Classic Schedule Layout 28-Jul-22 18:57

Activity ID Activity Name Original Planned Planned Physical % Remaining


Duration Start Finish Complete Duration 2011 2012 2013 2014
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
650 01-Nov-10 08-Jan-14 0 08-Jan-14 A, EC00620-1 Ju
EC00620-1 Juniper Nursing Home - copy
EC1010 Building Pad Delivered by Owner 0 01-Nov-10 0% 0 Building Pad Delivered by Owner, 01-Nov-10 A
EC1080 Curbing 0 02-Nov-10 0% 0 Curbing, 02-Nov-10 A
EC2430 Substantial Completion - All TCO 0 08-Jan-14 0% 0 Substantial Completion - All T
649 02-Nov-10 08-Jan-14 0 08-Jan-14 A, EC00620-1.1
EC00620-1.1 Building 1
EC2440 Complete Building 1 0 08-Jan-14 0% 0 Complete Building 1,
EC00620-1.1.1 Structure 165 02-Nov-10 24-Aug-11 0 24-Aug-11 A, EC00620-1.1.1 Structure
EC1090 Building Pad Including UG Utils 39 02-Nov-10 12-Jan-11 100% 0 Building Pad Including UG Utils
EC1140 First Floor Masonry Structure 10 07-Jan-11 25-Jan-11 100% 0 First Floor Masonry Structure
EC1170 Second Floor Slab & Collar Beam 19 25-Jan-11 28-Feb-11 100% 0 Second Floor Slab & Collar Beam
EC1190 Second Floor Masonry Structure 10 01-Mar-11 16-Mar-11 100% 0 Second Floor Masonry Structure
EC1210 Third Floor Slab & Collar Beam 19 17-Mar-11 20-Apr-11 100% 0 Third Floor Slab & Collar Beam
EC1240 Third Floor Masonry Structure 10 20-Apr-11 06-May-11 70% 0 Third Floor Masonry Structure
EC1250 Fourth Floor Slab & Collar Beam 19 06-May-11 10-Jun-11 0% 0 Fourth Floor Slab & Collar Beam
EC1300 Fourth Floor Masonry Structure 10 10-Jun-11 28-Jun-11 0% 0 Fourth Floor Masonry Structure
EC1310 Roof Slab 19 28-Jun-11 02-Aug-11 0% 0 Roof Slab
EC1340 Stair and Elevator Masonry Structure 4 02-Aug-11 08-Aug-11 0% 0 Stair and Elevator Masonry Structure
EC1350 Roof Slab/Collar Beam 10 08-Aug-11 24-Aug-11 0% 0 Roof Slab/Collar Beam
EC00620-1.1.2 Roof 56 24-Aug-11 02-Dec-11 0 02-Dec-11 A, EC00620-1.1.2 Roof
EC1390 Place Roof Trusses and Sheathing 19 24-Aug-11 28-Sep-11 0% 0 Place Roof Trusses and Sheathing
EC1400 Place Mechanical Equipment Supports 19 24-Aug-11 28-Sep-11 0% 0 Place Mechanical Equipment Supports
EC1530 Built-Up Asphalt Roofing 27 28-Sep-11 15-Nov-11 0% 0 Built-Up Asphalt Roofing
EC1540 Felt and Tile Roofing 37 28-Sep-11 02-Dec-11 0% 0 Felt and Tile Roofing
EC1780 Roof Complete 0 02-Dec-11 0% 0 Roof Complete,
EC00620-1.1.3 Envelope 148 08-Aug-11 27-Apr-12 0 27-Apr-12 A, EC00620-1.1.3 Envelope
EC1360 Mobilize Scaffolding 10 08-Aug-11 24-Aug-11 0% 0 Mobilize Scaffolding
EC1410 Install Exterior Windows and Sliding Glass Doors Floor 1 15 24-Aug-11 21-Sep-11 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 1
EC1470 Install Exterior Windows and Sliding Glass Doors Floor 2 15 15-Sep-11 12-Oct-11 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 2
EC1490 Install Backing & Cauld Windows Floor1 8 16-Sep-11 29-Sep-11 0% 0 Install Backing & Cauld Windows Floor1
EC1500 Install Exterior Windows and Sliding Glass Doors Floor 3 14 05-Oct-11 27-Oct-11 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 3
