Juniper Nursing Home Classic Schedule Layout 15-Jan-2023 14:39

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float 2010 2011 2012 2013 2014 2015 2016
Duration Complete
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1Q2
EC00620 Juniper Nursing Home 949d 822d 12.8% 01-Nov-2010 18-Jul-2014 0d 18-Jul-2014, EC00620 Juniper Nursing Home
A
EC1010 Building Pad Delivered by Owner 0d 0d 100% 01-Nov-2010 A Building Pad Delivered by Owner, 01-Nov-2010 A
EC1080 Curbing 0d 0d 100% 02-Nov-2010 A Curbing, 02-Nov-2010 A
EC2430 Substantial Completion -All TCO 0d 0d 0% 18-Jul-2014 0d Substantial Completion -All TCO,
EC00620.1 Building 1 948d 822d 5.3% 02-Nov-2010 A18-Jul-2014 0d 18-Jul-2014, EC00620.1 Building 1
EC2440 Complete Building 1 0d 0d 0% 18-Jul-2014 0d Complete Building 1,
EC00620.1.1 Structure 208d 82d 73.22% 02-Nov-2010 A25-Aug-2011 0d 25-Aug-2011, EC00620.1.1 Structure
EC1090 Building Pad Including UG Utils 48d 0d 100% 02-Nov-2010 A07-Jan-2011 A Building Pad Including UG Utils
EC1140 First Floor Masonry Structure 12d 0d 100% 06-Jan-2011 A26-Jan-2011 A First Floor Masonry Structure
EC1170 Second Floor Slab & Collar Beam 24d 0d 100% 25-Jan-2011 A25-Feb-2011 A Second Floor Slab & Collar Beam
EC1190 Second Floor Masonry Structure 12d 0d 100% 02-Mar-2011 A18-Mar-2011 A Second Floor Masonry Structure
EC1210 Third Floor Slab & Collar Beam 24d 0d 100% 15-Mar-2011 A21-Apr-2011 A Third Floor Slab & Collar Beam
EC1240 Third Floor Masonry Structure 12d 4d 75% 20-Apr-2011 A06-May-2011 0d Third Floor Masonry Structure
EC1250 Fourth Floor Slab & Collar Beam 24d 24d 0% 06-May-2011 10-Jun-2011 0d Fourth Floor Slab & Collar Beam
EC1300 Fourth Floor Masonry Structure 12d 12d 0% 10-Jun-2011 28-Jun-2011 0d Fourth Floor Masonry Structure
EC1310 Roof Slab 24d 24d 0% 28-Jun-2011 02-Aug-2011 0d Roof Slab
EC1340 Stair and Elevator Masonry Structure 5d 5d 0% 02-Aug-2011 09-Aug-2011 0d Stair and Elevator Masonry Structure
EC1350 Roof Slab/Collar Beam 12d 12d 0% 09-Aug-2011 25-Aug-2011 0d Roof Slab/Collar Beam
EC00620.1.2 Roof 70d 70d 0% 25-Aug-2011 05-Dec-2011 375d 05-Dec-2011, EC00620.1.2 Roof
EC1390 Place Roof Trusses and Sheathing 24d 24d 0% 25-Aug-2011 29-Sep-2011 82d Place Roof Trusses and Sheathing
EC1400 Place Mechanical Equipment Supports 24d 24d 0% 25-Aug-2011 29-Sep-2011 260d Place Mechanical Equipment Supports
EC1530 Built-Up Asphalt Roofing 34d 34d 0% 29-Sep-2011 16-Nov-2011 260d Built-Up Asphalt Roofing
EC1540 Felt and Tile Roofing 46d 46d 0% 29-Sep-2011 05-Dec-2011 82d Felt and Tile Roofing
EC1780 Roof Complete 0d 0d 0% 05-Dec-2011 375d Roof Complete,
EC00620.1.3 Envelope 185d 185d 0% 09-Aug-2011 30-Apr-2012 144d 30-Apr-2012, EC00620.1.3 Envelope
