MITSUI ENGINEERING & SHIP BUILDING CO.

PETRORABIGH
Activity ID Activity Name Original Start Finish 2010 2011
Duration Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 6465
RABIGH PC2 MEG UNIT STORAGE 308.00 03-Jul-10 A 06-Jul-11 RABIGH PC2 MEG UNIT STORAGE

CONSTRUCTION 308.00 03-Jul-10 A 06-Jul-11 CONSTRUCTION

C000 Commence demolation work 0.00 03-Jul-10 A Commence demolation work


C001 Commence roof removal work 0.00 06-Nov-10 A Commence roof removal work
C003 Commence erection of new tank 0.00 27-Nov-10 A Commence erection of new tank
C004 Complete demolation work 0.00 27-Nov-10 A Complete demolation work
C005 Complete roof removal work 0.00 24-Apr-11 Complete roof removal work
C006 Handing over of Tank 0.00 06-Jul-11 Handing over of Tank
C01 Tank construction 307.90 03-Jul-10 A 06-Jul-11 Tank construction
C01D Demolition of existing tank 90.10 04-Jul-10 A 27-Nov-10 A Demolition of existing tank
DEMOLITION OF EXISTING TANK 118.20 04-Jul-10 A 27-Nov-10 A DEMOLITION OF EXISTING TANK
C01C-010 Removing of damaged scaffold 6.00 04-Jul-10 A 09-Oct-10 A Removing of damaged scaffold
C01C-020 Installation of fire wall 6.00 20-Jul-10 A 13-Oct-10 A Installation of fire wall
C01C-030 Erection of scaffold 12.00 24-Jul-10 A 17-Aug-10 A Erection of scaffold
C01C-040 Removing of accessories 4.00 14-Aug-10 A 04-Sep-10 A Removing of accessories
C01C-050 Removing of instullation 15.00 29-Aug-10 A 23-Sep-10 A Removing of instullation
C01C-110 Cutting / releasing of 9th shell cource 3.00 30-Sep-10 A 04-Oct-10 A Cutting / releasing of 9th shell cource
C01C-120 Cutting / releasing of 8th shell cource 3.00 04-Oct-10 A 07-Oct-10 A Cutting / releasing of 8th shell cource
C01C-130 Cutting / releasing of 7th shell cource 3.00 07-Oct-10 A 11-Oct-10 A Cutting / releasing of 7th shell cource
C01C-140 Cutting / releasing of 6th shell cource 3.20 11-Oct-10 A 14-Oct-10 A Cutting / releasing of 6th shell cource
C01C-150 Cutting / releasing of 5th shell cource 3.40 16-Oct-10 A 19-Oct-10 A Cutting / releasing of 5th shell cource
C01C-160 Cutting / releasing of 4th shell cource 3.70 19-Oct-10 A 24-Oct-10 A Cutting / releasing of 4th shell cource
C01C-170 Cutting / releasing of 3th shell cource 4.00 24-Oct-10 A 28-Oct-10 A Cutting / releasing of 3th shell cource
C01C-180 Cutting / releasing of 2th shell cource 4.40 28-Oct-10 A 02-Nov-10 A Cutting / releasing of 2th shell cource
C01C-190 Cutting / releasing of 1th shell cource 4.40 02-Nov-10 A 07-Nov-10 A Cutting / releasing of 1th shell cource
C01C-200 Cutting / releasing of bottom plate 6.00 03-Nov-10 A 10-Nov-10 A Cutting / releasing of bottom plate
C01C-210 Dismantle of scaffold 26.00 04-Oct-10 A 03-Nov-10 A Dismantle of scaffold
C01C-310 Foundation inspection & repair 6.00 10-Nov-10 A 20-Nov-10 A Foundation inspection & repair
C01C-320 Check & change damaged anchor bolt 12.00 10-Nov-10 A 27-Nov-10 A Check & change damaged anchor bolt
ROOF REMOVAL 144.00 06-Nov-10 A 24-Apr-11 ROOF REMOVAL