EC1510 Install Backing & Cauld Windows Floor 2 8 06-Oct-11 19-Oct-11 0% 0 Install Backing & Cauld Windows Floor 2
EC1520 Install Exterior Windows and Sliding Glass Doors Floor 4 17 21-Oct-11 21-Nov-11 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 4
EC1570 Install Backing & Cauld Windows Floor 3 6 24-Oct-11 02-Nov-11 0% 0 Install Backing & Cauld Windows Floor 3
EC1580 Stucco Bands 8 15-Nov-11 29-Nov-11 0% 0 Stucco Bands
EC1650 Install Backing & Cauld Windows Floor 4 8 15-Nov-11 30-Nov-11 0% 0 Install Backing & Cauld Windows Floor 4
EC1660 Stucco Grey 15 29-Nov-11 27-Dec-11 0% 0 Stucco Grey
EC1690 Stucco Finish Coat 19 28-Dec-11 31-Jan-12 0% 0 Stucco Finish Coat
EC1840 Caulk 8 01-Feb-12 14-Feb-12 0% 0 Caulk
EC1900 Stucco Band Trim 10 14-Feb-12 01-Mar-12 0% 0 Stucco Band Trim
EC1980 Paint Exterior 10 08-Mar-12 26-Mar-12 0% 0 Paint Exterior
EC1990 Install Railings 29 08-Mar-12 27-Apr-12 0% 0 Install Railings
EC2110 Demobilize Scaffolding 10 26-Mar-12 11-Apr-12 0% 0 Demobilize Scaffolding
EC2140 Shell Complete 0 27-Apr-12 0% 0 Shell Complete,

Actual Work Critical Remaining Work Page 1 of 4 TASK filter: All Activities
Remaining Work Baseline Milestone © Oracle Corporation
Classic Schedule Layout 28-Jul-22 18:57
Activity ID Activity Name Original Planned Planned Physical % Remaining
Duration Start Finish Complete Duration 2011 2012 2013 2014
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
EC00620-1.1.4 Interior Finishes 257 28-Sep-11 03-Jan-13 0 03-Jan-13 A, EC00620-1.1.4 Interior Finishes
EC1550 Unit Finishes Building North - Floor 1 158 28-Sep-11 06-Jul-12 0% 0 Unit Finishes Building North - Floor 1
EC1630 Unit Finishes Building South - Floor 1 159 05-Oct-11 17-Jul-12 0% 0 Unit Finishes Building South - Floor 1
EC1670 Unit Finishes Building North - Floor 2 159 12-Oct-11 24-Jul-12 0% 0 Unit Finishes Building North - Floor 2
EC1700 Unit Finishes Building South - Floor 2 159 19-Oct-11 31-Jul-12 0% 0 Unit Finishes Building South - Floor 2
EC1790 Unit Finishes Building North - Floor 3 159 26-Oct-11 07-Aug-12 0% 0 Unit Finishes Building North - Floor 3
EC1820 Building 2 Elevators Complete 56 02-Dec-11 12-Mar-12 0% 0 Building 2 Elevators Complete
EC1850 Unit Finishes Building South - Floor 3 159 02-Nov-11 14-Aug-12 0% 0 Unit Finishes Building South - Floor 3
EC1910 Unit Finishes Building North - Floor 4 161 09-Nov-11 24-Aug-12 0% 0 Unit Finishes Building North - Floor 4
EC1950 Unit Finishes Building South - Floor 4 161 16-Nov-11 31-Aug-12 0% 0 Unit Finishes Building South - Floor 4
EC2240 Tenant Finishes for Clubhouse Areas 102 03-Jul-12 03-Jan-13 0% 0 Tenant Finishes for Clubhouse Areas
EC2370 Final Inspections and Punchlist 27 13-Nov-12 03-Jan-13 0% 0 Final Inspections and Punchlist
EC00620-1.1.5 Pool & Courtyard 138 28-Mar-12 29-Nov-12 0 29-Nov-12 A, EC00620-1.1.5 Pool & Courtyard
EC2080 Pool & Deck 113 28-Mar-12 17-Oct-12 0% 0 Pool & Deck
