Professional Documents
Culture Documents
L = hydraulic length of catchments, measured along flow path from the catchment
boundary to the point where the flood needs to be determined (km) = 0.7982km
Sav = average slope (m/m)
. − .
=
(1000)(0.75 )
H 0.10L = elevation height at 10% of the length of the watercourse (m) = 2950.80
H 0.85L = elevation height at 85% of the length of the watercourse (m) = 3058.70
3058.7 − 2950.8
= = .
1000 ∗ 0.75 ∗ 0.7982
.
. ∗ .
Tc = time of concentration (hours) = = .
∗ .
200.00
Intensity in mm/hr
150.00 2 years
5 years
10 years
100.00 25 years
50 years
100 years
50.00
0.00
0 50 100 150 200
Duration in Min
The catchment area were found in rainfall region A1, use the IDF curve of rainfall region
A1 (or use project specific IDF curve) and find the rainfall intensity for different return
periods.
I2=59.5mm/hr ; I5=78.6mm/hr; I10=90mm/hr; I25=107.3mm/hr; I50=119.4mm/hr;
I100=130mm/hr
Return 2 10 25
period 5 Year 50 Year 100 Year
Year Year Year
I =mm/hr 59.5 78.6 90 107.3 119.4 130
Cf 1.0 1.0 1.0 1.1 1.2 1.3
3
Q =m /s 8.71 11.50 13.17 17.27 20.97 23.78
Normal
Land Hydrologic Soil Wet Region
Soil Type Rainfall Region AMC Curve
Cover Group Soil Type Curve no.
No
Grass Dystric Rainfall Region
B Wet 69 85
land Cambisols B1
Grass Orthic Rainfall Region
B Wet 69 85
land Acrisols B1
H 0.10L = elevation height at 10% of the length of the watercourse (m) = 1323.00
H 0.805L = elevation height at 85% of the length of the watercourse (m) = 1411.099
1411.099 − 1323.00
= = .
1000 ∗ 0.75 ∗ 10.399
.
. ∗ .
Tc = time of concentration (hours) = ∗ . .
= 2.2613
( − )
=
( − )+
Where: Q = accumulated direct runoff, mm
P = accumulated rainfall (potential maximum runoff), mm
Ia= initial abstraction including surface storage, interception, and infiltration prior
to runoff, mm Ia=0.2*S
= − 254
S = potential maximum retention, mm
Ia = initial abstraction including surface storage, interception, and infiltration prior
to runoff, mm Ia = 0.2*S
CN= Curve Number , in the above catchment characteristics table the area were
located in WET region of the country the normal curve number changed to wet
region as per the manual. = 88
The catchment area located in rainfall region B1 use the 24hr rainfall depth of
Nekempte meteorological station.
= ∗ ∗
Where qp = peak discharge, m3/s
qu = unit peak discharge, m3/s/km2/mm
( )
=∝∗ 10
Where Co, C1 and C2 = regression coefficients given in table 5… for various Ia/p
ratios: = unit conversion factor equal to 0.000431 in SI unit.
A = drainage area, Km2
Q = depth of runoff, mm
Return 10
period 2 Years 5Years Years 25 Years 50 Years 100 Years
Ia/p 0.130 0.107 0.097 0.087 0.0816 0.0769
Qu 0.0821 0.0837 0.0845 0.0853 0.0861 0.0865
Meadow, continuous grass, protected from grazing and generally mowed for hay
30 58 71 78
Woods. Poor 45 66 77 83
Fair 36 60 73 79
Good 30 55 70 77
Because of the varied shape and topography of the Stickle Pond watershed, three paths of
flow were selected to determine TC, see Figure 2. These three paths are located in the top,
middle and bottom of the watershed. The TR-55 reference 1 is used to determine TC.
45.00
40.00
35.00
Axum
30.00 Maichew
Mekele
25.00
20.00
15.00
10.00
5.00
0.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
60.00
50.00
Addis Ababa
40.00
Bahir Dar
Deber Tabor
20.00
Deber Zeit
Fitch
10.00
Gonder
0.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
45.00
40.00
35.00
Kulumsa
30.00
Nazeret
Robe
25.00
20.00
15.00
10.00
5.00
0.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
30.00
25.00
Dire Dawa
20.00 Metehara
Mieso
15.00
10.00
5.00
0.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
60.00
50.00
Bedele
40.00 Gore
Jimma
30.00 Nekempte
20.00
10.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12
40.00
35.00
30.00
Arbaminch
25.00 Awassa
Wolita Sodo
20.00
15.00
10.00
5.00
0.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
50.00
40.00
Komobolcha
Sirinka
Woldia
30.00
20.00
10.00
0.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
45.00
40.00
35.00
Keberi Dihar
25.00 Gode
Moyale
20.00
Negele
15.00
Yabello
10.00
5.00
0.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
6.1 Introduction
An open channel is a conduit in which water is conveyed with a free surface. Although
closed conduits such as culverts and storm drains are open channels when flowing partially
full, the term is generally applied to natural and improved watercourses, gutters, ditches,
and channels. While the hydraulic principles discussed in this section are valid for all
drainage structures, the primary consideration is given to channels along, across,
approaching and leaving the highway.
In addition to performing its hydraulic function, the drainage channel should be
economical to construct and maintain. Open channels should be reasonably safe for
vehicles accidentally leaving the traveled way, pleasing in appearance, convey collected
water without damage to the highway or adjacent property and minimize the environmental
impacts.
These considerations are usually so interrelated that optimum conditions cannot be met for
one without compromising one or more of the others. The objective is to achieve a
reasonable balance, but the importance of traffic safety must not be underrated.
There are various types of open channels encountered by the road drainage designer of
highway facilities including:
• Stream channels;
• Chutes;
• Roadside channels or ditches;
• Irrigation channels; and
• Drainage ditches.
The principles of open channel flow hydraulics are applicable to all drainage systems
including culverts.
Stream channels are usually:
• Natural channels with their size and shape determined by natural forces
(morphology);
• Compound in cross section with a main channel for conveying low flows and a
floodplain to transport extreme flood flows; and
• Shaped geomorphologically by the long-term history of the sediment load and
water discharge that they have experienced.
Artificial channels include roadside channels, irrigation channels, and drainage ditches that
are man-made with regular geometric cross sections, and unlined, or lined with artificial or
natural material to protect against erosion.
While the principles of open channel flow are the same regardless of the channel type,
stream channels and artificial channels (primarily roadside channels) are treated separately
in this chapter.
When assessing the need for permanent or temporary access easements, entrance ramps
and gates through the right of way fences, consideration should be given to the size and
type of maintenance equipment required. Damaged channels can be expensive to repair
and interfere with the safe and orderly movement of traffic. Minor erosion damage within
the right of way should be repaired immediately after it occurs and action taken to prevent
the recurrence.
Conditions, which require extensive repair or frequently recurring maintenance, may
require a complete redesign rather than repetitive or extensive reconstruction. The advice
of an Expert Drainage Engineer should be sought when evaluating the need for major
restoration.
The growth of weeds, brush, and trees in a drainage channel can effectively reduce its
hydraulic efficiency. The result being that a portion of the design flow may overflow the
channel banks causing flooding and possible erosion.
Channel work on some projects may be completed several months before total project
completion. During this interim period, the contractor must provide interim protection
measures and possibly advance the planned erosion control program to assure that minor
erosion will not develop into major damage.