CRRC-010 Civil contractor mobilization 6.00 06-Nov-10 A 06-Dec-10 A Civil contractor mobilization
CRRC-020 Preparation of work area 2.00 13-Nov-10 A 14-Nov-10 A Preparation of work area
CRRC-030 Form work / inspection of foundations 9.00 20-Nov-10 A 07-Dec-10 A Form work / inspection of foundations
CRRC-040 Pouring of concrete / inspection of foundations 3.00 08-Dec-10 A 09-Dec-10 A Pouring of concrete / inspection of foundations
CRRC-050 Installation / alignment of temp. columns 3.00 11-Dec-10 A 03-Feb-11 A Installation / alignment of temp. columns
CRRC-060 Installation of bracing 2.00 14-Dec-10 A 03-Feb-11 A Installation of bracing
CRRC-070 Handling / cutting of roof 6.00 02-Apr-11 A 07-Apr-11 Handling / cutting of roof
CRRC-080 Releasing cut portions 2.00 09-Apr-11 10-Apr-11 Releasing cut portions
CRRC-090 Removing of temp. structure 2.00 11-Apr-11 12-Apr-11 Removing of temp. structure
CRRC-100 Removing of temp. concrete foundation 4.00 13-Apr-11 17-Apr-11 Removing of temp. concrete foundation
CRRC-110 Site cleaing 3.00 18-Apr-11 20-Apr-11 Site cleaing
CRRC-120 Civil contractor demobilization 3.00 21-Apr-11 24-Apr-11 Civil contractor demobilization
CONST. NEW TANK TK-2502-001 (FR 16.47M DIA X 19.70M H) 189.80 27-Nov-10 A 06-Jul-11 CONST. NEW TANK TK-2502-001 (FR 16.47M DIA X 19.70M H)
C01E Erection of tank 80.50 27-Nov-10 A 20-Apr-11 Erection of tank
C01H Hydro test of tank 15.20 18-Apr-11 05-May-11 Hydro test of tank
C01P Painting of tank 76.90 02-Apr-11 29-Jun-11 Painting of tank
C01V Handing over of tank 37.00 24-May-11 06-Jul-11 Handing over of tank
ERECTION 120.50 27-Nov-10 A 20-Apr-11 ERECTION
TANK BASE 52.00 27-Nov-10 A 28-Feb-11 A TANK BASE
Annular Plate 4.00 27-Nov-10 A 02-Dec-10 A Annular Plate
C01EB1-010 Erection / fit up of annular plate 1.50 27-Nov-10 A 29-Nov-10 A Erection / fit up of annular plate
C01EB1-020 Welding of annular plate 2.50 29-Nov-10 A 02-Dec-10 A Welding of annular plate
Bottom Plate 48.00 29-Dec-10 A 28-Feb-11 A Bottom Plate
C01EB2-010 Erection / fit up of bottom plate 5.00 29-Dec-10 A 28-Feb-11 A Erection / fit up of bottom plate
C01EB2-020 Welding of bottom plate 8.00 02-Jan-11 A 10-Jan-11 A Welding of bottom plate
C01EB2-030 Fit up bottom to annular 2.50 22-Jan-11 A 24-Jan-11 A Fit up bottom to annular
C01EB2-040 Welding bottom to annular 4.00 23-Jan-11 A 27-Jan-11 A Welding bottom to annular
TANK SHELL 102.80 04-Dec-10 A 05-Apr-11 TANK SHELL
1st Shell Cource 46.20 04-Dec-10 A 28-Feb-11 A 1st Shell Cource
C01ES1-010 Erection / fit up of 1st shell plates 1.30 04-Dec-10 A 28-Dec-10 A Erection / fit up of 1st shell plates
C01ES1-020 Welding vertical 1st shell joints 2.50 05-Dec-10 A 09-Dec-10 A Welding vertical 1st shell joints
C01ES1-030 Fit up annular to shell 2.00 22-Jan-11 A 30-Jan-11 A Fit up annular to shell
C01ES1-040 Welding annular to shell 4.50 23-Jan-11 A 28-Feb-11 A Welding annular to shell
2nd Shell Cource 32.00 25-Dec-10 A 11-Jan-11 A 2nd Shell Cource