EC1360 Mobilize Scaffolding 12d 12d 0% 09-Aug-2011 25-Aug-2011 32d Mobilize Scaffolding
EC1410 Install Exterior Windows and Sliding Glass Doors
19dFloor 1 19d 0% 25-Aug-2011 22-Sep-2011 0d Install Exterior Windows and Sliding Glass Doors Floor 1
EC1470 Install Exterior Windows and Sliding Glass Doors
19dFloor 2 19d 0% 15-Sep-2011 13-Oct-2011 0d Install Exterior Windows and Sliding Glass Doors Floor 2
EC1490 Install Backing & Cauld Windows Floor1 10d 10d 0% 16-Sep-2011 30-Sep-2011 16d Install Backing & Cauld Windows Floor1
EC1500 Install Exterior Windows and Sliding Glass Doors
17dFloor 3 17d 0% 06-Oct-2011 31-Oct-2011 0d Install Exterior Windows and Sliding Glass Doors Floor 3
EC1510 Install Backing & Cauld Windows Floor 2 10d 10d 0% 07-Oct-2011 20-Oct-2011 12d Install Backing & Cauld Windows Floor 2
EC1520 Install Exterior Windows and Sliding Glass Doors
22dFloor 4 22d 0% 24-Oct-2011 22-Nov-2011 0d Install Exterior Windows and Sliding Glass Doors Floor 4
EC1570 Install Backing & Cauld Windows Floor 3 7d 7d 0% 25-Oct-2011 03-Nov-2011 9d Install Backing & Cauld Windows Floor 3
EC1580 Stucco Bands 10d 10d 0% 16-Nov-2011 01-Dec-2011 0d Stucco Bands
EC1650 Install Backing & Cauld Windows Floor 4 10d 10d 0% 16-Nov-2011 01-Dec-2011 0d Install Backing & Cauld Windows Floor 4
EC1660 Stucco Grey 19d 19d 0% 01-Dec-2011 29-Dec-2011 0d Stucco Grey
EC1690 Stucco Finish Coat 24d 24d 0% 29-Dec-2011 02-Feb-2012 0d Stucco Finish Coat
EC1840 Caulk 10d 10d 0% 02-Feb-2012 15-Feb-2012 0d Caulk
EC1900 Stucco Band Trim 12d 12d 0% 15-Feb-2012 02-Mar-2012 0d Stucco Band Trim
EC1980 Paint Exterior 12d 12d 0% 09-Mar-2012 27-Mar-2012 0d Paint Exterior
EC1990 Install Railings 36d 36d 0% 09-Mar-2012 30-Apr-2012 144d Install Railings
EC2110 Demobilize Scaffolding 12d 12d 0% 27-Mar-2012 12-Apr-2012 0d Demobilize Scaffolding
EC2140 Shell Complete 0d 0d 0% 30-Apr-2012 144d Shell Complete,
EC00620.1.4 Interior Finishes 322d 322d 0% 29-Sep-2011 04-Jan-2013 260d 04-Jan-2013, EC00620.1.4 Interior Finishes
EC1550 Unit Finishes Building North - Floor 1 197d 197d 0% 29-Sep-2011 09-Jul-2012 260d Unit Finishes Building North - Floor 1
EC1630 Unit Finishes Building South - Floor 1 199d 199d 0% 06-Oct-2011 18-Jul-2012 260d Unit Finishes Building South - Floor 1
EC1670 Unit Finishes Building North - Floor 2 199d 199d 0% 13-Oct-2011 25-Jul-2012 311d Unit Finishes Building North - Floor 2
EC1700 Unit Finishes Building South - Floor 2 199d 199d 0% 20-Oct-2011 01-Aug-2012 311d Unit Finishes Building South - Floor 2
EC1790 Unit Finishes Building North - Floor 3 199d 199d 0% 27-Oct-2011 08-Aug-2012 311d Unit Finishes Building North - Floor 3
EC1820 Building 2 Elevators Complete 70d 70d 0% 05-Dec-2011 13-Mar-2012 375d Building 2 Elevators Complete