6.5 Economics
Economical drainage design is achieved by selecting the design alternative which best
satisfies the established design criteria at the lowest cost.
The economic evaluation of design alternatives should be commensurate with the
complexity and importance of the facility. Analysis of the channel location, shape, size,
and materials involved may reveal possibilities for reducing construction costs, flood
damage potential, maintenance problems and environmental impacts.
In principle, a drainage channel should have a flow velocity that neither erodes nor cause
deposition in the channel (refer to Chapter 2, Section 2.17.3 Table 2. 3. This optimum
velocity is dependent on the size and slope of channel, the quantity of flowing water, the
material used to line the channel, the nature of the bedding soil and the sediment being
transported by the flow.
The point of discharge into a natural watercourse requires special attention. Water entering
a natural watercourse from a highway drainage channel should not cause eddies with
attendant scour of the natural watercourse. In erodible embankment soils, if the flow line of
the drainage channel is appreciably higher than that of the watercourse at the point of
discharge, then the use of a spillway is advisable to prevent erosion of the channel.
Natural channels are water conveying sections such as streams, rivers, and swales which
have been formed by natural forces. Good drainage design involving natural channels will
ensure that the existing flow characteristics are retained such as size and shape of channel,
flow velocities, and flow distributions.
Channel cross sections at roadside locations should be determined by hydraulic and erosion
considerations to achieve a channel that has adequate capacity for the flow quantity to be
handled, will require little or no maintenance, will fit in the space available and will be
economically acceptable to construct.
The most common channel shape for large flows is the trapezoidal section. Trapezoidal
channels are easily constructed by machinery and are often the most economical to
construct. When a wide trapezoidal section is proposed, both traffic safety and aesthetics
can be improved by rounding all angles of the channel cross section with vertical curves.
Rectangular channels are often used to convey large flows in areas with limited right of
way and at town sections. At some locations, guardrail or other types of positive traffic
barrier may be necessary between the traveled way and the channel.
Although rectangular channels are relatively expensive to construct, since the walls must
be designed as earth retaining structures, the construction costs can be somewhat offset by
the reduced costs associated with right of way, materials, and channel excavation.
The need for scour checks should be assessed according to the gradient, soil type, velocity
and volume of water in the side drain.
Look for evidence of erosion to assess the severity of the problem and the frequency of
scour checks required. In extreme cases (steep slopes where there is no possibility of using
relief culverts to evacuate water) the side drain will have to be lined in either masonry or
concrete to prevent erosion. Where gullies outlets are proposed, the discharge can be
controlled by using check dams (see figure 6.12) built from rock just downstream of the
gully outlet. Gabion baskets should be used for stability in deeper gullies.
Figure 6-12: Check dams in Tigray Region on the left and in Gojam on the right
Although it is more of a construction rather than a design issue, it is best practice to leave a
solid bund of earth to dam the drain downstream of the turnout. If drains are being built by
hand then a short section of drain can be left un-excavated to provide the bund (refer to
Figure 13).
The frequency of turnouts is controlled by various factors. On flat ground, the capacity of
the side drain is critical: turnouts are required to prevent the side drain from overflowing.
On sloping ground concentration of flows is critical: as the ground and hence the side drain
becomes steeper more turnouts are required to prevent the flow concentration leading to
Relief culverts are different from watercourse culverts. Their purpose is to relieve the flow
from long stretches of side drain ditches located on the uphill side of a road where miter
drains cannot be provided. These culverts should be used where possible instead of using
a long side ditch without relief culverts.
Side drain relief culverts are normally provided with a catch pit inlet structure. This is
designed to capture the water flowing along the side drain and turn that flow through 90o.
It then flows under the road and is discharged through an outfall channel.
The provision of access across drainage channels is often overlooked in Ethiopia. If access
across drainage channels is not provided, people will block the drain if it presents an
obstruction, causing water to flood the road. Therefore, access needs to be considered
carefully at a design stage (refer to figures 6.15, 6.16 and 6.17).
In rural areas a small number of accesses may be required in villages – for a market or
shop for instance. Lined drains with cover slabs are a typical solution (see figure 6.16).
The purpose of an access culvert is to allow water in side drains to flow under a minor road
where it branches off from the main road at a junction.
• An access culvert will be required if the minor road slopes towards the main road;
• But if the minor road slopes away from the main road the side drains can be
connected.
An access culvert will normally be required at junctions between a feeder road and a
collector road. Crossroads junctions will typically require one or two access culverts unless
located on a natural ridge or saddle. Access to plots or property is usually provided in the
form of access slabs over lined drains.
The invert level of an access culvert should be the same as (or slightly lower) than that of
the uphill side drain that needs to be passed under the road.
It is common to provide a bell mouth to allow longer turning vehicles to negotiate the
junction. For reasons of economy, the access culvert is often sited away from the collector
road edge before the bell mouth where the feeder road is of normal width. The collector
road side drain should be diverted to flow through the access culvert. Such diversions are
frequently lined in stone pitching and may have a slightly greater fall than the side drain to
encourage the change in flow direction.
Access culverts should be of just sufficient capacity to accommodate the maximum side
drain flow.
Side drains Keep water off the surface of the road and keep the foundations of the road dry.
Effective side drains will reduce the need for maintenance by preventing deterioration of
the surface and will provide a drier and hence safer road.
If the side drains are missing or not working then, water running along or across the road
may lead to gully erosion. The foundations may get wet and soft leading to rutting.
A common reason that side drains stop working is that people crossing the drain block
them: either vehicles driving across the drain and damaging it or pedestrians trying to make
walking over it easier.
Water Disposal
Side drains collect runoff water. That water then has to be discharged from the drain. This
can be either:
• To the adjoining ground by means of a turnout; or
• Across the road to the side drain on the downstream side of the road via a side drain
relief culvert.
The position and number of turnouts should be indicated on the design drawings. The final
location should be determined by site inspection so they are provided where they will
work.
Erosion Control
Side drains channel water and concentrate flows, especially where water is discharged via
turnouts. Scour of the side drains, if not controlled, can lead to the formation of gullies that
eventually can become so deep that the road may have to be abandoned. The construction
of simple scour checks and check dams in the side drains will reduce velocity, remove silt,
and allow vegetation to become established thus controlling erosion.
Erosion downstream of turnouts can affect not only the road but also the adjoining land. To
prevent erosion provide sufficient turnouts to disperse the flow and provide erosion
protection where necessary.
Channel Location and Type
Assuming adequate functional design, the next most important design consideration is
channel location. Locations that avoid poorly drained areas, unstable soil conditions, and
frequently flooded areas can greatly reduce drainage related problems.
Often drainage and open channel considerations are not considered the primary decision
factors in the roadway location; however, they are factors, which will often directly or
indirectly affect many other considerations. Often minor alignment adjustments can avoid
serious drainage problems.
If a channel can be located far enough away from the highway, the concerns of traffic
safety and aesthetics can be somewhat mitigated. The cost of additional right of way may
be offset somewhat by the reduced cost of erosion control, traffic protection, and
landscaping.
Ditches should be located where they can fully intercept the flow from the natural
catchments adjacent to the road. The location of ditches is mainly dependent on the space
available. Possible locations are:
• Along the edge of the road;
• Along the top of cuttings; or
• At the toe of embankments.
