Professional Documents
Culture Documents
Transmission Directorate
Koshi Corridor 220 KV Transmission Line Project
A REPORT
ON
PLATE LOAD TEST
FOR
CONSTRUCTION OF STONE COLUMN
AT
220 KV SUB-STATION AT INARUWA, SUNSARI
(IFB No: KOSHI/NEA/KC-2)
CONSULTANT
WAPCOS LTD. in Association with TMS Pvt. Ltd.
CONTRACTOR
M/S Larsen & Toubro Limited
PREPARED FOR
Imperial Construction (P.) Ltd.
Balkumari, Lalitpur
PREPARED BY
PLANET TEST (P.) LTD.
KMC-31, Shantingar, Kathmandu
Telephone: 977-1- 4107665
E-mail: planettest2074@gmail.com
Report on Plate Load Test for Construction of Stone Column
At 220 KV SUB-STATION AT INARUWA, SUNSARI
Table of Contents
1. GENERAL INTRODUCTION ......................................................................................................................................................... 1
2. DESCRIPTION OF SITE .................................................................................................................................................................. 1
3. OBJECTIVES ........................................................................................................................................................................................ 1
4. PLATE LOAD TEST ........................................................................................................................................................................... 1
5. FIELD WORK PROCEDURE .......................................................................................................................................................... 2
6. ANALYSIS AND RESULTS OF PLATE LOAD TEST ............................................................................................................. 2
7. LIMITATIONS AND UNIFORMITY OF CONDITIONS ....................................................................................................... 6
ANNEXES
Page I
Report on Plate Load Test for Construction of Stone Column
At 220 KV SUB-STATION AT INARUWA, SUNSARI
1. GENERAL INTRODUCTION
The suitability of the foundation depends upon the geometrical and the strength property of the soil strata. The
Plate Load test in one part of geotechnical investigation to get the ultimate load capacity of ground strata and
to determine the load settlement relationships under compression load. The plate load test has been done as per
the request by the Design and Build of Koshi Corridor 220 KV Transmission Line Project of IFB No:-
KOSHI/NEA/KC-2 through the Contractor L&T Construction to determine the bearing capacity, settlement of
Stone column area within Inaruwa Sub-station.
This report is prepared in accordance with an agreement between Imperial Construction (P.) Ltd,
Balkumari, Lalitpur and Planet Test (P.) Ltd, KMC-31, Shantinagar, Kathmandu.
2. DESCRIPTION OF SITE
The proposed load test site is located in Inaruwa, Sunsari. Inaruwa is headquater of Sunsari District located in
25 Km east of Koshi Barrage in Province-1.
3. OBJECTIVES
The plate load test is an important test of geotechnical investigation to find out the strength and compression
properties of the ground strata. This assignment of conducting plate load test is to get reliable information on:
The plate load test is a semi-direct method to estimate the allowable bearing pressure of soil to induce a given
amount of settlement. The IS 15284 (Part 1):2003 has been followed for the equipment setup and the test
procedure for plate load test on single column.
i. Bearing Plate:
Dial gauge capable of measuring settlement of the loaded plate to an accuracy of 0.001 mm.
Plates, square in shape having sizes 0.45m X 0.45m dia and thickness of about 25 mm are has been used for
this test. The load on the plate is applied by hydraulic jack. The reaction of the jack load is taken by an
excavator of having load more than 1.5 times the design load. The settlement of the plate is measured by a set
of two dial gauges of sensitivity 0.01 mm placed at about 180° apart. The dial gauges are fixed to independent
supports which do not get disturbed during the test.
The fieldwork was scheduled from September 10th 2020. At the time of investigation a team of experts and
workers with necessary equipment were mobilized to the site to conduct the plate load test.
The Plate load test at the proposed site is conducted at 3.0 m depth from the existing ground level. During the
field tests, a 100 tons hydraulic jack was used to press the soil strata below by a 45cm x 45 cm square steel
plate of thickness 25 mm. The plate was kept at the center of open excavated rectangular pit of about 2.0m
depth. Ram of Hydraulic jack was rested at the boom of 10.0 tons excavator.