EC2270 Pergola and Amenities 40 19-Sep-12 29-Nov-12 0% 0 Pergola and Amenities
464 30-Nov-10 11-Mar-13 0 11-Mar-13 A, EC00620-1.2 Building 2
EC00620-1.2 Building 2
EC2420 Complete Building 2 0 11-Mar-13 0% 0 Complete Building 2,
EC00620-1.2.1 Structure 171 30-Nov-10 03-Oct-11 0 03-Oct-11 A, EC00620-1.2.1 Structure
EC1150 Building Slab Incl. UG Utils 38 30-Nov-10 07-Feb-11 100% 0 Building Slab Incl. UG Utils
EC1220 First Floor Masonry Structure 10 01-Mar-11 16-Mar-11 100% 0 First Floor Masonry Structure
EC1230 Second Floor Slab & Collar Beam 19 24-Mar-11 27-Apr-11 100% 0 Second Floor Slab & Collar Beam
EC1260 Second Floor Masonry Structure 10 28-Mar-11 13-Apr-11 100% 0 Second Floor Masonry Structure
EC1290 Third Floor Slab & Collar Beam 19 08-Apr-11 12-May-11 60% 0 Third Floor Slab & Collar Beam
EC1320 Third Floor Masonry Structure 10 12-May-11 31-May-11 0% 0 Third Floor Masonry Structure
EC1330 Fourth Floor Slab & Collar Beam 19 31-May-11 05-Jul-11 0% 0 Fourth Floor Slab & Collar Beam
EC1380 Fourth Floor Masonry Structure 10 05-Jul-11 21-Jul-11 0% 0 Fourth Floor Masonry Structure
EC1480 Roof Slab 17 21-Jul-11 22-Aug-11 0% 0 Roof Slab
EC1620 Stair and Elevator Masonry Structure 4 22-Aug-11 29-Aug-11 0% 0 Stair and Elevator Masonry Structure
EC1640 Roof Slab/Collar Beam 19 29-Aug-11 03-Oct-11 0% 0 Roof Slab/Collar Beam
EC00620-1.2.2 Roof 56 03-Oct-11 11-Jan-12 0 11-Jan-12 A, EC00620-1.2.2 Roof
EC1710 Place Roof Trusses and Sheathing 19 03-Oct-11 04-Nov-11 0% 0 Place Roof Trusses and Sheathing
EC1720 Place Mechanical Equipment Supports 19 03-Oct-11 04-Nov-11 0% 0 Place Mechanical Equipment Supports
EC1860 Built-Up Asphalt Roofing 27 04-Nov-11 22-Dec-11 0% 0 Built-Up Asphalt Roofing
EC1870 Felt and Tile Roofing 37 04-Nov-11 11-Jan-12 0% 0 Felt and Tile Roofing
EC2020 Roof Complete 0 11-Jan-12 0% 0 Roof Complete,
EC00620-1.2.3 Envelope 188 03-Oct-11 04-Sep-12 0 04-Sep-12 A, EC00620-1.2.3 Envelope
EC1730 Install Exterior Windows and Sliding Glass Doors Floor 1 19 03-Oct-11 04-Nov-11 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 1
EC1740 Mobilize Scaffolding 10 03-Oct-11 19-Oct-11 0% 0 Mobilize Scaffolding
EC1800 Install Exterior Windows and Sliding Glass Doors Floor 2 17 28-Oct-11 29-Nov-11 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 2
EC1830 Install Backing & Cauld Windows Floor1 10 31-Oct-11 16-Nov-11 0% 0 Install Backing & Cauld Windows Floor1
EC1880 Install Exterior Windows and Sliding Glass Doors Floor 3 17 21-Nov-11 22-Dec-11 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 3
EC1890 Install Backing & Cauld Windows Floor 2 8 22-Nov-11 07-Dec-11 0% 0 Install Backing & Cauld Windows Floor 2
EC1920 Install Exterior Windows and Sliding Glass Doors Floor 4 19 15-Dec-11 20-Jan-12 0% 0 Install Exterior Windows and Sliding Glass Doors Floor 4

Actual Work Critical Remaining Work Page 2 of 4 TASK filter: All Activities
Remaining Work Baseline Milestone © Oracle Corporation
Classic Schedule Layout 28-Jul-22 18:58