C01ES2-010 Erection / fit up of 2nd shell plates 1.20 25-Dec-10 A 26-Dec-10 A Erection / fit up of 2nd shell plates
C01ES2-020 Welding vertical 2nd shell joints 2.40 01-Jan-11 A 04-Jan-11 A Welding vertical 2nd shell joints
C01ES2-030 Fit up for 1st Circumferential joint 1.80 05-Jan-11 A 06-Jan-11 A Fit up for 1st Circumferential joint
C01ES2-040 Welding of 1st Circumferential joint 4.00 06-Jan-11 A 11-Jan-11 A Welding of 1st Circumferential joint
3rd Shell Cource 6.90 16-Jan-11 A 20-Jan-11 A 3rd Shell Cource
C01ES3-010 Erection / fit up of 3rd shell plates 1.10 16-Jan-11 A 17-Jan-11 A Erection / fit up of 3rd shell plates
C01ES3-020 Welding vertical 3rd shell joints 2.30 18-Jan-11 A 19-Jan-11 A Welding vertical 3rd shell joints
C01ES3-030 Fit up for 2nd Circumferential joint 1.60 19-Jan-11 A 19-Jan-11 A Fit up for 2nd Circumferential joint
C01ES3-040 Welding of 2nd Circumferential joint 3.80 19-Jan-11 A 20-Jan-11 A Welding of 2nd Circumferential joint
4th Shell Cource 10.00 29-Jan-11 A 02-Feb-11 A 4th Shell Cource
C01ES4-010 Erection / fit up of 4th shell plates 1.00 29-Jan-11 A 29-Jan-11 A Erection / fit up of 4th shell plates
C01ES4-020 Welding vertical 4th shell joints 2.20 29-Jan-11 A 30-Jan-11 A Welding vertical 4th shell joints
C01ES4-030 Fit up for 3rd Circumferential joint 1.50 31-Jan-11 A 01-Feb-11 A Fit up for 3rd Circumferential joint
C01ES4-040 Welding of 3rd Circumferential joint 2.00 01-Feb-11 A 02-Feb-11 A Welding of 3rd Circumferential joint
5th Shell Cource 6.00 07-Feb-11 A 12-Feb-11 A 5th Shell Cource
MITSUI ENGINEERING & SHIP BUILDING CO. PETRORABIGH
Activity ID Activity Name Original Start Finish 2010 2011
Duration Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 6465
C01ES5-010 Erection / fit up of 5th shell plates 0.80 07-Feb-11 A 07-Feb-11 A Erection / fit up of 5th shell plates
C01ES5-020 Welding vertical 5th shell joints 2.10 08-Feb-11 A 08-Feb-11 A Welding vertical 5th shell joints
C01ES5-030 Fit up for 4th Circumferential joint 1.40 08-Feb-11 A 09-Feb-11 A Fit up for 4th Circumferential joint
C01ES5-040 Welding of 4th Circumferential joint 3.30 10-Feb-11 A 12-Feb-11 A Welding of 4th Circumferential joint
Wind Girder#1 13.00 15-Feb-11 A 20-Mar-11 A Wind Girder#1
C01ESW-010 Erection / fit up of wind girder 3.00 15-Feb-11 A 24-Feb-11 A Erection / fit up of wind girder
C01ESW-020 Welding of wind girder 4.00 24-Feb-11 A 20-Mar-11 A Welding of wind girder
6th Shell Cource 6.20 14-Feb-11 A 19-Feb-11 A 6th Shell Cource
C01ES6-010 Erection / fit up of 6th shell plates 0.70 14-Feb-11 A 15-Feb-11 A Erection / fit up of 6th shell plates
C01ES6-020 Welding vertical 6th shell joints 2.00 14-Feb-11 A 16-Feb-11 A Welding vertical 6th shell joints
C01ES6-030 Fit up for 5th Circumferential joint 1.30 17-Feb-11 A 17-Feb-11 A Fit up for 5th Circumferential joint
C01ES6-040 Welding of 5th Circumferential joint 3.20 17-Feb-11 A 19-Feb-11 A Welding of 5th Circumferential joint
7th Shell Cource 4.40 21-Feb-11 A 24-Feb-11 A 7th Shell Cource
