547 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY HEALTH CENTRE) 08-Jun-15 22-Aug-13 08-Jun-15 0

CONSTRUCTION 547 22-Aug-13 08-Jun-15 22-Aug-13 08-Jun-15 0

PROJECT INITIATION & STARTUP 547 22-Aug-13 08-Jun-15 10-Sep-13 08-Jun-15 0


53150-AUPR-00-112 Site Running, Supervision,Safety and other Indirect Costs 548 06-Dec-13 06-Jun-15 08-Dec-13 08-Jun-15 2
Project Milestones 461 06-Dec-13 08-Jun-15 06-Dec-13 08-Jun-15 0
Major key Milestones 550 06-Dec-13 08-Jun-15 06-Dec-13 08-Jun-15 0
53150-MILE-00-130 Commencement of works 0 06-Dec-13 06-Dec-13 0
53150-MILE-00-127 Issue of Taking O ver C ertificate 0 08-Jun-15 08-Jun-15 0
Control and Monitoring Milestones 448 20-Dec-13 07-Jun-15 26-Jan-14 08-Jun-15 1
53150-MILE-00-100 Submit 90-Day Schedule 0 20-Dec-13 26-Jan-14 37
53150-MILE-00-103 Demolition of existing structures 0 31-Dec-13 26-Jan-14 26
53150-MILE-00-101 Submit Project Detailed Schedule 0 04-Jan-14 14-Feb-14 41
53150-MILE-00-102 Mobilization 0 04-Jan-14 26-Jan-14 22
53150-MILE-00-106 Obtain Building Permit 0 15-Jan-14 26-Jan-14 11
53150-MILE-00-104 Review, Approve detailed schedule 0 24-Jan-14 26-Jan-14 2
53150-MILE-00-105 Finalize Major Sub-contractor Agreements 0 28-Jan-14 10-Mar-14 41
53150-MILE-00-107 Completion of all Engineering / Shop drawing approvals 0 04-Jun-14 02-Sep-14 90
53150-MILE-00-109 Completion of all Material /Vendors appr ovals 0 07-Jun-14 02-Sep-14 87
53150-MILE-00-108 Substantial completion of Main Building Substructure including basement 0 11-Aug-14 10-Sep-14 30
53150-MILE-00-111 Substantial completion of Main Building structure 0 30-Sep-14 30-Sep-14 0
53150-MILE-00-110 Major Equipment (Elevators, Chillers, Generators) procurement and delivery 0 20-Dec-14 03-Feb-15 45
53150-MILE-00-112 Completion of MEP major equipment installation 0 26-Jan-15 30-Jan-15 4
53150-MILE-00-114 Completion of MEP 1st Fix 0 26-Jan-15 30-Jan-15 4
53150-MILE-00-113 Completion of External and Internal walls 0 30-Jan-15 15-Feb-15 17
53150-MILE-00-119 Completion of suspended ceiling installation 0 15-Feb-15 15-Feb-15 0
53150-MILE-00-115 Substantial completion of External window, claddings and curtain walling 0 03-Mar-15 04-May-15 62
53150-MILE-00-116 Early date for FF&E and Medical Equipment access to building (coordination) 0 06-Mar-15 05-Apr-15 30
53150-MILE-00-117 Medical Equipment approval, procurement and delivery 0 06-Mar-15 05-Apr-15 30
53150-MILE-00-121 Completion of MEP 2nd Fix 0 07-Mar-15 04-May-15 58
53150-MILE-00-120 Furniture, Fittings and Equipment (FF&E) approvals, procurement and delivery 0 13-Mar-15 04-May-15 53
53150-MILE-00-118 Completion of all internal finishes 0 24-Mar-15 04-May-15 41
53150-MILE-00-122 Utility connections to main(s) 0 19-Apr-15 04-May-15 15
53150-MILE-00-126 Completion of hard / soft landscaping and boundary wall 0 08-May-15 07-Jun-15 31
53150-MILE-00-123 Completion of Medical equipment installation 0 12-May-15 27-May-15 15
53150-MILE-00-125 Completion of testing and commissioning 0 01-Jun-15 08-Jun-15 7
53150-MILE-00-124 Remove temporary site office / facilities 0 03-Jun-15 07-Jun-15 4
53150-MILE-00-137 Power on 0 07-Jun-15 08-Jun-15 1
Provisional Sum 461 07-Dec-13 08-Jun-15 07-Dec-13 08-Jun-15 0
53150-PROV- 00-100 Provisional Sum 461 07-Dec-13 08-Jun-15 07-Dec-13 08-Jun-15 0
Mobilization/Demobilization 543 22-Aug-13 03-Jun-15 10-Sep-13 07-Jun-15 3
53150-MOBL-00-100 Letter of Acceptance/Award 1 22-Aug-13 22-Aug-13 10-Sep-13 10-Sep-13 16
53150-MOBL-00-101 Contract negotiations 45 22-Aug-13 13-Oct-13 10-Sep-13 05-Nov-13 16
53150-MOBL-00-102 Contract signing 1 14-Oct-13 14-Oct-13 06-Nov-13 06-Nov-13 16
53150-MOBL-00-103 Mobilization 24 07-Dec-13 04-Jan-14 11-Dec-13 08-Jan-14 4
53150-HAND-00-106 Removal of Temp. site offices/facilities (Demob) 20 12-May-15 03-Jun-15 16-May-15 07-Jun-15 3
Work Program/Plan 40 06-Dec-13 24-Jan-14 08-Dec-13 10-Mar-14 39
Submittals 24 06-Dec-13 04-Jan-14 08-Dec-13 22-Feb-14 41
53150-PRGS-00-100 Submit 90-Day Schedule Submittal 15 06-Dec-13 20-Dec-13 08-Dec-13 22-Dec-13 2
53150-PRGS-00-103 Preparation/submittal of HSE Plan 21 07-Dec-13 30-Dec-13 29-Jan-14 22-Feb-14 44
53150-PRGS-00-104 Preparation/submittal of PQP Plan 21 07-Dec-13 30-Dec-13 29-Jan-14 22-Feb-14 44
53150-PRGS-00-101 Detailed Schedule Submittal 15 21-Dec-13 04-Jan-14 23-Dec-13 06-Jan-14 2

Actual Work Critical Remaining Work Summary Page 1 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
Approvals 28 21-Dec-13 24-Jan-14 12-Jan-14 10-Mar-14 39
53150-PRGA-00-100 Submit 90-Day Schedule Approval 15 21-Dec-13 04-Jan-14 12-Jan-14 26-Jan-14 22
53150-PRGA-00-103 Approval of HSE Plan 14 31-Dec-13 18-Jan-14 23-Feb-14 10-Mar-14 44
53150-PRGA-00-104 Approval of PQP Plan 14 31-Dec-13 18-Jan-14 23-Feb-14 10-Mar-14 44
53150-PRGA-00-101 Detailed Schedule Approval 14 11-Jan-14 24-Jan-14 13-Jan-14 26-Jan-14 2
TEMPORARY PLANT 253 05-Jan-14 04-Nov-14 08-Apr-14 12-Nov-14 7
Temporary Plant 253 05-Jan-14 04-Nov-14 08-Apr-14 12-Nov-14 7
Logistics Plan 31 05-Jan-14 10-Feb-14 08-Apr-14 13-May-14 79
53150-LOGP-00-100 Temporary site installation/services 30 05-Jan-14 09-Feb-14 08-Apr-14 12-May-14 79
53150-LOGP-00-101 Completion of site installation 1 10-Feb-14 10-Feb-14 13-May-14 13-May-14 79
Tower Cranes 107 26-Jun-14 04-Nov-14 05-Jul-14 12-Nov-14 7
53150-TOWC-00-100 Installation of Tower Cr ane 5 26-Jun-14 01-Jul-14 05-Jul-14 09-Jul-14 7
53150-TOWC-00-101 Removal of Tow er Crane 5 30-Oct-14 04-Nov-14 08-Nov-14 12-Nov-14 7
UTILITIES AND AUTHORITIES AND APPROVALS 434 22-Aug-13 17-May-15 22-Aug-13 08-Jun-15 16
Authorities Approval 96 22-Aug-13 15-Jan-14 22-Aug-13 15-Jan-14 0
53150-AUPR-00-100 Collection of Demolition Permit 69 22-Aug-13 05-Dec-13 22-Aug-13 05-Dec-13 0
53150-AUPR-00-102 Obtaining Construction Building Permit 9 02-Jan-14 15-Jan-14 02-Jan-14 15-Jan-14 0
Shop Drawings to Authorities 37 08-May-14 30-Jun-14 08-Jun-14 28-Jul-14 20
Submittal 16 08-May-14 01-Jun-14 08-Jun-14 29-Jun-14 20
53150-ASDS-00-100 ADDC Electrical Shop Drawings Submittal 3 08-May-14 12-May-14 08-Jun-14 10-Jun-14 20
53150-ASDS-00-103 ADSSC Sewer Connections Shop Drawings Submittal 2 13-May-14 14-May-14 11-Jun-14 12-Jun-14 20
53150-ASDS-00-101 ADDC Water Connection Shop Drawings Submittal 2 15-May-14 18-May-14 15-Jun-14 16-Jun-14 20
53150-ASDS-00-102 Civil Defence Fire fighintg Shop Drawings Submittal 2 19-May-14 20-May-14 17-Jun-14 18-Jun-14 20
53150-ASDS-00-104 Etisalat IT/Telephone Connections Shop Drawings Submittal 2 29-May-14 01-Jun-14 26-Jun-14 29-Jun-14 20
Approval 34 13-May-14 30-Jun-14 16-Jun-14 28-Jul-14 20
53150-ASDA-00-100 ADDC Electrical Shop Drawings Approval 21 13-May-14 11-Jun-14 24-Jun-14 22-Jul-14 29
53150-ASDA-00-103 ADSSC Sewer Connections Shop Drawings Approval 21 15-May-14 15-Jun-14 16-Jun-14 14-Jul-14 21
53150-ASDA-00-101 ADDC Water Connection Shop Drawings Approval 21 19-May-14 17-Jun-14 23-Jun-14 21-Jul-14 24
53150-ASDA-00-102 Civil Defence Fire fighintg Shop Drawings Submittal 21 21-May-14 19-Jun-14 19-Jun-14 17-Jul-14 20
53150-ASDA-00-104 Etisalat IT/Telephone Connections Shop Drawings Approval 21 02-Jun-14 30-Jun-14 30-Jun-14 28-Jul-14 20
Construction NOC Submittals 19 16-Feb-15 12-Mar-15 22-Mar-15 05-Apr-15 16
53150-NOCS-00-101 ADDC Power 10 16-Feb-15 01-Mar-15 23-Mar-15 05-Apr-15 25
53150-NOCS-00-102 ADDC Water 10 18-Feb-15 03-Mar-15 22-Mar-15 02-Apr-15 22
53150-NOCS-00-103 Civil Defence 10 22-Feb-15 05-Mar-15 22-Mar-15 02-Apr-15 20
53150-NOCS-00-104 Department of Transport 10 23-Feb-15 08-Mar-15 22-Mar-15 02-Apr-15 19
53150-NOCS-00-105 ADSSC Sewer 10 01-Mar-15 12-Mar-15 22-Mar-15 02-Apr-15 15
53150-NOCS-00-106 Etisalat IT/Telephone 10 01-Mar-15 12-Mar-15 22-Mar-15 02-Apr-15 15
Construction NOC Approvals 7 07-May-15 17-May-15 31-May-15 08-Jun-15 16
53150-NOCA-00-101 ADDC Power 6 07-May-15 14-May-15 01-Jun-15 08-Jun-15 17
53150-NOCA-00-102 ADDC Water 6 07-May-15 14-May-15 31-May-15 07-Jun-15 16
53150-NOCA-00-103 Civil Defence 6 07-May-15 14-May-15 31-May-15 07-Jun-15 16
53150-NOCA-00-105 ADSSC Sewer 6 10-May-15 17-May-15 31-May-15 07-Jun-15 15
53150-NOCA-00-106 Etisalat NOC 6 10-May-15 17-May-15 31-May-15 07-Jun-15 15
553150-NOCA-00-104 Department of Transport 6 10-May-15 17-May-15 31-May-15 07-Jun-15 15
ENGINEERING PHASE 399 26-Oct-13 16-Feb-15 14-Nov-13 18-Apr-15 52
Subcontractor Prequalification Submission / Approvals 198 26-Oct-13 18-Jun-14 14-Nov-13 05-Jul-14 14
DSC Civil 198 26-Oct-13 18-Jun-14 14-Nov-13 23-Jun-14 4
DSC Submittals 184 26-Oct-13 02-Jun-14 14-Nov-13 07-Jun-14 4
53150-SCCS-00-101 Demolition Subcontractor submittal 6 26-Oct-13 31-Oct-13 14-Nov-13 20-Nov-13 16
53150-SCCS-00-102 Piles Subcontractor submittal 6 16-Dec-13 22-Dec-13 28-Dec-13 04-Jan-14 10
53150-SCCS-00-103 Dewatering Subcontractor submittal 6 21-Dec-13 26-Dec-13 05-Mar-14 11-Mar-14 62
53150-SCCS-00-104 Precast Concrete submittal 6 29-Mar-14 03-Apr-14 03-May-14 08-May-14 30

Actual Work Critical Remaining Work Summary Page 2 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-SCCS-00-107 Landscape Subcontractor submittal 6 29-Mar-14 03-Apr-14 24-May-14 31-May-14 48
53150-SCCS-00-105 Radiation Protection Subcontractor submittal 6 21-Apr-14 27-Apr-14 22-May-14 29-May-14 27
53150-SCCS-00-108 Roads Works Subcontractor submittal 6 26-May-14 02-Jun-14 01-Jun-14 07-Jun-14 4
DSC Approvals 192 02-Nov-13 18-Jun-14 21-Nov-13 23-Jun-14 4
53150-SCCA-00-100 Demolition Subcontractor approval 14 02-Nov-13 18-Nov-13 21-Nov-13 08-Dec-13 16
53150-SCCA-00-101 Piles Subcontractor approval 14 23-Dec-13 08-Jan-14 05-Jan-14 21-Jan-14 10
53150-SCCA-00-102 Dewatering Subcontractor approval 14 28-Dec-13 13-Jan-14 12-Mar-14 27-Mar-14 62
53150-SCCA-00-103 Precast Concrete approval 14 05-Apr-14 20-Apr-14 10-May-14 25-May-14 30
53150-SCCA-00-106 Landscape Subcontractor approval 14 05-Apr-14 20-Apr-14 01-Jun-14 16-Jun-14 48
53150-SCCA-00-104 Radiation Protection Subcontractor approval 14 28-Apr-14 13-May-14 31-May-14 15-Jun-14 27
53150-SCCA-00-107 Roads Works Subcontractor approval 14 03-Jun-14 18-Jun-14 08-Jun-14 23-Jun-14 4
DSC Architecture 65 27-Feb-14 13-May-14 05-Apr-14 19-Jun-14 31
DSC Submittals 51 27-Feb-14 27-Apr-14 05-Apr-14 03-Jun-14 31
53150-SCAS-00-101 Wooden works Subcontractor submittal 6 27-Feb-14 05-Mar-14 05-May-14 11-May-14 57
53150-SCAS-00-106 Interior Signage Subcontractor submittal 6 05-Mar-14 11-Mar-14 08-May-14 14-May-14 55
53150-SCAS-00-104 Furniture Supplier submittal 6 17-Mar-14 23-Mar-14 05-Apr-14 10-Apr-14 16
53150-SCAS-00-107 Painting Subcontractor submittal 6 17-Mar-14 23-Mar-14 29-Apr-14 05-May-14 37
53150-SCCS-00-106 Metal works Subcontractor submittal 6 17-Mar-14 23-Mar-14 08-May-14 14-May-14 45
53150-SCAS-00-105 Exterior Signage Subcontractor submittal 6 29-Mar-14 03-Apr-14 14-May-14 20-May-14 40
53150-SCAS-00-102 Aluminium works Subcontractor submittal 6 03-Apr-14 09-Apr-14 17-May-14 22-May-14 37
53150-SCAS-00-103 GRC works Subcontractor submittal 6 19-Apr-14 24-Apr-14 13-May-14 19-May-14 21
53150-SCAS-00-100 False Ceiling Subcontractor submittal 6 21-Apr-14 27-Apr-14 28-May-14 03-Jun-14 31
DSC Approvals 59 06-Mar-14 13-May-14 12-Apr-14 19-Jun-14 31
53150-SCAA-00-101 Wooden works Subcontractor approval 14 06-Mar-14 22-Mar-14 12-May-14 28-May-14 57
53150-SCAA-00-106 Interior Signage Subcontractor approval 14 12-Mar-14 27-Mar-14 15-May-14 01-Jun-14 55
53150-SCAA-00-104 Furniture Supplier approval 14 24-Mar-14 08-Apr-14 12-Apr-14 27-Apr-14 16
53150-SCAA-00-107 Painting Subcontractor approval 14 24-Mar-14 08-Apr-14 06-May-14 21-May-14 37
53150-SCCA-00-105 Metal works Subcontractor approval 14 24-Mar-14 08-Apr-14 15-May-14 01-Jun-14 45
53150-SCAA-00-105 Exterior Signage Subcontractor approval 14 05-Apr-14 20-Apr-14 21-May-14 07-Jun-14 40
53150-SCAA-00-102 Aluminium works Subcontractor approval 14 10-Apr-14 26-Apr-14 24-May-14 09-Jun-14 37
53150-SCAA-00-103 GRC works Subcontractor approval 14 26-Apr-14 11-May-14 20-May-14 05-Jun-14 21
53150-SCAA-00-100 False Ceiling Subcontractor approval 14 28-Apr-14 13-May-14 04-Jun-14 19-Jun-14 31
DSC MEP 110 05-Jan-14 13-May-14 21-Jan-14 05-Jul-14 44
DSC Submittals 96 05-Jan-14 27-Apr-14 21-Jan-14 18-Jun-14 44
53150-SCMS-00-100 Electrical Subcontractor submittal 6 05-Jan-14 11-Jan-14 04-Feb-14 10-Feb-14 25
53150-SCMS-00-106 Medical Equipements Subcontractor submittal 6 05-Jan-14 11-Jan-14 21-Jan-14 27-Jan-14 13
53150-SCMS-00-101 Plumbing Subcontractor submittal 6 17-Feb-14 23-Feb-14 07-Apr-14 13-Apr-14 42
53150-SCMS-00-103 Fire Fighting Subcontractor submittal 6 12-Mar-14 18-Mar-14 30-Apr-14 06-May-14 42
53150-SCMS-00-105 Lifts Subcontractor submittal 6 09-Apr-14 15-Apr-14 01-Jun-14 07-Jun-14 44
53150-SCMS-00-107 Visual Display Units Subcontractor submittal 6 09-Apr-14 15-Apr-14 12-Jun-14 18-Jun-14 54
53150-SCMS-00-102 HVAC Subcontractor submittal 6 15-Apr-14 21-Apr-14 29-May-14 04-Jun-14 37
53150-SCMS-00-104 IT/Telephone Subcontractor submittal 6 21-Apr-14 27-Apr-14 19-May-14 25-May-14 24
DSC Approvals 104 12-Jan-14 13-May-14 28-Jan-14 05-Jul-14 44
53150-SCMA-00-100 Electrical Subcontractor approval 14 12-Jan-14 28-Jan-14 11-Feb-14 26-Feb-14 25
53150-SCMA-00-106 Medical Equipements Subcontractor approval 14 12-Jan-14 28-Jan-14 28-Jan-14 12-Feb-14 13
53150-SCMA-00-101 Plumbing Subcontractor approval 14 24-Feb-14 11-Mar-14 28-Apr-14 13-May-14 54
53150-SCMA-00-103 Fire Fighting Subcontractor approval 14 19-Mar-14 03-Apr-14 07-May-14 22-May-14 42
53150-SCMA-00-105 Lifts Subcontractor approval 14 16-Apr-14 01-May-14 08-Jun-14 23-Jun-14 44
53150-SCMA-00-107 Visual Display Units Subcontractor approval 14 16-Apr-14 01-May-14 19-Jun-14 05-Jul-14 54
53150-SCMA-00-102 HVAC Subcontractor approval 14 22-Apr-14 07-May-14 05-Jun-14 21-Jun-14 37
53150-SCMA-00-104 IT/Telephone Subcontractor approval 14 28-Apr-14 13-May-14 26-May-14 11-Jun-14 24
Materials Submission / Approval 250 29-Jan-14 24-Nov-14 04-Mar-14 19-Jan-15 47