Activity ID Activity Name Original Planned Planned Physical % Remaining
Duration Start Finish Complete Duration 2011 2012 2013 2014
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
EC1930 Install Backing & Cauld Windows Floor 3 10 16-Dec-11 05-Jan-12 0% 0 Install Backing & Cauld Windows Floor 3
EC1940 Stucco Bands 10 18-Jan-12 03-Feb-12 0% 0 Stucco Bands
EC1960 Install Backing & Cauld Windows Floor 4 10 16-Jan-12 01-Feb-12 0% 0 Install Backing & Cauld Windows Floor 4
EC1970 Stucco Grey 19 03-Feb-12 08-Mar-12 0% 0 Stucco Grey
EC2050 Stucco Finish Coat 19 08-Mar-12 11-Apr-12 0% 0 Stucco Finish Coat
EC2130 Caulk 10 11-Apr-12 27-Apr-12 0% 0 Caulk
EC2160 Stucco Band Trim 19 27-Apr-12 01-Jun-12 0% 0 Stucco Band Trim
EC2220 Paint Exterior 39 08-Jun-12 16-Aug-12 0% 0 Paint Exterior
EC2230 Install Railings 29 08-Jun-12 31-Jul-12 0% 0 Install Railings
EC2300 Demobilize Scaffolding 10 16-Aug-12 04-Sep-12 0% 0 Demobilize Scaffolding
EC2320 Shell Complete 0 04-Sep-12 0% 0 Shell Complete,
EC00620-1.2.4 Interior Finishes 241 04-Jan-12 11-Mar-13 0 11-Mar-13 A, EC00620-1.2.4 Interior Finishes
EC2000 Unit Finishes Building North - Floor 1 161 04-Jan-12 17-Oct-12 0% 0 Unit Finishes Building North - Floor 1
EC2030 Unit Finishes Building South - Floor 1 161 11-Jan-12 24-Oct-12 0% 0 Unit Finishes Building South - Floor 1
EC2040 Building 1 Elevators Complete 56 11-Jan-12 18-Apr-12 0% 0 Building 1 Elevators Complete
EC2070 Unit Finishes Building North - Floor 2 157 18-Jan-12 24-Oct-12 0% 0 Unit Finishes Building North - Floor 2
EC2120 Unit Finishes Building South - Floor 2 157 25-Jan-12 31-Oct-12 0% 0 Unit Finishes Building South - Floor 2
EC2150 Unit Finishes Building North - Floor 3 157 01-Feb-12 07-Nov-12 0% 0 Unit Finishes Building North - Floor 3
EC2170 Unit Finishes Building South - Floor 3 157 08-Feb-12 14-Nov-12 0% 0 Unit Finishes Building South - Floor 3
EC2200 Unit Finishes Building North - Floor 4 156 15-Feb-12 19-Nov-12 0% 0 Unit Finishes Building North - Floor 4
EC2210 Unit Finishes Building South - Floor 4 156 22-Feb-12 27-Nov-12 0% 0 Unit Finishes Building South - Floor 4
EC2410 Final Inspections and Punchlist 58 27-Nov-12 11-Mar-13 0% 0 Final Inspections and Punchlist
EC00620-1.2.5 Courtyard 73 04-Sep-12 14-Jan-13 0 14-Jan-13 A, EC00620-1.2.5 Courtyard
EC2330 Courtyard Walks and Amenities 73 04-Sep-12 14-Jan-13 0% 0 Courtyard Walks and Amenities
303 23-Jun-11 18-Dec-12 0 18-Dec-12 A, EC00620-1.5 Garage 1
EC00620-1.5 Garage 1
EC1420 Start Garage 0 23-Jun-11 0% 0 Start Garage, 23-Jun-11 A
EC1430 Shop Drawings, Review & Approval 58 23-Jun-11 05-Oct-11 0% 0 Shop Drawings, Review & Approval
EC1810 Fab & Delivery 58 05-Oct-11 18-Jan-12 0% 0 Fab & Delivery
EC2090 Erect Precast Structure 77 18-Jan-12 01-Jun-12 0% 0 Erect Precast Structure
EC2280 Fire Protection and Lighting 58 01-Jun-12 13-Sep-12 0% 0 Fire Protection and Lighting
EC2310 Finishes, Barrier Cables & Striping 58 15-Aug-12 27-Nov-12 0% 0 Finishes, Barrier Cables & Striping