C01ES7-010 Erection / fit up of 7th shell plates 0.60 21-Feb-11 A 22-Feb-11 A Erection / fit up of 7th shell plates
C01ES7-020 Welding vertical 7th shell joints 1.90 22-Feb-11 A 22-Feb-11 A Welding vertical 7th shell joints
C01ES7-030 Fit up for 6th Circumferential joint 0.80 23-Feb-11 A 23-Feb-11 A Fit up for 6th Circumferential joint
C01ES7-040 Welding of 6th Circumferential joint 2.90 23-Feb-11 A 24-Feb-11 A Welding of 6th Circumferential joint
Wind Girder#2 29.00 26-Feb-11 A 05-Apr-11 A Wind Girder#2
C01ESW-030 Erection / fit up of wind girder 3.00 26-Feb-11 A 15-Mar-11 A Erection / fit up of wind girder
C01ESW-040 Welding of wind girder 4.00 16-Mar-11 A 05-Apr-11 A Welding of wind girder
8th Shell Cource 7.00 28-Feb-11 A 07-Mar-11 A 8th Shell Cource
C01ES8-010 Erection / fit up of 8th shell plates 0.60 28-Feb-11 A 28-Feb-11 A Erection / fit up of 8th shell plates
C01ES8-020 Welding vertical 8th shell joints 1.90 01-Mar-11 A 02-Mar-11 A Welding vertical 8th shell joints
C01ES8-030 Fit up for 7th Circumferential joint 0.80 02-Mar-11 A 02-Mar-11 A Fit up for 7th Circumferential joint
C01ES8-040 Welding of 7th Circumferential joint 2.90 05-Mar-11 A 07-Mar-11 A Welding of 7th Circumferential joint
9th Shell Cource 6.20 21-Mar-11 A 28-Mar-11 A 9th Shell Cource
C01ES9-010 Erection / fit up of 9th shell plates 0.60 21-Mar-11 A 21-Mar-11 A Erection / fit up of 9th shell plates
C01ES9-020 Welding vertical of 9th shell joints 1.90 21-Mar-11 A 23-Mar-11 A Welding vertical of 9th shell joints
C01ES9-030 Fit up for 8th Circumferential joint 0.80 23-Mar-11 A 24-Mar-11 A Fit up for 8th Circumferential joint
C01ES9-040 Welding of 8th Circumferential joint 2.90 24-Mar-11 A 28-Mar-11 A Welding of 8th Circumferential joint
Curb Angle 5.60 28-Mar-11 A 05-Apr-11 Curb Angle
C01ESC-010 Erection / fit up of curb angle 2.00 28-Mar-11 A 30-Mar-11 A Erection / fit up of curb angle
C01ESC-020 Welding curb angle 3.50 30-Mar-11 A 05-Apr-11 Welding curb angle
TANK ROOF 102.20 14-Dec-10 A 10-Apr-11 TANK ROOF
C01R-010 Erection of temporary structure 6.00 14-Dec-10 A 02-Jan-11 A Erection of temporary structure
C01R-020 Erection of roof frames 4.00 14-Dec-10 A 17-Jan-11 A Erection of roof frames
C01R-030 Erection of secondary rafters & plates 3.00 18-Jan-11 A 22-Jan-11 A Erection of secondary rafters & plates
C01R-040 Welding top side 6.00 23-Jan-11 A 29-Jan-11 A Welding top side
C01R-050 Welding under side 8.00 25-Jan-11 A 01-Feb-11 A Welding under side
C01R-060 Installation of roof appurtenance & walkway 6.00 12-Feb-11 A 19-Feb-11 A Installation of roof appurtenance & walkway
C01R-070 Lifting and seal welding to curb angle 2.00 07-Apr-11 10-Apr-11 Lifting and seal welding to curb angle
TANK ACCESSORIES 48.50 19-Feb-11 A 16-Apr-11 TANK ACCESSORIES
C01EAD Drip ring 5.00 02-Apr-11 06-Apr-11 Drip ring
C01EAS-G1 Shell appurtenance 0.00 02-Apr-11 02-Apr-11 Shell appurtenance
C01EAS-G3 Stairway 0.00 26-Feb-11 A 16-Apr-11 Stairway
C01EAS-G4 Misc. 0.00 16-Mar-11 A 16-Mar-11 A Misc.