In cuttings, ditches should preferably be positioned at the top of the cuttings to avoid
potential erosion of the slope by surface water. Large sized ditches may create stability
problems in the cutting slope and, therefore, appropriate measures should be taken.
Where ditches are located alongside the road, they may be designed to convey the runoff
from the carriageway as well as that of the natural catchment. Ditches should preferably
consist of earth channels lined with a native grass species (or combination of species), in
order to provide adequate resistance to flow erosion. However, this depends on the
availability of water throughout the year in order for the native grass to grow.
The following design criteria apply to roadside channels:
• Channel side slopes shall not exceed the angle of repose of the soil and/or lining
and shall be 2:1 or flatter in the case of rock-riprap lining. Stone pitching or grouted
riprap must be used for channel side slopes steeper than 2:1;
• Flexible linings shall be calculated using the method of allowable tractive force;
• The design discharge frequency for permanent, roadside, ditch linings and for
temporary linings shall be per Table 2.1, Chapter 2; and
• Channel freeboard shall be 0.3 meters.
The following equations are those most commonly used to analyze open channel flow and
are included here.
Continuity Equation – The continuity equation is the statement of mass in fluid
mechanics. For the special case of one dimensional, steady flow of an incompressible fluid,
it assumes the form:
= = (6-1)
Where
Q = discharge, m3/s
A = cross-sectional area of flow, m2
V = mean cross-sectional velocity, m/s (which is perpendicular to the cross
section). Subscripts 1 and 2 refer to successive cross sections along the flow path.
Manning’s Equation –For a given depth of flow in a channel with a steady, uniform flow,
the mean velocity, V, can be computed with Manning’s equation:
/ /
= (6-2)
Where
V = velocity, m/s
n = Manning’s roughness coefficient
R = hydraulic radius = A/P, m
P = wetted perimeter, m
S = slope of the energy gradeline, m/m (note: for steady uniform flow,
S = channel slope, m/m)
In channel analysis, it is often convenient to group the channel properties in a single term
called the channel conveyance K:
/
= (6-4)
and then Manning’s Equation can be written as:
/
= (6-5)
The conveyance represents the carrying capacity of a stream cross-section based upon its
geometry and roughness characteristics alone and is independent of the streambed slope.
The concept of channel conveyance is useful when computing the distribution of overbank
flood flows in the stream cross section and the flow distribution through the opening in a
proposed stream crossing. Manning’s Equation should not be used for determining high-
water elevations in a bridge opening.
Energy Equation - The energy equation expresses conservation of energy in open channel
flow as energy per unit weight of fluid that has a dimension of head and it therefore called
energy head. The energy head is composed of potential energy head (elevation head),
pressure head, and kinetic energy head (velocity head). These energy heads are scalar
quantities that give the total energy head at any cross section when added. In comparing an
upstream open channel cross section designated 1 and a downstream cross section
designated 2, the energy equation is:
ℎ + ∝ = ℎ + ∝ + ℎ (6-6)
Where:
h1 and h2 = the upstream and downstream stages, respectively, m
α = kinetic energy correction coefficient
V = mean velocity, m/s
hL = head loss due to local cross-sectional changes (minor loss) as well as
boundary resistance, m
The stage ‘h’ is the sum of the elevation head ‘z’ at the channel bottom and the pressure
head, or depth of flow ‘y,’ i.e. h = z + y. The terms in the energy equation are illustrated
graphically in Figure 6-2. The energy equation states that the total energy head at an
upstream cross section is equal to the energy head at a downstream section plus the
intervening energy head loss. The energy equation can only be applied between two cross
sections at which the streamlines are nearly straight and parallel so that vertical
accelerations can be neglected.
Two methods are commonly used in hydraulic analysis of open channels. The Single-
Section method is a simple application of Manning’s Equation to determine tailwater rating
curves for culverts, or to analyze other situations in which uniform or nearly uniform flow
conditions exist. The Step-Backwater method is used to compute the complete water
surface profile in a stream reach to evaluate the unrestricted water surface elevations for
bridge hydraulic design, or to analyze other gradually varied flow problems in streams.
The single-section method will generally yield less reliable results because it requires more
judgment and assumption than the step-backwater method. In many designs, however, the
single-section method is all that is justified, for example, for a standard roadway ditch,
culvert, storm drain outfall, etc.
A computer program best performs hydraulic analysis of open channel problems. The
recommended personal computer program is the US Army Corps of Engineers HEC-RAS
River Analysis System. The Program was specifically developed for analysis of Highway
Bridge and culvert backwater analysis. HEC-RAS is designed to perform one-dimensional
hydraulic calculations for a full network of natural and constructed channels. HEC-RAS is
capable of importing GIS/CAD data. For more information on computer programs refer to
Chapter 15.
Another open channel modelling software is ISIS. ISIS is a full hydrodynamic simulator
for modelling flows and levels in open channels. ISIS is able to model complex looped and
branched networks, and is designed to provide a comprehensive range of methods for
simulating floodplain flows. ISIS incorporates both unsteady and steady flow solvers, with
options that include simple backwaters, flow routing and full unsteady simulation. The
simulation engine provides a direct steady-state solver and adaptive time-stepping methods
to optimize run-time and enhance model stability.
ERA should adapt standard software program to be used in all its drainage design works.
HEC-RAS should be used in all routing design except minor ditches. Based on our
assessment, only a minority of drainage designers use software for hydraulic analysis. The
current drainage design practice in Ethiopia is based on manual calculation in the form of
spreadsheet. It is recommended that drainage engineers to adopt hydraulic analysis
software in the design of road drainage systems.
The mathematical equations provided in this manual are embedded in the software
program; however, some of these equations have been retained in the manual as the
majority of drainage designers in Ethiopia use tradition manual calculation methods. Once
the skill in the use of software programs is developed in the country, these equations
should be used for information only.
Manning’s ‘n’ is affected by many factors and its selection in natural channels depends
heavily on engineering experience. Pictures of channels and flood plains for which the
discharge has been measured and Manning’s ‘n’ has been calculated are very useful (see
Ref. 3 and 4). Once the Manning’s ‘n’ values have been selected, it is highly recommended
that they be verified with historical high water marks and/or gauged stream flow data.
Manning’s ‘n’ values for artificial channels are more easily defined than for natural stream
channels. See Table 6-1 for typical ‘n’ values for both artificial and natural stream
channels. Photos 6.1-6.8 following table 6-1 also illustrate various types of channels and
their corresponding Manning’s n.
Equations can be calibrated to ensure that they accurately represent local channel
conditions. However, the calibration process requires a large amount of data, including
cross-sections, recorded water levels and flow rates. It should be considered if the failure
of a facility would increase risk to life or property.
The calibration process involves varying input parameters until a good agreement exists
between measured and simulated values. Hydraulic parameters which are varied include
roughness coefficients and expansion and contraction coefficients. The parameter with the
greatest influence on water levels is the Manning roughness coefficient.
If the cross section is improperly subdivided, the mathematics of the Manning’s Equation
causes a switchback. A switchback results when the calculated discharge decreases with an
associated increase in elevation. This occurs when, with a minor increase in water depth,
there is a large increase of wetted perimeter. Simultaneously, there is a corresponding
small increase in cross-sectional area which causes a net decrease in the hydraulic radius
from the value it had for a lesser water depth. With the combination of the lower hydraulic
radius and the slightly larger cross-sectional area, a discharge is computed which is lower
than the discharge based upon the lower water depth. More subdivisions within such cross-
sections should be used in order to avoid the switchback.
