MID-TERM
MANAGEMENT REVIEW
FOR YEAR 2020

Confidential
SUMMARY TARGET LIST TO BE REALISED Q3 & Q4 2020
Confidential

No Company Name Project Steps to be Realised Target Realised OIC Investment Jobs BO
(i.e. : earthwork or land clearing, 2020 (RM Bill)
in operation, under-construction,
installation/acquisition mach)
1 Jianhui Paper Kuantan (Malaysia) Manufacturing of paper INDUSTRIAL
 To start the land clearing work at
Q4 2020 KJ PARK
2.9 2200 20
Sdn. Bhd. project site (MCKIP2)
2 ND Paper (M) Sdn Bhd Paper and pulp manufacturing Installation of new machine Q3 2020 KJ 0.5 350 20
plant
3 PCC Oxyalkylates Malaysis Sdn. Bhd. Production of Polyols and   Q4 2020 Adil 0.4 18 26
Ethoxylates
4 Halpro Engineering Sdn Bhd Development of solar farm   Q3 2020 Adil 0.2 17 35
5 Kenyir Gunkul Solar Sdn Bhd Development of solar farm In operation Q3 2020 Adil 0.2 15 35
6 TNB Property Ventures Mixed development Extension from UPENT to obtain Q4 2020 Ikhwan 0.14 98 25
planning permission (KM)
7 Bandar Lojing Development Sdn. Taman Industri Pertanian   Q4 2020 Farid 0.07 25 20
Bhd.
8 AFI Brake Manufacturing Sdn. Bhd. Manufacturing of automotive   Q4 2020 Shamini 0.02 55 20
disc brake pads
9 Persatuan Nelayan Kebangsaan Deep sea Fishing, Primary Fish   Q4 2020 Farid 0.01 7 20
(NEKMAT) Processing Plant, Cold storage
10 Power Gas Industrial Bhd Industrial Food Gas   Q4 2020 Farid 0.005 25 20
11 AL Builders Sdn Bhd - Project 2 Pembelian lima (5) unit lori 5 Acqusition of machine Q3 2020 Fayyadh 0.005 4 25
tan berserta dua (2) unit
jentolak
       
Grand Total         4.45 2,814 266
TNB Property Venture
Sulit

Details of Company Steps Timeline


TNB Property Venture Company just appointed an
architect to complete the
building layout and design

Company expect to obtain


planning permission (KM) by
September 2020.

1. Investment:RM 140 million


2. Jobs: 98
3. BO: 25
4. Steps to recognise as
committed
5. Target Timeline: Q4 2020
6. OIC: Md Sezehli