Shell Accessories 48.50 19-Feb-11 A 16-Apr-11 Shell Accessories
Shell Appurtenance 36.90 19-Feb-11 A 02-Apr-11 Shell Appurtenance
C01EAS-020 Manways 0.30 26-Feb-11 A 26-Feb-11 A Manways
C01EAS-030 Inlet Nozzle N1 - 8" 0.60 16-Mar-11 A 16-Mar-11 A Inlet Nozzle N1 - 8"
C01EAS-040 To P 2502 N2 - 6" 1.20 16-Mar-11 A 17-Mar-11 A To P 2502 N2 - 6"
C01EAS-050 Return P 2502 N3 - 4" 1.00 19-Feb-11 A 19-Feb-11 A Return P 2502 N3 - 4"
C01EAS-060 Drain Nozzle N4 - 3" 1.20 19-Feb-11 A 20-Feb-11 A Drain Nozzle N4 - 3"
C01EAS-070 Thermo wall K3 - 1 1/2" 0.80 02-Apr-11 02-Apr-11 Thermo wall K3 - 1 1/2"
C01EAS-080 Foam chamber N8 - 8" 0.60 02-Apr-11 02-Apr-11 Foam chamber N8 - 8"
Stairway 42.20 26-Feb-11 A 16-Apr-11 Stairway
C01EAS-210 Preparation of Stairway 5.00 26-Feb-11 A 06-Apr-11 Preparation of Stairway
C01EAS-220 Erection/welding of supports 3.00 26-Feb-11 A 04-Apr-11 Erection/welding of supports
C01EAS-230 Erection/welding of stringer/platform/brackets 4.00 07-Apr-11 11-Apr-11 Erection/welding of stringer/platform/brackets
C01EAS-240 Erection of grating 2.50 12-Apr-11 14-Apr-11 Erection of grating
C01EAS-250- Erection of handrail 3.50 12-Apr-11 16-Apr-11 Erection of handrail
Misc. 29.20 26-Feb-11 A 02-Apr-11 Misc.
C01EAS-420 Fire fighting bracket supports 4.00 26-Feb-11 A 12-Mar-11 A Fire fighting bracket supports
C01EAS-440 Insulating supports 3.00 28-Mar-11 A 31-Mar-11 A Insulating supports
C01EAS-450 Earthing lug/Name plate 0.20 28-Mar-11 A 02-Apr-11 Earthing lug/Name plate
Drip Ring 5.00 02-Apr-11 06-Apr-11 Drip Ring
C01EAD-010 Erection / fit up of drip ring 2.00 02-Apr-11 03-Apr-11 Erection / fit up of drip ring
C01EAD-020 Welding of drip ring 3.00 04-Apr-11 06-Apr-11 Welding of drip ring
TANK CLEANING 14.30 31-Mar-11 A 20-Apr-11 TANK CLEANING
C01EC-010 Shell internal cleaning 8.00 03-Apr-11 A 14-Apr-11 Shell internal cleaning
C01EC-020 Shell external cleaning 4.00 31-Mar-11 A 20-Apr-11 A Shell external cleaning
C01EC-040 Temorary blind flanges 1.00 16-Apr-11 17-Apr-11 Temorary blind flanges
C01EC-050 Temporary piping and hydrotest connections 1.00 16-Apr-11 17-Apr-11 Temporary piping and hydrotest connections
HYDRO TEST 15.20 18-Apr-11 05-May-11 HYDRO TEST
C13H-010 Filling water 7.20 18-Apr-11 26-Apr-11 Filling water
C13H-020 Draining water 6.00 26-Apr-11 03-May-11 Draining water
C13H-030 Washing and cleaning 2.00 03-May-11 05-May-11 Washing and cleaning
PAINTING 77.00 02-Apr-11 A 29-Jun-11 PAINTING
ROOF PAINTING 17.00 02-Apr-11 A 14-Apr-11 ROOF PAINTING
MITSUI ENGINEERING & SHIP BUILDING CO. PETRORABIGH
Activity ID Activity Name Original Start Finish 2010 2011
Duration Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 6465
C01P0 ROOF PAINTING 17.00 02-Apr-11 A 07-Apr-11 ROOF PAINTING
C01P0-010 Blasting & 1st primer coat for internal roof 4.00 02-Apr-11 A 05-Apr-11 A Blasting & 1st primer coat for internal roof
C01P0-020 2nd primer coat for internal roof 1.40 06-Apr-11 A 07-Apr-11 A 2nd primer coat for internal roof
C01P0-030 1st Intermediate coat for internal roof 2.20 07-Apr-11 A 10-Apr-11 A 1st Intermediate coat for internal roof
C01P0-040 2nd Intermediate coat for internal roof 1.00 10-Apr-11 A 11-Apr-11 A 2nd Intermediate coat for internal roof
