FRABELLE SHIPYARD CORPORATION

SANGALI, ZAMBOANGA FISH PORT COMPLEX, ZAMBOANGA CITY

STATUS REPORT ON CIVIL WORKS


FOR THE SHIPYARD SITE DEVELOPMENT
AS OF JUNE 5, 2020

Scope of Works Sub-Contractor Previous Completion Rate Completion Rate

1. Ground Leveling Megalith 80% 100%


2. Perimeter Fencing Double E 18% 25%
3. Technical Shop Megalith 40% 51%
4. Office and Accomodation Double E 15% 18%
5. Electrical Phase 1 Legendary Seven 12% 20%
SUB-TOTAL 43%

ECQ Start Date: 19 Mar 2020


ECQ End Date: 15 May 2020
GCQ Start Date: 16 May 2020 up to present

PREPARED BY:

PAUL BANDILLA
Superintendent, FSC- Zambo

CHECKED BY:

DAN BOLANOS / CONRAD VIEJO / BOGS DE GUZMAN


FSC-Zambo Project Team
Scope of Works: GROUND LEVELING & GRADING Status as of: 5 Jun 2020
Contractor: MEGALITH BUILDERS Actual Start: 24 Feb 2020

ACTIVITY: GROUND CLEARING


ACTUAL DAYS WORKED AS DATED: 24 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Grass removal for the Ship Building Area and Dry-docking Area
- Subjected for Herbicide Treatment Prior to Turnover
- 100% Completion (March 19,2020) of the Qouted and Approved Works
Scope of Works: GROUND LEVELING & GRADING Status as of: 5 Jun 2020
Contractor: MEGALITH BUILDERS Actual Start: 24 Feb 2020

ACTIVITY: DOCKWAY ENTRANCE EXCAVATIONAND CONCRETE REINFORMENT


ACTUAL DAYS WORKED AS DATED: - (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Waiting for the Supplementary quotation of Megalith for Slope Excavation and
Concrete Reinforcement Works
Scope of Works: PERIMETER FENCING Status as of: 5 Jun 2020
Contractor: DOUBLE E Actual Start: 6 Mar 2020

ACTIVITY: CONCRETE FENCE FOUNDATION LAYING AND METAL FRAME INSTALLATION


ACTUAL DAYS WORKED AS DATED: 22 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Ongoing construction of concrete foundations in drydocking area (First Photo)
- Ongoing installation of Metal Frame of Cyclone Wires (Second Photo)
Scope of Works: TECHNICAL SHOPS (MACHINE SHOP/WAREHOUSE) Status as of: 5 Jun 2020
Contractor: MEGALITH Actual Start: 5 Mar 2020
ACTIVITY: CONSTRUCTION OF CONCRETE PARTITION
ACTUAL DAYS WORKED AS DATED: 27 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Done layouting of the partition
- Ongoing construction of concrete partition
Scope of Works: OFFICE AND ACCOMMODATION Status as of: 5 Jun 2020
Contractor: DOUBLE E Actual Start: 6 Mar 2020

ACTIVITY: SEWAGE TANK CONSTRUCTION


ACTUAL DAYS WORKED AS DATED: 22 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Ongoing construction of the sewage tank for the Office and Accomodation
Scope of Works: OFFICE AND ACCOMMODATION Actual Start: 5 Jun 2020
Contractor: DOUBLE E Actual Start: 26 May 2020
ACTIVITY: CONSTRUCTION OF WALL PARTITION BETWEEN OFFICE AND ACCOMODATION
ACTUAL DAYS WORKED AS DATED: 22 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Ongoing construction of the walls for Office and Accomodation Area
Scope of Works: ELECTRICAL LAYOUT PHASE 1 Status as of: 5 Jun 2020
Contractor: LEGENDARY SEVEN Actual Start: 21 May 2020
ACTIVITY: PANEL BOARD HOUSING AND FOUNDATION
ACTUAL DAYS WORKED AS DATED: 27 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Done fabricating Panel Houses
- Ongoing Construction for Panel Board Concrete Foundation in the Drydocking
Area
Scope of Works: ELECTRICAL LAYOUT PHASE 1 Status as of: 5 Jun 2020
Contractor: LEGENDARY SEVEN Actual Start: 21 May 2020
ACTIVITY: PIPE WIREWAYS INSTALLATION
ACTUAL DAYS WORKED AS DATED: 27 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Ongoing concreting of excavated wire ways
- Ongoing laying out of piping wire ways from Switch Gear to Panel Boards in
Drydocking Area