This phenomenon can occur in any type of conveyance computation, including the step-
backwater method. Computer logic can be seriously confused if a switchback were to
occur in any cross-section being used in a step backwater program. For this reason, the
cross-section should always be subdivided with respect to both vegetation and geometric
changes. Note that the actual n-value, itself, may be the same in adjacent subsections (refer
to example, calculations for further details).
In stream channels the transverse variation of velocity in any cross section is a function of
subsection geometry and roughness and may vary considerably from one stage and
discharge to another. It is important to know this variation when designing erosion control
measures and locating relief openings in highway fills, for example. The best method of
establishing transverse velocity variations is by current meter measurements. If this is not
possible, the single section method can be used, whereby the cross section is divided into
subsections of relatively uniform roughness and geometry. It is assumed that the energy
grade line slope is the same across the cross section so that the total conveyance KT of the
cross section is the sum of the subsection conveyances:
= + + ⋯ + (6-7)
The total discharge is then KtS1/2 and the discharge in each subsection is proportional to its
conveyance. The velocity in each subsection is obtained from the continuity equation,
V = Q/A.
Alluvial channels present a more difficult problem in establishing stage-discharge relations
by the single-section method because the bed itself is deformable and may generate bed
forms such as ripples and dunes in lower regime flows. These bed forms are highly
variable with the addition of form resistance, and selection of a value of Manning’s ‘n’ is
not straightforward. Instead, several methods (Ref. 35) have been developed for this case
and shall be followed unless it is possible to obtain a measured stage-discharge relation.
There may be locations where a stage-discharge relationship has already been measured in
a channel. These could exist at gauging stations on streams monitored by the Ministry of
Water and Energy. Measured stage-discharge curves will generally yield more accurate
estimates of water surface elevation and should take precedence over the analytical
methods described above.
Step-backwater analysis is useful for determining unrestricted water surface profiles where
a highway crossing is planned, and for analyzing how far upstream the water surface
elevations are affected by a culvert or bridge. Because the calculations involved in this
analysis are tedious and repetitive, a computer program such as U.S. Army Corps of
Engineers HEC-RAS can be used to assist with the equations.
The method requires definition of the geometry and roughness of each cross section.
Manning’s n-values can vary both horizontally across the section as well as vertically.
Expansion and contraction head loss coefficients, variable main channel and overbank flow
lengths, and the method of averaging the slope of the energy grade line can all be specified.
To develop the methodology, the energy equation is repeated from Section 6.4:
ℎ + ∝ = ℎ + ∝ + ℎ (6-8)
Where:
h1, h2 = the upstream and downstream stages, respectively, m
α = velocity distribution coefficient
V = mean velocity, m/s
hL = head loss due to local cross-sectional changes (minor loss) as well as boundary
resistance, m
The stage ‘h’ is the sum of the elevation head ‘z’ at the channel bottom and the pressure
head, or depth of flow y, i.e., h = z+y. The energy equation is solved between successive
stream reaches with nearly uniform roughness, slope, and cross-sectional properties.
The total head loss is calculated from:
(∝ ) (∝ )
= − + (6-9)
Where:
Km = expansion or contraction loss coefficient.
Sf = mean slope of the energy grade line evaluated from Manning’s equation and a
selected averaging technique m/m
L = discharge-weighted or conveyance-weighted reach length, m
These equations are solved numerically in a systematic procedure called the Standard Step
Method from one cross section to the next.
Water surface profile computation requires a beginning value for elevation or depth
(boundary condition) and proceeds upstream for subcritical flow and downstream for
supercritical flow. In the case of supercritical flow, critical depth is often the boundary
condition at the control section, but in subcritical flow, uniform flow and normal depth
may be the boundary condition. The starting depth in this case can be found either by the
single-section method (slope-area method) or by computing the water surface profile
upstream to the desired location for several starting depths and the same discharge. These
profiles should converge toward the desired normal depth at the control section to establish
one point on the stage-discharge relation. If the profiles do not converge, then the stream
reach may need to be extended downstream, a shorter cross-section interval shall be used,
or the range of starting water surface elevations shall be adjusted. In any case, a plot of the
convergence profiles can be a very useful tool in such an analysis (see Figure 6.21).
Given a sufficiently long stream reach, the water surface profile computed by step-
backwater will converge to normal depth at some point upstream for subcritical flow.
Establishment of the upstream and downstream boundaries of the stream reach is required
to define limits of data collection and subsequent analysis. Calculations must begin
sufficiently far downstream to assure accurate results at the structure site, and continued a
sufficient distance upstream to determine accurately the impact of the structure on
upstream water surface profiles(refer to chapter 4 how to define limits of data collection).
Refer to Figure 6-21.
Water and sediment routing methods should be employed where possible scour and/or
sediment are of concern. It is generally not used at stable stream locations. Various
computer models can be employed to investigate water and sediment routing. The latest
version of HEC-RAS has a sediment transport-modeling module. The scour or deposits in
each stream tube, determined by sediment routing, will give the variation of channel
geometry in the vertical direction.
The analysis of a stream channel, in most cases, takes place in conjunction with the design
of a highway hydraulic structure such as a culvert or bridge. In general, the objective is to
convey the water along or under the highway in such a manner that will not cause damage
to the highway, stream, or adjacent property. An assessment of the existing channel is
usually necessary to determine the potential for problems that might result from a proposed
action. The detail of studies necessary shall be commensurate with the risk associated with
the action and the environmental sensitivity of the stream and adjoining flood plain.
Although the following step-by-step procedure may not be appropriate for all possible
applications, it does outline a process that, in general, will be applicable.
Step 1 Assemble Site Data and Project File (Consult Chapter 4 for more details)
A. Data Collection
• Topographic, site, and location maps
• Roadway profile
• Photographs
• Field reviews
• Design data at nearby structures
• Gauging records.
Step 7 Documentation
• Prepare report and file with background information.
Each project is unique, but the following six basic design steps are normally applicable:
Step 1 Establish a Roadside Plan
A. Collect available site data
B. Obtain or prepare existing and proposed plan-profile layout including highway,
culverts, bridges, etc.
C. Determine and plot on the plan the locations of natural basin divides and roadside
channel outlets. An example of a roadside channel plan/profile is shown in Figure
6.9; and
D. Perform the layout of the proposed roadside channels to minimize diversion flow
lengths.
Step 2 Obtain or Establish Cross Section Data
A. Provide channel depth adequate to drain the sub-base
B. Choose channel side slopes based on geometric design criteria including safety,
economics, soil, aesthetics, and access;
C. Establish cross sectional area required and determine appropriate ditch shape and
size;
D. Identify features that may restrict cross section design:
• Right-of-way limits, trees or environmentally-sensitive areas;
• Utilities, and existing drainage facilities.
The major complicating factors in river mechanics are: 1) the large number of interrelated
variables that can simultaneously respond to natural or imposed changes in a stream
system; and 2) the continual evolution of stream channel patterns, channel geometry, bars,
and forms of bed roughness with changing water and sediment discharge. In order to
understand better the responses of streams to the actions of man and nature, a few simple
hydraulic and geomorphic concepts are presented.