Actual Work Critical Remaining Work Summary Page 3 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
Domestic Subcontractors 250 29-Jan-14 24-Nov-14 04-Mar-14 19-Jan-15 47
DSC Civil 152 24-Feb-14 23-Aug-14 06-Apr-14 04-Oct-14 36
DSC Submittals 104 24-Feb-14 25-Jun-14 06-Apr-14 30-Jun-14 4
53150-MACS-00-100 Concrete Mix submittal 6 24-Feb-14 02-Mar-14 16-Apr-14 22-Apr-14 44
53150-MACS-00-101 Steel Reinforcement submittal 6 24-Feb-14 02-Mar-14 06-Apr-14 12-Apr-14 35
53150-MACS-00-124 Cement submittal 6 11-Mar-14 17-Mar-14 05-Jun-14 11-Jun-14 73
53150-MACS-00-105 Manholes submittals 6 12-Mar-14 18-Mar-14 14-May-14 20-May-14 54
53150-MACS-00-102 Water proofing submittal 6 05-Apr-14 10-Apr-14 05-May-14 11-May-14 26
53150-MACS-00-103 Shuttering system submittal 6 05-Apr-14 10-Apr-14 03-May-14 08-May-14 24
53150-MACS-00-131 Precast Concrete Cladding submittal 6 03-May-14 08-May-14 08-Jun-14 14-Jun-14 30
53150-MACS-00-140 Asphalt Paving submittal 6 19-Jun-14 25-Jun-14 24-Jun-14 30-Jun-14 4
DSC Approvals 146 03-Mar-14 23-Aug-14 13-Apr-14 04-Oct-14 36
53150-MACA-00-100 Concrete Mix approval 14 03-Mar-14 18-Mar-14 23-Apr-14 08-May-14 44
53150-MACA-00-101 Steel Reinforcement approval 14 03-Mar-14 18-Mar-14 13-Apr-14 28-Apr-14 35
53150-MACA-00-124 Cement approval 14 18-Mar-14 02-Apr-14 12-Jun-14 28-Jun-14 73
53150-MACA-00-105 Manholes approval 14 19-Mar-14 03-Apr-14 21-May-14 07-Jun-14 54
53150-MACA-00-102 Water proofing approval 14 12-Apr-14 27-Apr-14 12-May-14 28-May-14 26
53150-MACA-00-103 Shuttering system approval 14 12-Apr-14 27-Apr-14 10-May-14 25-May-14 24
53150-MACA-00-140 Asphalt Paving approval 14 26-Jun-14 12-Jul-14 01-Jul-14 16-Jul-14 4
53150-MACA-00-132 Miscellaneous approval 14 07-Aug-14 23-Aug-14 18-Sep-14 04-Oct-14 36
DSC Architecture 211 16-Mar-14 24-Nov-14 24-Apr-14 19-Jan-15 47
DSC Submittals 197 16-Mar-14 08-Nov-14 24-Apr-14 03-Jan-15 47
53150-MAAS-00-100 Linoleum Sheet submittal 6 16-Mar-14 22-Mar-14 26-Apr-14 01-May-14 35
53150-MAAS-00-105 Wall Ceramic tiles submittal 6 16-Mar-14 22-Mar-14 24-Apr-14 30-Apr-14 34
53150-MAAS-00-102 Corner Guards submittal 6 17-Mar-14 23-Mar-14 04-May-14 10-May-14 41
53150-MAAS-00-111 Reception Counter submittal 6 23-Mar-14 29-Mar-14 02-Jun-14 08-Jun-14 60
53150-MAAS-00-112 Wooden Cladding material submital 6 23-Mar-14 29-Mar-14 09-Jun-14 15-Jun-14 66
53150-MACS-00-107 Cafe storage shelves submittal 6 23-Mar-14 29-Mar-14 05-Jun-14 11-Jun-14 63
53150-MACS-00-108 Cafe Cabinet submittal 6 23-Mar-14 29-Mar-14 09-Jun-14 15-Jun-14 66
53150-MACS-00-109 Cafe Counter submittal 6 23-Mar-14 29-Mar-14 29-May-14 04-Jun-14 57
53150-MAAS-00-110 Wooden Doors submittal 6 31-Mar-14 06-Apr-14 14-Jun-14 19-Jun-14 63
53150-MAAS-00-119 Interior Signage submittal 6 03-Apr-14 09-Apr-14 08-Jun-14 14-Jun-14 55
53150-MAAS-00-116 Shoe rack submittal 6 09-Apr-14 15-Apr-14 16-Jun-14 22-Jun-14 57
53150-MAAS-00-117 Furniture submittal 6 09-Apr-14 15-Apr-14 01-Jul-14 07-Jul-14 70
53150-MAAS-00-121 Painting submittal 6 09-Apr-14 15-Apr-14 30-Jun-14 06-Jul-14 69
53150-MACS-00-111 Entrance Canopy submittal 6 09-Apr-14 15-Apr-14 02-Jul-14 08-Jul-14 71
53150-MACS-00-113 Grab bar submittal 6 09-Apr-14 15-Apr-14 02-Jul-14 08-Jul-14 71
53150-MACS-00-116 Gratings submittal 6 09-Apr-14 15-Apr-14 29-Jun-14 05-Jul-14 68
53150-MACS-00-117 Stair Gate submittal 6 09-Apr-14 15-Apr-14 29-Jun-14 05-Jul-14 68
53150-MACS-00-118 Handrail submittal 6 09-Apr-14 15-Apr-14 17-Jun-14 23-Jun-14 58
53150-MACS-00-119 Balustrade to staircase submittal 6 09-Apr-14 15-Apr-14 18-Jun-14 24-Jun-14 59
53150-MACS-00-120 Staircase enclosure submittal 6 09-Apr-14 15-Apr-14 03-Jul-14 09-Jul-14 72
53150-MACS-00-121 Roof Louvered Screen submittal 6 09-Apr-14 15-Apr-14 16-Jun-14 22-Jun-14 57
53150-MACS-00-122 Main Entrance Gate submittal 6 09-Apr-14 15-Apr-14 30-Jun-14 06-Jul-14 69
53150-MACS-00-136 Interlock submittal 6 09-Apr-14 15-Apr-14 24-May-14 31-May-14 38
53150-MAAS-00-103 Terrazzo Tiles/skirting submittal 6 15-Apr-14 21-Apr-14 04-Jun-14 10-Jun-14 42
53150-MAAS-00-104 Porcelain (Floor) submittal 6 15-Apr-14 21-Apr-14 23-Jun-14 29-Jun-14 58
53150-MAAS-00-118 Plants submittal 6 21-Apr-14 27-Apr-14 17-Jun-14 23-Jun-14 48
53150-MAAS-00-120 Exterior Signage submittal 6 21-Apr-14 27-Apr-14 08-Jun-14 14-Jun-14 40
53150-MAAS-00-101 Carpets submittal 6 24-Apr-14 01-May-14 02-Jul-14 08-Jul-14 57
53150-MACS-00-106 X-ray Exam room Cabinet/Counter submittal 6 27-Apr-14 03-May-14 14-Jul-14 20-Jul-14 66
53150-MACS-00-115 Sliding door (entrance) submittal 6 27-Apr-14 03-May-14 02-Jul-14 08-Jul-14 56

Actual Work Critical Remaining Work Summary Page 4 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAAS-00-113 Aluminium Doors/windows submittal 6 03-May-14 08-May-14 16-Jun-14 22-Jun-14 37
53150-MACS-00-138 Precast Concrete Curbstone submittal 6 03-May-14 08-May-14 19-Jul-14 24-Jul-14 65
53150-MACS-00-123 Hollow Block submittal 6 05-May-14 11-May-14 03-Jul-14 09-Jul-14 50
53150-MAAS-00-114 Wall Covering submittal 6 12-May-14 18-May-14 27-Jul-14 04-Aug-14 64
53150-MAAS-00-115 GRC material submittal 6 12-May-14 18-May-14 07-Jun-14 12-Jun-14 21
53150-MACS-00-114 Curtain Wall submittal 6 13-May-14 19-May-14 28-Jun-14 03-Jul-14 38
53150-MACS-00-104 Radiation Protection submittal 6 14-May-14 20-May-14 16-Jun-14 22-Jun-14 27
53150-MACS-00-112 Steel Staircase submittal 6 14-May-14 20-May-14 19-Jul-14 24-Jul-14 55
53150-MACS-00-129 Plaster Access or ies submittal 6 15-May-14 21-May-14 30-Jun-14 06-Jul-14 38
53150-MACS-00-125 Roof tiling submittal 6 26-May-14 02-Jun-14 14-Aug-14 20-Aug-14 66
53150-MAAS-00-107 Gypsum Board/tiles submittal 6 01-Jun-14 07-Jun-14 07-Jul-14 13-Jul-14 31
53150-MAAS-00-108 Mirrors submittal 6 04-Jun-14 10-Jun-14 10-Aug-14 16-Aug-14 55
53150-MAAS-00-109 Glass tiles with channel submittal 6 04-Jun-14 10-Jun-14 26-Aug-14 01-Sep-14 69
53150-MACS-00-126 Thermal Insulation submittal 6 24-Jun-14 30-Jun-14 24-Aug-14 30-Aug-14 50
53150-MAAS-00-106 Robe hook submittal 6 01-Jul-14 07-Jul-14 30-Aug-14 04-Sep-14 49
53150-MACS-00-132 Miscellaneous submittal 6 31-Jul-14 06-Aug-14 11-Sep-14 17-Sep-14 36
53150-MACS-00-130 Refuse chute enclosure submittal 6 31-Aug-14 06-Sep-14 10-Nov-14 16-Nov-14 57
53150-MACS-00-135 Residential Appliances submit tal 6 02-Nov-14 08-Nov-14 28-Dec-14 03-Jan-15 47
DSC Approvals 205 23-Mar-14 24-Nov-14 01-May-14 19-Jan-15 47
53150-MAAA-00-100 Linoleum Sheet approval 14 23-Mar-14 07-Apr-14 03-May-14 18-May-14 35
53150-MAAA-00-105 Wall Ceramic tiles approval 14 23-Mar-14 07-Apr-14 01-May-14 17-May-14 34
53150-MAAA-00-102 Corner Guards approval 14 24-Mar-14 08-Apr-14 11-May-14 26-May-14 41
53150-MAAA-00-111 Reception Counter approval 14 30-Mar-14 14-Apr-14 09-Jun-14 24-Jun-14 60
53150-MAAA-00-112 Wooden Cladding material approval 14 30-Mar-14 14-Apr-14 16-Jun-14 01-Jul-14 66
53150-MACA-00-107 Cafe storage shelves approval 14 30-Mar-14 14-Apr-14 12-Jun-14 28-Jun-14 63
53150-MACA-00-108 Cafe Cabinet approval 14 30-Mar-14 14-Apr-14 16-Jun-14 01-Jul-14 66
53150-MACA-00-109 Cafe Counter approval 14 30-Mar-14 14-Apr-14 05-Jun-14 21-Jun-14 57
53150-MAAA-00-110 Wooden Doors approval 14 07-Apr-14 22-Apr-14 21-Jun-14 06-Jul-14 63
53150-MAAA-00-119 Interior Signage approval 14 10-Apr-14 26-Apr-14 15-Jun-14 30-Jun-14 55
53150-MAAA-00-116 Shoe rack approval 14 16-Apr-14 01-May-14 23-Jun-14 08-Jul-14 57
53150-MAAA-00-117 Furniture approval 14 16-Apr-14 01-May-14 08-Jul-14 23-Jul-14 70
53150-MAAA-00-121 Painting approval 14 16-Apr-14 01-May-14 07-Jul-14 22-Jul-14 69
53150-MACA-00-111 Entrance Canopy approval 14 16-Apr-14 01-May-14 09-Jul-14 24-Jul-14 71
53150-MACA-00-113 Grab bar approval 14 16-Apr-14 01-May-14 09-Jul-14 24-Jul-14 71
53150-MACA-00-116 Gratings approval 14 16-Apr-14 01-May-14 06-Jul-14 21-Jul-14 68
53150-MACA-00-117 Stair Gate approval 14 16-Apr-14 01-May-14 06-Jul-14 21-Jul-14 68
53150-MACA-00-118 Handrail approval 14 16-Apr-14 01-May-14 24-Jun-14 09-Jul-14 58
53150-MACA-00-119 Balustrade to staircase approval 14 16-Apr-14 01-May-14 25-Jun-14 10-Jul-14 59
53150-MACA-00-120 Staircase enclosure approval 14 16-Apr-14 01-May-14 10-Jul-14 26-Jul-14 72
53150-MACA-00-121 Roof Louvered Screen approval 14 16-Apr-14 01-May-14 23-Jun-14 08-Jul-14 57
53150-MACA-00-122 Main Entrance Gate approval 14 16-Apr-14 01-May-14 07-Jul-14 22-Jul-14 69
53150-MACA-00-136 Interlock approval 14 16-Apr-14 01-May-14 01-Jun-14 16-Jun-14 38
53150-MAAA-00-103 Terrazzo Tiles/skirting approval 14 22-Apr-14 07-May-14 11-Jun-14 26-Jun-14 42
53150-MAAA-00-104 Porcelain (Floor) approval 14 22-Apr-14 07-May-14 30-Jun-14 15-Jul-14 58
53150-MAAA-00-118 Plants approval 14 28-Apr-14 13-May-14 24-Jun-14 09-Jul-14 48
53150-MAAA-00-120 Exterior Signage approval 14 28-Apr-14 13-May-14 15-Jun-14 30-Jun-14 40
53150-MAAA-00-101 Carpets approval 14 01-May-14 18-May-14 09-Jul-14 24-Jul-14 57
53150-MACA-00-106 X-ray Exam room Cabinet/Counter approval 14 04-May-14 19-May-14 21-Jul-14 07-Aug-14 66
53150-MACA-00-115 Sliding door (entrance) approval 14 04-May-14 19-May-14 09-Jul-14 24-Jul-14 56
53150-MAAA-00-113 Aluminium Doors/windows approval 14 10-May-14 25-May-14 23-Jun-14 08-Jul-14 37
53150-MACA-00-131 Precast Concrete Cladding approval 14 10-May-14 25-May-14 15-Jun-14 30-Jun-14 30
53150-MACA-00-138 Precast Concrete Curbstone approval 14 10-May-14 25-May-14 26-Jul-14 12-Aug-14 65

Actual Work Critical Remaining Work Summary Page 5 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MACA-00-123 Hollow Block approval 14 12-May-14 28-May-14 10-Jul-14 26-Jul-14 50
53150-MAAA-00-114 Wall Covering approval 14 19-May-14 04-Jun-14 05-Aug-14 20-Aug-14 64
53150-MAAA-00-115 GRC material approval 14 19-May-14 04-Jun-14 14-Jun-14 29-Jun-14 21
53150-MACA-00-114 Curtain Wall approval 14 20-May-14 05-Jun-14 05-Jul-14 20-Jul-14 38
53150-MACA-00-104 Radiation Protection approval 14 21-May-14 07-Jun-14 23-Jun-14 08-Jul-14 27
53150-MACA-00-112 Steel Staircase approval 14 21-May-14 07-Jun-14 26-Jul-14 12-Aug-14 55
53150-MACA-00-129 Plaster Access or ies approval 14 22-May-14 08-Jun-14 07-Jul-14 22-Jul-14 38
53150-MACA-00-125 Roof tiling approval 14 03-Jun-14 18-Jun-14 21-Aug-14 06-Sep-14 66
53150-MAAA-00-107 Gypsum Board/tiles approval 14 08-Jun-14 23-Jun-14 14-Jul-14 31-Jul-14 31
53150-MAAA-00-108 Mirrors approval 14 11-Jun-14 26-Jun-14 17-Aug-14 01-Sep-14 55
53150-MAAA-00-109 Glass tiles with channel approval 14 11-Jun-14 26-Jun-14 02-Sep-14 17-Sep-14 69
53150-MACA-00-126 Thermal Insulation approval 14 01-Jul-14 16-Jul-14 31-Aug-14 15-Sep-14 50
53150-MAAA-00-106 Robe hook approval 14 08-Jul-14 23-Jul-14 06-Sep-14 21-Sep-14 49
53150-MACA-00-130 Refuse chute enclosure approval 14 07-Sep-14 22-Sep-14 17-Nov-14 03-Dec-14 57
53150-MACA-00-135 Residential Appliances appr oval 14 09-Nov-14 24-Nov-14 04-Jan-15 19-Jan-15 47
DSC MEP 174 29-Jan-14 23-Aug-14 04-Mar-14 13-Nov-14 67
DSC Submittals 160 29-Jan-14 06-Aug-14 04-Mar-14 28-Oct-14 67
53150-MAMS-00-102 Electrical cable tray submittal 6 29-Jan-14 04-Feb-14 23-Mar-14 29-Mar-14 45
53150-MAMS-00-105 Lightning Protection System submittal 6 29-Jan-14 04-Feb-14 13-Apr-14 19-Apr-14 63
53150-MAMS-00-106 Emergency lights submittal 6 29-Jan-14 04-Feb-14 04-Mar-14 10-Mar-14 29
53150-MAMS-00-136 Medical Equipments submittal 6 15-Feb-14 20-Feb-14 12-May-14 18-May-14 74
53150-MAMS-00-132 Hydronic pumps submittal 6 24-Feb-14 02-Mar-14 26-Apr-14 01-May-14 52
53150-MAMS-00-113 Water feeding pipes/accessories submittal 6 12-Mar-14 18-Mar-14 29-Jun-14 05-Jul-14 92
53150-MAMS-00-114 Disposal pipes/accessories submittal 6 12-Mar-14 18-Mar-14 01-Jun-14 07-Jun-14 68
53150-MAMS-00-115 Storm drainage piping submittal 6 12-Mar-14 18-Mar-14 22-Jun-14 28-Jun-14 86
53150-MAMS-00-116 Water heaters submittal 6 12-Mar-14 18-Mar-14 28-May-14 03-Jun-14 65
53150-MAMS-00-131 Gas pipes submittal 6 12-Mar-14 18-Mar-14 02-Jun-14 08-Jun-14 69
53150-MAMS-00-112 Lighting fixtures submittal 6 29-Mar-14 03-Apr-14 02-Jun-14 08-Jun-14 55
53150-MAMS-00-120 Fire alarm system submittal 6 05-Apr-14 10-Apr-14 25-Jun-14 01-Jul-14 69
53150-MAMS-00-122 Fire fighting pipes/accessories submittal 6 05-Apr-14 10-Apr-14 18-Jun-14 24-Jun-14 63
53150-MAMS-00-123 Fire hose cabinets submittal 6 05-Apr-14 10-Apr-14 26-Jun-14 02-Jul-14 70
53150-MAMS-00-133 Fire fighting pumps submittal 6 05-Apr-14 10-Apr-14 10-Jul-14 16-Jul-14 82
53150-MAMS-00-100 Sanitary ware submittal 6 09-Apr-14 15-Apr-14 29-May-14 04-Jun-14 42
53150-MAMS-00-101 Earthing system submittal 6 09-Apr-14 15-Apr-14 24-May-14 31-May-14 38
53150-MAMS-00-104 Lighting Management system submittal 6 09-Apr-14 15-Apr-14 08-May-14 14-May-14 25
53150-MAMS-00-107 Transformers submittal 6 09-Apr-14 15-Apr-14 30-Jun-14 06-Jul-14 69
53150-MAMS-00-108 switchgears submittal 6 09-Apr-14 15-Apr-14 30-Jun-14 06-Jul-14 69
53150-MAMS-00-109 Generator submittal 6 09-Apr-14 15-Apr-14 22-May-14 29-May-14 37
53150-MAMS-00-110 Exterior lighting submittal 6 09-Apr-14 15-Apr-14 17-Jun-14 23-Jun-14 58
53150-MAMS-00-137 Medical Gas system submittal 6 09-Apr-14 15-Apr-14 14-May-14 20-May-14 30
53150-MACS-00-110 Fire resistive joint system submittal 6 13-Apr-14 19-Apr-14 18-Jun-14 24-Jun-14 56
53150-MAMS-00-103 Sanitary fixtures submittal 6 21-Apr-14 27-Apr-14 14-Jul-14 20-Jul-14 71
53150-MAMS-00-111 Audio system submittal 6 21-Apr-14 27-Apr-14 05-Jul-14 10-Jul-14 63
53150-MAMS-00-126 Smoke dedectors submittal 6 21-Apr-14 27-Apr-14 14-Jul-14 20-Jul-14 71
53150-MACS-00-128 Foam water system submittal 6 22-Apr-14 28-Apr-14 15-Jul-14 21-Jul-14 71
53150-MAMS-00-135 Lifts materials submittal 6 03-May-14 08-May-14 24-Jun-14 30-Jun-14 44
53150-MAMS-00-117 HVAC Ducts submittal 6 08-May-14 14-May-14 05-Jul-14 10-Jul-14 48
53150-MAMS-00-118 Chilled water pipes submittal 6 08-May-14 14-May-14 30-Jun-14 06-Jul-14 44
53150-MAMS-00-119 HVAC fans submittal 6 08-May-14 14-May-14 21-Jul-14 27-Jul-14 62
53150-MAMS-00-121 Power Ventilator s s ubmittal 6 08-May-14 14-May-14 10-Jul-14 16-Jul-14 53
53150-MAMS-00-124 Air handling unit (AHU) submittal 6 08-May-14 14-May-14 23-Jun-14 29-Jun-14 38
53150-MAMS-00-125 Fan coil units (FCU) submittal 6 08-May-14 14-May-14 10-Jul-14 16-Jul-14 53