EC2380 Punchlist Garage 12 27-Nov-12 18-Dec-12 0% 0 Punchlist Garage
EC2390 Complete Garage 1 0 18-Dec-12 0% 0 Complete Garage 1,
EC2400 Complete Garage 0 18-Dec-12 0% 0 Complete Garage,
342 01-Nov-10 05-Jul-12 0 05-Jul-12 A, EC00620-1.6 Garage 2
EC00620-1.6 Garage 2
EC1020 Design Building Addition 0 01-Nov-10 0% 0 Design Building Addition, 01-Nov-10 A
EC1030 Shop Drawings, Review and Approval 58 01-Nov-10 14-Feb-11 100% 0 Shop Drawings, Review and Approval
EC1180 Fab & Delivery 58 22-Feb-11 02-Jun-11 76% 0 Fab & Delivery
EC1280 Erect Precast Structure 77 31-May-11 14-Oct-11 0% 0 Erect Precast Structure
EC1590 Fire Protection and Lighting 58 14-Oct-11 27-Jan-12 0% 0 Fire Protection and Lighting
EC1680 Finishes and Striping 67 29-Dec-11 26-Apr-12 0% 0 Finishes and Striping
EC2060 Punch List Garage 39 26-Apr-12 05-Jul-12 0% 0 Punch List Garage
EC2180 Complete Garage 2 0 05-Jul-12 0% 0 Complete Garage 2,

Actual Work Critical Remaining Work Page 3 of 4 TASK filter: All Activities
Remaining Work Baseline Milestone © Oracle Corporation
Classic Schedule Layout 28-Jul-22 18:58
Activity ID Activity Name Original Planned Planned Physical % Remaining
Duration Start Finish Complete Duration 2011 2012 2013 2014
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
EC2190 Complete Garage 0 05-Jul-12 0% 0 Complete Garage,
439 01-Nov-10 26-Dec-12 0 26-Dec-12 A, EC00620-1.7 Roads, Utilities & Pavers
EC00620-1.7 Roads, Utilities & Pavers
EC1000 Curbing 58 01-Nov-10 14-Feb-11 100% 0 Curbing
EC1040 Electric to Building 4 Power Vault 58 01-Nov-10 14-Feb-11 100% 0 Electric to Building 4 Power Vault
EC1050 Electric to Building 3 Power Vault 19 01-Nov-10 06-Dec-10 100% 0 Electric to Building 3 Power Vault
EC1100 Storm Drainage Site Work 58 02-Nov-10 15-Feb-11 100% 0 Storm Drainage Site Work
EC1110 Site Electrical Work & Temp Power 10 02-Nov-10 18-Nov-10 100% 0 Site Electrical Work & Temp Power
EC1130 Walkways 54 15-Nov-10 21-Feb-11 100% 0 Walkways
EC1200 Roadway Pavers 54 21-Feb-11 25-May-11 65% 0 Roadway Pavers
EC1270 Finish Paving, Striping and Signs 39 02-Jun-11 10-Aug-11 0% 0 Finish Paving, Striping and Signs
EC1440 Electric to Building 2 Power Vault 73 24-Aug-11 04-Jan-12 0% 0 Electric to Building 2 Power Vault
EC1610 Curbs & Paving 46 14-Oct-11 06-Jan-12 0% 0 Curbs & Paving
EC1750 Electric to Building 1 Power Vault 56 03-Oct-11 11-Jan-12 0% 0 Electric to Building 1 Power Vault
EC2250 Fountain/Water Feature 92 25-May-12 07-Nov-12 0% 0 Fountain/Water Feature
EC2260 Entry Feature/Sign Wall 83 01-Jun-12 26-Oct-12 0% 0 Entry Feature/Sign Wall
EC2290 Curbs & Paving 58 01-Jun-12 13-Sep-12 0% 0 Curbs & Paving
EC2340 Curbs & Paving 63 04-Sep-12 26-Dec-12 0% 0 Curbs & Paving
536 24-May-11 08-Jan-14 0 08-Jan-14 A, EC00620-1.8
EC00620-1.8 Landscape & Irrigation
EC1600 Site Cleanup 39 24-May-11 02-Aug-11 0% 0 Site Cleanup
EC2360 Landscape & Irrigation 230 20-Nov-12 08-Jan-14 0% 0 Landscape & Irrigation

Actual Work Critical Remaining Work Page 4 of 4 TASK filter: All Activities