Any natural or artificial change that alters channel slope can result in modifications to the
existing stream pattern. For example, a cutoff of a meander loop decreases channel
sinuosity and increases channel slope. Conversely, it is possible that a slight decrease in
slope could change an unstable braided stream into a meandering one.
The different channel dimensions, shapes, and patterns associated with different quantities
of discharge and amounts of sediment load indicate that as these independent variables
change, major adjustments of channel morphology can be anticipated. Further, a change in
hydrology may cause changes in stream sinuosity, meander wavelength, and channel width
and depth. A long period of channel instability with considerable bank erosion and lateral
shifting of the channel may be required for the stream to compensate for the hydrologic
change.
Degradation in streams can cause the loss of bridge piers in stream channels, as well as
piers and abutments in caving banks. A check dam, which is a mini dam or weir
constructed across a channel, is one of the most successful techniques for halting
degradation on small to medium streams.
Longitudinal stone dikes placed at the toe of channel banks can be effective
countermeasures for bank caving in degrading streams. Precautions to prevent outflanking
such as tiebacks to the banks, may be necessary where installations are limited to the
vicinity of the highway stream crossing. In general, channel lining alone is not a successful
countermeasure against degradation problems (Ref. 21).
Current measures in use to alleviate aggradation problems at highways include
channelization, bridge modification, continued maintenance, or any combination of these.
Channelization may include excavating and cleaning channels, constructing cutoffs to
increase the local slope, constructing flow control structures to reduce and control the local
channel width, and constructing relief channels to improve flow capacity at the crossing.
Except for relief channels, these measures are intended to increase the sediment transport
capacity of the channel, thus reducing or eliminating problems with aggradation.
The flow rate to use in the design of the outlets should be calculated using Manning's
resistance equation:
/ /
=
where Q is the flow rate (m3/s); A is the cross-sectional area of the flow (m2), S is the
longitudinal gradient of the channel (m/m); and n is the Manning roughness coefficient.
The hydraulic radius R is defined by:
where P is the wetted perimeter, ie the perimeter of the channel in contact with the water
flow. If the longitudinal gradient of the channel is not uniform along its length, an
equivalent value of the slope, S, should be used in the calculation of the flow rate.
When checking for surcharged conditions, the flow rate, Qs , to use in the design of outlets
can be estimated from Figure B3 for triangular channels and Figure B4 for trapezoidal
channels. In these Figures Bd and Qd are respectively the surface width of the flow and the
discharge corresponding to the design capacity of the channel. Qd is equal to the value of Q
given by Manning’s Equation when A and R corresponds to the design depth of flow, y1, in
the channel (measured from the invert centerline to the lower edge of the carriageway).
The curves in Figures B3 and B4 in Appendix 6A are based on 1m width of surcharging of
the carriageway at cross-falls of 1:30, 1:40 and 1:60. The value of Qs /Qd can be read off
the curves and, with Qs calculated using Manning’s Equation, the value of Qd can then be
determined.
Triangular Channels
The in-line outlet geometry recommended for this type of cahnnel consisits of pairs of
gratings positioned on the side slopes of the channel (see Figure B5). The number of pairs
of gratings reqiured will depend on the amount of flow in the channel. More than three
pairs of gratings are likely to be uneconomical, and other measures should be taken to cope
with higher flows.
The spacing between pairs of gratings should not be less than 1.7G, where G is the width
of the gratings (see Figure B4, Appendix 6A). The size of the required gratings should be
chosen so that the ratio of the width G over the depth of the channel y1, is within the
following limits:
1.5 ≤ 5.1
The lower limit corresponds to the minimum width of grating necessary to achieve the
performance specified. The upper limit corresponds to the widest grating that can be
installed in the channel. The required length H of each grating is given by:
≥
The lower edge of each grating should be set as close as possible to the invert of the
channel in order to maximize flow interception, ie distance in Figure B5 should be
minimized. A design of in-line outlet with gratings set flat in the channel invert is not
included because the limit with maximum cross fails of 1:4 would allow the use of only
small gratings with inefficient flow capacity.
The recommended geometry for off-line outlets is shown in Figure B6. The number of
gratings may vary from one to three depending on the amount of flow approaching the
outlet. However, outlets formed by a single grating may have the disadvantage of being
easily blocked by debris, particularly when the outlets are widely spaced than 1.25G where
G is the width of the gratings. The size of the gratings is determined by:
≥ 4.5
Trapezoidal Channels
The in-line outlet geometries recommended for trapezoidal channels are shown in Figures
B7 and B9, Appendix 6A. The width of the gratings is determined by:
= 3.0
The off-line geometries recommended are shown in Figure B8 and B10, Appendix 6A. The
width of the gratings is determined by:
≥ 4.0
Terminal Outlets
The requirement that surface water channels should not have any sides steeper than 1:4
applies also to the geometry of terminal outlets. When not protected by a safety barrier,
surface water channels must therefore terminate with a smooth transition, without abrupt
changes in level or width. Examples of recommended terminal outlets are shown in dashed
lines in Figures B5 to B10, Appendix 6A. The terminal ramps should be built at a certain
minimum distance from the grating furthest downstream. This reduces the probability of
blockage of the gratings by debris since some of the debris will tend to accumulate in the
area between the gratings and the terminal ramp. For in-line and off-line outlets in
triangular channels, this distance should equal the grating width. For in-line and off-line
outlets in trapezoidal channels, the recommended distances are given in terms of the
grating width, G, and are shown in Figures B7 to B10.
An outfall conveys water from one or more outlets in surface water channel to a suitable
discharge point. The design of an outfall may vary considerably depending on the general
topography and nature of the ground, the layout of the road scheme and weather the water
is discharged to a watercourse or below –ground pipe system. A chamber or gully pot
should be located below or immediately adjacent to each outlet to collect sediment carried
with the flow from the surface water channel. Standard circular gully pots have a limited
hydraulic capacity and it is recommended that they should not be used for flow rates
exceeding 5 l/s unless their suitability has been determined by test. The plan shape of the
chamber will be determined by the layout of the gratings forming the outlet. The invert of
the outgoing pipe from the chamber should be set a minimum of 300mm above the bottom
of the chamber to retain an adequate volume of sediment.
The invert level of the outgoing pipe should be chosen so that the water level in the
chamber does not raise high enough to prevent flow discharging freely from the surface
water channel into the outlet. For design, it is recommended that the water level in the
chamber should be at least 150mm below the underside of the gratings when the outlet is
receiving flow from the channel under surcharged condition. The height Z (in m), of the
water surface in the chamber above the invert of the outgoing pipe can be estimated from
the equation:
= + 0.23
2
where D is the diameter of the pipe (in m) and Q is the flow rate (in m3/s) in the chamber
corresponding to surcharge conditions in the surface water channel. The gradient and
diameter of the outgoing pipe should be determined from standard flow tables or resistance
equation so that the pipe is just flowing full under surcharged conditions.