Actual Work Critical Remaining Work Summary Page 6 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAMS-00-127 Nurse call system submittal 6 14-May-14 20-May-14 07-Jul-14 13-Jul-14 45
53150-MAMS-00-128 IT/Telephone system submittal 6 14-May-14 20-May-14 07-Jul-14 13-Jul-14 45
53150-MAMS-00-129 Speakers submittal 6 14-May-14 20-May-14 07-Jul-14 13-Jul-14 45
53150-MAMS-00-130 BMS system submittal 6 14-May-14 20-May-14 13-Jul-14 19-Jul-14 50
53150-MAMS-00-134 Chillers Submittal 6 17-May-14 22-May-14 30-Jun-14 06-Jul-14 37
53150-MACS-00-137 Irrigation system submittal 6 21-May-14 28-May-14 05-Aug-14 11-Aug-14 62
53150-MACS-00-139 Visual Display Units submittal 6 28-May-14 03-Jun-14 02-Aug-14 07-Aug-14 54
53150-MACS-00-127 Security system submittal 6 19-Jun-14 25-Jun-14 21-Aug-14 27-Aug-14 52
53150-MACS-00-133 Master clock system submittal 6 31-Jul-14 06-Aug-14 21-Oct-14 28-Oct-14 67
53150-MACS-00-134 Queuing System submittal 6 31-Jul-14 06-Aug-14 18-Oct-14 23-Oct-14 64
DSC Approvals 168 05-Feb-14 23-Aug-14 11-Mar-14 13-Nov-14 67
53150-MAMA-00-102 Electrical cable tray approval 14 05-Feb-14 20-Feb-14 30-Mar-14 14-Apr-14 45
53150-MAMA-00-105 Lightning Protection System approval 14 05-Feb-14 20-Feb-14 20-Apr-14 05-May-14 63
53150-MAMA-00-106 Emergency lights approval 14 05-Feb-14 20-Feb-14 11-Mar-14 26-Mar-14 29
53150-MAMA-00-136 Medical Equipments approval 14 22-Feb-14 09-Mar-14 19-May-14 04-Jun-14 74
53150-MAMA-00-132 Hydronic pumps approval 14 03-Mar-14 18-Mar-14 03-May-14 18-May-14 52
53150-MAMA-00-113 Water feeding pipes/accessories approval 14 19-Mar-14 03-Apr-14 06-Jul-14 21-Jul-14 92
53150-MAMA-00-114 Disposal pipes/accessories approval 14 19-Mar-14 03-Apr-14 08-Jun-14 23-Jun-14 68
53150-MAMA-00-115 Storm drainage piping approval 14 19-Mar-14 03-Apr-14 29-Jun-14 14-Jul-14 86
53150-MAMA-00-116 Water heaters approval 14 19-Mar-14 03-Apr-14 04-Jun-14 19-Jun-14 65
53150-MAMA-00-131 Gas pipes approval 14 19-Mar-14 03-Apr-14 09-Jun-14 24-Jun-14 69
53150-MAMA-00-112 Lighting fixtures approval 14 05-Apr-14 20-Apr-14 09-Jun-14 24-Jun-14 55
53150-MAMA-00-120 Fire alarm system approval 14 12-Apr-14 27-Apr-14 02-Jul-14 17-Jul-14 69
53150-MAMA-00-122 Fire fighting pipes/accessories approval 14 12-Apr-14 27-Apr-14 25-Jun-14 10-Jul-14 63
53150-MAMA-00-123 Fire hose cabinets approval 14 12-Apr-14 27-Apr-14 03-Jul-14 19-Jul-14 70
53150-MAMA-00-133 Fire fighting pumps approval 14 12-Apr-14 27-Apr-14 17-Jul-14 04-Aug-14 82
53150-MAMA-00-100 Sanitary ware approval 14 16-Apr-14 01-May-14 05-Jun-14 21-Jun-14 42
53150-MAMA-00-101 Earthing system approval 14 16-Apr-14 01-May-14 01-Jun-14 16-Jun-14 38
53150-MAMA-00-104 Lighting Management system approval 14 16-Apr-14 01-May-14 15-May-14 01-Jun-14 25
53150-MAMA-00-107 Transformers approval 14 16-Apr-14 01-May-14 07-Jul-14 22-Jul-14 69
53150-MAMA-00-108 switchgears approval 14 16-Apr-14 01-May-14 07-Jul-14 22-Jul-14 69
53150-MAMA-00-109 Generator approval 14 16-Apr-14 01-May-14 31-May-14 15-Jun-14 37
53150-MAMA-00-110 Exterior lighting approval 14 16-Apr-14 01-May-14 24-Jun-14 09-Jul-14 58
53150-MAMA-00-137 Medical Gas system approval 14 16-Apr-14 01-May-14 21-May-14 07-Jun-14 30
53150-MACA-00-110 Fire resistive joint system approval 14 20-Apr-14 05-May-14 25-Jun-14 10-Jul-14 56
53150-MAMA-00-103 Sanitary fixtures approval 14 28-Apr-14 13-May-14 21-Jul-14 07-Aug-14 71
53150-MAMA-00-111 Audio system approval 14 28-Apr-14 13-May-14 12-Jul-14 27-Jul-14 63
53150-MAMA-00-126 Smoke dedectors approval 14 28-Apr-14 13-May-14 21-Jul-14 07-Aug-14 71
53150-MACA-00-128 Foam water system approval 14 29-Apr-14 14-May-14 22-Jul-14 09-Aug-14 71
53150-MAMA-00-135 Lifts materials approval 14 10-May-14 25-May-14 01-Jul-14 16-Jul-14 44
53150-MAMA-00-117 HVAC Ducts approval 14 15-May-14 01-Jun-14 12-Jul-14 27-Jul-14 48
53150-MAMA-00-118 Chilled water pipes approval 14 15-May-14 01-Jun-14 07-Jul-14 22-Jul-14 44
53150-MAMA-00-119 HVAC fans approval 14 15-May-14 01-Jun-14 28-Jul-14 14-Aug-14 62
53150-MAMA-00-121 Power Ventilator s approval 14 15-May-14 01-Jun-14 17-Jul-14 04-Aug-14 53
53150-MAMA-00-124 Air handling unit (AHU) approval 14 15-May-14 01-Jun-14 30-Jun-14 15-Jul-14 38
53150-MAMA-00-125 Fan coil units (FCU) approval 14 15-May-14 01-Jun-14 17-Jul-14 04-Aug-14 53
53150-MAMA-00-127 Nurse call system approval 14 21-May-14 07-Jun-14 14-Jul-14 31-Jul-14 45
53150-MAMA-00-128 IT/Telephone system approval 14 21-May-14 07-Jun-14 14-Jul-14 31-Jul-14 45
53150-MAMA-00-129 Speakers approval 14 21-May-14 07-Jun-14 14-Jul-14 31-Jul-14 45
53150-MAMA-00-130 BMS system approval 14 21-May-14 07-Jun-14 20-Jul-14 06-Aug-14 50
53150-MAMA-00-134 Chillers approval 14 24-May-14 09-Jun-14 07-Jul-14 22-Jul-14 37
53150-MACA-00-137 Irrigation system approval 14 29-May-14 14-Jun-14 12-Aug-14 27-Aug-14 62

Actual Work Critical Remaining Work Summary Page 7 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MACA-00-139 Visual Display Units approval 14 04-Jun-14 19-Jun-14 09-Aug-14 24-Aug-14 54
53150-MACA-00-127 Security system approval 14 26-Jun-14 12-Jul-14 28-Aug-14 13-Sep-14 52
53150-MACA-00-133 Master clock system approval 14 07-Aug-14 23-Aug-14 29-Oct-14 13-Nov-14 67
53150-MACA-00-134 Queuing System approval 14 07-Aug-14 23-Aug-14 26-Oct-14 10-Nov-14 64
DSC Medical Equipment 45 29-Mar-14 19-May-14 12-May-14 21-Jun-14 27
DSC Submittals 31 29-Mar-14 03-May-14 12-May-14 04-Jun-14 27
53150-MAQS-00-100 AMA010-Amalgamator, Digital-Submittal 6 29-Mar-14 03-Apr-14 12-May-14 18-May-14 38
53150-MAQS-00-104 BUC010-Bucket, Kick, Stainless Steel-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-105 CAB010-Pass-Through Speciemen Cabinet-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-107 CAB073-Cabinet, Laboratory, Metal, Epoxy Resin Lined,-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-110 CAR034-Cart, Waste, Trash, w/Lid, Heavy Duty Molded-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-111 CAR036-Cart, Housekeeping,-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-112 CAR042-Cart, Dressing, Stainless Steel, Surgery-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-113 CAS002-Cassettes, Exam and Check-7 Instrument-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-115 CEN101-Centrifuge, General Purpose-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-126 DIS053-Dispenser, Glov e, Size S-M-L-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-127 DPR001-Doppler, Fetal, Ultrasound with Speaker, Table Top-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-129 EXE004-Exercise, Grab Bars, Parallel, Adjustable, Stainless Steel, 7 Feet (213 c m)-Submittal
6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-130 EXE015-Exercise, Recliner-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-131 EXE020-Exercise, Treadmill- Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-132 EXE028-Exercise, Mat-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-133 EXE041-Exercise, Balls, Disk, Pads, Roller, Dome, Pendulum,Physical Therapy-Submittal
6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-134 FLO900-Flowmeter, Gas, Oxygen- Submittal 6 09-Apr-14 15-Apr-14 29-May-14 04-Jun-14 42
53150-MAQS-00-139 IMG010-Imaging, Ultrasonic, Cardiac-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-140 IMG028-Imaging, Radiographic Digital System, General-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-141 IMG030-Imaging, Scanner, X-Ray F ilm-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-142 IMG065-Image Digitization Systems, Computed Radiography,Dental, Handheld-Submittal6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-143 LIG040-Luminaire, Examination, Flex, LED, Single Lamp,Table-Chair mount-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-144 LIG053-Luminaire, Examination, Ceiling, Adjus table, LED, 3 Lamps-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-145 LIG057-Luminaire, Tr eatment, Ceiling, Adjustable, 3 Lamps-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-146 MIC015-Microscope, Laboratory, Light-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-154 ORT001-Ortho, Cast, Plaster, Wedge Set-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-155 ORT005-Ortho, Cast, Plaster, Knee Rest-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-156 ORT010-Ortho, Cast, Plaster, Instruments (Scissors and Spreader)-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-157 ORT021-Ortho, Cast, Plaster Saw, Orthopedic, Blade Set-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-158 ORT025-Ortho, Cast, Plaster Saw and Vacuum-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-164 REF033-Refrigerator, Blood Bank, Upright, Mobile-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-165 REF064-Refrigerator, Under-counter, Domestic, Stainless Steel-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-166 REF071-Refrigerator, Under-counter, Glass Door, Pharmacy-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-167 REF072-Refrigerator, Full Height, G lass Door, Casters,Pharmacy-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-169 SCA010-Scale, CounterTop, Infant-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-170 SCA082-Scale, Standing, Digital, W/Height Measurement-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-171 SCA083-Scale, Wheelchair, mobile-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-172 SCA123-Scale, Patient, Platform, Electronic-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-174 SHL001-Shields, X-Ray, Apron-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-175 SHL002-Shields, X-Ray, Gonad-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-176 SHL003-Shields, X-Ray, Throat-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-180 STE060-Sterilizer, Flash, Plas ma, Low- Temp, Bench Top-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-181 STE070-Sterilizer, Autoclave, Dental, Bench Top-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-182 STE900-Stethoscope, Ultrasond with Cardio-beat Doppler-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-187 STO004-Stool, height adjustable, swivel, mobile-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-188 STO006-Stool, Physician, height adjustable, swivel, mobile-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28

Actual Work Critical Remaining Work Summary Page 8 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAQS-00-189 STO009-Stool, Step-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-191 STO024-Stool, dental, with back support, mobile-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-193 TAB071-Table, Operating, Minor, Variable Heights, Flat Upholstery, Power-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-199 TRO005-Trolley, Plaster with (8) drawers-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-200 TRO149-Trolley, 5 Drawer, Unequal, Medical-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-208 ULT910-Ultrasound/Electro Therapy System, General Purpose,-Submittal 6 09-Apr-14 15-Apr-14 12-May-14 18-May-14 28
53150-MAQS-00-194 TAB098-Table, Examination/Treatment, Variable Heights,-Submittal 6 10-Apr-14 16-Apr-14 12-May-14 18-May-14 27
53150-MAQS-00-195 TAB125-Table, Examination/Treatment, Variable Heights-Submittal 6 10-Apr-14 16-Apr-14 12-May-14 18-May-14 27
53150-MAQS-00-196 TAB131-Table, Multi-Position, 249 kg. lift capacity, Physical Therapy-Submittal 6 10-Apr-14 16-Apr-14 12-May-14 18-May-14 27
53150-MAQS-00-197 TAB200-Table, Accessories, Pads and Pillows, Physical-Submittal 6 10-Apr-14 16-Apr-14 12-May-14 18-May-14 27
53150-MAQS-00-101 ANA901-Analyzer, Body Fat-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-102 AUD005-Audiometer, D igital, Software with Headphones-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-103 BAL009-Balances, Analytical, Countertop, Phar macy- Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-106 CAB060-Cabinet, Dispensary, Modular, Free Standing-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-108 CAB290-Cabinet, Storage, Medicine, Narcotic Control-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-109 CAR032-Cart, Recyclable, Plastic, w/Lid, Heavy Duty Molded Polyethylene-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-114 CAS003-Cassettes, Hygiene-9 Instrument-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-116 CHA003-Chair, height adjustable, tilt ing back, adj. footrest,-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-117 CHA025-Chair, Blood Dr aw R ecliner, Phlebotomy, Mobile-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-118 CHA040-Chair, Dental, with multi-serv ic es, fully adjus table,elec. Operated-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-119 CHT001-Chart, Eye, Snellen Eye Chart, wall mounted with-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-120 CON001-Control Booth, Radiology, Free Standing-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-121 COU049-Counter, Tablet, Electrical, Small Quantities,Accuracy 0.001g / 0.01g-Submittal6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-122 CRT092-Cart, Ear/Nose/Throat Treatment Unit-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-123 CSR001-Air Compressor, Dental-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-124 DIC014-Dictation, Handheld, Physician-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-125 DIG011-Diagnostic Set - Ophthalmoscope/Otoscope Thermometer, Elec ., infrared, Ear-6Submittal
21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-128 DSU020-Disposal Unit, 5 Lt. Sharps Container w/ Glove-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-135 HAM001-Hamper,Linen/Laundry, Heavy Duty Molded Polyethylene-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-136 HOI007-Lift, Patient, Transfer, Power Operated, 450 lbs. max-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-137 HOL006-Holder, s ack, with lid foot operated, Hamper -Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-138 ILL011-Illuminator-View Box, X-Ray, One Tier, Two- Bank -Submit tal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-147 MON051-Monitor, Fetal-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-148 MON090-Monitor, Vital Signs, Stand, Mobile - (55.8 cm. dia. Stand)-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-149 MON095-Monitor, Cardiac Stress-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-150 OPH020-Ophthalmoscope and Retinoscopes, Direct, Combo-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-151 OPH021-Ophthalmoscope, Indirect Set-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-152 OPH030-Tonometer, Handheld-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-153 OPH200-Ophthalmic Lamp, Slit-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-159 PAC001-Picture Archiving and Communication System (refer to Imaging; IMG028 for Specifications)-Submittal
6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-160 POL001-Stand, IV, Antistatic C astors, S/S-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-161 RAC196-Rack, x-ray lead apron, 5 hangers hinged, wall-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-162 RCL005-Receptacle, Waste-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-163 REC010-Recorder, Electrocardiograph, 12 Channels-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-168 REF124-Refrigerator/Freezer, Full Height, Casters-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-173 SEA002-Heat sealer, Dental- Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-177 SPH003-Sphygmomanometers, Aner oid, Mobile-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-178 STD001-Stand, Mayo-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-179 STD095-Stand-Instrument, Examination/Treatment,-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-184 STE920-Stethoscope, Pediatric-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-185 STG200-Storage, Medical Records, lateral, Single Guide-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-186 STM050-Stimulator,EMS/T EN S (Elec t. Muscle/Transcutaneous Elec. Nerve Stimulator)-Submittal
6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18

Actual Work Critical Remaining Work Summary Page 9 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAQS-00-190 VAC001-Vacuum Pump, D ental (Cyclonic Separator Tank -56 x 41 x 117)-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-192 SUC900-Regulator, Suction, Low Volume-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-198 THE001-Thermometer, Electr onic with wall holder-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-201 TRO200-Trolley, Gas Cylinders-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-202 TRO255-Trolley, 6 Drawer, Unequal, Dental-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-203 TRO255-Trolley, 6 Drawer, Unequal, Medical-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-204 TRO255-Trolley, 6 Drawer, Unequal, Ophthalmology-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-205 TRO255-Trolley, 6 Drawer, Unequal, Special Procedures-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-206 TRO285-Stretcher, Patient Transfer-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-207 TRO310-Trolley, Emergency/Resuscitation, complete with-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-209 WHC059-Wheelchair, 17 inc h s eat, Attended Propelled-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-210 WSH042-Wash, Instrument, Ultrasonic with a pre-soak tray,-Submittal 6 21-Apr-14 27-Apr-14 12-May-14 18-May-14 18
53150-MAQS-00-183 STE905-Stethoscope, Electronic-Submittal 6 27-Apr-14 03-May-14 12-May-14 18-May-14 13
DSC Approvals 39 05-Apr-14 19-May-14 19-May-14 21-Jun-14 27
53150-MAQA-00-100 AMA010-Amalgamator, Digital-Approval 14 05-Apr-14 20-Apr-14 19-May-14 04-Jun-14 38
53150-MAQA-00-104 BUC010-Bucket, Kick, Stainless Steel-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-105 CAB010-Pass-Through Speciemen Cabinet-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-107 CAB073-Cabinet, Laboratory, Metal, Epoxy Resin Lined,-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-110 CAR034-Cart, Waste, Trash, w/Lid, Heavy Duty Molded-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-111 CAR036-Cart, Housekeeping,-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-112 CAR042-Cart, Dressing, Stainless Steel, Surgery-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-113 CAS002-Cassettes, Exam and Check-7 Instrument-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-115 CEN101-Centrifuge, General Purpose-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-126 DIS053-Dispenser, Glov e, Size S-M-L-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-127 DPR001-Doppler, Fetal, Ultrasound with Speaker, Table Top-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-129 EXE004-Exercise, Grab Bars, Parallel, Adjustable, Stainless Steel, 7 Feet (213 c m)-Appr
14oval16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-130 EXE015-Exercise, Recliner-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-131 EXE020-Exercise, Treadmill- Approv al 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-132 EXE028-Exercise, Mat-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-133 EXE041-Exercise, Balls, Disk, Pads, Roller, Dome, Pendulum,Physical Therapy-Approval
14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-134 FLO900-Flowmeter, Gas, Oxygen- Appr oval 14 16-Apr-14 01-May-14 05-Jun-14 21-Jun-14 42
53150-MAQA-00-139 IMG010-Imaging, Ultrasonic, Cardiac-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-140 IMG028-Imaging, Radiographic Digital System, General-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-141 IMG030-Imaging, Scanner, X-Ray F ilm-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-142 IMG065-Image Digitization Systems, Computed Radiography,Dental, Handheld-Approval
14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-143 LIG040-Luminaire, Examination, Flex, LED, Single Lamp,Table-Chair mount-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-144 LIG053-Luminaire, Examination, Ceiling, Adjus table, LED, 3 Lamps-Appr oval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-145 LIG057-Luminaire, Tr eatment, Ceiling, Adjustable, 3 Lamps-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-146 MIC015-Microscope, Laboratory, Light-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-154 ORT001-Ortho, Cast, Plaster, Wedge Set-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-155 ORT005-Ortho, Cast, Plaster, Knee Rest-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-156 ORT010-Ortho, Cast, Plaster, Instruments (Scissors and Spreader)-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-157 ORT021-Ortho, Cast, Plaster Saw, Orthopedic, Blade Set-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-158 ORT025-Ortho, Cast, Plaster Saw and Vacuum-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-164 REF033-Refrigerator, Blood Bank, Upright, Mobile-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-165 REF064-Refrigerator, Under-counter, Domestic, Stainless Steel-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-166 REF071-Refrigerator, Under-counter, Glass Door, Pharmacy-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-167 REF072-Refrigerator, Full Height, G lass Door, Casters,Pharmacy-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-169 SCA010-Scale, CounterTop, Infant-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-170 SCA082-Scale, Standing, Digital, W/Height Measurement-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-171 SCA083-Scale, Wheelchair, mobile-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-172 SCA123-Scale, Patient, Platform, Electronic-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28

