RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station

General Information
Owner Royal Commission for Progress 96%
Jubail & Yanbu
Master Project - Estimated $30m
Budget Value
Location Jubail,Eastern Contract Value $24m
Province,Saudi Arabia
Status Execution Net Value $24m

Sector Seawater Cooling Plant, Award Date October 2012


Cooling, Water
Contract Type Engineering Completion June 2022
Procurement Date
Construction (EPC)
Onshore/Offshore Onshore Last Updated December 2021
On
Greenfield/Brownfield Greenfield

Description & Scope


Royal Commission for Jubail and Yanbu is undertaking the construction of Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station in
Jubayl.
The US$30 million project includes the following :
1. Site development
2. Construction of seawater cooling pump station intake structure
3. Construction of booster pumps
4. Construction of control building
5. Construction of electrical buildings
6. Construction of distributed control system
7.Construction of an emergency shutdown system
8.Construction of instrumentation works
9. Construction of a fiber-optic network
10. Construction of electric power supply
11. Construction of guardhouse
12.Construction of manifold structures
13.Construction of valve chambers
14. Construction of flow chambers
15. Construction of fire water system including tanks and pumps
16. Construction of potable water system
17. Construction industrial wastewater system
18. Construction of sanitary wastewater system
19. Construction of fiberglass reinforced plastic (FRP)
20. Laying of piping distribution network
21. Installing of valves
22. Construction of security fencing
23. Construction of gates
24. Construction of associated works

News and Updates


20/Feb/2022 05:49:36

Page 1
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station

Published Date Description

13/12/2021 The project was in the execution stage as per the last update in April,
2020. Since then, no further information has been procured related to its
progress, nor obtainable from contact with key stakeholders. We believe
the project to still be in the execution stage and have amended the project
dates accordingly. We continue our efforts to obtain information on this
project.
24/03/2021 The project was in the execution stage as per the last update in April,
2020. Since then, no further information has been procured related to its
progress, nor obtainable from contact with key stakeholders. We believe
the project to still be in the execution stage and have amended the project
dates accordingly. We continue our efforts to obtain information on this
project.
09/04/2020 Finishing works are ongoing at a slow pace due to the financial issues
and the completion time frame is unknown.
27/12/2019 The project was in the execution stage as per the last update in May
2019. Since then, no further information has been procured related to its
progress, or obtainable from contact with key stakeholders. We believe
the project to still be in the execution stage and have amended the project
dates accordingly. We will continue our efforts to obtain information on
this project.
16/05/2019 This project was expected to be completed in Q4 2018, however, there is
no news in the market on the completion status at this juncture.The
completion date, therefore, has been moved to Q4 2019
19/04/2018 The construction works are ongoing on the project and is near to
completion. MEIC works are done inhouse
29/12/2017 This project was created based on a market news in year 2012. The last
update received on the project over the phone was that the construction
works on the project are ongoing and overall completion is expected by
August 2018.However, since then we have not been able to obtain a
definite update as to the status of the project. Until we obtain information
to the contrary, we will not alter the status of the project, but we have
changed the time frame to make it more accurate. In the meantime, we
will continue to try and obtain updates for this project.
22/08/2017 The construction works on the project are ongoing and overall completion
is expected by August 2018.
23/03/2017 Construction works on the project is ongoing and completion is expected
by January 2018.
08/12/2016 Construction works on the project is 95 per cent complete and time frame
for the completion is unknown.
17/11/2016 Finishing works are ongoing on the project and overall project is likely to
get complete by end of November 2016.
01/06/2016 Construction on the project is ongoing.

01/02/2016 Construction work on the project is ongoing. Khaled Juffali Industrial


Company has been awarded the contract to fabricate and erect two
tanks.
04/05/2015 Construction works on the project are ongoing and is estimated to
complete by Q4 2015
13/02/2015 Construction works on the project are ongoing and estimated to get
completed by Q4 2015. Also the project is at an advanced stage.
31/12/2014 Construction works on this project are ongoing as per the schedule.

20/Feb/2022 05:49:36

Page 2
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station

30/09/2014 The construction works on the project is ongoing and is expected to be


completed by mid 2015.
27/06/2013 A company active quoted that construction works are progressing as per
schedule.
13/02/2013 Industry sources indicate that LOA has been singed by China
Communications Construction Company (CCCC) to develop the eastern
part of the residential area of Jubail city.The contract duration is 26
months
29/10/2012 The main contract for the project has been awarded to China
Communications Construction Company Ltd. (CCCC) as per article dated
October 19, 2012. The project is expected to be completed in 26 months.
26/09/2012 A company active on the project quoted that the bids are under evaluation
and likely to get awarded by November 2012.
16/08/2012 Prospectives EPC Bidders

*Saudi Binladin Group


*Saudi Archirodon Ltd
*Al Harbi Trading & Contracting Company
*Saudi Tumpane Company
*Al Meer Contracting company
*Azmeel Contracting Establishment
*SNC-Lavalin Group Incorporated
06/08/2012 Background
In order to protect the environment by using a district air cooling system,
Royal Commission for Jubail & Yanbu (RCJ&Y) plans to build a seawater
cooling station in Jubail. Royal Commission for Jubail & Yanbu (RCJ&Y)
is planning to construct a seawater cooling plant for the Jubail Industrial
City.

Key project milestones


Published Date Description

20 Jun 2012 Main Contract Tender Issue (ITB, RFP)

5 Sep 2012 Main Contract Commercial Bid Submission

19 Oct 2012 Main Contract Award

30 Jun 2022 Main Contract Completion, Commissioning

Product & Capacities


Description Value

Cooling (ton) 80,000

Companies and Contacts


Role Company Contact

20/Feb/2022 05:49:36

Page 3
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station

Owner Royal Commission for Project Manager, Mike Shaun,Phone:(+966) 133413376


Jubail & Yanbu
Main Contract Bidder China Communications Phone:+86 10 8201 6655
Construction Company
Main Contract Bidder Archirodon Phone:(+30) 2106073300

Main Contractor China Communications Phone:+86 10 8201 6655


Construction Company
Civil China Communications Phone:+86 10 8201 6655
Construction Company
MEI China Communications Phone:+86 10 8201 6655
Construction Company

Potential Bidders(Main Contractors)


Company Name Contact

China Communications Construction Company(1) +86 10 8201 6655

Potential Bidders(MEI)
Company Name Contact

China Communications Construction Company(1) +86 10 8201 6655

20/Feb/2022 05:49:36

Page 4