Provided the chamber below the outlet is designed to trap sediment, the outgoing pipe from
the chamber may be connected directly to a collector pipe by means of a 45o Y junction
without the need for a manhole at the junction. If weir outlet is used, the collecting channel
into which flow drops from the weir should be deep enough to allow the outlet to discharge
freely when the surface water channel is flowing under surcharged conditions. The design
flow depth, J (in m), can be estimated from the equation:
= 4.82( )
Where E is the top width of flow (in m) and Q is design rate of flow (in m3/s). The overall
depth of the channel is obtained by adding 0.15m to the value of J14. The top width of the
channel should not be less than 0.5m. It is recommended that the collecting channel below
a weir outlet should discharge into a chamber with a removable cover in order to sill the
flow and allow sediment to be collected.
6.17 References
1. AASHTO, Vol. VI-Highway Drainage Guidelines, “Hydraulic Analysis and Design
of Open Channels,” AASHTO Task Force on Hydrology and Hydraulics, 1982.
2. American Society of Civil Engineers, High Velocity Flow in Open Channels: A
Symposium, “Design of Channel Curves for Supercritical Flow,” Transactions, Vol.
116, 1951.
3. Arcement, G.J., Jr., and Schneider, V.R., “Guide for Selecting Manning’s Roughness
Coefficients for Natural Channels and Flood Plains,’ Report No. FHWA-TS-84-204,
Federal Highway Administration, 1984.
4. Barnes, Harry H. Jr., “Roughness Characteristics of Natural Channels,” U.S.
Geological Survey Water Supply Paper 1849, U.S. Government Printing Office,
Washington, D.C., 1975.
5. Behlke, C.E., “The Design of Supercritical Flow Channel Junctions,” Highway
Research Record No. 123, Transportation Research Board, 1966.
6. Blodgett, J.C., “Rock Riprap Design for Protection of Stream Channels Near
Highway Structures,” Vol. 1, Water Resources Investigations Report 864127, U.S.
Geological Survey, prepared in cooperation with Federal Highway Administration,
1986.
7. Blalock, M.E., and Sturm, T.W., “Minimum Specific Energy in Compound Open
Channel,” Journal of Hydraulics Division, ASCE, Vol. 107, No. HY6, pp. 699-717,
June 1981.
8. Blodgett, J.C., and McConaughy, C.E., “Rock Riprap Design for Protection of
Stream Channels Near Highway Structures,” Vol. 2, Water Resources Investigations
Report 864127, U.S. Geological Survey, prepared in cooperation with Federal
Highway Administration, 1986.
9. Brice, J.C., and J.C. Blodgett, ‘Countermeasures for Hydraulic Problems at Bridges,
Vol. 1, Analysis and Assessment,” Federal Highway Administration /RD-75-162,
Federal Highway Administration, Washington, D.C., 1975.
10. Brown, S.A., “Streambank Stabilization Measures for Stream Crossings--Executive
Summary,” FHWA/RD-84/099, Federal Highway Administration, Washington, D.C.,
1985.
11. Brown, S.A., “Design of Spur-Type Streambank Stabilization Structures,” Federal
Highway Administration /RD-84/101, Federal Highway Administration,
Washington, D.C., 1985.
14
Design of Outfalls for Surface Water Channels, HA78/96.
12. Brown, S.A., “Streambank Stabilization Measures for Highway Engineers,’ Federal
Highway Administration /RD-84/100, Federal Highway Administration,
Washington, D.C., 1985.
13. Chow, V.T., Open Channel Hydraulics, McGraw-Hill, 1970.
14. Clopper, Paul E., “Hydraulic Stability of Articulated Concrete Block Revetment
Systems During Overtopping Flow,” FHWA-RD-89-199, FHWA, Washington, D.C.,
November 1989.
15. Davidian, Jacob, “Computation of Water Surface Profiles in Open Channels,”
Techniques of Water Resources Investigation, Book 3, Chapter A15, U.S. Geological
Survey, 1984.
16. Federal Highway Administration, “Highways in the River Environment,” Training
and Design Manual, 1990.
17. Federal Highway Administration, “Hydraulic Design of Energy Dissipators for
Culverts and Channels,” Hydraulic Engineering Circular No. 14, U.S. DOT, U.S.
Government Printing Office, Washington, D.C., 1983.
18. Federal Highway Administration, “Design of Roadside Channels with Flexible
Linings, “ Hydraulic Engineering Circular No. 15, U. S. DOT, U. S. Government
Printing Office, Washington, D.C., 1985.
19. Federal Highway Administration, “Use of Riprap for Bank Protection,” Hydraulic
Engineering Circular No. I-1, U.S. Department of Transportation, U.S. Government
Printing Office, Washington, D.C., 1967.
20. Federal Highway Administration, “Design Of Riprap Revetments,” Hydraulic
Engineering Circular FHWA 89-016 Government Printing Office, Washington, D.C.,
1989.
21. Federal Highway Administration, “Stream Stability,” Hydraulic Engineering Circular
No. 20, U.S. DOT, 1991.
22. Henderson, F.M., Open Channel Flow, Macmillan, 1966.
23. Lane, E.W., “A Study of the Shape of Channels Formed by Natural Stream Flowing
in Erodible Material,” M.R.D. Sediment Series No. 9, U.S. Army Corps of Engineer
Division, Missouri River, Corps of Engineers, Omaha, Nebraska, 1957.
24. Molinas, Albert, Users Manual for BRI-STARS, NCHRP Project HR 15-11, 1990
(Dram Report), National Cooperative Highway Research Program.
25. Molinas, Albert, BRI-STARS Expert System For Stream Classification, NCHRP
Project 15-11, 1990 (Dram Report).
26. Odgaard, A. Jacob, and Spoljaric, Anita, “Sediment Control by submerged Vanes,”
Journal of Hydraulic Engineering, ASCE, Vol. 112, No. 12 December 1986.
27. Odgaard, Jacob A., and Mosconi, Carlos E., “Streambank Protection by Submerged
Vanes, Journal of Hydraulic Engineering, ASCE, Vol. 113, No. 4, April 1987.
28. Richardson, E.V., D.B. Simons, and P.Y. Julien, “Highways in the River
Environment,” prepared for the Federal Highway Administration, Washington, D.C.
by the Department of Civil Engineering, Colorado State University, Fort Collins,
Colorado, June 1990.
29. Rouse, Hunter, ed., Engineering Hydraulics, John Wiley & Sons, Inc., 1950.
30. Shearman, J.0., “WSPRO User’s Instructions,” FHWA IP-89-27, 1990.
31. Shen, H.W., Schumm, S.A. Nelson, J.D. Doehring, D.O. and M.M. Skinner,
“Methods for Assessment of Stream-Related Hazards to Highways and Bridges,”
FHWA/RD-80/160, Federal Highway Administration, Washington, D.C., 1981.
32. Sturm, T.W., “Simplified Design of Contractions in Supercritical Flow,” Journal of
Hydraulic Engineering, ASCE, Vol. 11, No. 5, May 1985.
33. U.S. Army Corps of Engineers, “Accuracy of Computed Water Surface Profiles”,
The Hydrologic Engineering Center, Davis, California, December 1986.
34. U.S. Army Corps of Engineers, “HEC-2 Water Surface Profiles, User’s Manual,”
The Hydrologic Engineering Center, Davis, CA, 1982.
35. Vanoni, Vito A., ed., Sedimentation Engineering, ASCE Manual No. 54, ASCE, 345
East 47th St., New York, NY, 1977.
