Professional Documents
Culture Documents
General Information
Owner Royal Commission for Progress 96%
Jubail & Yanbu
Master Project - Estimated $30m
Budget Value
Location Jubail,Eastern Contract Value $24m
Province,Saudi Arabia
Status Execution Net Value $24m
Page 1
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station
13/12/2021 The project was in the execution stage as per the last update in April,
2020. Since then, no further information has been procured related to its
progress, nor obtainable from contact with key stakeholders. We believe
the project to still be in the execution stage and have amended the project
dates accordingly. We continue our efforts to obtain information on this
project.
24/03/2021 The project was in the execution stage as per the last update in April,
2020. Since then, no further information has been procured related to its
progress, nor obtainable from contact with key stakeholders. We believe
the project to still be in the execution stage and have amended the project
dates accordingly. We continue our efforts to obtain information on this
project.
09/04/2020 Finishing works are ongoing at a slow pace due to the financial issues
and the completion time frame is unknown.
27/12/2019 The project was in the execution stage as per the last update in May
2019. Since then, no further information has been procured related to its
progress, or obtainable from contact with key stakeholders. We believe
the project to still be in the execution stage and have amended the project
dates accordingly. We will continue our efforts to obtain information on
this project.
16/05/2019 This project was expected to be completed in Q4 2018, however, there is
no news in the market on the completion status at this juncture.The
completion date, therefore, has been moved to Q4 2019
19/04/2018 The construction works are ongoing on the project and is near to
completion. MEIC works are done inhouse
29/12/2017 This project was created based on a market news in year 2012. The last
update received on the project over the phone was that the construction
works on the project are ongoing and overall completion is expected by
August 2018.However, since then we have not been able to obtain a
definite update as to the status of the project. Until we obtain information
to the contrary, we will not alter the status of the project, but we have
changed the time frame to make it more accurate. In the meantime, we
will continue to try and obtain updates for this project.
22/08/2017 The construction works on the project are ongoing and overall completion
is expected by August 2018.
23/03/2017 Construction works on the project is ongoing and completion is expected
by January 2018.
08/12/2016 Construction works on the project is 95 per cent complete and time frame
for the completion is unknown.
17/11/2016 Finishing works are ongoing on the project and overall project is likely to
get complete by end of November 2016.
01/06/2016 Construction on the project is ongoing.
20/Feb/2022 05:49:36
Page 2
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station
20/Feb/2022 05:49:36
Page 3
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station
Potential Bidders(MEI)
Company Name Contact
20/Feb/2022 05:49:36
Page 4
RCJ&Y - Jubail Industrial City 2: Phase 3 and 4 Sea Water Cooling Station
Page 5