Actual Work Critical Remaining Work Summary Page 10 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAQA-00-174 SHL001-Shields, X-Ray, Apron-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-175 SHL002-Shields, X-Ray, Gonad-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-176 SHL003-Shields, X-Ray, Throat-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-180 STE060-Sterilizer, Flash, Plas ma, Low- Temp, Bench Top-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-181 STE070-Sterilizer, Autoclave, Dental, Bench Top-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-182 STE900-Stethoscope, Ultrasond with Cardio-beat Doppler-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-187 STO004-Stool, height adjustable, swivel, mobile-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-188 STO006-Stool, Physician, height adjustable, swivel, mobile-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-189 STO009-Stool, Step-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-191 STO024-Stool, dental, with back support, mobile-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-193 TAB071-Table, Operating, Minor, Variable Heights, Flat Upholstery, Power-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-199 TRO005-Trolley, Plaster with (8) drawers-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-200 TRO149-Trolley, 5 Drawer, Unequal, Medical-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-208 ULT910-Ultrasound/Electro Therapy System, General Purpose,-Approval 14 16-Apr-14 01-May-14 19-May-14 04-Jun-14 28
53150-MAQA-00-194 TAB098-Table, Examination/Treatment, Variable Heights,-Approval 14 17-Apr-14 03-May-14 19-May-14 04-Jun-14 27
53150-MAQA-00-195 TAB125-Table, Examination/Treatment, Variable Heights-Approval 14 17-Apr-14 03-May-14 19-May-14 04-Jun-14 27
53150-MAQA-00-196 TAB131-Table, Multi-Position, 249 kg. lift capacity, Physical Therapy-Approval 14 17-Apr-14 03-May-14 19-May-14 04-Jun-14 27
53150-MAQA-00-197 TAB200-Table, Accessories, Pads and Pillows, Physical-Approval 14 17-Apr-14 03-May-14 19-May-14 04-Jun-14 27
53150-MAQA-00-101 ANA901-Analyzer, Body Fat-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-102 AUD005-Audiometer, D igital, Software with Headphones-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-103 BAL009-Balances, Analytical, Countertop, Phar macy- Approv al 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-106 CAB060-Cabinet, Dispensary, Modular, Free Standing-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-108 CAB290-Cabinet, Storage, Medicine, Narcotic Control-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-109 CAR032-Cart, Recyclable, Plastic, w/Lid, Heavy Duty Molded Polyethylene-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-114 CAS003-Cassettes, Hygiene-9 Instrument-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-116 CHA003-Chair, height adjustable, tilt ing back, adj. footrest,-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-117 CHA025-Chair, Blood Dr aw R ecliner, Phlebotomy, Mobile-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-118 CHA040-Chair, Dental, with multi-serv ic es, fully adjus table,elec. Operated-Appr oval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-119 CHT001-Chart, Eye, Snellen Eye Chart, wall mounted with-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-120 CON001-Control Booth, Radiology, Free Standing-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-121 COU049-Counter, Tablet, Electrical, Small Quantities,Accuracy 0.001g / 0.01g-Approval
14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-122 CRT092-Cart, Ear/Nose/Throat Treatment Unit-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-123 CSR001-Air Compressor, Dental-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-124 DIC014-Dictation, Handheld, Physician-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-125 DIG011-Diagnostic Set - Ophthalmoscope/Otoscope Thermometer, Elec ., infrared, Ear-
14Appr28-Apr-14
ov al 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-128 DSU020-Disposal Unit, 5 Lt. Sharps Container w/ Glove-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-135 HAM001-Hamper,Linen/Laundry, Heavy Duty Molded Polyethylene-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-136 HOI007-Lift, Patient, Transfer, Power Operated, 450 lbs. max-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-137 HOL006-Holder, s ack, with lid foot operated, Hamper -Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-138 ILL011-Illuminator-View Box, X-Ray, One Tier, Two- Bank -Appr oval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-147 MON051-Monitor, Fetal-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-148 MON090-Monitor, Vital Signs, Stand, Mobile - (55.8 cm. dia. Stand)-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-149 MON095-Monitor, Cardiac Stress-Approv al 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-150 OPH020-Ophthalmoscope and Retinoscopes, Direct, Combo-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-151 OPH021-Ophthalmoscope, Indirect Set-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-152 OPH030-Tonometer, Handheld-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-153 OPH200-Ophthalmic Lamp, Slit-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-159 PAC001-Picture Archiving and Communication System (refer to Imaging; IMG028 for Specifications)-Approval
14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-160 POL001-Stand, IV, Antistatic C astors, S/S-Appr ov al 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-161 RAC196-Rack, x-ray lead apron, 5 hangers hinged, wall-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-162 RCL005-Receptacle, Waste-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-163 REC010-Recorder, Electrocardiograph, 12 Channels-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18

Actual Work Critical Remaining Work Summary Page 11 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAQA-00-168 REF124-Refrigerator/Freezer, Full Height, Casters-Appr oval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-173 SEA002-Heat sealer, Dental- Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-177 SPH003-Sphygmomanometers, Aner oid, Mobile-Appr oval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-178 STD001-Stand, Mayo-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-179 STD095-Stand-Instrument, Examination/Treatment,-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-184 STE920-Stethoscope, Pediatric-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-185 STG200-Storage, Medical Records, lateral, Single Guide-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-186 STM050-Stimulator,EMS/T EN S (Elec t. Muscle/Transcutaneous Elec. Nerve Stimulator)-Approval
14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-190 VAC001-Vacuum Pump, D ental (Cyclonic Separator Tank -56 x 41 x 117)-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-192 SUC900-Regulator, Suction, Low Volume-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-198 THE001-Thermometer, Electr onic with wall holder-Appr oval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-201 TRO200-Trolley, Gas Cylinders-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-202 TRO255-Trolley, 6 Drawer, Unequal, Dental-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-203 TRO255-Trolley, 6 Drawer, Unequal, Medical-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-204 TRO255-Trolley, 6 Drawer, Unequal, Ophthalmology-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-205 TRO255-Trolley, 6 Drawer, Unequal, Special Procedures-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-206 TRO285-Stretcher, Patient Transfer-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-207 TRO310-Trolley, Emergency/Resuscitation, complete with-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-209 WHC059-Wheelchair, 17 inc h s eat, Attended Propelled-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-210 WSH042-Wash, Instrument, Ultrasonic with a pre-soak tray,-Approval 14 28-Apr-14 13-May-14 19-May-14 04-Jun-14 18
53150-MAQA-00-183 STE905-Stethoscope, Electronic-Approval 14 04-May-14 19-May-14 19-May-14 04-Jun-14 13
Shop Drawings Submission / Approvals 124 09-Jan-14 04-Jun-14 22-Jan-14 02-Sep-14 75
DSC Civil 122 09-Jan-14 02-Jun-14 22-Jan-14 02-Sep-14 77
DSC Submittals 108 09-Jan-14 15-May-14 22-Jan-14 17-Aug-14 77
53150-SDCS-00-100 Secant Piles Design submittal 6 09-Jan-14 16-Jan-14 22-Jan-14 28-Jan-14 10
53150-SDCS-00-101 Concrete Piles Design submittal 6 09-Jan-14 16-Jan-14 16-Feb-14 22-Feb-14 31
53150-SDCS-00-109 Dewatering system S.Drawings submittal 6 15-Jan-14 21-Jan-14 29-Mar-14 03-Apr-14 62
53150-SDCS-00-104 Steel Reinforcement S.Drawings submittal - Basement 6 19-Mar-14 25-Mar-14 26-May-14 02-Jun-14 58
53150-SDCS-00-130 Steel Reinforcement S.Drawings submittal - Ground Floor 6 31-Mar-14 06-Apr-14 22-Jun-14 28-Jun-14 70
53150-SDCS-00-120 Steel Reinforcement S.Drawings submittal - First Floor 6 19-Apr-14 24-Apr-14 10-Jul-14 16-Jul-14 70
53150-SDCS-00-107 Soft landscape S.Drawings submittal 6 29-Apr-14 05-May-14 11-Aug-14 17-Aug-14 86
53150-SDCS-00-110 Hardscape S.Drawings submittal 6 10-May-14 15-May-14 26-Jul-14 03-Aug-14 65
DSC Approvals 116 18-Jan-14 02-Jun-14 29-Jan-14 02-Sep-14 77
53150-SDCA-00-100 Secant Piles Design approval 14 18-Jan-14 02-Feb-14 29-Jan-14 13-Feb-14 10
53150-SDCA-00-101 Concrete Piles Design approval 14 18-Jan-14 02-Feb-14 23-Feb-14 10-Mar-14 31
53150-SDCA-00-107 Dewatering system S.Drawings approval 14 22-Jan-14 06-Feb-14 05-Apr-14 20-Apr-14 62
53150-SDCA-00-108 Steel Reinforcement S.Drawings approval - Basement 14 26-Mar-14 10-Apr-14 10-Jun-14 25-Jun-14 64
53150-SDCA-00-120 Steel Reinforcement S.Drawings approval- Ground Floor 14 07-Apr-14 22-Apr-14 24-Jul-14 11-Aug-14 92
53150-SDCA-00-130 Steel Reinforcement S.Drawings approval - First Floor 14 26-Apr-14 11-May-14 17-Aug-14 01-Sep-14 94
53150-SDCA-00-106 Soft landscape S.Drawings approval 14 06-May-14 21-May-14 18-Aug-14 02-Sep-14 86
53150-SDCA-00-110 Hardscape S.Drawings approval 14 17-May-14 02-Jun-14 04-Aug-14 19-Aug-14 65
DSC Architecture 57 30-Mar-14 04-Jun-14 24-May-14 02-Sep-14 75
DSC Submittals 43 30-Mar-14 18-May-14 24-May-14 17-Aug-14 75
53150-SDAS-00-104 Wooden works S.Drawings submittal 6 30-Mar-14 05-Apr-14 19-Jul-14 24-Jul-14 94
53150-SDAS-00-101 Corner Guards/wall protection S.Drawings submittal 6 09-Apr-14 15-Apr-14 17-Jun-14 23-Jun-14 58
53150-SDAS-00-102 Wall tiles S.Drawings submittal 6 14-Apr-14 20-Apr-14 24-May-14 31-May-14 34
53150-SDAS-00-100 Flooring Layout S.Drawings submittal 6 16-Apr-14 22-Apr-14 28-May-14 03-Jun-14 35
53150-SDAS-00-109 Marking S.Drawings submittal 6 16-Apr-14 22-Apr-14 02-Jul-14 08-Jul-14 65
53150-SDCS-00-102 Entrance Canopy S.Drawings submittal 6 17-Apr-14 23-Apr-14 05-Jul-14 10-Jul-14 66
53150-SDCS-00-103 Steel Staircase S.Drawings submittal 6 26-Apr-14 01-May-14 18-Jun-14 24-Jun-14 45
53150-SDCS-00-105 Handrail S.Drawings submittal 6 26-Apr-14 01-May-14 11-Aug-14 17-Aug-14 89
53150-SDCS-00-106 Stair Gate S.Drawings submittal 6 26-Apr-14 01-May-14 11-Aug-14 17-Aug-14 89

Actual Work Critical Remaining Work Summary Page 12 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-SDCS-00-108 Metal works S.Drawings submittal 6 26-Apr-14 01-May-14 11-Aug-14 17-Aug-14 89
53150-SDAS-00-107 Wooden doors S.Drawings submittal 6 01-May-14 07-May-14 11-Aug-14 17-Aug-14 84
53150-SDAS-00-110 Interior Signage S.Drawings submittal 6 04-May-14 10-May-14 19-Jul-14 24-Jul-14 64
53150-SDAS-00-103 False ceiling S.Drawings submittal 6 05-May-14 11-May-14 15-Jun-14 21-Jun-14 34
53150-SDAS-00-105 Aluminium doors/windows S.Drawings submittal 6 05-May-14 11-May-14 08-Jul-14 14-Jul-14 54
53150-SDAS-00-106 Curtain wall S.Drawings submittal 6 05-May-14 11-May-14 28-Jun-14 03-Jul-14 45
53150-SDAS-00-111 Exterior Signage S.Drawings submittal 6 05-May-14 11-May-14 22-Jun-14 28-Jun-14 40
53150-SDAS-00-112 GRC works S.Drawings submittal 6 12-May-14 18-May-14 11-Aug-14 17-Aug-14 75
DSC Approvals 51 06-Apr-14 04-Jun-14 01-Jun-14 02-Sep-14 75
53150-SDAA-00-104 Wooden works S.Drawings approval 14 06-Apr-14 21-Apr-14 26-Jul-14 12-Aug-14 94
53150-SDAA-00-101 Corner Guards/wall protection S.Drawings approval 14 16-Apr-14 01-May-14 24-Jun-14 09-Jul-14 58
53150-SDAA-00-102 Wall tiles S.Drawings approval 14 21-Apr-14 06-May-14 01-Jun-14 16-Jun-14 34
53150-SDAA-00-100 Flooring Layout S.Drawings approval 14 23-Apr-14 08-May-14 04-Jun-14 19-Jun-14 35
53150-SDAA-00-109 Marking S.Drawings approval 14 23-Apr-14 08-May-14 09-Jul-14 24-Jul-14 65
53150-SDCA-00-102 Entrance Canopy S.Drawings approval 14 24-Apr-14 10-May-14 12-Jul-14 27-Jul-14 66
53150-SDCA-00-103 Steel Staircase S.Drawings approval 14 03-May-14 18-May-14 18-Aug-14 02-Sep-14 89
53150-SDCA-00-104 Handrail S.Drawings approval 14 03-May-14 18-May-14 18-Aug-14 02-Sep-14 89
53150-SDCA-00-105 Stair Gate S.Drawings approval 14 03-May-14 18-May-14 18-Aug-14 02-Sep-14 89
53150-SDCA-00-109 Metal works S.Drawings approval 14 03-May-14 18-May-14 18-Aug-14 02-Sep-14 89
53150-SDAA-00-107 Wooden doors S.Drawings approval 14 08-May-14 24-May-14 18-Aug-14 02-Sep-14 84
53150-SDAA-00-110 Interior Signage S.Drawings approval 14 11-May-14 26-May-14 26-Jul-14 12-Aug-14 64
53150-SDAA-00-103 False ceiling S.Drawings approval 14 12-May-14 28-May-14 22-Jun-14 07-Jul-14 34
53150-SDAA-00-105 Aluminium doors/windows S.Drawings approval 14 12-May-14 28-May-14 15-Jul-14 02-Aug-14 54
53150-SDAA-00-106 Curtain wall S.Drawings approval 14 12-May-14 28-May-14 05-Jul-14 20-Jul-14 45
53150-SDAA-00-111 Exterior Signage S.Drawings approval 14 12-May-14 28-May-14 29-Jun-14 14-Jul-14 40
53150-SDAA-00-108 GRC works S.Drawings approval 14 19-May-14 04-Jun-14 18-Aug-14 02-Sep-14 75
DSC MEP 69 12-Mar-14 01-Jun-14 14-May-14 02-Sep-14 78
DSC Submittals 55 12-Mar-14 14-May-14 14-May-14 17-Aug-14 78
53150-SDMS-00-101 Plumbing S.Drawings submittal 6 12-Mar-14 18-Mar-14 18-May-14 24-May-14 57
53150-SDMS-00-103 Fire fighting S.Drawings submittal 6 05-Apr-14 10-Apr-14 24-May-14 31-May-14 42
53150-SDMS-00-100 Electrical S.Drawings submittal 6 15-Apr-14 21-Apr-14 14-May-14 20-May-14 25
53150-SDMS-00-104 Fire alarm S.Drawings submittal 6 29-Apr-14 05-May-14 11-Aug-14 17-Aug-14 86
53150-SDMS-00-106 Lifts S.Drawings submittal 6 03-May-14 08-May-14 24-Jun-14 30-Jun-14 44
53150-SDMS-00-105 IT/Telephone S.Drawings submittal 6 05-May-14 11-May-14 03-Jun-14 09-Jun-14 24
53150-SDMS-00-102 HVAC S.Drawings submittal 6 08-May-14 14-May-14 05-Jul-14 10-Jul-14 48
DSC Approvals 63 19-Mar-14 01-Jun-14 21-May-14 02-Sep-14 78
53150-SDMA-00-101 Plumbing S.Drawings approval 14 19-Mar-14 03-Apr-14 25-May-14 10-Jun-14 57
53150-SDMA-00-103 Fire fighting S.Drawings approval 14 12-Apr-14 27-Apr-14 01-Jun-14 16-Jun-14 42
53150-SDMA-00-100 Electrical S.Drawings approval 14 22-Apr-14 07-May-14 21-May-14 07-Jun-14 25
53150-SDMA-00-104 Fire alarm S.Drawings approval 14 06-May-14 21-May-14 18-Aug-14 02-Sep-14 86
53150-SDMA-00-106 Lifts S.Drawings approval 14 10-May-14 25-May-14 01-Jul-14 16-Jul-14 44
53150-SDMA-00-105 IT/Telephone S.Drawings approval 14 12-May-14 28-May-14 10-Jun-14 25-Jun-14 24
53150-SDMA-00-102 HVAC S.Drawings approval 14 15-May-14 01-Jun-14 12-Jul-14 27-Jul-14 48
Method Statements Submission / Approvals 365 07-Dec-13 16-Feb-15 08-Dec-13 18-Apr-15 52
Civil 138 07-Dec-13 18-May-14 08-Dec-13 11-Aug-14 70
Submittals 124 07-Dec-13 01-May-14 08-Dec-13 23-Jul-14 70
53150-MSCS-00-100 Method Statement for Demolition Works submittal 1 07-Dec-13 07-Dec-13 08-Dec-13 08-Dec-13 1
53150-MSCS-00-101 Method Statement for Tempor ar y F encing & Sig nage submittal 6 07-Dec-13 12-Dec-13 16-Mar-14 22-Mar-14 83
53150-MSCS-00-104 Method statement submittal Excavation 6 21-Dec-13 26-Dec-13 02-Jan-14 08-Jan-14 10
53150-MSCS-00-108 Method Statement for Blinding Concrete Works submittal 6 05-Jan-14 11-Jan-14 30-Apr-14 06-May-14 98
53150-MSCS-00-102 Method Statement for Shoring/Piling Works submittal 6 09-Jan-14 16-Jan-14 22-Jan-14 28-Jan-14 10
53150-MSCS-00-106 Method statement submittal Dewatering 6 15-Jan-14 21-Jan-14 29-Mar-14 03-Apr-14 62