A seating load of 0.5 t was applied with hydraulic jack and released after some time. The load was then
gradually increased from 0 to 2, 4, 6, 8 and 10 (tons) respectively. For each increment of loading the
settlement of steel plate was recorded with the two different dial gauges till the rate of settlement is less than
0.25mm per hour.
Testing was continued until one of the following stages were reached (i) the settlement became definitely
progressive which indicated shear failure, (ii) the applied pressure was exceeded 3 times the allowable
pressure, or (iii) the total settlement exceeded 10% the width of the plate. The load was then released. The
recorded load and deformation has been attached to the annex.
The result obtained from the test following the applied pressure exceeds 3 times the allowable pressure. The
average of the settlements recorded by both dial gauges is taken as the settlements of the plate for each of the
load increment. A graph is plotted between applied pressure intensity versus final settlement on linear scales
and time-settlement-curve on log-log scales, as shown in Fig. to the Annex.
From the curve shows the nature of semi cohesive soil under pressure where in the ultimate failure point is
found out by crossing two tangents at a common point in such a way that tangents could be drawn to the two
distinct curvatures. The intersection of the two tangents gives the net ultimate bearing capacity of the plate.
Further, allowable safe bearing capacity is found out by dividing the ultimate load intensity by a factor of
safety, usually taken as 2.5.
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 350.00/2.5
= 140.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (15.51 mm).
= 350.00/0.01551
= 22,566.09 KN/m3
d. Seepage water table was found around at vicinity of the foundation trench.
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 275.00/2.5
= 110.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (19.30 mm).
= 275.00/0.01930
= 14,248.70 KN/m3
d. Seepage water table was found around at vicinity of the foundation trench.
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 360.00/2.5
= 144.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (12.81 mm).
= 360.00/0.01281
= 28,103.044 KN/m3
d. Seepage water table was found around at vicinity of the foundation trench.
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 300.00/2.5
= 120.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (15.85 mm).
= 300.00/0.01585
= 18,927.444 KN/m3
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 210.00/2.5
= 84.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (20.95 mm).
= 210.00/0.02095
= 10,023.866 KN/m3
d. Seepage water table was found around at vicinity of the foundation trench.
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 225.00/2.5
= 90.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (18.92 mm).
= 225.00/0.01892
= 11,892.178 KN/m3
d. Seepage water table was found around at vicinity of the foundation trench.
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 250.00/2.5
= 100.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (14.76 mm).
= 250.00/0.01476
= 16,937.669 KN/m3
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 200.00/2.5
= 80.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (11.59 mm).
= 200.00/0.01159
= 17,256.255 KN/m3
a. Hence, (i) allowable bearing capacity = ultimate bearing capacity / factor of safety
= 200.00/2.5
= 80.00 KN/m2
b. As the rate of settlement is found minimum with respect to time, which is seen in the time-settlement
graph the permissible long-term settlement could be opted for the minimum value (18.24 mm).
= 200.00/0.01824
= 10,964.912 KN/m3
o The recommendations of this report pertain only to the site investigated and are based upon the
assumption that the soil conditions do not deviate from those disclosed in the investigation. If any
variations or undesirable conditions are encountered during construction, or if the proposed construction
will differ from that anticipated herein, Planet Test should be notified so that supplement recommendation
can be given.
Planet Test (P.) Ltd, Kathmandu, 2020 Page 6
Report on Plate Load Test for Construction of Stone Column
At 220 KV SUB-STATION AT INARUWA, SUNSARI
o This report is issued with the understanding that it is the responsibility of the client, or of their
representative, to ensure that the information and recommendations contained herein are brought to the
attention of the design engineer for the project and incorporated into the plan, and the necessary steps are
taken to see that the contractor and the sub-contractor carry out such recommendations in the field.
o The findings of this report are valid as of the present date. However, changes in the conditions of a
property can occur with the passage of time, whether they are due to natural process or the works of man
on this or adjacent properties.
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
38.00
40.00
42.00
44.00
46.00
48.00
50.00