36. Drainage Manual, Drainage and Hydrology Section, Highway Design Office,
Ontario Ministry of Transportation, Downsview, Ontario, 1986-1993.
Figure 6A-3: Relationship between surcharged and channel-full flows: Trapezoidal channels
3 U1
2,5
U2
2
U3
1,5
U4
Discharge, m3/s
1
CHART 6-1
U5
0,5
U6
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07 0,08 0,09 0,1 0,11 0,12
Slope, m/m
Ethiopian Roads Authority Page 6-137
Chapter 6
Hydraulic Design of Open Channels Drainage Design Manual – 2013
20,0 R1
18,0 R2
16,0 R3
14,0 R4
12,0 R5
10,0 R6
CHART 6-2
8,0 R7
Discharge, m3/s
6,0 C1
4,0 C2
2,0 C3
0,0 C4
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07 0,08 0,09 0,1 0,11 0,12
Slope, m/m
G5
4,0
G6
R1
R2
Discharge, m3/s
2,0 R3
CHART 6-3
R4
R5
G4
0,0
0 0,01 0,02 0,03 0,04
Slope, m/m
G5
4,0
G6
R1
R2
Discharge, m3/s
2,0 R3
R4
CHART 6-4
R5
G4
0,0
0 0,01 0,02 0,03 0,04
Slope, m/m
Solution
We need to determine the velocity of flow using Manning’s formula first, then the flow
rate using the fundamental equation and finally, determine Froude’s number to describe the
state of flow.
Manning’s equation is:
. .
=
Where R is the hydraulic radius, determines as cross sectional area of flow (A) divided by
the wetted perimeter (P). Also, S is the slope of the energy line which we don’t have,
therefore we can use the bed slope (So) to approximate S.
Step 1. Calculate the cross sectional area of the flow.
= 1.2 ∗ 1.2 + 1.2 ∗ 2.5 = 4.44
Step 2. Calculate the wetted perimeter.
We have determined that Q = 4.71 m3/s, A = 4.44 m2 and g is acceleration due to gravity
(taken as 9.81 m/s2), therefore we need to calculate B, the width of flow across the surface.
= 1.2 + 2.5 + 1.2 = 4.9
Therefore:
4.9
= 4.71
9.81 ∗ 4.44
= 0.36
Froude’s number is below 1.0, therefore the flow is subcritical.
End of Example
Example 6-2
This example describes the process to determine the depth and velocity of flow based on a
known discharge / flow rate in a stream, based on discussion in Section 8.4.
The example commences after the stream data (such as cross section, terrain, condition of
channel and stream profile to determine site bed slope) has been gathered (refer Chapter 4)
and the flow rate (as determine using Rational Method) has been determined (refer Chapter
5). The task for this example is, given the stream data and flow rate (see diagram below),
determine the depth and velocity of flow in the channel.
Stream Data
• Discharge/flow rate = 17.86 m3/s
• Bed slope about the site is 1.2%
• Ht of channel bed is 65.10 m
• Max depth of flow is 2.0 m
• Manning’s n = 0.06.
Solution
To solve for d, we need to use Manning’s formula and develop a Stage-Discharge curve.
. .
∗
=
Step 3. Now draw the Stage-Discharge curve for this site/channel (refer next page).
Step 4. From the curve, we can now read of the flow depth for our design flow of
17.86 m3/s.
Q = 17.86 m3/s, therefore d = 1.62 m
Step 5. Now we can use the depth to calculate flow area, then Q = V.A to determine the
average flow velocity.
A = 1.62 2 + 1.62 x 4 = 9.10 m2
17.86 m 3/s = V x 9.10 m2
V = 1.96 m/s
End of Exercise
Example 6- 3
This example describes the process to determine the flow rate, the average velocity of a
flow in a compound stream.
The example commences after the stream data (such as cross section, terrain, Manning’s n
and stream profile to determine site bed slope) has been gathered (refer Chapter 4).
The task for this example is, given the stream data and height of flow (see diagram below),
determine the average velocity of flow in the channel and the flow rate.
Stream Data
• Bed slope about the site is 0.8%
Solution
To solve for Q, we need to use Manning’s formula for each sub section of stream:
. .
∗
=
Using , = 6.90 /
Step 2. For sub-section B, calculate VB using Manning’s equation.
= 7.39
= 4.83
= 1.53
Now,
. .
1.531 ∗ 0.008
= = 3.40 /
0.035
Using , = 25.09 /
Step 3. For sub-section C, calculate V C using Manning’s equation.
= 3.50
= 4.41
= 0.79
Now,
. .
0.793 ∗ 0.008
= = 1.28 /
0.06
Using , = 4.47 /
Example 6-5
Given: A median ditch is lined with a good stand of native grasses (approximately 0.203m
in height). The ditch is trapezoidal with a bottom width of 1.2m and side
slopes of 1V:4H. The ditch slope is 0.010m/m.
Find: Compute the maximum discharge for which this lining will be stable and the
corresponding flow depth.
Solution: From Table 6-2, the native grass has a retardance class of C and from Table
6-3, the permissible shear stress is
τp = 48 Pa
Then the allowable depth can be determined by assuming τp = τd:
48
= = = 0.49
9800 9800 ∗ 0.01
Now determine the flow area A and hydraulic radius R:
= ( + ) = 0.49 1.2 + (4 ∗ 0.49) = 1.55
/ /
= + 2 (1 + ) = 1.2 + (2 ∗ 0.49)(1 + 15) = 5.24
1.55
= = = 0.30
5.24
Finally determine the Manning’s n value from Photo 21 and solve for Q from
Manning’s equation:
From Photo 21, n = 0.080 and
1 / /
=
1
= (1.55)(0.30) / (0.01) / = 0.86 /
0.080
(This method is called the maximum discharge method and is useful for determining
the stable channel capacity for a variety of different linings for purposes of
comparison).
Example 6-6
Given: A rectangular channel on a slope of 0.001 with a width of 1.8m expands to a width
of 3 m in a straight walled transition, Z = 0. The design discharge is 8.5 m3/s
and Manning’s n = 0.02.
Find: Calculate the depth of flow in the upstream 1.8m wide channel if normal depth is the
downstream control.
Solution: (1) Compute the downstream normal depth y2:
1.486 1.486 ∗ 0.02 ∗ 8.5
/ /
= = 0.427
3.0 / ∗ 0.001 /
Then from Figure 6-4 with z = 0: y2/b = 0.68 and y2 = 2.04 m and
for a rectangular channel, yc = ((Q/b)2/g)1/2 = 0.9 m
SUBCRITICAL
Example 6.7
Given: A rectangular transition contracts from a width of 3.0 m to a width of 1.5 m. The
approach flow rate is 8.5 m3/s with a depth of 0.3 m.
Find: Calculate the depth in the contracted section and the angle and length of the
contraction so that the transmission of standing waves downstream is
minimized.
Solution: (1) ............... Calculate the approach Froude number for a rectangular channel.
8.5
(3.0 ∗ 0.3)
= = = 5.5
( ) / (9.8 ∗ 0.3) /
= 5° = 2.1 = 0.62
/
= = 0.66 = 3.6
−
= 2 = 8.57
tan 5°
This design satisfies the criterion F3>2 and also is just to the left of curve, A which means
choking is not possible (for the complete equations see HEC-14 and Storm. 1985).