Actual Work Critical Remaining Work Summary Page 13 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MSCS-00-110 Method statement submittal Wtater Proofing 6 04-Feb-14 10-Feb-14 14-May-14 20-May-14 85
53150-MSCS-00-105 Method statement submittal Backfill 6 27-Feb-14 05-Mar-14 29-Apr-14 05-May-14 52
53150-MSCS-00-107 Method Statement for Anti Termite submittal 6 17-Mar-14 23-Mar-14 03-Jun-14 09-Jun-14 66
53150-MSCS-00-109 Method Statement for Substructure and RCC concrete Works submittal 6 09-Apr-14 15-Apr-14 03-Jun-14 09-Jun-14 46
53150-MSCS-00-111 Method Statement for Superstructure and RCC concrete Works submittal 6 26-Apr-14 01-May-14 17-Jul-14 23-Jul-14 70
Approvals 137 08-Dec-13 18-May-14 09-Dec-13 11-Aug-14 70
53150-MSCA-00-100 Method Statement for Demolition Works Approval 14 08-Dec-13 23-Dec-13 09-Dec-13 24-Dec-13 1
53150-MSCA-00-101 Method Statement for Tempor ar y F encing & Sig nage Approval 14 14-Dec-13 29-Dec-13 23-Mar-14 07-Apr-14 83
53150-MSCA-00-104 Method statement Approval Exc avation 14 28-Dec-13 13-Jan-14 09-Jan-14 26-Jan-14 10
53150-MSCA-00-108 Method Statement for Blinding Concrete Works Approval 14 12-Jan-14 28-Jan-14 07-May-14 22-May-14 98
53150-MSCA-00-102 Method Statement for Shoring/Piling Works Approval 14 18-Jan-14 02-Feb-14 29-Jan-14 13-Feb-14 10
53150-MSCA-00-106 Method statement Approval D ewatering 14 22-Jan-14 06-Feb-14 05-Apr-14 20-Apr-14 62
53150-MSCA-00-110 Method statement Approval Wtater Proofing 14 11-Feb-14 26-Feb-14 21-May-14 07-Jun-14 85
53150-MSCA-00-105 Method statement Approval Backfill 14 06-Mar-14 22-Mar-14 06-May-14 21-May-14 52
53150-MSCA-00-107 Method Statement for Anti Termite Approval 14 24-Mar-14 08-Apr-14 10-Jun-14 25-Jun-14 66
53150-MSCA-00-109 Method Statement for Substructure and RCC concrete Works Approval 14 16-Apr-14 01-May-14 10-Jun-14 25-Jun-14 46
53150-MSCA-00-111 Method Statement for Superstructure and RCC concrete Works Approval 14 03-May-14 18-May-14 24-Jul-14 11-Aug-14 70
Architecture 205 15-Jun-14 16-Feb-15 19-Aug-14 18-Apr-15 52
Submittals 191 15-Jun-14 31-Jan-15 19-Aug-14 23-Mar-15 44
53150-MSAS-00-100 Method Statement for Block Works submittal 6 15-Jun-14 21-Jun-14 19-Aug-14 25-Aug-14 54
53150-MSAS-00-102 Method Statement for Precast Concrete Façade Elements Works submittal 6 01-Jul-14 07-Jul-14 06-Sep-14 11-Sep-14 55
53150-MSAS-00-103 Method Statement for Painting Works submittal 6 24-Jul-14 02-Aug-14 13-Sep-14 18-Sep-14 41
53150-MSAS-00-113 Method Statement for External Paint submittal 6 07-Aug-14 13-Aug-14 20-Sep-14 25-Sep-14 37
53150-MSAS-00-109 Method Statement for Ceramic Tiling Works submittal 6 18-Aug-14 24-Aug-14 27-Sep-14 02-Oct-14 34
53150-MSAS-00-101 Method Statement for Plaster Works submittal 6 25-Aug-14 31-Aug-14 04-Oct-14 13-Oct-14 34
53150-MSAS-00-107 Method Statement for Dry Walls/Gypsum Wall submittal 6 04-Sep-14 10-Sep-14 14-Oct-14 20-Oct-14 31
53150-MSAS-00-110 Method Statement for Vinyl Flooring submittal 6 11-Sep-14 17-Sep-14 21-Oct-14 28-Oct-14 31
53150-MSAS-00-112 Method Statement for Window Shade Installation submittal 6 18-Sep-14 24-Sep-14 29-Oct-14 04-Nov-14 31
53150-MSAS-00-114 Method Statement for Installation of Doors & Windows submittal 6 25-Sep-14 01-Oct-14 05-Nov-14 11-Nov-14 31
53150-MSAS-00-118 Method Statement for Radiation Protection Installation submittal 6 02-Oct-14 12-Oct-14 12-Nov-14 18-Nov-14 31
53150-MSAS-00-106 Method Statement for Steel Staircase installation submittal 6 20-Oct-14 27-Oct-14 14-Dec-14 20-Dec-14 45
53150-MSAS-00-108 Method Statement for False Ceiling Installation submittal 6 01-Nov-14 06-Nov-14 21-Dec-14 27-Dec-14 42
53150-MSAS-00-115 Method Statement for Internal Signage Works submittal 6 26-Nov-14 03-Dec-14 10-Feb-15 16-Feb-15 64
53150-MSAS-00-116 Method Statement for Paving and Curbs submittal 6 04-Dec-14 10-Dec-14 17-Feb-15 23-Feb-15 64
53150-MSAS-00-111 Method Statement for Carpet Flooring submittal 6 14-Dec-14 21-Dec-14 24-Feb-15 02-Mar-15 61
53150-MSAS-00-105 Method Statement for Canopy submittal 6 21-Dec-14 28-Dec-14 03-Mar-15 09-Mar-15 61
53150-MSAS-00-104 Method Statement for Curtain Walling submittal 6 18-Jan-15 24-Jan-15 10-Mar-15 16-Mar-15 44
53150-MSAS-00-117 Method Statement for Road Works submittal 6 25-Jan-15 31-Jan-15 17-Mar-15 23-Mar-15 44
Approvals 199 22-Jun-14 16-Feb-15 26-Aug-14 18-Apr-15 52
53150-MSAA-00-100 Method Statement for Block Works Approval 14 22-Jun-14 07-Jul-14 26-Aug-14 10-Sep-14 54
53150-MSAA-00-102 Method Statement for Precast Concrete Façade Elements Works Approval 14 08-Jul-14 23-Jul-14 02-Oct-14 21-Oct-14 72
53150-MSAA-00-103 Method Statement for Painting Works Approval 14 03-Aug-14 18-Aug-14 16-Oct-14 02-Nov-14 61
53150-MSAA-00-113 Method Statement for External Paint Approval 14 14-Aug-14 30-Aug-14 22-Nov-14 08-Dec-14 81
53150-MSAA-00-109 Method Statement for Ceramic Tiling Works Approval 14 25-Aug-14 09-Sep-14 11-Dec-14 27-Dec-14 88
53150-MSAA-00-101 Method Statement for Plaster Works Approval 14 01-Sep-14 16-Sep-14 16-Oct-14 02-Nov-14 36
53150-MSAA-00-107 Method Statement for Dry Walls/Gypsum Wall Approval 14 11-Sep-14 27-Sep-14 28-Dec-14 12-Jan-15 87
53150-MSAA-00-110 Method Statement for Vinyl Flooring Approval 14 18-Sep-14 04-Oct-14 26-Nov-14 13-Dec-14 55
53150-MSAA-00-114 Method Statement for Installation of Doors & Windows Appr oval 14 02-Oct-14 21-Oct-14 18-Jan-15 02-Feb-15 87
53150-MSAA-00-118 Method Statement for Radiation Protection Installation Approval 14 13-Oct-14 29-Oct-14 19-Nov-14 06-Dec-14 31
53150-MSAA-00-112 Method Statement for Window Shade Installation Approv al 14 15-Oct-14 01-Nov-14 18-Jan-15 02-Feb-15 79
53150-MSAA-00-106 Method Statement for Steel Staircase installation Approval 14 28-Oct-14 12-Nov-14 07-Jan-15 22-Jan-15 60
53150-MSAA-00-108 Method Statement for False Ceiling Installation Approval 14 08-Nov-14 23-Nov-14 28-Dec-14 12-Jan-15 42

Actual Work Critical Remaining Work Summary Page 14 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MSAA-00-115 Method Statement for Internal Signage Works Approval 14 04-Dec-14 20-Dec-14 25-Feb-15 12-Mar-15 71
53150-MSAA-00-116 Method Statement for Paving and Curbs Approv al 14 11-Dec-14 27-Dec-14 24-Mar-15 08-Apr-15 88
53150-MSAA-00-111 Method Statement for Carpet Flooring Approval 14 21-Dec-14 06-Jan-15 05-Mar-15 21-Mar-15 63
53150-MSAA-00-105 Method Statement for Canopy Approval 14 28-Dec-14 13-Jan-15 02-Apr-15 18-Apr-15 81
53150-MSAA-00-104 Method Statement for Curtain Walling Approval 14 25-Jan-15 09-Feb-15 24-Mar-15 08-Apr-15 50
53150-MSAA-00-117 Method Statement for Road Works Approval 14 01-Feb-15 16-Feb-15 24-Mar-15 08-Apr-15 44
MEP 141 08-May-14 27-Oct-14 01-Jul-14 25-Jan-15 76
Submittals 127 08-May-14 09-Oct-14 01-Jul-14 08-Jan-15 76
53150-MSES-00-100 Method Statement for Electrical Installation submittal 6 08-May-14 14-May-14 01-Jul-14 07-Jul-14 45
53150-MSES-00-102 Method Statement for Lift Installation submittal 6 13-Jul-14 19-Jul-14 08-Sep-14 14-Sep-14 47
53150-MSES-00-101 Method Statement for Mechanical Installations submittal 6 20-Jul-14 26-Jul-14 23-Sep-14 29-Sep-14 54
53150-MSES-00-103 Method Statement for Medical Equipment submittal 6 30-Sep-14 09-Oct-14 03-Jan-15 08-Jan-15 76
Approvals 135 15-May-14 27-Oct-14 08-Jul-14 25-Jan-15 76
53150-MSEA-00-100 Method Statement for Electrical Installation Approval 14 15-May-14 01-Jun-14 08-Jul-14 23-Jul-14 45
53150-MSEA-00-102 Method Statement for Lift Installation Approval 14 20-Jul-14 06-Aug-14 15-Sep-14 30-Sep-14 47
53150-MSEA-00-101 Method Statement for Mechanical Installations Approval 14 27-Jul-14 13-Aug-14 30-Sep-14 19-Oct-14 54
53150-MSEA-00-103 Method Statement for Medical Equipment Approval 14 11-Oct-14 27-Oct-14 10-Jan-15 25-Jan-15 76
PROCUREMENT PHASE 340 22-Feb-14 03-Apr-15 29-Apr-14 06-May-15 29
Place Order 245 22-Feb-14 13-Dec-14 29-Apr-14 05-Feb-15 47
Civil 208 19-Mar-14 24-Nov-14 29-Apr-14 29-Nov-14 4
53150-MAOR-00-100 Concrete Order 6 19-Mar-14 25-Mar-14 10-May-14 15-May-14 44
53150-MAOR-00-101 Steel Reinforcement Order 15 19-Mar-14 05-Apr-14 29-Apr-14 15-May-14 35
53150-MAOR-00-169 Cement Order 10 03-Apr-14 14-Apr-14 29-Jun-14 09-Jul-14 73
53150-MAOR-00-102 Water proofing Order 2 28-Apr-14 29-Apr-14 29-May-14 31-May-14 26
53150-MAOR-00-103 Shuttering system Order 6 28-Apr-14 04-May-14 26-May-14 02-Jun-14 24
53150-MAOR-00-186 Precast Concrete Cladding Order 6 02-Jun-14 08-Jun-14 07-Jul-14 13-Jul-14 30
53150-MAOR-00-197 Asphalt Paving Order 60 11-Sep-14 24-Nov-14 16-Sep-14 29-Nov-14 4
Architecture 176 09-Apr-14 08-Nov-14 14-May-14 14-Jan-15 57
53150-MAOR-00-109 Corner Guards Order 6 09-Apr-14 15-Apr-14 28-May-14 03-Jun-14 41
53150-MAOR-00-180 Furniture Order 60 26-Apr-14 05-Jul-14 14-May-14 23-Jul-14 16
53150-MAOR-00-105 Sanitary ware Order 30 03-May-14 07-Jun-14 22-Jun-14 26-Jul-14 42
53150-MAOR-00-115 Porcelain (Floor) Order 6 10-May-14 15-May-14 16-Jul-14 22-Jul-14 57
53150-MAOR-00-104 Linoleum Sheet Order 10 13-May-14 24-May-14 19-Jul-14 31-Jul-14 56
53150-MAOR-00-190 Painting Order 6 28-May-14 03-Jun-14 19-Aug-14 25-Aug-14 69
53150-MAOR-00-136 Wooden Doors Order 6 29-May-14 04-Jun-14 13-Aug-14 19-Aug-14 63
53150-MAOR-00-121 Wall Ceramic tiles Order 6 02-Jun-14 08-Jun-14 12-Jul-14 17-Jul-14 34
53150-MAOR-00-139 Cafe Cabinet Order 6 02-Jun-14 08-Jun-14 20-Aug-14 26-Aug-14 66
53150-MAOR-00-114 Terrazzo Tiles/skirting Order 6 03-Jun-14 09-Jun-14 22-Jul-14 28-Jul-14 42
53150-MAOR-00-168 Hollow Block Order 6 07-Jun-14 12-Jun-14 06-Aug-14 12-Aug-14 50
53150-MAOR-00-142 Wooden Cladding material Order 15 08-Jun-14 24-Jun-14 26-Aug-14 11-Sep-14 66
53150-MAOR-00-160 Staircase enclosure Order 20 08-Jun-14 30-Jun-14 02-Sep-14 24-Sep-14 72
53150-MAOR-00-183 Shoe rack Order 20 08-Jun-14 30-Jun-14 16-Aug-14 07-Sep-14 57
53150-MAOR-00-178 GRC material Order 6 14-Jun-14 19-Jun-14 08-Jul-14 14-Jul-14 21
53150-MAOR-00-137 X-ray Exam room Cabinet/Counter Order 6 15-Jun-14 21-Jun-14 02-Sep-14 08-Sep-14 66
53150-MAOR-00-166 Curtain Wall Order 6 15-Jun-14 21-Jun-14 31-Jul-14 06-Aug-14 38
53150-MAOR-00-179 Plaster Access or ies Or der 6 17-Jun-14 23-Jun-14 27-Aug-14 02-Sep-14 59
53150-MAOR-00-128 Radiation Protection Order 20 19-Jun-14 12-Jul-14 21-Jul-14 14-Aug-14 27
53150-MAOR-00-177 Wall Covering Order 6 22-Jun-14 28-Jun-14 07-Sep-14 13-Sep-14 64
53150-MAOR-00-154 Aluminium Doors/windows Order 6 23-Jun-14 29-Jun-14 27-Aug-14 02-Sep-14 54
53150-MAOR-00-140 Cafe Counter Order 15 25-Jun-14 12-Jul-14 02-Sep-14 18-Sep-14 57
53150-MAOR-00-138 Cafe storage shelves Order 20 25-Jun-14 17-Jul-14 09-Sep-14 01-Oct-14 63
53150-MAOR-00-141 Reception Counter Order 20 25-Jun-14 17-Jul-14 06-Sep-14 28-Sep-14 60

Actual Work Critical Remaining Work Summary Page 15 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAOR-00-151 Entrance Canopy Order 20 25-Jun-14 17-Jul-14 18-Sep-14 14-Oct-14 71
53150-MAOR-00-155 Sliding door (entrance) Order 6 01-Jul-14 07-Jul-14 07-Sep-14 13-Sep-14 56
53150-MAOR-00-170 Roof tiling Order 6 06-Jul-14 12-Jul-14 23-Sep-14 29-Sep-14 66
53150-MAOR-00-152 Steel Staircase Order 6 07-Jul-14 13-Jul-14 25-Sep-14 01-Oct-14 67
53150-MAOR-00-199 Interior Signage Order 20 07-Jul-14 31-Jul-14 11-Sep-14 04-Oct-14 55
53150-MAOR-00-107 Carpets Order 6 10-Jul-14 17-Jul-14 18-Sep-14 24-Sep-14 57
53150-MAOR-00-158 Handrail Order 20 13-Jul-14 06-Aug-14 21-Sep-14 16-Oct-14 58
53150-MAOR-00-159 Balustrade to staircase Order 20 13-Jul-14 06-Aug-14 22-Sep-14 18-Oct-14 59
53150-MAOR-00-164 Main Entrance Gate Order 20 13-Jul-14 06-Aug-14 04-Oct-14 30-Oct-14 69
53150-MAOR-00-129 Mirrors Order 6 22-Jul-14 28-Jul-14 27-Sep-14 02-Oct-14 55
53150-MAOR-00-153 Grab bar Order 20 24-Jul-14 18-Aug-14 21-Oct-14 13-Nov-14 71
53150-MAOR-00-184 Plants Order 20 24-Jul-14 18-Aug-14 21-Sep-14 16-Oct-14 48
53150-MAOR-00-156 Gratings Order 20 02-Aug-14 24-Aug-14 23-Oct-14 16-Nov-14 68
53150-MAOR-00-157 Stair Gate Order 20 02-Aug-14 24-Aug-14 23-Oct-14 16-Nov-14 68
53150-MAOR-00-130 Glass tiles with channel Order 15 04-Aug-14 20-Aug-14 28-Oct-14 13-Nov-14 69
53150-MAOR-00-161 Roof Louvered Screen Order 20 07-Aug-14 30-Aug-14 16-Oct-14 09-Nov-14 57
53150-MAOR-00-127 Gypsum Board/tiles Order 20 10-Aug-14 01-Sep-14 18-Sep-14 14-Oct-14 34
53150-MAOR-00-171 Thermal Insulation Order 6 13-Aug-14 19-Aug-14 14-Oct-14 20-Oct-14 50
53150-MAOR-00-196 Precast Concrete Curbstone Order 6 14-Aug-14 20-Aug-14 05-Nov-14 11-Nov-14 67
53150-MAOR-00-192 Interlock Order 15 19-Aug-14 04-Sep-14 02-Oct-14 22-Oct-14 38
53150-MAOR-00-187 Miscellaneous Order 6 24-Aug-14 30-Aug-14 08-Oct-14 14-Oct-14 36
53150-MAOR-00-200 Exterior Signage Order 20 02-Sep-14 24-Sep-14 22-Oct-14 15-Nov-14 40
53150-MAOR-00-123 Robe hook Order 20 17-Sep-14 13-Oct-14 18-Nov-14 11-Dec-14 49
53150-MAOR-00-185 Refuse chute enclosure Order 15 21-Oct-14 08-Nov-14 29-Dec-14 14-Jan-15 57
MEP 245 22-Feb-14 13-Dec-14 06-May-14 05-Feb-15 47
53150-MAOR-00-112 Lightning Protection System Order 20 22-Feb-14 16-Mar-14 06-May-14 29-May-14 63
53150-MAOR-00-125 Disposal pipes/accessories Order 6 05-Apr-14 10-Apr-14 24-Jun-14 30-Jun-14 68
53150-MAOR-00-172 Gas pipes Order 6 05-Apr-14 10-Apr-14 25-Jun-14 01-Jul-14 69
53150-MAOR-00-132 Water heaters Order 15 05-Apr-14 21-Apr-14 21-Jun-14 07-Jul-14 65
53150-MAOR-00-108 Electrical cable tray Order 20 15-Apr-14 07-May-14 08-Jun-14 30-Jun-14 45
53150-MAOR-00-147 Fire hose cabinets Order 15 28-Apr-14 14-May-14 20-Jul-14 07-Aug-14 70
53150-MAOR-00-131 Manholes Order 15 29-Apr-14 15-May-14 02-Jul-14 19-Jul-14 54
53150-MAOR-00-120 Generator Order 15 03-May-14 19-May-14 16-Jun-14 02-Jul-14 37
53150-MAOR-00-106 Earthing system Order 20 03-May-14 25-May-14 17-Jun-14 09-Jul-14 38
53150-MAOR-00-111 Lighting Management system Order 20 03-May-14 25-May-14 02-Jun-14 24-Jun-14 25
53150-MAOR-00-113 Emergency lights Order 20 03-May-14 25-May-14 07-Jun-14 29-Jun-14 29
53150-MAOR-00-116 Exterior lighting Order 20 03-May-14 25-May-14 10-Jul-14 04-Aug-14 58
53150-MAOR-00-193 Medical Gas system Order 25 03-May-14 01-Jun-14 08-Jun-14 06-Jul-14 30
53150-MAOR-00-117 Audio system Order 20 14-May-14 07-Jun-14 28-Jul-14 21-Aug-14 63
53150-MAOR-00-175 Foam water system Order 15 15-May-14 02-Jun-14 10-Aug-14 26-Aug-14 71
53150-MAOR-00-194 Medical Equipments Order 21 20-May-14 14-Jun-14 05-Jun-14 29-Jun-14 13
53150-MAOR-00-146 Fire fighting pipes/accessories Order 6 22-May-14 29-May-14 07-Aug-14 13-Aug-14 63
53150-MAOR-00-182 Lifts materials Order 6 26-May-14 02-Jun-14 17-Jul-14 23-Jul-14 44
53150-MAOR-00-173 Hydronic pumps Order 20 29-May-14 21-Jun-14 31-Jul-14 23-Aug-14 52
53150-MAOR-00-145 Fire resistive joint system Order 6 01-Jun-14 07-Jun-14 07-Aug-14 13-Aug-14 56
53150-MAOR-00-150 Smoke dedectors Order 6 01-Jun-14 07-Jun-14 25-Aug-14 31-Aug-14 71
53150-MAOR-00-133 HVAC Ducts Order 6 02-Jun-14 08-Jun-14 28-Jul-14 05-Aug-14 48
53150-MAOR-00-134 Chilled water pipes Order 6 02-Jun-14 08-Jun-14 23-Jul-14 31-Jul-14 44
53150-MAOR-00-135 HVAC fans Order 6 02-Jun-14 08-Jun-14 16-Aug-14 21-Aug-14 62
53150-MAOR-00-144 Power Ventilator s Order 6 02-Jun-14 08-Jun-14 05-Aug-14 11-Aug-14 53
53150-MAOR-00-148 Air handling unit (AHU) Order 6 02-Jun-14 08-Jun-14 16-Jul-14 22-Jul-14 38
53150-MAOR-00-149 Fan coil units (FCU) Order 6 02-Jun-14 08-Jun-14 05-Aug-14 11-Aug-14 53

