25.4 meter, the boom angle is 70º, the lifting capacity of
crane is 18 tons according to the crane load chart , the lifting weight of the skid
is 13 tons in addition to the lifting tools weight 0.2 tons the total weight of load
will be 13.2 tons, which meets the requirements of the lifting activity.

6. Working Process:

11 | P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

7. Details

7.1- Lifting Preparation


1) Check Lifting prerequisite to confirm it meet the requirements of
lifting.
2) Crane into the construction site and the crane located as close as possible to
the tank.

7.2- Rigging Connection and Skid Trial-hoisting


1) Workers must check the skid before the lifting carefully, define the hoisting
points, the location of the center of gravity, overall dimensions and the total
weight.
2) Choose rigging and sling reasonably according to the weight, overall
dimensions and the number of hanging points of the skid.
3) Establish lifting operation warning zone before the construction and prohibit
irrelevant personnel go inside.
4) Rigging should avoid contact with the skid body.
5) The position of hanging point or binding point should choose the hanging
point or binding part which has been already welded to the Skid.
6) The angle between riggings should fixed according to the calculation of the
load, it shall be 70 deg.
7) The gap between the rigging and Skid sharpness must be isolated with hard
protection.
8) Tag line shall be attached to a lifted load for purposes of controlling load
spinning and pendular motions.
9) After finishing the rigging connection, hoist the Skid above the ground
100~300mm to trial hoisting
10) When trial hoisting, use hand -operated hoist to adjust if the Skid does not
balance.
11) The purpose of trial-hoisting is mainly to check the state of rigging
connection, Skid balance or not, braking apparatus of the crane and the ground
subsidence or not and so on.

12 | P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

7.3- Skid Hoisting in Position


1. According to the Skid installation location and hoisting condition,
prepare the hoisting tools.
2. Hoist the Skid above the ground 100~300mm to trial hoisting, adjust the
Skid by use the hand -operated hoist if required.
3. Check the crane, the shackles, lifting polyester webbing sling and the
load stability.
4. Hoist the Skid to the adequate height slowly, use the tag lines to control
the load orientation.
5. After reach to the adequate height, start the rotating of the crane boom
to allocate the Skid in position.
6. After set the Skid in position, Support the Skid.
7. After ensure that the Skid is fixed, dismantle the hoisting tools, the
permanent Skid ladder and handrail shall be used during dismantling the
hoisting and harness shall be fixed to the handrail.

7.4- Site Cleaning


After complete the hoisting activity and the Crane exits, cleaning up the scene
at the same time, transporting the hoisting tools and material away the
hoisting construction site, the hoisting work finished.

8. HSE Requirements

1) All staff involved in the lifting operation shall be qualified rigger and crane
operator with relevant certificates.
2) Conduct internal meeting rigger and crane operator should be attendant
to discus the hazards and control measures of this lifting operation, HSE
representative, mechanical team, rigger, crane operator should agree with all
lifting plan and control measures.
3) TBT should be conducted for all staff involve in the lifting operation.
4) Barricade the work site Make sure both construction work and staff are
safe. Safety signs to keep away unauthorized personnel from lifting area.
5) Whenever there is a concern as to safety, the operator must have the
13 | P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

authority to stop and refuse to handle loads until a qualified person has
determined that safety has been assured.
6) Get relevant permits before lifting.
7) Lifting training prepare for workers involved in the lifting operation by
authorized trainer.
8) Lifting area should be clear from pedestrians and other construction
activities, prevent SIMOPS activities.
9) Provide crane and equipment check list, inspection that will be performed
by HSE and carne operator before lifting is starting.
10) Workers involved in lifting work shall follow the Construction Regulations
of Lifting Work Safety.
11) Team Leader (lifting commander) Coordinator authorized to organize and
coordinate all actions related to this lifting all staff including rigger, crane
operator should follow his instruction.
12) Start lifting and positioning the equipment steady with low speed. During
lifting, crane shall keep being steady and with a constant speed. Prohibit
speeding up the crane suddenly.
13) Crane driver and person in charge of lifting work shall carry out the
compliance inspection for crane situation, ground bearing capacity and sling
preparation, etc. before lifting.
14) Before lifting, staffs involved in lifting work shall be familiar with the
parameters (including weight, gravity center, outline dimension, and precision)
of equipment to be hoisted, and adopt necessary technical measures.
15) Standing under the equipment being hoisted or the crane beam is
prohibited. Do not stay close to stressed slings.
16) If wind speed is more than 10.8 m/s, or there is heavy rain or fog, do not
perform any lifting work.
17) During lifting, use hemp rope to control direction and swing of the
equipment being hoisted.
18) During crane operated, all staffs shall obey the command and cooperate
with each other. Crane driver shall comply with the Crane Operation Regulations.
Signal from the commander shall be accurate and correct.
19) For lifting work, the walkie-talkie is used as the main communication way,
and defined a specialized channel for lifting work. Whistle is the backup
communication way.