Actual Level of Effort Remaining Work Milestone Page 1 of 3

Actual Work Critical Remaining Work summary


Juniper Nursing Home Classic Schedule Layout 15-Jan-2023 14:39

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float 2010 2011 2012 2013 2014 2015 2016
Duration Complete
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1Q2
EC1850 Unit Finishes Building South - Floor 3 199d 199d 0% 03-Nov-2011 15-Aug-2012 311d Unit Finishes Building South - Floor 3
EC1910 Unit Finishes Building North - Floor 4 202d 202d 0% 10-Nov-2011 27-Aug-2012 311d Unit Finishes Building North - Floor 4
EC1950 Unit Finishes Building South - Floor 4 202d 202d 0% 17-Nov-2011 04-Sep-2012 311d Unit Finishes Building South - Floor 4
EC2240 Tenant Finishes for Clubhouse Areas 127d 127d 0% 05-Jul-2012 04-Jan-2013 260d Tenant Finishes for Clubhouse Areas
EC2370 Final Inspections and Punchlist 34d 34d 0% 14-Nov-2012 04-Jan-2013 260d Final Inspections and Punchlist
EC00620.1.5 Pool & Courtyard 307d 307d 0% 29-Mar-2012 13-Jun-2013 0d 13-Jun-2013, EC00620.1.5 Pool & Courtyard
EC2080 Pool & Deck 142d 142d 0% 29-Mar-2012 18-Oct-2012 0d Pool & Deck
EC2270 Pergola and Amenities 51d 51d 0% 02-Apr-2013 13-Jun-2013 0d Pergola and Amenities
EC00620.2 Building 2 598d 491d 6.59% 30-Nov-2010 A04-Apr-2013 213d 04-Apr-2013, EC00620.2 Building 2
EC2420 Complete Building 2 0d 0d 0% 04-Apr-2013 213d Complete Building 2,
EC00620.2.1 Structure 215d 108d 70.91% 30-Nov-2010 A03-Oct-2011 121d 03-Oct-2011, EC00620.2.1 Structure
EC1150 Building Slab Incl. UG Utils 48d 0d 100% 30-Nov-2010 A09-Feb-2011 A Building Slab Incl. UG Utils
EC1220 First Floor Masonry Structure 12d 0d 100% 07-Feb-2011 A25-Feb-2011 A First Floor Masonry Structure
EC1230 Second Floor Slab & Collar Beam 24d 0d 100% 24-Mar-2011 A29-Apr-2011 A Second Floor Slab & Collar Beam
EC1260 Second Floor Masonry Structure 12d 0d 100% 28-Mar-2011 A11-Apr-2011 A Second Floor Masonry Structure
EC1290 Third Floor Slab & Collar Beam 24d 9d 54.17% 08-Apr-2011 A12-May-2011 121d Third Floor Slab & Collar Beam
EC1320 Third Floor Masonry Structure 12d 12d 0% 12-May-2011 31-May-2011 121d Third Floor Masonry Structure
EC1330 Fourth Floor Slab & Collar Beam 24d 24d 0% 31-May-2011 05-Jul-2011 121d Fourth Floor Slab & Collar Beam
EC1380 Fourth Floor Masonry Structure 12d 12d 0% 05-Jul-2011 21-Jul-2011 121d Fourth Floor Masonry Structure
EC1480 Roof Slab 22d 22d 0% 22-Jul-2011 22-Aug-2011 121d Roof Slab
EC1620 Stair and Elevator Masonry Structure 5d 5d 0% 22-Aug-2011 29-Aug-2011 121d Stair and Elevator Masonry Structure
EC1640 Roof Slab/Collar Beam 24d 24d 0% 29-Aug-2011 03-Oct-2011 121d Roof Slab/Collar Beam
EC00620.2.2 Roof 82d 82d 0% 03-Oct-2011 30-Jan-2012 121d 30-Jan-2012, EC00620.2.2 Roof
EC1710 Place Roof Trusses and Sheathing 24d 24d 0% 03-Oct-2011 04-Nov-2011 121d Place Roof Trusses and Sheathing
