Professional Documents
Culture Documents
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station
General Information
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
You are using a browser that is not supported by the Google Maps JavaScript API. Please consider changing your browser. Learn more
Dismiss
Project timeline
Project timeline ?
Show all Today center + – Event News item
📣 2 📣 📣 3 📣 2 📣 📣 📣
6 2 📣 📣
https://premium.meedprojects.com/Projects/Overview/289450 20/02/2022
MEED Projects | MENA Project Tracking and Intelligence Tool Page 2 of 5
Royal Commission for Jubail and Yanbu is undertaking the construction of Jubail Industrial City 2: Phase 3 and 4 Sea Water
Cooling Station in Jubayl.
1. Site development
2. Construction of seawater cooling pump station intake structure
3. Construction of booster pumps
4. Construction of control building
5. Construction of electrical buildings
6. Construction of distributed control system
7.Construction of an emergency shutdown system
8.Construction of instrumentation works
9. Construction of a fiber-optic network
10. Construction of electric power supply
11. Construction of guardhouse
12.Construction of manifold structures
13.Construction of valve chambers
14. Construction of flow chambers
15. Construction of fire water system including tanks and pumps
16. Construction of potable water system
17. Construction industrial wastewater system
18. Construction of sanitary wastewater system
19. Construction of fiberglass reinforced plastic (FRP)
20. Laying of piping distribution network
21. Installing of valves
22. Construction of security fencing
23. Construction of gates
24. Construction of associated works
Owner
Pre-Qualified
Bidder
Main Contractor
Pre-Qualified
Bidder China Communications Construction Company
+86 10 8201 6655
Archirodon
(+30) 2106073300
Civil
Pre-Qualified
Bidder
Awarded China Communications Construction Company
+86 10 8201 6655
https://premium.meedprojects.com/Projects/Overview/289450 20/02/2022
MEED Projects | MENA Project Tracking and Intelligence Tool Page 3 of 5
MEI
Pre-Qualified
Bidder
Awarded China Communications Construction Company
+86 10 8201 6655
The project was in the execution stage as per the last update in April, 2020. Since then, no further information has
been procured related to its progress, nor obtainable from contact with key stakeholders. We believe the project to
13/12/2021
still be in the execution stage and have amended the project dates accordingly. We continue our efforts to obtain
information on this project.
The project was in the execution stage as per the last update in April, 2020. Since then, no further information has
been procured related to its progress, nor obtainable from contact with key stakeholders. We believe the project to
24/03/2021
still be in the execution stage and have amended the project dates accordingly. We continue our efforts to obtain
information on this project.
09/04/2020 Finishing works are ongoing at a slow pace due to the financial issues and the completion time frame is unknown.
The project was in the execution stage as per the last update in May 2019. Since then, no further information has
been procured related to its progress, or obtainable from contact with key stakeholders. We believe the project to
27/12/2019
still be in the execution stage and have amended the project dates accordingly. We will continue our efforts to
obtain information on this project.
This project was expected to be completed in Q4 2018, however, there is no news in the market on the completion
16/05/2019
status at this juncture.The completion date, therefore, has been moved to Q4 2019
19/04/2018 The construction works are ongoing on the project and is near to completion. MEIC works are done inhouse
This project was created based on a market news in year 2012. The last update received on the project over the
phone was that the construction works on the project are ongoing and overall completion is expected by August
29/12/2017 2018.However, since then we have not been able to obtain a definite update as to the status of the project. Until we
obtain information to the contrary, we will not alter the status of the project, but we have changed the time frame to
make it more accurate. In the meantime, we will continue to try and obtain updates for this project.
22/08/2017 The construction works on the project are ongoing and overall completion is expected by August 2018.
23/03/2017 Construction works on the project is ongoing and completion is expected by January 2018.
08/12/2016 Construction works on the project is 95 per cent complete and time frame for the completion is unknown.
17/11/2016 Finishing works are ongoing on the project and overall project is likely to get complete by end of November 2016.
01/06/2016 Construction on the project is ongoing.
Construction work on the project is ongoing. Khaled Juffali Industrial Company has been awarded the contract to
01/02/2016
fabricate and erect two tanks.
04/05/2015 Construction works on the project are ongoing and is estimated to complete by Q4 2015
Construction works on the project are ongoing and estimated to get completed by Q4 2015. Also the project is at
13/02/2015
an advanced stage.
31/12/2014 Construction works on this project are ongoing as per the schedule.
30/09/2014 The construction works on the project is ongoing and is expected to be completed by mid 2015.
27/06/2013 A company active quoted that construction works are progressing as per schedule.
Industry sources indicate that LOA has been singed by China Communications Construction Company (CCCC) to
13/02/2013
develop the eastern part of the residential area of Jubail city.The contract duration is 26 months
The main contract for the project has been awarded to China Communications Construction Company Ltd. (CCCC)
29/10/2012
as per article dated October 19, 2012. The project is expected to be completed in 26 months.
https://premium.meedprojects.com/Projects/Overview/289450 20/02/2022
MEED Projects | MENA Project Tracking and Intelligence Tool Page 4 of 5
A company active on the project quoted that the bids are under evaluation and likely to get awarded by November
26/09/2012
2012.
Prospectives EPC Bidders *Saudi Binladin Group *Saudi Archirodon Ltd *Al Harbi Trading & Contracting Company
16/08/2012 *Saudi Tumpane Company *Al Meer Contracting company *Azmeel Contracting Establishment *SNC-Lavalin
Group Incorporated
Background In order to protect the environment by using a district air cooling system, Royal Commission for Jubail
06/08/2012 & Yanbu (RCJ&Y) plans to build a seawater cooling station in Jubail. Royal Commission for Jubail & Yanbu
(RCJ&Y) is planning to construct a seawater cooling plant for the Jubail Industrial City.
Eastern Province ?
94
Jizan Province
150
Totals
244
Seawater Cooling Plant projects in Saudi Arabia Value of Seawater Cooling Plant projects in Saudi
awards ? Arabia completing ?
https://premium.meedprojects.com/Projects/Overview/289450 20/02/2022
MEED Projects | MENA Project Tracking and Intelligence Tool Page 5 of 5
https://premium.meedprojects.com/Projects/Overview/289450 20/02/2022