Actual Work Critical Remaining Work Summary Page 16 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MAOR-00-162 Nurse call system Order 6 08-Jun-14 14-Jun-14 02-Aug-14 07-Aug-14 45
53150-MAOR-00-163 Speakers Order 6 08-Jun-14 14-Jun-14 02-Aug-14 07-Aug-14 45
53150-MAOR-00-165 BMS system Order 6 08-Jun-14 14-Jun-14 07-Aug-14 13-Aug-14 50
53150-MAOR-00-122 Lighting fixtures Order 15 08-Jun-14 24-Jun-14 13-Aug-14 30-Aug-14 55
53150-MAOR-00-118 Transformers Order 15 12-Jun-14 29-Jun-14 23-Jul-14 11-Aug-14 35
53150-MAOR-00-119 switchgears Order 15 12-Jun-14 29-Jun-14 23-Jul-14 11-Aug-14 35
53150-MAOR-00-126 Storm drainage piping Order 6 16-Jun-14 22-Jun-14 15-Jul-14 21-Jul-14 25
53150-MAOR-00-124 Water feeding pipes/accessories Order 6 18-Jun-14 24-Jun-14 22-Jul-14 28-Jul-14 29
53150-MAOR-00-110 Sanitary fixtures Order 15 19-Jun-14 06-Jul-14 13-Sep-14 29-Sep-14 71
53150-MAOR-00-176 Fire fighting pumps Order 12 21-Jun-14 03-Jul-14 05-Aug-14 18-Aug-14 37
53150-MAOR-00-143 Fire alarm system Order 15 21-Jun-14 07-Jul-14 19-Jul-14 06-Aug-14 24
53150-MAOR-00-167 IT/Telephone system Order 6 01-Jul-14 07-Jul-14 02-Aug-14 07-Aug-14 25
53150-MAOR-00-181 Chillers Order 15 05-Jul-14 21-Jul-14 19-Aug-14 04-Sep-14 37
53150-MAOR-00-195 Irrigation system Order 15 09-Jul-14 26-Jul-14 22-Sep-14 12-Oct-14 62
53150-MAOR-00-174 Security system Order 20 13-Jul-14 06-Aug-14 14-Sep-14 09-Oct-14 52
53150-MAOR-00-198 Visual Display Units Order 30 09-Aug-14 11-Sep-14 14-Oct-14 18-Nov-14 54
53150-MAOR-00-188 Master clock system Order 15 24-Aug-14 09-Sep-14 15-Nov-14 01-Dec-14 67
53150-MAOR-00-189 Queuing System Order 15 24-Aug-14 09-Sep-14 11-Nov-14 27-Nov-14 64
53150-MAOR-00-191 Residential Appliances Order 15 25-Nov-14 13-Dec-14 20-Jan-15 05-Feb-15 47
Fabrication / Manufacture 313 26-Mar-14 01-Feb-15 16-May-14 27-Mar-15 54
Civil 75 26-Mar-14 08-Jun-14 16-May-14 02-Sep-14 86
53150-MAFA-00- 100 Concrete Fabrication / Manufacture 7 26-Mar-14 01-Apr-14 16-May-14 22-May-14 51
53150-MAFA-00- 101 Steel Reinforcement Fabrication / Manufacture 20 06-Apr-14 25-Apr-14 17-May-14 05-Jun-14 41
53150-MAFA-00- 158 Cement Fabrication / Manufacture 55 15-Apr-14 08-Jun-14 10-Jul-14 02-Sep-14 86
53150-MAFA-00- 102 Water proofing Fabrication / Manufacture 5 30-Apr-14 04-May-14 01-Jun-14 05-Jun-14 32
53150-MAFA-00- 103 Shuttering system Fabrication / Manufacture 15 05-May-14 19-May-14 03-Jun-14 17-Jun-14 29
Architecture 252 16-Apr-14 23-Dec-14 04-Jun-14 13-Feb-15 52
53150-MAFA-00- 108 Corner Guards Fabrication / Manufacture 21 16-Apr-14 06-May-14 04-Jun-14 24-Jun-14 49
53150-MAFA-00- 174 Painting Fabrication / Manufacture 45 04-Jun-14 18-Jul-14 26-Aug-14 09-Oct-14 83
53150-MAFA-00- 170 Precast Concrete Cladding Fabrication / Manufacture 40 09-Jun-14 18-Jul-14 14-Jul-14 22-Aug-14 35
53150-MAFA-00- 157 Hollow Block Fabrication / Manufacture 21 13-Jun-14 03-Jul-14 13-Aug-14 02-Sep-14 61
53150-MAFA-00- 165 GRC material Fabrication / Manufacture 40 20-Jun-14 29-Jul-14 15-Jul-14 23-Aug-14 25
53150-MAFA-00- 166 Plaster Access or ies Fabr ic ation / Manufacture 10 24-Jun-14 03-Jul-14 03-Sep-14 12-Sep-14 71
53150-MAFA-00- 128 Wooden Doors Fabrication / Manufacture 60 30-Jun-14 28-Aug-14 14-Sep-14 12-Nov-14 76
53150-MAFA-00- 129 X-ray Exam room Cabinet/Counter Fabrication / Manufacture 55 16-Jul-14 08-Sep-14 03-Oct-14 26-Nov-14 79
53150-MAFA-00- 133 Reception Counter Fabrication / Manufacture 50 14-Aug-14 02-Oct-14 28-Oct-14 16-Dec-14 75
53150-MAFA-00- 171 Miscellaneous Fabrication / Manufacture 50 31-Aug-14 19-Oct-14 15-Oct-14 03-Dec-14 45
53150-MAFA-00- 121 Gypsum Board/tiles Fabrication / Manufacture 60 02-Sep-14 31-Oct-14 15-Oct-14 13-Dec-14 43
53150-MAFA-00- 144 Grab bar Fabrication / Manufacture 55 23-Sep-14 16-Nov-14 21-Dec-14 13-Feb-15 89
53150-MAFA-00- 117 Robe hook Fabrication / Manufacture 50 14-Oct-14 02-Dec-14 12-Dec-14 30-Jan-15 59
53150-MAFA-00- 182 Exterior Signage Fabrication / Manufacture 50 04-Nov-14 23-Dec-14 22-Dec-14 09-Feb-15 48
MEP 263 15-May-14 01-Feb-15 07-Jul-14 27-Mar-15 54
53150-MAFA-00- 138 Fire hose cabinets Fabrication / Manufacture 60 15-May-14 13-Jul-14 09-Aug-14 07-Oct-14 86
53150-MAFA-00- 177 Medical Gas system Fabrication / Manufacture 55 02-Jun-14 26-Jul-14 07-Jul-14 30-Aug-14 35
53150-MAFA-00- 154 Speakers Fabrication / Manufacture 40 15-Jun-14 24-Jul-14 09-Aug-14 17-Sep-14 55
53150-MAFA-00- 153 Nurse call system Fabrication / Manufacture 50 15-Jun-14 03-Aug-14 09-Aug-14 27-Sep-14 55
53150-MAFA-00- 137 Fire fighting pipes/accessories Fabrication / Manufacture 50 24-Jun-14 12-Aug-14 08-Sep-14 27-Oct-14 76
53150-MAFA-00- 118 Water feeding pipes/accessories Fabrication / Manufacture 21 25-Jun-14 15-Jul-14 31-Jul-14 20-Aug-14 36
53150-MAFA-00- 136 Fire resistive joint system Fabrication / Manufacture 50 02-Jul-14 20-Aug-14 08-Sep-14 27-Oct-14 68
53150-MALL-00-110 IT/Telephone system Fabrication / Manufacture 50 08-Jul-14 26-Aug-14 09-Aug-14 27-Sep-14 32
53150-MAFA-00- 175 Residential Appliances F abrication / Manufac ture 50 14-Dec-14 01-Feb-15 06-Feb-15 27-Mar-15 54
Long Lead Items 317 17-Mar-14 27-Jan-15 31-May-14 05-Apr-15 68

Actual Work Critical Remaining Work Summary Page 17 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
Architecture 257 16-May-14 27-Jan-15 19-Jul-14 04-Apr-15 67
53150-MAFA-00- 113 Porcelain (Floor) Fabrication / Manufacture 90 16-May-14 13-Aug-14 23-Jul-14 20-Oct-14 68
53150-MALL-00-141 Smoke dedectors Fabrication / Manufacture 80 08-Jun-14 26-Aug-14 01-Sep-14 19-Nov-14 85
53150-MAFA-00- 116 Wall Ceramic tiles Fabrication / Manufacture 70 09-Jun-14 17-Aug-14 19-Jul-14 26-Sep-14 40
53150-MAFA-00- 112 Terrazzo Tiles/skirting Fabrication / Manufacture 90 10-Jun-14 07-Sep-14 31-Jul-14 28-Oct-14 51
53150-MALL-00-180 Linoleum Sheet Fabrication / Manufacture 120 19-Jun-14 16-Oct-14 26-Aug-14 23-Dec-14 68
53150-MALL-00-109 Curtain Wall Fabrication / Manufacture 90 22-Jun-14 19-Sep-14 07-Aug-14 04-Nov-14 46
53150-MALL-00-164 Wall Covering Fabrication / Manufacture 75 29-Jun-14 11-Sep-14 14-Sep-14 27-Nov-14 77
53150-MAFA-00- 131 Cafe Cabinet Fabrication / Manufacture 80 03-Jul-14 20-Sep-14 21-Sep-14 09-Dec-14 80
53150-MALL-00-113 Furniture Fabrication / Manufacture 200 06-Jul-14 21-Jan-15 24-Jul-14 08-Feb-15 18
53150-MALL-00-101 Sanitary fixtures Fabrication / Manufacture 120 07-Jul-14 03-Nov-14 30-Sep-14 27-Jan-15 85
53150-MAFA-00- 106 Carpets Fabrication / Manufacture 90 17-Jul-14 15-Oct-14 25-Sep-14 23-Dec-14 69
53150-MALL-00-134 Wooden Cladding material Fabrication / Manufacture 100 20-Jul-14 27-Oct-14 11-Oct-14 18-Jan-15 83
53150-MALL-00-145 Aluminium Doors/windows Fabrication / Manufacture 90 24-Jul-14 21-Oct-14 28-Sep-14 26-Dec-14 66
53150-MALL-00-122 Mirrors Fabrication / Manufacture 90 29-Jul-14 26-Oct-14 03-Oct-14 31-Dec-14 66
53150-MAFA-00- 181 Interior Signage Fabrication / Manufacture 100 01-Aug-14 08-Nov-14 05-Oct-14 12-Jan-15 65
53150-MAFA-00- 132 Cafe Counter Fabrication / Manufacture 100 08-Aug-14 15-Nov-14 18-Oct-14 25-Jan-15 71
53150-MAFA-00- 143 Steel Staircase Fabrication / Manufacture 80 10-Aug-14 28-Oct-14 31-Oct-14 18-Jan-15 82
53150-MALL-00-146 Sliding door (entrance) Fabrication / Manufacture 100 14-Aug-14 21-Nov-14 22-Oct-14 29-Jan-15 69
53150-MAFA-00- 130 Cafe storage shelves Fabrication / Manufacture 120 14-Aug-14 11-Dec-14 01-Nov-14 28-Feb-15 79
53150-MALL-00-142 Entrance Canopy Fabrication / Manufacture 140 14-Aug-14 31-Dec-14 10-Nov-14 29-Mar-15 88
53150-MALL-00-159 Roof tiling Fabrication / Manufacture 80 19-Aug-14 06-Nov-14 09-Nov-14 27-Jan-15 82
53150-MALL-00-160 Thermal Insulation Fabrication / Manufacture 80 20-Aug-14 07-Nov-14 21-Oct-14 08-Jan-15 62
53150-MALL-00-123 Glass tiles with channel Fabrication / Manufacture 80 21-Aug-14 08-Nov-14 15-Nov-14 02-Feb-15 86
53150-MALL-00-179 Precast Concrete Curbstone Fabrication / Manufacture 90 21-Aug-14 18-Nov-14 12-Nov-14 09-Feb-15 83
53150-MALL-00-151 Staircase enclosure Fabrication / Manufacture 80 25-Aug-14 12-Nov-14 21-Nov-14 08-Feb-15 88
53150-MALL-00-150 Balustrade to staircase Fabrication / Manufacture 60 04-Sep-14 02-Nov-14 17-Nov-14 15-Jan-15 74
53150-MALL-00-149 Handrail Fabrication / Manufacture 90 04-Sep-14 02-Dec-14 16-Nov-14 13-Feb-15 73
53150-MALL-00-176 Interlock Fabrication / Manufacture 120 05-Sep-14 02-Jan-15 23-Oct-14 19-Feb-15 48
53150-MAFA-00- 167 Shoe rack Fabrication / Manufacture 120 11-Sep-14 08-Jan-15 21-Nov-14 20-Mar-15 71
53150-MAFA-00- 168 Plants Fabrication / Manufacture 120 12-Sep-14 09-Jan-15 12-Nov-14 11-Mar-15 61
53150-MALL-00-147 Gratings Fabrication / Manufacture 60 18-Sep-14 16-Nov-14 13-Dec-14 10-Feb-15 86
53150-MALL-00-148 Stair Gate Fabrication / Manufacture 70 18-Sep-14 26-Nov-14 13-Dec-14 20-Feb-15 86
53150-MALL-00-155 Main Entrance Gate Fabrication / Manufacture 60 23-Sep-14 21-Nov-14 18-Dec-14 15-Feb-15 86
53150-MALL-00-152 Roof Louvered Screen Fabrication / Manufacture 60 27-Oct-14 25-Dec-14 02-Jan-15 02-Mar-15 67
53150-MAFA-00- 169 Refuse chute enclosure Fabrication / Manufacture 80 09-Nov-14 27-Jan-15 15-Jan-15 04-Apr-15 67
MEP 316 17-Mar-14 26-Jan-15 31-May-14 05-Apr-15 69
53150-MAFA-00- 110 Lightning Protection System Fabrication / Manufacture 100 17-Mar-14 24-Jun-14 31-May-14 07-Sep-14 75
53150-MALL-00-119 Disposal pipes/accessories Fabrication / Manufacture 120 11-Apr-14 08-Aug-14 01-Jul-14 28-Oct-14 81
53150-MALL-00-161 Gas pipes Fabrication / Manufacture 150 11-Apr-14 07-Sep-14 02-Jul-14 28-Nov-14 82
53150-MALL-00-107 Water heaters Fabrication / Manufacture 150 22-Apr-14 18-Sep-14 08-Jul-14 04-Dec-14 77
53150-MAFA-00- 107 Electrical cable tray Fabrication / Manufacture 100 08-May-14 15-Aug-14 01-Jul-14 08-Oct-14 54
53150-MALL-00-104 Generator Fabrication / Manufacture 120 20-May-14 16-Sep-14 03-Jul-14 30-Oct-14 44
53150-MAFA-00- 111 Emergency lights Fabrication / Manufacture 70 26-May-14 03-Aug-14 30-Jun-14 07-Sep-14 35
53150-MAFA-00- 109 Lighting Management system Fabrication / Manufacture 75 26-May-14 08-Aug-14 25-Jun-14 07-Sep-14 30
53150-MAFA-00- 105 Earthing system Fabrication / Manufacture 80 26-May-14 13-Aug-14 10-Jul-14 27-Sep-14 45
53150-MAFA-00- 1151 Audio system Fabrication / Manufacture 60 08-Jun-14 06-Aug-14 22-Aug-14 20-Oct-14 75
53150-MALL-00-100 Sanitary ware Fabrication / Manufacture 120 08-Jun-14 05-Oct-14 27-Jul-14 23-Nov-14 49
53150-MALL-00-125 HVAC Ducts Fabrication / Manufacture 60 09-Jun-14 07-Aug-14 06-Aug-14 04-Oct-14 58
53150-MALL-00-127 HVAC fans Fabrication / Manufacture 60 09-Jun-14 07-Aug-14 22-Aug-14 20-Oct-14 74
53150-MALL-00-140 Fan coil units (FCU) Fabrication / Manufacture 60 09-Jun-14 07-Aug-14 12-Aug-14 10-Oct-14 64
53150-MALL-00-126 Chilled water pipes Fabrication / Manufacture 80 09-Jun-14 27-Aug-14 02-Aug-14 20-Oct-14 54

Actual Work Critical Remaining Work Summary Page 18 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MALL-00-135 Power Ventilator s Fabric ation / Manufacture 90 09-Jun-14 06-Sep-14 12-Aug-14 09-Nov-14 64
53150-MALL-00-139 Air handling unit (AHU) Fabrication / Manufacture 90 09-Jun-14 06-Sep-14 23-Jul-14 20-Oct-14 44
53150-MAFA-00- 114 Exterior lighting Fabrication / Manufacture 140 12-Jun-14 29-Oct-14 21-Aug-14 07-Jan-15 70
53150-MALL-00-156 BMS system Fabrication / Manufacture 180 15-Jun-14 11-Dec-14 14-Aug-14 09-Feb-15 60
53150-MALL-00-116 Medical Equipments Fabrication / Manufacture 190 15-Jun-14 21-Dec-14 30-Jun-14 05-Jan-15 15
53150-MALL-00-124 Manholes Fabrication / Manufacture 150 22-Jun-14 18-Nov-14 26-Aug-14 22-Jan-15 65
53150-MALL-00-162 Hydronic pumps Fabrication / Manufacture 210 22-Jun-14 17-Jan-15 24-Aug-14 21-Mar-15 63
53150-MALL-00-120 Storm drainage piping Fabrication / Manufacture 60 23-Jun-14 21-Aug-14 22-Jul-14 19-Sep-14 29
53150-MALL-00-105 Lighting fixtures Fabrication / Manufacture 150 25-Jun-14 21-Nov-14 31-Aug-14 27-Jan-15 67
53150-MALL-00-102 Transformers Fabrication / Manufacture 120 30-Jun-14 27-Oct-14 12-Aug-14 09-Dec-14 43
53150-MALL-00-103 switchgears Fabrication / Manufacture 120 30-Jun-14 27-Oct-14 12-Aug-14 09-Dec-14 43
53150-MALL-00-112 Fire fighting pumps Fabrication / Manufacture 80 04-Jul-14 21-Sep-14 19-Aug-14 06-Nov-14 46
53150-MALL-00-163 Foam water system Fabrication / Manufacture 70 08-Jul-14 15-Sep-14 01-Oct-14 09-Dec-14 85
53150-MALL-00-115 Lifts materials Fabrication / Manufacture 100 08-Jul-14 15-Oct-14 31-Aug-14 08-Dec-14 54
53150-MALL-00-108 Fire alarm system Fabrication / Manufacture 120 08-Jul-14 04-Nov-14 07-Aug-14 04-Dec-14 30
53150-MALL-00-106 Radiation Protection Fabrication / Manufacture 100 13-Jul-14 20-Oct-14 15-Aug-14 22-Nov-14 33
53150-MALL-00-114 Chillers Fabrication / Manufacture 150 22-Jul-14 18-Dec-14 05-Sep-14 01-Feb-15 45
53150-MALL-00-178 Irrigation system Fabrication / Manufacture 120 27-Jul-14 23-Nov-14 13-Oct-14 09-Feb-15 78
53150-MALL-00-111 Security system Fabrication / Manufacture 150 07-Aug-14 03-Jan-15 11-Oct-14 09-Mar-15 65
53150-MALL-00-172 Master clock system Fabrication / Manufacture 120 10-Sep-14 07-Jan-15 02-Dec-14 31-Mar-15 83
53150-MALL-00-173 Queuing System Fabrication / Manufacture 120 10-Sep-14 07-Jan-15 29-Nov-14 28-Mar-15 80
53150-MALL-00-117 Visual Display Units Fabrication / Manufacture 120 29-Sep-14 26-Jan-15 07-Dec-14 05-Apr-15 69
DSC Civil/Architecture/MEP 367 02-Apr-14 03-Apr-15 23-May-14 06-May-15 33
Delivery to site 367 02-Apr-14 03-Apr-15 23-May-14 06-May-15 33
Civil 367 02-Apr-14 03-Apr-15 23-May-14 08-Apr-15 5
53150-MADL-00-100 Concrete Delivery Start 1 02-Apr-14 02-Apr-14 23-May-14 23-May-14 51
53150-MADL-00-101 Steel Reinforcement Delivery 20 26-Apr-14 15-May-14 06-Jun-14 25-Jun-14 41
53150-MADL-00-102 Water proofing Delivery 2 05-May-14 06-May-14 06-Jun-14 07-Jun-14 32
53150-MADL-00-105 Shuttering system Delivery 8 20-May-14 27-May-14 18-Jun-14 25-Jun-14 29
53150-MADL-00-158 Cement Delivery 20 09-Jun-14 28-Jun-14 03-Sep-14 22-Sep-14 86
53150-MADL-00-184 Precast Concrete Cladding Delivery 60 19-Jul-14 16-Sep-14 23-Aug-14 21-Oct-14 35
53150-MAFA-00- 180 Asphalt Paving Fabrication / Manufacture 120 25-Nov-14 24-Mar-15 30-Nov-14 29-Mar-15 5
53150-MADL-00-185 Asphalt Paving Delivery 10 25-Mar-15 03-Apr-15 30-Mar-15 08-Apr-15 5
Architecture 310 07-May-14 12-Mar-15 25-Jun-14 20-Apr-15 39
53150-MADL-00-108 Corner Guards Delivery 15 07-May-14 21-May-14 25-Jun-14 09-Jul-14 49
53150-MADL-00-166 Plaster Access or ies D elivery 10 04-Jul-14 13-Jul-14 13-Sep-14 22-Sep-14 71
53150-MADL-00-136 Hollow Block Delivery 20 04-Jul-14 23-Jul-14 03-Sep-14 22-Sep-14 61
53150-MADL-00-178 Painting Delivery 60 19-Jul-14 16-Sep-14 10-Oct-14 08-Dec-14 83
53150-MADL-00-165 GRC material Delivery 15 30-Jul-14 13-Aug-14 24-Aug-14 07-Sep-14 25
53150-MADL-00-113 Porcelain (Floor) Delivery 60 14-Aug-14 12-Oct-14 29-Oct-14 27-Dec-14 76
53150-MADL-00-116 Wall Ceramic tiles Delivery 60 18-Aug-14 16-Oct-14 29-Oct-14 27-Dec-14 72
53150-MADL-00-128 Wooden Doors Delivery 80 29-Aug-14 16-Nov-14 13-Nov-14 31-Jan-15 76
53150-MADL-00-112 Terrazzo Tiles/skirting Delivery 60 08-Sep-14 06-Nov-14 29-Oct-14 27-Dec-14 51
53150-MADL-00-129 X-ray Exam room Cabinet/Counter Delivery 100 09-Sep-14 17-Dec-14 27-Nov-14 06-Mar-15 79
53150-MADL-00-167 Wall Covering Delivery 30 12-Sep-14 11-Oct-14 28-Nov-14 27-Dec-14 77
53150-MADL-00-193 Curtain Wall Delivery 15 20-Sep-14 04-Oct-14 05-Nov-14 19-Nov-14 46
53150-MADL-00-131 Cafe Cabinet Delivery 90 21-Sep-14 19-Dec-14 10-Dec-14 09-Mar-15 80
53150-MADL-00-133 Reception Counter Delivery 80 03-Oct-14 21-Dec-14 17-Dec-14 06-Mar-15 75
53150-MADL-00-106 Carpets Delivery 60 15-Oct-14 14-Dec-14 24-Dec-14 21-Feb-15 69
53150-MADL-00-103 Linoleum Sheet Delivery 60 17-Oct-14 15-Dec-14 24-Dec-14 21-Feb-15 68
53150-MADL-00-172 Miscellaneous Delivery 20 20-Oct-14 08-Nov-14 04-Dec-14 23-Dec-14 45
53150-MADL-00-146 Aluminium Doors/windows Delivery 40 22-Oct-14 30-Nov-14 27-Dec-14 04-Feb-15 66