EC1720 Place Mechanical Equipment Supports 24d 24d 0% 04-Nov-2011 09-Dec-2011 133d Place Mechanical Equipment Supports
EC1860 Built-Up Asphalt Roofing 34d 34d 0% 09-Dec-2011 30-Jan-2012 133d Built-Up Asphalt Roofing
EC1870 Felt and Tile Roofing 46d 46d 0% 16-Nov-2011 23-Jan-2012 121d Felt and Tile Roofing
EC2020 Roof Complete 0d 0d 0% 30-Jan-2012 121d Roof Complete,
EC00620.2.3 Envelope 241d 241d 0% 03-Oct-2011 12-Sep-2012 264d 12-Sep-2012, EC00620.2.3 Envelope
EC1730 Install Exterior Windows and Sliding Glass Doors
24dFloor 1 24d 0% 03-Oct-2011 04-Nov-2011 252d Install Exterior Windows and Sliding Glass Doors Floor 1
EC1740 Mobilize Scaffolding 12d 12d 0% 03-Oct-2011 19-Oct-2011 279d Mobilize Scaffolding
EC1800 Install Exterior Windows and Sliding Glass Doors
22dFloor 2 22d 0% 04-Nov-2011 07-Dec-2011 252d Install Exterior Windows and Sliding Glass Doors Floor 2
EC1830 Install Backing & Cauld Windows Floor1 12d 12d 0% 31-Oct-2011 17-Nov-2011 271d Install Backing & Cauld Windows Floor1
EC1880 Install Exterior Windows and Sliding Glass Doors
22dFloor 3 22d 0% 30-Nov-2011 03-Jan-2012 252d Install Exterior Windows and Sliding Glass Doors Floor 3
EC1890 Install Backing & Cauld Windows Floor 2 10d 10d 0% 01-Dec-2011 15-Dec-2011 266d Install Backing & Cauld Windows Floor 2
EC1920 Install Exterior Windows and Sliding Glass Doors
24dFloor 4 24d 0% 23-Dec-2011 30-Jan-2012 252d Install Exterior Windows and Sliding Glass Doors Floor 4
EC1930 Install Backing & Cauld Windows Floor 3 12d 12d 0% 27-Dec-2011 13-Jan-2012 259d Install Backing & Cauld Windows Floor 3
EC1940 Stucco Bands 12d 12d 0% 26-Jan-2012 13-Feb-2012 252d Stucco Bands
EC1960 Install Backing & Cauld Windows Floor 4 12d 12d 0% 24-Jan-2012 09-Feb-2012 252d Install Backing & Cauld Windows Floor 4
EC1970 Stucco Grey 24d 24d 0% 13-Feb-2012 16-Mar-2012 252d Stucco Grey
EC2050 Stucco Finish Coat 24d 24d 0% 16-Mar-2012 19-Apr-2012 252d Stucco Finish Coat
EC2130 Caulk 12d 12d 0% 19-Apr-2012 07-May-2012 252d Caulk
EC2160 Stucco Band Trim 24d 24d 0% 07-May-2012 11-Jun-2012 252d Stucco Band Trim
EC2220 Paint Exterior 48d 48d 0% 18-Jun-2012 24-Aug-2012 252d Paint Exterior
EC2230 Install Railings 36d 36d 0% 18-Jun-2012 08-Aug-2012 288d Install Railings
EC2300 Demobilize Scaffolding 12d 12d 0% 24-Aug-2012 12-Sep-2012 252d Demobilize Scaffolding
EC2320 Shell Complete 0d 0d 0% 12-Sep-2012 264d Shell Complete,
EC00620.2.4 Interior Finishes 301d 301d 0% 30-Jan-2012 04-Apr-2013 213d 04-Apr-2013, EC00620.2.4 Interior Finishes
EC2000 Unit Finishes Building North - Floor 1 202d 202d 0% 30-Jan-2012 12-Nov-2012 213d Unit Finishes Building North - Floor 1
EC2030 Unit Finishes Building South - Floor 1 202d 202d 0% 06-Feb-2012 19-Nov-2012 213d Unit Finishes Building South - Floor 1