C01P0-050 1st top coat for internal roof 2.00 11-Apr-11 A 13-Apr-11 A 1st top coat for internal roof
C01P0-060 2nd top coat for internal roof 0.90 13-Apr-11 A 14-Apr-11 A 2nd top coat for internal roof
C01P0-070 Stripe coat for external roof 4.50 02-Apr-11 06-Apr-11 Stripe coat for external roof
C01P0-080 Final inspection and touch up of roof 1.00 20-Apr-11 A 07-Apr-11
INTERNAL PAINTING 47.20 05-May-11 29-Jun-11 INTERNAL PAINTING
C01P1 Internal painting 47.20 05-May-11 29-Jun-11 Internal painting
C01P1-010 Erect internal scaffolding 10.00 05-May-11 17-May-11 Erect internal scaffolding
C01P1-020 Blasting & 1st primer coat for internal shell 5.00 17-May-11 23-May-11 Blasting & 1st primer coat for internal shell
C01P1-030 2nd primer coat for internal shell 3.00 23-May-11 26-May-11 2nd primer coat for internal shell
C01P1-040 1st Intermediate coat for internal shell 4.00 26-May-11 31-May-11 1st Intermediate coat for internal shell
C01P1-050 2nd Intermediate coat for internal shell 2.40 31-May-11 04-Jun-11 2nd Intermediate coat for internal shell
C01P1-080 1st top coat for internal shell 3.00 04-Jun-11 07-Jun-11 1st top coat for internal shell
C01P1-085 2nd top coat for internal shell 2.00 07-Jun-11 09-Jun-11 2nd top coat for internal shell
C01P1-090 Final inspection & touch up for internal roof & shell 1.00 09-Jun-11 11-Jun-11 Final inspection & touch up for internal roof & shell
C01P1-100 Dismantal of scaffolding 8.00 11-Jun-11 20-Jun-11 Dismantal of scaffolding
C01P1-110 Tank cleaning 2.00 20-Jun-11 22-Jun-11 Tank cleaning
C01P1-130 Blasting & 1st primer coat of bottom plate 1.80 22-Jun-11 23-Jun-11 Blasting & 1st primer coat of bottom plate
C01P1-135 2nd primer coat of bottom plate 1.00 23-Jun-11 25-Jun-11 2nd primer coat of bottom plate
C01P1-140 1st Intermediate coat of bottom plate 1.40 25-Jun-11 27-Jun-11 1st Intermediate coat of bottom plate
C01P1-145 2nd Intermediate coat of bottom plate 0.70 27-Jun-11 27-Jun-11 2nd Intermediate coat of bottom plate
C01P1-150 1st top coat of bottom plate 0.90 28-Jun-11 28-Jun-11 1st top coat of bottom plate
C01P1-155 2nd top coat of bottom plate 0.50 28-Jun-11 29-Jun-11 2nd top coat of bottom plate
C01P1-160 Final inspection of bottom plate 0.50 29-Jun-11 29-Jun-11 Final inspection of bottom plate
EXTERNAL PAINTING 16.00 05-May-11 24-May-11 EXTERNAL PAINTING
C01P2-010 Erection of external scaffolding 10.00 05-May-11 17-May-11 Erection of external scaffolding
C01P2-020 Stripe coat for external shell 10.00 12-May-11 24-May-11 Stripe coat for external shell
INSULATION / INSTALLATION / HANDING OVER 37.00 24-May-11 06-Jul-11 INSULATION / INSTALLATION / HANDING OVER
C01V-010 Tank calibration 1.00 29-Jun-11 30-Jun-11 Tank calibration
C01V-030 Instruments Installation 3.40 30-Jun-11 05-Jul-11 Instruments Installation
C01V-050 Tank insulation 30.00 24-May-11 28-Jun-11 Tank insulation
C01V-060 Dismantal of extenal scaffolding 8.00 25-Jun-11 04-Jul-11 Dismantal of extenal scaffolding
C01V-070 Box up 2.00 04-Jul-11 06-Jul-11 Box up

Actual Work Critical Remaining Work Summary Page 3 of 3 Date Revision Checked Approved
23-Oct-10 REV.10 UPD.1 Amir Hegazy Abdul Kadir Umar
Remaining Work Milestone
04-Dec-10 REV.10 UPD.2 Amir Hegazy Abdul Kadir Umar