Actual Work Critical Remaining Work Summary Page 19 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MADL-00-122 Mirrors Delivery 90 27-Oct-14 24-Jan-15 01-Jan-15 31-Mar-15 66
53150-MADL-00-134 Wooden Cladding material Delivery 80 28-Oct-14 15-Jan-15 19-Jan-15 08-Apr-15 83
53150-MADL-00-144 Steel Staircase Delivery 40 29-Oct-14 07-Dec-14 19-Jan-15 27-Feb-15 82
53150-MADL-00-121 Gypsum Board/tiles Delivery 30 01-Nov-14 30-Nov-14 14-Dec-14 12-Jan-15 43
53150-MADL-00-151 Balustrade to staircase Delivery 90 03-Nov-14 31-Jan-15 16-Jan-15 15-Apr-15 74
53150-MADL-00-168 Sanitary fixtures Delivery 25 04-Nov-14 28-Nov-14 28-Jan-15 21-Feb-15 85
53150-MADL-00-159 Roof tiling Delivery 60 07-Nov-14 05-Jan-15 28-Jan-15 28-Mar-15 82
53150-MADL-00-160 Thermal Insulation Delivery 60 08-Nov-14 06-Jan-15 09-Jan-15 09-Mar-15 62
53150-MADL-00-123 Glass tiles with channel Delivery 60 09-Nov-14 07-Jan-15 03-Feb-15 03-Apr-15 86
53150-MADL-00-186 Interior Signage Delivery 60 09-Nov-14 07-Jan-15 13-Jan-15 13-Mar-15 65
53150-MADL-00-152 Staircase enclosure Delivery 40 13-Nov-14 22-Dec-14 09-Feb-15 20-Mar-15 88
53150-MADL-00-132 Cafe Counter Delivery 40 16-Nov-14 25-Dec-14 26-Jan-15 06-Mar-15 71
53150-MADL-00-145 Grab bar Delivery 40 17-Nov-14 26-Dec-14 14-Feb-15 25-Mar-15 89
53150-MADL-00-148 Gratings Delivery 50 17-Nov-14 05-Jan-15 11-Feb-15 01-Apr-15 86
53150-MADL-00-189 Precast Concrete Curbstone Deliver 60 19-Nov-14 17-Jan-15 10-Feb-15 10-Apr-15 83
53150-MADL-00-147 Sliding door (entrance) Delivery 15 22-Nov-14 06-Dec-14 30-Jan-15 13-Feb-15 69
53150-MADL-00-156 Main Entrance Gate Delivery 45 22-Nov-14 05-Jan-15 16-Feb-15 01-Apr-15 86
53150-MADL-00-149 Stair Gate Delivery 40 27-Nov-14 05-Jan-15 21-Feb-15 01-Apr-15 86
53150-MADL-00-150 Handrail Delivery 40 03-Dec-14 11-Jan-15 14-Feb-15 25-Mar-15 73
53150-MADL-00-117 Robe hook Delivery 60 03-Dec-14 31-Jan-15 31-Jan-15 31-Mar-15 59
53150-MADL-00-130 Cafe storage shelves Delivery 30 12-Dec-14 10-Jan-15 01-Mar-15 30-Mar-15 79
53150-MADL-00-187 Exterior Signage 60 24-Dec-14 21-Feb-15 10-Feb-15 10-Apr-15 48
53150-MADL-00-153 Roof Louvered Screen Delivery 30 26-Dec-14 24-Jan-15 03-Mar-15 01-Apr-15 67
53150-MADL-00-143 Entrance Canopy Delivery 20 01-Jan-15 20-Jan-15 30-Mar-15 18-Apr-15 88
53150-MADL-00-180 Interlock Delivery 60 03-Jan-15 03-Mar-15 20-Feb-15 20-Apr-15 48
53150-MADL-00-169 Shoe rack Delivery 21 09-Jan-15 29-Jan-15 21-Mar-15 10-Apr-15 71
53150-MADL-00-170 Plants Delivery 40 10-Jan-15 18-Feb-15 12-Mar-15 20-Apr-15 61
53150-MADL-00-188 Furniture Delivery 50 22-Jan-15 12-Mar-15 09-Feb-15 30-Mar-15 18
53150-MADL-00-171 Refuse chute enclosure Delivery 14 28-Jan-15 10-Feb-15 05-Apr-15 18-Apr-15 67
MEP 262 25-Jun-14 13-Mar-15 21-Aug-14 06-May-15 54
53150-MADL-00-110 Lightning Protection System Delivery 30 25-Jun-14 24-Jul-14 08-Sep-14 07-Oct-14 75
53150-MADL-00-139 Fire hose cabinets Delivery 60 14-Jul-14 11-Sep-14 08-Oct-14 06-Dec-14 86
53150-MADL-00-118 Water feeding pipes/accessories Delivery 60 16-Jul-14 13-Sep-14 21-Aug-14 19-Oct-14 36
53150-MADL-00-155 Speakers Delivery 20 25-Jul-14 13-Aug-14 18-Sep-14 07-Oct-14 55
53150-MADL-00-154 Nurse call system Delivery 10 04-Aug-14 13-Aug-14 28-Sep-14 07-Oct-14 55
53150-MADL-00-111 Emergency lights Delivery 30 04-Aug-14 02-Sep-14 08-Sep-14 07-Oct-14 35
53150-MADL-00-115 Audio system Delivery 60 07-Aug-14 05-Oct-14 21-Oct-14 19-Dec-14 75
53150-MADL-00-125 HVAC Ducts Delivery 50 08-Aug-14 26-Sep-14 05-Oct-14 23-Nov-14 58
53150-MADL-00-127 HVAC fans Delivery 60 08-Aug-14 06-Oct-14 21-Oct-14 19-Dec-14 74
53150-MADL-00-141 Fan coil units (FCU) Delivery 70 08-Aug-14 16-Oct-14 11-Oct-14 19-Dec-14 64
53150-MADL-00-109 Lighting Management system Delivery 30 09-Aug-14 07-Sep-14 08-Sep-14 07-Oct-14 30
53150-MADL-00-119 Disposal pipes/accessories Delivery 52 09-Aug-14 29-Sep-14 29-Oct-14 19-Dec-14 81
53150-MADL-00-138 Fire fighting pipes/accessories Delivery 40 13-Aug-14 21-Sep-14 28-Oct-14 06-Dec-14 76
53150-MADL-00-104 Earthing system Delivery 10 14-Aug-14 23-Aug-14 28-Sep-14 07-Oct-14 45
53150-MADL-00-181 Medical Gas system Delivery 30 16-Aug-14 14-Sep-14 20-Sep-14 19-Oct-14 35
53150-MADL-00-137 Fire resistive joint system Delivery 40 21-Aug-14 29-Sep-14 28-Oct-14 06-Dec-14 68
53150-MADL-00-120 Storm drainage piping Delivery 30 22-Aug-14 20-Sep-14 20-Sep-14 19-Oct-14 29
53150-MADL-00-194 IT/Telephone system Delivery 10 27-Aug-14 05-Sep-14 28-Sep-14 07-Oct-14 32
53150-MADL-00-142 Smoke detectors Delivery 30 27-Aug-14 25-Sep-14 20-Nov-14 19-Dec-14 85
53150-MADL-00-126 Chilled water pipes Delivery 60 28-Aug-14 26-Oct-14 21-Oct-14 19-Dec-14 54
53150-MADL-00-107 Electrical cable tray Delivery 30 30-Aug-14 28-Sep-14 20-Nov-14 19-Dec-14 82
53150-MADL-00-135 Power Ventilator s Deliv ery 40 07-Sep-14 16-Oct-14 10-Nov-14 19-Dec-14 64

Actual Work Critical Remaining Work Summary Page 20 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MADL-00-140 Air handling unit (AHU) Delivery 60 07-Sep-14 05-Nov-14 21-Oct-14 19-Dec-14 44
53150-MADL-00-161 Gas pipes Delivery 21 08-Sep-14 28-Sep-14 29-Nov-14 19-Dec-14 82
53150-MADL-00-164 Foam water system Delivery 90 16-Sep-14 14-Dec-14 10-Dec-14 09-Mar-15 85
53150-MADL-00-191 Water heaters Delivery 15 19-Sep-14 03-Oct-14 05-Dec-14 19-Dec-14 77
53150-MADL-00-196 Fire fighting pumps Delivery 30 22-Sep-14 21-Oct-14 07-Nov-14 06-Dec-14 46
53150-MADL-00-163 Sanitary ware Delivery 90 06-Oct-14 03-Jan-15 24-Nov-14 21-Feb-15 49
53150-MADL-00-177 Generator Delivery 30 07-Oct-14 05-Nov-14 20-Nov-14 19-Dec-14 44
53150-MADL-00-198 Lifts materials Delivery 15 16-Oct-14 30-Oct-14 09-Dec-14 23-Dec-14 54
53150-MADL-00-190 Radiation Protection Delivery 14 21-Oct-14 03-Nov-14 23-Nov-14 06-Dec-14 33
53150-MADL-00-175 Transformers Delivery 10 28-Oct-14 06-Nov-14 10-Dec-14 19-Dec-14 43
53150-MADL-00-176 switchgears Delivery 10 28-Oct-14 06-Nov-14 10-Dec-14 19-Dec-14 43
53150-MADL-00-114 Exterior lighting Delivery 45 30-Oct-14 13-Dec-14 08-Jan-15 21-Feb-15 70
53150-MADL-00-192 Fire alarm system Delivery 15 05-Nov-14 19-Nov-14 05-Dec-14 19-Dec-14 30
53150-MADL-00-124 Manholes Delivery 30 19-Nov-14 18-Dec-14 23-Jan-15 21-Feb-15 65
53150-MADL-00-183 Lighting fixtures Delivery 25 22-Nov-14 16-Dec-14 28-Jan-15 21-Feb-15 67
53150-MADL-00-182 Irrigation system Delivery 60 24-Nov-14 22-Jan-15 10-Feb-15 10-Apr-15 78
53150-MADL-00-157 BMS system Delivery 60 12-Dec-14 09-Feb-15 10-Feb-15 10-Apr-15 60
53150-MADL-00-197 Chillers Delivery 2 19-Dec-14 20-Dec-14 02-Feb-15 03-Feb-15 45
53150-MADL-00-199 Medical Equipments Delivery 75 22-Dec-14 06-Mar-15 06-Jan-15 21-Mar-15 15
53150-MADL-00-195 Security system Delivery 15 04-Jan-15 18-Jan-15 10-Mar-15 24-Mar-15 65
53150-MADL-00-173 Master clock system Delivery 10 08-Jan-15 17-Jan-15 01-Apr-15 10-Apr-15 83
53150-MADL-00-174 Queuing System Delivery 10 08-Jan-15 17-Jan-15 29-Mar-15 07-Apr-15 80
53150-MADL-00-162 Hydronic pumps Delivery 20 18-Jan-15 06-Feb-15 22-Mar-15 10-Apr-15 63
53150-MADL-00-200 Visual Display Units Delivery 16 27-Jan-15 11-Feb-15 06-Apr-15 21-Apr-15 69
53150-MADL-00-179 Residential Appliances Delivery 40 02-Feb-15 13-Mar-15 28-Mar-15 06-May-15 54
CONSTRUCTION PHASE 446 09-Dec-13 24-May-15 09-Dec-13 08-Jun-15 13
CONCRETE WORKS 271 24-May-14 13-Apr-15 24-May-14 04-May-15 18
Sub-structure 66 24-May-14 11-Aug-14 24-May-14 11-Aug-14 0
Foundation 40 24-May-14 09-Jul-14 24-May-14 09-Jul-14 0
53150-CONC-FD-103 Blinding Concrete Pile Caps 2 24-May-14 25-May-14 24-May-14 25-May-14 0
53150-CONC-FD-123 Block Work for Pile Caps 15 26-May-14 12-Jun-14 26-May-14 12-Jun-14 0
53150-CONC-FD-113 Blinding Conrete Raft 2 15-Jun-14 16-Jun-14 15-Jun-14 16-Jun-14 0
53150-CONC-FD-104 Protection screed 2 24-Jun-14 25-Jun-14 24-Jun-14 25-Jun-14 0
53150-CONC-FD-101 Pile Caps 12 26-Jun-14 09-Jul-14 26-Jun-14 09-Jul-14 0
53150-CONC-FD-105 Raft 12 26-Jun-14 09-Jul-14 26-Jun-14 09-Jul-14 0
Basement Floor (Columns/Walls/Slabs) 26 10-Jul-14 11-Aug-14 10-Jul-14 11-Aug-14 0
53150-CONC-BF-100 Basement Retaining walls 21 10-Jul-14 05-Aug-14 10-Jul-14 05-Aug-14 0
53150-CONC-BF-110 Basement Colums 21 10-Jul-14 05-Aug-14 10-Jul-14 05-Aug-14 0
53150-CONC-BF-101 Slab and beams Basement Floor 16 22-Jul-14 11-Aug-14 22-Jul-14 11-Aug-14 0
Super structure 43 12-Aug-14 30-Sep-14 12-Aug-14 30-Sep-14 0
Ground Floor (Columns/Walls/Slabs) 18 12-Aug-14 01-Sep-14 12-Aug-14 01-Sep-14 0
53150-CONC-GF-100 Wall/Columns Ground Floor 12 12-Aug-14 25-Aug-14 12-Aug-14 25-Aug-14 0
53150-CONC-GF-101 Slab and beams Ground Floor 13 18-Aug-14 01-Sep-14 18-Aug-14 01-Sep-14 0
First Floor (Columns/Walls/Slabs) 16 02-Sep-14 20-Sep-14 02-Sep-14 20-Sep-14 0
53150-CONC-FF-100 Wall/Columns First Floor 10 02-Sep-14 13-Sep-14 02-Sep-14 13-Sep-14 0
53150-CONC-FF-101 Slab and beams First Floor 11 08-Sep-14 20-Sep-14 08-Sep-14 20-Sep-14 0
Roof Floor (Columns/Walls/Slabs) 9 21-Sep-14 30-Sep-14 21-Sep-14 30-Sep-14 0
53150-CONC-RF-100 Upper Roof/Parapets 9 21-Sep-14 30-Sep-14 21-Sep-14 30-Sep-14 0
General Works 162 01-Oct-14 13-Apr-15 01-Oct-14 04-May-15 18
53150-CONC-00-100 Scaffolding Erection for Elevations 15 01-Oct-14 21-Oct-14 01-Oct-14 21-Oct-14 0
53150-CONC-00-101 Precast Concrete Facade works (Rear Elevation) 18 22-Oct-14 12-Nov-14 22-Oct-14 12-Nov-14 0
53150-CONC-00-102 Precast Concrete Facade works (Left Elevation) 18 13-Nov-14 04-Dec-14 13-Nov-14 04-Dec-14 0

Actual Work Critical Remaining Work Summary Page 21 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-CONC-00-103 Precast Concrete Facade works (Front Elevation) 18 06-Dec-14 25-Dec-14 06-Dec-14 25-Dec-14 0
53150-CONC-00-104 Precast Concrete Facade works (Right Elevation) 18 27-Dec-14 15-Jan-15 27-Dec-14 15-Jan-15 0
53150-CONC-00-105 Completion of Envelope works 0 15-Jan-15 05-Feb-15 18
53150-CONC-FD-106 Precast Curbstones and bumbers 21 21-Mar-15 13-Apr-15 11-Apr-15 04-May-15 18
MASONRY 112 09-Sep-14 22-Jan-15 11-Sep-14 29-Jan-15 6
Sub-structure 10 09-Sep-14 20-Sep-14 11-Sep-14 22-Sep-14 2
Basement Floor 10 09-Sep-14 20-Sep-14 11-Sep-14 22-Sep-14 2
53150-BLOK-BF-100 Internal Block work Basement Floor 10 09-Sep-14 20-Sep-14 11-Sep-14 22-Sep-14 2
Super structure 102 21-Sep-14 22-Jan-15 23-Sep-14 29-Jan-15 6
Ground Floor 8 21-Sep-14 29-Sep-14 23-Sep-14 01-Oct-14 2
53150-BLOK-GF-100 External Block work Ground Floor 6 21-Sep-14 27-Sep-14 23-Sep-14 29-Sep-14 2
53150-BLOK-GF-101 Internal Block work Ground Floor 8 21-Sep-14 29-Sep-14 23-Sep-14 01-Oct-14 2
First Floor 16 28-Sep-14 19-Oct-14 21-Oct-14 09-Nov-14 17
53150-BLOK-FF-100 External Block work First Floor 8 28-Sep-14 09-Oct-14 21-Oct-14 30-Oct-14 17
53150-BLOK-FF-101 Internal Block work First Floor 8 11-Oct-14 19-Oct-14 01-Nov-14 09-Nov-14 17
Roof Floor 6 17-Jan-15 22-Jan-15 24-Jan-15 29-Jan-15 6
53150-BLOK-RF-100 External/Internal Block work Roof 6 17-Jan-15 22-Jan-15 24-Jan-15 29-Jan-15 6
METAL WORK 57 23-Feb-15 29-Apr-15 28-Feb-15 10-May-15 9
Structural Steal 57 23-Feb-15 29-Apr-15 28-Feb-15 04-May-15 4
Ground Floor 28 29-Mar-15 29-Apr-15 02-Apr-15 04-May-15 4
53150-METL-GF-101 Stair Gate Ground Floor 14 29-Mar-15 13-Apr-15 02-Apr-15 18-Apr-15 4
53150-METL-GF-100 Entrance Canopy Ground Floor 14 14-Apr-15 29-Apr-15 19-Apr-15 04-May-15 4
First Floor 14 12-Apr-15 27-Apr-15 19-Apr-15 04-May-15 6
53150-METL-FF-100 Refuse chute enclosure First Floor 14 12-Apr-15 27-Apr-15 19-Apr-15 04-May-15 6
Roof Floor 39 23-Feb-15 08-Apr-15 28-Feb-15 13-Apr-15 4
53150-METL-RF-100 Steel Staircase from ground to roof 18 23-Feb-15 15-Mar-15 28-Feb-15 19-Mar-15 4
53150-METL-RF-101 Staircase enclosure from ground to roof 21 16-Mar-15 08-Apr-15 21-Mar-15 13-Apr-15 4
Non-Structural Steel 39 16-Mar-15 29-Apr-15 26-Mar-15 10-May-15 9
First Floor 34 16-Mar-15 23-Apr-15 26-Mar-15 04-May-15 9
53150-METL-FF-201 Handrail First Floor 18 16-Mar-15 05-Apr-15 26-Mar-15 15-Apr-15 9
53150-METL-FF-200 Balustrade to staircase First Floor 16 06-Apr-15 23-Apr-15 16-Apr-15 04-May-15 9
Roof Floor 14 26-Mar-15 11-Apr-15 02-Apr-15 18-Apr-15 6
53150-METL-RF-200 Roof Louvered Screen 14 26-Mar-15 11-Apr-15 02-Apr-15 18-Apr-15 6
General 21 06-Apr-15 29-Apr-15 16-Apr-15 10-May-15 9
53150-METL-RF-210 Metal Gratings and Railings 21 06-Apr-15 29-Apr-15 16-Apr-15 10-May-15 9
WOOD, PLASTICS, AND COMPOSITES 63 28-Feb-15 11-May-15 07-Mar-15 18-May-15 6
Basement Floor 48 03-Mar-15 27-Apr-15 10-Mar-15 07-May-15 9
Dry Areas 18 07-Apr-15 27-Apr-15 18-Apr-15 07-May-15 9
53150-WOOD-BF-100 Desks - Basement Floor 18 07-Apr-15 27-Apr-15 18-Apr-15 07-May-15 9
Wet Areas 18 03-Mar-15 23-Mar-15 10-Mar-15 30-Mar-15 6
53150-WOOD-BF-101 Cabinets - Basement Floor 18 03-Mar-15 23-Mar-15 10-Mar-15 30-Mar-15 6
Ground Floor 51 28-Feb-15 27-Apr-15 07-Mar-15 07-May-15 9
Dry Areas 51 28-Feb-15 27-Apr-15 07-Mar-15 07-May-15 9
53150-WOOD-GF-100 Counters Ground Floor 21 28-Feb-15 23-Mar-15 07-Mar-15 30-Mar-15 6
53150-WOOD-GF-102 Curtains Ground Floor 14 24-Mar-15 08-Apr-15 09-Apr-15 25-Apr-15 14
53150-WOOD-GF-101 Shelves Ground Floor 21 24-Mar-15 16-Apr-15 31-Mar-15 23-Apr-15 6
53150-WOOD-GF-103 Desks Ground Floor 18 07-Apr-15 27-Apr-15 18-Apr-15 07-May-15 9
Wet Areas 21 24-Mar-15 16-Apr-15 31-Mar-15 27-Apr-15 9
53150-WOOD-GF-104 Glass tiles Ground Floor 21 24-Mar-15 16-Apr-15 04-Apr-15 27-Apr-15 9
53150-WOOD-GF-105 cabinets Ground Floor 21 24-Mar-15 16-Apr-15 31-Mar-15 23-Apr-15 6
First Floor 42 24-Mar-15 11-May-15 11-Apr-15 18-May-15 6
Dry Areas 42 24-Mar-15 11-May-15 11-Apr-15 18-May-15 6