Actual Level of Effort Remaining Work Milestone Page 2 of 3

Actual Work Critical Remaining Work summary


Juniper Nursing Home Classic Schedule Layout 15-Jan-2023 14:39

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float 2010 2011 2012 2013 2014 2015 2016
Duration Complete
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1Q2
EC2040 Building 1 Elevators Complete 70d 70d 0% 14-Mar-2012 20-Jun-2012 315d Building 1 Elevators Complete
EC2070 Unit Finishes Building North - Floor 2 197d 197d 0% 13-Feb-2012 19-Nov-2012 213d Unit Finishes Building North - Floor 2
EC2120 Unit Finishes Building South - Floor 2 197d 197d 0% 20-Feb-2012 27-Nov-2012 213d Unit Finishes Building South - Floor 2
EC2150 Unit Finishes Building North - Floor 3 197d 197d 0% 27-Feb-2012 04-Dec-2012 213d Unit Finishes Building North - Floor 3
EC2170 Unit Finishes Building South - Floor 3 197d 197d 0% 05-Mar-2012 11-Dec-2012 213d Unit Finishes Building South - Floor 3
EC2200 Unit Finishes Building North - Floor 4 194d 194d 0% 12-Mar-2012 14-Dec-2012 213d Unit Finishes Building North - Floor 4
EC2210 Unit Finishes Building South - Floor 4 194d 194d 0% 19-Mar-2012 21-Dec-2012 213d Unit Finishes Building South - Floor 4
EC2410 Final Inspections and Punchlist 72d 72d 0% 21-Dec-2012 04-Apr-2013 213d Final Inspections and Punchlist
EC00620.2.5 Courtyard 91d 91d 0% 12-Sep-2012 22-Jan-2013 252d 22-Jan-2013, EC00620.2.5 Courtyard
EC2330 Courtyard Walks and Amenities 91d 91d 0% 12-Sep-2012 22-Jan-2013 252d Courtyard Walks and Amenities
EC00620.5 Garage 1 429d 429d 0% 02-May-2011 08-Jan-2013 270d 08-Jan-2013, EC00620.5 Garage 1
EC1420 Start Garage 0d 0d 0% 02-May-2011 159d Start Garage, 02-May-2011
EC1430 Shop Drawings, Review & Approval 72d 72d 0% 02-May-2011 12-Aug-2011 159d Shop Drawings, Review & Approval
EC1810 Fab & Delivery 72d 72d 0% 12-Aug-2011 23-Nov-2011 159d Fab & Delivery
EC2090 Erect Precast Structure 96d 96d 0% 06-Feb-2012 20-Jun-2012 121d Erect Precast Structure
EC2280 Fire Protection and Lighting 72d 72d 0% 20-Jun-2012 02-Oct-2012 270d Fire Protection and Lighting
EC2310 Finishes, Barrier Cables & Striping 72d 72d 0% 04-Sep-2012 14-Dec-2012 270d Finishes, Barrier Cables & Striping
EC2380 Punchlist Garage 14d 14d 0% 14-Dec-2012 08-Jan-2013 270d Punchlist Garage
EC2390 Complete Garage 1 0d 0d 0% 08-Jan-2013 270d Complete Garage 1,
EC2400 Complete Garage 0d 0d 0% 08-Jan-2013 270d Complete Garage,
EC00620.6 Garage 2 428d 301d 31.41% 01-Nov-2010 A05-Jul-2012 386d 05-Jul-2012, EC00620.6 Garage 2
EC1020 Design Building Addition 0d 0d 100% 01-Nov-2010 A Design Building Addition, 01-Nov-2010 A