7 CULVERTS
7.1 Introduction
Cross drainage involves the conveyance of surface water and stream flow across or from
the highway right of way. This is accomplished by providing either a culvert or a bridge to
convey the flow from one side of the roadway to the other side or past some form of flow
obstruction.
In addition to the hydraulic function, a culvert must carry construction and highway traffic
and earth loads. Culvert design, therefore, involves both hydraulic and structural design.
However, this section of the manual is concerned with the hydraulic design of culverts.
Both the hydraulic and structural designs must be consistent with good engineering
practice and economics.
The culvert should be designed to suit the outlet conditions even if inlet conditions have to
be modified (e.g. a drop inlet to reduce potential scouring velocities through the culvert).
In most cases, culvert locations are predetermined by the intersection of a watercourse and
an existing roadway. However, where circumstances allow, culverts should be located
away from:
• Erodible or meandering channel bends or banks;
• Critical or isolated aquatic habitat areas; and
• Isolated sections of remnant, valued, or protected riparian vegetation.
If at all possible, culverts should not be located on the bend of an unstable or otherwise
meandering channel. Realigning short sections of an existing channel to fit the culvert
alignment should also be avoided. Where roads traverse broad floodplains or otherwise
interfere with overland flow patterns, regular culverts may be needed to mitigate against
the adverse environmental effects of drainage shadow.
Where possible, culverts should be designed to provide acceptable velocities without the
need for additional stream bed protection. Allowable streambed velocities to avoid scour
vary according to soil type and topography. Suggested maximum average culvert velocities
for various stream bed materials are given in Table 7.1. Scour and preventative measures
are discussed further in Section 7.18.
(Sources: Left South African Manual 2006, Right Photo from Tigray Ethiopia)
In flat terrain it may be necessary to construct levee banks (Figure 7.3) to achieve the
design headwater at the culvert location. Where necessary, approval of the local road
authorities should be obtained prior to construction of any levee banks.
7.8 Siltation/Blockage
The likelihood of blockage should be considered for all culverts. Blockage can occur
through siltation or vegetation, although blockage by siltation is more likely to be
temporary in nature. This is because during flood events, silt deposits can be removed by
high velocity flows. To prevent siltation the desirable minimum velocity in the culvert
should be above 0.7 m/s. A check of velocities should be undertaken as part of design
process.
Where debris blockage is considered likely, larger culvert sizes may be required, in
accordance with the extent of adverse impacts that could occur to the roadway or to
surrounding properties. Blockage by debris is more likely to occur where the catchment
contains significant woody riparian vegetation. In this case detailed assessment of the
catchment is required.
7.10 Tailwater
Tailwater (TW) is the depth at the culvert outlet, measured from the water surface in the
downstream channel to the invert of the culvert. Tailwater is significant for the following
reasons;
• A high tailwater may cause the culvert to flow full or under pressure, so increasing
the headwater necessary to pass the flow; and
• A low tailwater relative to the depth of flow in the culvert can result in erosion of
the downstream channel.
If the channel is regular in shape and steady uniform flow conditions can be expected, the
tailwater level can be determined using Manning’s formula as follows:
• Select a trial value of TW. This could be based on the suggested maximum velocity
in Table 7.1 and A = Q/V. The closer the trial TW is to the true value, the less
iteration will be required;
• Calculate the average channel velocity for this trial depth using Manning’s formula,
then calculate Q = AV;
• If the channel capacity exceeds the design discharge, recalculate with a reduced
depth; or if the channel capacity is less than the design discharge, recalculate with
an increased depth; and
• Repeat these steps until the estimated channel capacity is within 10% of the design
discharge.
For complex channels, backwater models such as HY8, the Hydraulic Engineering Centres
River Analysis System (HEC-RAS) MIKE, or ISIS can be used, although this would
normally only be necessary for large catchments.
For one-dimensional flow, the relationship between the discharge and the upstream energy
can be computed by an iterative process.
Inlet control can occur with the inlet submerged and the outlet not submerged. Under these
conditions, the flow contracts to a supercritical jet immediately downstream from the inlet.
When the tailwater depth exceeds critical depth, hc and the culvert is laid on a steep grade,
flow remains supercritical in the barrel and a hydraulic jump will form near the outlet. If
the culvert is laid on a slope less than critical, then a hydraulic jump will form in the barrel.
When the culvert flows under inlet control, the roughness and length of the culvert barrel
and the outlet conditions (including the depth of tailwater) are not factors in determining
culvert capacity. An increase in the slope of the culvert reduces headwater only to a small
degree, and can normally be neglected for conventional culverts flowing under inlet
control. Design charts for the design of concrete culverts with inlet control are provided in
Appendix 7A.
Flow under outlet control can be calculated from the formulae below, the parameters for
which are illustrated in Figure 7.5. The total head (H) required to pass water through a
culvert flowing under outlet control is determined by:
H = Hv+He+Hf
Where:
= ( )=
= ( )=
.
= ( )= .
∗
and
V = velocity of flow in the culvert barrel, (m/s)
Ke = entrance loss coefficient, for values see Table 7.2
N = Manning’s friction factor, for values see Table 7.3
L = length of culvert barrel, (m)
g = acceleration due to gravity = 9.8 m/s²
= ,( ) =
Substituting in the first equation above and simplifying:
.
= + + .
∗
This equation can be solved for H by the use of the full flow nomographs in Figure A 5
and Figure A 6 for concrete culverts and Figure A 7 to Figure A 10 for metal culverts
(refer to Appendix 7A).
From the development of this energy equation and Figure 7.4, H is the difference between
the elevation of the hydraulic grade line at the outlet and the energy line at the inlet. Since
the velocity head in the entrance pool usually is small when ponded conditions occur
(v2/2g ≈ 0), the water surface of headwater pool elevation can be assumed to equal the
elevation of the energy line.
Notes: The effect of wingwalls reduces with multi-cell culverts for 3 – 6 cell culverts,
assume entrance loss for wingwalls 100 to 250 to barrel; for culverts with more than 6
cells, assume wingwalls parallel (extension of sides), regardless of actual wings.
Concrete pipe
Projecting from fill, socket end (grove end) 0.2
Projecting from fill, square cut end 0.5
Headwall or headwall and wingwalls, socket end of pipe 0.2
Square edge 0.5
Rounded (radius = D/12) 0.2
Mitred to conform to fill slope 0.7
End section confirming to fill slope 0.5
Corrugated metal pipe
Projecting from fill (no headwall) 0.9
Headwall or headwall and wingwalls, square edge 0.5
Mitred to conform to fill slope 0.7
End section confirming to fill slope 0.5
Reinforced concrete box
Headwall parallel to embankment (no wingwalls), square edged on 3 edges 0.5
Rounded on 3 edges to radius of 1/12 cell dimensions 0.2
Wingwalls at 30º to 75º to cell, square edged at crown 0.4
Crown edge rounded to radius of 1/12 cell dimension 0.2
Wingwalls at 10º to 25º to cell, square edged at crown 0.5
Wingwalls parallel (extension of sides), square edged at crown 0.7
Note: end sections conforming to fill slope, refers to the sections available from manufacturers
Source: Bureau of Public Road (1965)
Where:
hc = Tailwater depth (m)
D = Diameter of culvert, (m).
For calculation of the outlet velocity, the TW may be slightly different than shown in Step
11 in Figure 7.6.