14 | P a g e
Contract No. Document No.
EPCC of Water Injection Station
CMIT-PRT-10.53-180025 FW-796-SAF-62.20-0029-A

9. Appendix

- List of Lifting Team:

No. Position Numbers Remarks


1 Lifting supervisor 1
2 Rigger 2
3 Commander 1
4 Crane operator 1
Names, positions, qualifications and phone numbers of lifting team will mention
in the lifting PTW

- List of Main Materials and Tools:


No. Item Specification Unit Qty. Remarks
1 Crane 50 ton set 1
2 shackle 4 ton Pcs. 4
3 Tag lines Pcs. 2
4 Safety belts Pcs. 4

- Calculation of lifting tools


Description Symbol Formula Weight Unit
Skid M1 13 T
Hook M2 0.2 T
lifting M3 4 * 15 = 60 Kg
polyester
webbing
sling
Shackles M4 4* 10 = 40 Kg
Total Load M M=M1+M2+M3+M4 13.3 T
Rated Load SWL 18 T
Radius R 6 M
Load Rate η η=M/SWL 73.8 %

15 | P a g e
10. Appendix II

Risk Assessment Table for Equipment Lifting


is not enough, emergency people injured equipment and medicine, etc.
measure is not adequate.
Warning sign or line is
People injured 2 2 4 Define warning line, set out safety sign. 1 2 2 Acceptable
not set out on site.
Realize weather condition before liftin g. Do not perform the lifting work
Work under bad weather. Safety accident 1 4 4 1 3 3 Acceptable
under heavy rain /fog, or wind speed exceeds level 5.
Cause accident due to
Crane does not stand as
crane work under 1 4 4 Crane shall stand as shown on plane view strictly. 1 3 3 Acceptable
required.
overload.
Crane inclined,
Subsidence on ground people injured, 2 4 8 Perform lifting work only if ground meets requirement. 1 3 3 Acceptable
equipment damaged
Sling is with bad quality
Equipment equipment damaged 1 4 4 Check tools and machines before lifting. Do not u se unqualified item. 1 3 3 Acceptable
or broken.
Unloading
Equipment/crane
Crane runs under Choose crane as required by plan. Do not perform lifting work when crane is
damaged, people 1 4 4 1 3 3 Acceptable
overload. under overload.
injured
Rigger shall have the certificate. Define the channel of walkie-talkie before
Signal is bad,
People injured, use it. Confirm the battery of walkie-talkie. Order shall be given clearly and
commander do not
equipment damaged, 1 4 4 accurately. Commander and driver shall test the communication signal before 1 3 3 Acceptable
cooperate with each other
property loss lifting. Get familiar with site environment before working. Driver shall not
well.
perform any action when the signal is bad.
Unauthorized people Set out warning area, define obvious warning sign and appoint a specialized
People injured 2 2 4 1 2 2 Acceptable
enter working site. staff to supervise it.
Specification of “do not People injured, 2 4 8 Implement relevant stipulations strictly. Do not perform any lifting work 1 3 2 Acceptable

17 | P a g e
Risk Assessment Table for Equipment Lifting
perform lifting under crane/equipment when signal is not clear. Do not perform any lifting work when crane is over
those ten conditions” is damaged loaded or lifting weight is unknown. Do not lift the inclined item. Do not
not implemented strictly. perform any liftin g work when the hoisted item cannot be seen clearly. Do
not stand on/under the hoisted item. Do not lift the buried item. Do not
perform liftin g work when hoisted item is not fixed firmly, rope is knotted or
not complete. Do not perform lifting work when item with angle or blade is
not protected. Do not perform liftin g work when safety dev ice is failure. Do
not perform liftin g work when wind speed exceeds requirement.
Equipment damaged, Follow the liftin g work specification, perform the construction work as per
Lifting against regulation 3 4 12 1 3 3 Acceptable
people injured plan strictly.
Worker for special type of operation shall have certificate. All stall involved
Abnormal situation is
Equipment damaged, in construction shall attend technical disclosure and get familiar with working
caused by improper 2 2 4 1 3 3 Acceptable
people injured process.
operation.

Warning sign or line is


people injured 2 2 4 Define warning line, set out safety sign. 1 2 2 Acceptable
not set out on site.
Cause accident due to
Crane does not stand as
crane work under 1 4 4 Crane shall stand as shown on plane view strictly. 1 3 3 Acceptable
required.
overload.
Lifting
Signal is bad, Rigger shall have the certificate. Define the channel of walkie-talkie before
Equipment
commander do not age, People injured, use it. Confirm the battery of walkie-talkie. Order shall be given clearly and
cooperate with each other equipment damaged, 1 4 4 accurately. Commander and driver shall test the communication signal before 1 3 3 Acceptable
well. property loss lifting. Get familiar with site environment before working. Driver shall not
perform any action when the signal is bad.
Crane runs under People injured, 1 4 4 Choose crane as required by plan. Do not perform lifting work when crane is 1 3 3 Acceptable

18 | P a g e
Risk Assessment Table for Equipment Lifting
overload. crane/equipment under overload.
damaged
Equipment damaged, Follow the liftin g work specification, perform the construction work as per
Lifting against regulation 3 2 6 1 3 3 Acceptable
people injured plan strictly.
Unhook accidently,
people get hurt by falling People injured 1 4 4 Crane hook shall be equipped with spring lock device. 1 2 2 Acceptable
things.
Clear up Do not clear up working
People injured 1 2 2 Clear up in time. 1 2 2 Acceptable
working site site.

Remarks: Low risk (R= l~3); Genera l risk (R=4~6); Medium risk (R=8~12); High risk (R= l5~25).

19 | P a g e