EC1030 Shop Drawings, Review and Approval 72d 0d 100% 01-Nov-2010 A10-Feb-2011 A Shop Drawings, Review and Approval
EC1180 Fab & Delivery 72d 20d 80.56% 22-Feb-2011 A31-May-2011 386d Fab & Delivery
EC1280 Erect Precast Structure 96d 96d 0% 31-May-2011 14-Oct-2011 386d Erect Precast Structure
EC1590 Fire Protection and Lighting 72d 72d 0% 14-Oct-2011 27-Jan-2012 386d Fire Protection and Lighting
EC1680 Finishes and Striping 84d 84d 0% 29-Dec-2011 26-Apr-2012 386d Finishes and Striping
EC2060 Punch List Garage 48d 48d 0% 26-Apr-2012 05-Jul-2012 386d Punch List Garage
EC2180 Complete Garage 2 0d 0d 0% 05-Jul-2012 386d Complete Garage 2,
EC2190 Complete Garage 0d 0d 0% 05-Jul-2012 386d Complete Garage,
EC00620.7 Roads, Utilities & Pavers 617d 490d 32.07% 01-Nov-2010 A02-Apr-2013 264d 02-Apr-2013, EC00620.7 Roads, Utilities & Pavers
EC1000 Curbing 72d 0d 100% 01-Nov-2010 A15-Feb-2011 A Curbing
EC1040 Electric to Building 4 Power Vault 72d 0d 100% 01-Nov-2010 A11-Feb-2011 A Electric to Building 4 Power Vault
EC1050 Electric to Building 3 Power Vault 24d 0d 100% 01-Nov-2010 A06-Dec-2010 A Electric to Building 3 Power Vault
EC1100 Storm Drainage Site Work 72d 0d 100% 02-Nov-2010 A15-Feb-2011 A Storm Drainage Site Work
EC1110 Site Electrical Work & Temp Power 12d 0d 100% 02-Nov-2010 A17-Nov-2010 A Site Electrical Work & Temp Power
EC1130 Walkways 67d 0d 100% 15-Nov-2010 A16-Feb-2011 A Walkways
EC1200 Roadway Pavers 67d 22d 78.57% 23-Feb-2011 A02-Jun-2011 617d Roadway Pavers
EC1270 Finish Paving, Striping and Signs 48d 48d 0% 02-Jun-2011 10-Aug-2011 617d Finish Paving, Striping and Signs
EC1440 Electric to Building 2 Power Vault 91d 91d 0% 25-Aug-2011 05-Jan-2012 408d Electric to Building 2 Power Vault
EC1610 Curbs & Paving 58d 58d 0% 14-Oct-2011 09-Jan-2012 513d Curbs & Paving
EC1750 Electric to Building 1 Power Vault 70d 70d 0% 03-Oct-2011 12-Jan-2012 370d Electric to Building 1 Power Vault
EC2250 Fountain/Water Feature 115d 115d 0% 18-Oct-2012 02-Apr-2013 297d Fountain/Water Feature
EC2260 Entry Feature/Sign Wall 103d 103d 0% 20-Jun-2012 14-Nov-2012 305d Entry Feature/Sign Wall
EC2290 Curbs & Paving 72d 72d 0% 20-Jun-2012 02-Oct-2012 321d Curbs & Paving
EC2340 Curbs & Paving 79d 79d 0% 02-Oct-2012 24-Jan-2013 264d Curbs & Paving
EC00620.8 Landscape & Irrigation 806d 806d 0% 24-May-2011 18-Jul-2014 0d 18-Jul-2014, EC00620.8 Landscape & Irrigation
EC1600 Site Cleanup 48d 48d 0% 24-May-2011 02-Aug-2011 623d Site Cleanup
EC2360 Landscape & Irrigation 288d 288d 0% 05-Jun-2013 18-Jul-2014 0d Landscape & Irrigation

Actual Level of Effort Remaining Work Milestone Page 3 of 3

Actual Work Critical Remaining Work summary