Actual Work Critical Remaining Work Summary Page 22 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-WOOD-FF-100 counters First Floor 21 24-Mar-15 16-Apr-15 11-Apr-15 04-May-15 15
53150-WOOD-FF-103 Desks First Floor 15 07-Apr-15 23-Apr-15 18-Apr-15 04-May-15 9
53150-WOOD-FF-102 Curtains First Floor 8 09-Apr-15 18-Apr-15 26-Apr-15 04-May-15 14
53150-WOOD-FF-101 Shelves First Floor 21 18-Apr-15 11-May-15 25-Apr-15 18-May-15 6
Wet Areas 21 18-Apr-15 11-May-15 25-Apr-15 18-May-15 6
53150-WOOD-FF-104 Glass tiles First Floor 18 18-Apr-15 07-May-15 28-Apr-15 18-May-15 9
53150-WOOD-FF-105 cabinets First Floor 21 18-Apr-15 11-May-15 25-Apr-15 18-May-15 6
THERMAL A ND MOISTURE PROTECTION 262 02-Jun-14 11-Apr-15 08-Jun-14 18-Apr-15 6
Structure Water Proofing 112 02-Jun-14 15-Oct-14 08-Jun-14 02-Nov-14 14
Piles Caps/Raft/Foundation 19 02-Jun-14 23-Jun-14 08-Jun-14 23-Jun-14 0
53150-TMPR-FD-100 Water Proofing under the pile caps 14 02-Jun-14 17-Jun-14 08-Jun-14 23-Jun-14 5
53150-TMPR-FD-101 Horizontal / Ver tical Water proofing under foundation 6 17-Jun-14 23-Jun-14 17-Jun-14 23-Jun-14 0
Basement Retaining Walls 48 18-Aug-14 15-Oct-14 03-Sep-14 02-Nov-14 14
53150-TMPR-BF-100 Vertical Water proofing for basement walls Stage 1 21 18-Aug-14 10-Sep-14 03-Sep-14 27-Sep-14 14
53150-TMPR-BF-211 Vertical Water proofing for basement walls Stage 2 21 18-Sep-14 15-Oct-14 08-Oct-14 02-Nov-14 14
Finishes Water Proofing 160 01-Oct-14 11-Apr-15 14-Oct-14 18-Apr-15 6
53150-TMPR-00-100 Bituminous coating on block/concrete Elevations (2 sides) 16 11-Oct-14 29-Oct-14 14-Oct-14 02-Nov-14 3
53150-TMPR-00-101 Bituminous coating on block/concrete Elevations (2 sides) 16 11-Oct-14 29-Oct-14 14-Oct-14 02-Nov-14 3
Basement Floor 42 01-Oct-14 23-Nov-14 20-Oct-14 09-Dec-14 13
Wet Areas 42 01-Oct-14 23-Nov-14 20-Oct-14 09-Dec-14 13
53150-TMPR-BF-201 Water proofing for water tanks - Basement Floor 21 01-Oct-14 29-Oct-14 20-Oct-14 13-Nov-14 13
53150-TMPR-BF-200 Water proofing for wet areas (Basement) 21 30-Oct-14 23-Nov-14 15-Nov-14 09-Dec-14 13
Ground Floor 18 06-Dec-14 25-Dec-14 10-Dec-14 30-Dec-14 4
Wet Areas 18 06-Dec-14 25-Dec-14 10-Dec-14 30-Dec-14 4
53150-TMPR-GF-200 Water proofing for wet areas (Ground Floor) 18 06-Dec-14 25-Dec-14 10-Dec-14 30-Dec-14 4
First Floor 18 27-Dec-14 15-Jan-15 31-Dec-14 20-Jan-15 4
Wet Areas 18 27-Dec-14 15-Jan-15 31-Dec-14 20-Jan-15 4
53150-TMPR-FF-200 Water proofing for wet areas (First Floor) 18 27-Dec-14 15-Jan-15 31-Dec-14 20-Jan-15 4
Roof Floor 55 07-Feb-15 11-Apr-15 14-Feb-15 18-Apr-15 6
53150-TMPR-RF-200 Water Proofing for Roof 18 07-Feb-15 26-Feb-15 14-Feb-15 05-Mar-15 6
53150-TMPR-RF-201 Thermal Insulation for Roof 16 03-Mar-15 21-Mar-15 10-Mar-15 28-Mar-15 6
53150-TMPR-RF-202 Roof tiles/finishes 18 22-Mar-15 11-Apr-15 29-Mar-15 18-Apr-15 6
OPENINGS (DOORS AND WINDOWS) 95 13-Nov-14 04-Mar-15 20-Nov-14 12-Mar-15 7
Basement Floor 14 26-Jan-15 10-Feb-15 05-Feb-15 21-Feb-15 9
Rooms 14 26-Jan-15 10-Feb-15 05-Feb-15 21-Feb-15 9
53150-DORW-BF-101 Aluminum Doors works - Basement Floor 7 26-Jan-15 02-Feb-15 05-Feb-15 12-Feb-15 9
53150-DORW-BF-100 Wooden Doors works - Basement Floor 10 26-Jan-15 05-Feb-15 10-Feb-15 21-Feb-15 13
53150-DORW-BF-102 Full glass sliding doors - Basement Floor 7 03-Feb-15 10-Feb-15 14-Feb-15 21-Feb-15 9
Ground Floor 47 10-Jan-15 04-Mar-15 01-Feb-15 12-Mar-15 7
Wet Areas 21 09-Feb-15 04-Mar-15 17-Feb-15 12-Mar-15 7
53150-DORW-GF-100 Aluminium Doors works Ground Floor 21 09-Feb-15 04-Mar-15 17-Feb-15 12-Mar-15 7
Dry Areas 40 10-Jan-15 24-Feb-15 01-Feb-15 12-Mar-15 14
53150-DORW-GF-101 Aluminum Doors works Ground Floor 12 10-Jan-15 22-Jan-15 03-Feb-15 16-Feb-15 21
53150-DORW-GF-102 Wooden Doors works Ground Floor 12 17-Jan-15 29-Jan-15 01-Feb-15 14-Feb-15 13
53150-DORW-GF-104 Aluminium windows Ground Floor 10 03-Feb-15 14-Feb-15 03-Feb-15 14-Feb-15 0
53150-DORW-GF-103 Main entrance sliding doors Ground Floor 18 04-Feb-15 24-Feb-15 21-Feb-15 12-Mar-15 14
First Floor 40 17-Jan-15 03-Mar-15 01-Feb-15 03-Mar-15 0
Wet Areas 7 21-Jan-15 28-Jan-15 12-Feb-15 19-Feb-15 19
53150-DORW-FF-100 Aluminum Doors works First Floor 7 21-Jan-15 28-Jan-15 12-Feb-15 19-Feb-15 19
Dry Areas 40 17-Jan-15 03-Mar-15 01-Feb-15 03-Mar-15 0
53150-DORW-FF-101 Wooden Doors works First Floor 12 17-Jan-15 29-Jan-15 01-Feb-15 14-Feb-15 13
53150-DORW-FF-102 Aluminum Doors works First Floor 12 21-Jan-15 03-Feb-15 01-Feb-15 14-Feb-15 9

Actual Work Critical Remaining Work Summary Page 23 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-DORW-FF-103 Aluminium windows First Floor 15 15-Feb-15 03-Mar-15 15-Feb-15 03-Mar-15 0
Facade 69 13-Nov-14 02-Feb-15 20-Nov-14 02-Feb-15 0
53150-DORW-00-100 Aluminium Works/Curtain wall installation (Rear Elevation) 18 13-Nov-14 04-Dec-14 20-Nov-14 11-Dec-14 6
53150-DORW-00-101 Aluminium Works/Curtain wall installation (Left Elevation) 15 06-Dec-14 22-Dec-14 13-Dec-14 29-Dec-14 6
53150-DORW-00-102 Aluminium Works/Curtain wall installation (Front Elevation) 15 27-Dec-14 12-Jan-15 30-Dec-14 15-Jan-15 3
53150-DORW-00-103 Aluminium Works/Curtain wall installation (Right Elevation) 15 17-Jan-15 02-Feb-15 17-Jan-15 02-Feb-15 0
FINISHES 175 30-Sep-14 27-Apr-15 22-Oct-14 10-May-15 11
Basement Floor 147 30-Oct-14 20-Apr-15 03-Nov-14 10-May-15 17
Rooms 129 30-Oct-14 30-Mar-15 03-Nov-14 07-Apr-15 7
53150-FNSh-BF-100 Plaster works - Basement Floor 18 30-Oct-14 19-Nov-14 03-Nov-14 23-Nov-14 3
53150-FNSh-BF-101 Screed - Basement Floor 14 20-Nov-14 07-Dec-14 25-Nov-14 11-Dec-14 4
53150-FNSh-BF-103 Painting Primier/1st Coat - Basement Floor 16 03-Dec-14 21-Dec-14 09-Dec-14 27-Dec-14 5
53150-FNSh-BF-102 Wall tiles works - Basement Floor 14 22-Dec-14 06-Jan-15 28-Dec-14 12-Jan-15 5
53150-FNSh-BF-105 False ceiling works - Basement Floor 14 10-Jan-15 25-Jan-15 13-Jan-15 28-Jan-15 3
53150-FNSh-BF-106 Painting 2nd coat - Basement Floor 16 26-Jan-15 12-Feb-15 29-Jan-15 16-Feb-15 3
53150-FNSh-BF-104 Floors finishes - Basement Floor 21 14-Feb-15 09-Mar-15 22-Feb-15 17-Mar-15 7
53150-FNSh-BF-107 Painting Final coat - Basement Floor 18 10-Mar-15 30-Mar-15 18-Mar-15 07-Apr-15 7
Parking & Open Areas 147 30-Oct-14 20-Apr-15 03-Nov-14 10-May-15 17
53150-FNSh-BF-108 Plaster works (part1) - Basement Floor 18 30-Oct-14 19-Nov-14 03-Nov-14 23-Nov-14 3
53150-FNSh-BF-109 Painting Primier/1st Coat(part1) - Basement Floor 16 08-Dec-14 25-Dec-14 13-Dec-14 30-Dec-14 4
53150-FNSh-BF-110 Plaster works (part2) - Basement Floor 18 27-Dec-14 15-Jan-15 31-Dec-14 20-Jan-15 4
53150-FNSh-BF-111 Painting Primier/1st Coat(part2) - Basement Floor 16 17-Jan-15 03-Feb-15 21-Jan-15 08-Feb-15 4
53150-FNSh-BF-112 Painting 2nd coat - Basement Floor 16 04-Feb-15 22-Feb-15 09-Feb-15 26-Feb-15 4
53150-FNSh-BF-113 Floors finishes - Basement Floor 21 02-Mar-15 25-Mar-15 23-Mar-15 15-Apr-15 18
53150-FNSh-BF-114 Painting Final coat - Basement Floor 18 31-Mar-15 20-Apr-15 20-Apr-15 10-May-15 17
Ground Floor 167 30-Sep-14 18-Apr-15 22-Oct-14 21-Apr-15 3
Wet Areas 104 15-Nov-14 16-Mar-15 19-Nov-14 21-Mar-15 4
53150-FNSh-GF-100 Partitions 1st Installation Ground Floor 10 15-Nov-14 25-Nov-14 19-Nov-14 30-Nov-14 4
53150-FNSh-GF-120 Partition Final Installation Grount Floor 10 13-Dec-14 23-Dec-14 20-Dec-14 30-Dec-14 6
53150-FNSh-GF-102 Painting Ground Floor 10 24-Dec-14 04-Jan-15 31-Dec-14 11-Jan-15 6
53150-FNSh-GF-101 Wall tiles works Ground Floor 16 05-Jan-15 22-Jan-15 12-Jan-15 29-Jan-15 6
53150-FNSh-GF-103 False ceiling works Ground Floor 14 24-Jan-15 08-Feb-15 31-Jan-15 15-Feb-15 6
53150-FNSh-GF-104 Floors finishes (linoleum,porcelain) Ground Floor 12 03-Mar-15 16-Mar-15 08-Mar-15 21-Mar-15 4
Dry Areas 165 30-Sep-14 15-Apr-15 22-Oct-14 20-Apr-15 4
53150-FNSh-GF-106 Screed Ground Floor 18 30-Sep-14 23-Oct-14 22-Oct-14 12-Nov-14 16
53150-FNSh-GF-107 Stud Partitions 1st Installation (whole floor) Ground Floor 11 13-Nov-14 25-Nov-14 13-Nov-14 25-Nov-14 0
53150-FNSh-GF-105 Plaster works Ground Floor 8 26-Nov-14 06-Dec-14 01-Dec-14 10-Dec-14 4
53150-FNSh-GF-117 Partition Final Installation Ground Floor 10 13-Dec-14 23-Dec-14 15-Dec-14 25-Dec-14 2
53150-FNSh-GF-108 Painting Primier/1st Coat Ground Floor 12 24-Dec-14 06-Jan-15 27-Dec-14 08-Jan-15 2
53150-FNSh-GF-109 False ceiling works Ground Floor 14 13-Jan-15 28-Jan-15 18-Jan-15 02-Feb-15 4
53150-FNSh-GF-111 Painting 2nd Coat (whole floor) Ground Floor 12 14-Feb-15 26-Feb-15 16-Feb-15 01-Mar-15 2
53150-FNSh-GF-110 Floors finishes (linoleum,carpet,terrazzo) Ground Floor 12 17-Mar-15 30-Mar-15 22-Mar-15 04-Apr-15 4
53150-FNSh-GF-112 Painting Final coat (whole floor) Ground Floor 14 31-Mar-15 15-Apr-15 05-Apr-15 20-Apr-15 4
Main Corridors 87 07-Jan-15 18-Apr-15 10-Jan-15 21-Apr-15 3
53150-FNSh-GF-113 Painting Primier/1st Coat Ground Floor 14 07-Jan-15 22-Jan-15 10-Jan-15 25-Jan-15 2
53150-FNSh-GF-114 False ceiling works Ground Floor 18 24-Jan-15 12-Feb-15 26-Jan-15 15-Feb-15 2
53150-FNSh-GF-123 Painting 2nd Coat Ground Floor 14 29-Jan-15 14-Feb-15 03-Feb-15 18-Feb-15 4
53150-FNSh-GF-115 Floors finishes (linoleum) Ground Floor 14 15-Feb-15 02-Mar-15 19-Feb-15 07-Mar-15 4
53150-FNSh-GF-133 Painting Final Coat Ground Floor 12 05-Apr-15 18-Apr-15 08-Apr-15 21-Apr-15 3
First Floor 161 20-Oct-14 27-Apr-15 10-Nov-14 02-May-15 4
Wet Areas 78 27-Nov-14 26-Feb-15 27-Nov-14 03-Mar-15 4
53150-FNSh-FF-100 Partitions 1st Installation First Floor 10 27-Nov-14 09-Dec-14 27-Nov-14 09-Dec-14 0

Actual Work Critical Remaining Work Summary Page 24 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-FNSh-FF-144 Partition Final Installation First Floor 10 20-Dec-14 30-Dec-14 20-Dec-14 30-Dec-14 0
53150-FNSh-FF-103 Painting First Floor 10 31-Dec-14 11-Jan-15 31-Dec-14 11-Jan-15 0
53150-FNSh-FF-101 Wall tiles works First Floor 16 12-Jan-15 29-Jan-15 12-Jan-15 29-Jan-15 0
53150-FNSh-FF-102 False ceiling works First Floor 14 31-Jan-15 15-Feb-15 31-Jan-15 15-Feb-15 0
53150-FNSh-FF-104 Floors finishes (linoleum,porcelain) First Floor 10 16-Feb-15 26-Feb-15 21-Feb-15 03-Mar-15 4
Dry Areas 142 20-Oct-14 05-Apr-15 10-Nov-14 05-Apr-15 0
53150-FNSh-FF-106 Screed First Floor 14 20-Oct-14 05-Nov-14 10-Nov-14 25-Nov-14 17
53150-FNSh-FF-107 Stud Partitions 1st Installation First Floor (whole floor) 11 26-Nov-14 09-Dec-14 26-Nov-14 09-Dec-14 0
53150-FNSh-FF-105 Plaster works First Floor 9 10-Dec-14 20-Dec-14 14-Dec-14 23-Dec-14 3
53150-FNSh-FF-122 Partition Final Installation First Floor 10 20-Dec-14 30-Dec-14 03-Jan-15 13-Jan-15 12
53150-FNSh-FF-108 Painting Primier/1st Coat First Floor 12 07-Jan-15 20-Jan-15 14-Jan-15 27-Jan-15 6
53150-FNSh-FF-109 False ceiling works First Floor 14 27-Jan-15 11-Feb-15 31-Jan-15 15-Feb-15 3
53150-FNSh-FF-111 Painting 2nd Coat First Floor 10 16-Feb-15 26-Feb-15 16-Feb-15 26-Feb-15 0
53150-FNSh-FF-110 Floors finishes (linoleum,carpet,terrazzo) First Floor 18 04-Mar-15 24-Mar-15 04-Mar-15 24-Mar-15 0
53150-FNSh-FF-112 Painting Final coat (whole floor) First Floor 10 25-Mar-15 05-Apr-15 25-Mar-15 05-Apr-15 0
Main Corridors 95 07-Jan-15 27-Apr-15 14-Jan-15 02-May-15 4
53150-FNSh-FF-113 Painting Primier/1st Coat First Floor 14 07-Jan-15 22-Jan-15 14-Jan-15 29-Jan-15 6
53150-FNSh-FF-114 False ceiling works First Floor 14 27-Jan-15 11-Feb-15 31-Jan-15 15-Feb-15 3
53150-FNSh-FF-124 Painting 2nd Coat First Floor 5 12-Feb-15 17-Feb-15 22-Feb-15 26-Feb-15 8
53150-FNSh-FF-115 Floors finishes (linoleum) First Floor 12 04-Mar-15 17-Mar-15 11-Mar-15 24-Mar-15 6
53150-FNSh-FF-134 Painting Final Coat First Floor 10 16-Apr-15 27-Apr-15 21-Apr-15 02-May-15 4
Roof Floor 12 24-Jan-15 05-Feb-15 31-Jan-15 12-Feb-15 6
53150-FNSh-RF-100 Plaster works roof 12 24-Jan-15 05-Feb-15 31-Jan-15 12-Feb-15 6
SPECIALTIES 54 05-Mar-15 06-May-15 14-Mar-15 18-May-15 10
Exterior 21 30-Mar-15 22-Apr-15 11-Apr-15 04-May-15 10
53150-SPEC-00-100 Exterior Signage 21 30-Mar-15 22-Apr-15 11-Apr-15 04-May-15 10
Basement Floor 10 10-Mar-15 21-Mar-15 01-Apr-15 12-Apr-15 19
Rooms 10 10-Mar-15 21-Mar-15 01-Apr-15 12-Apr-15 19
53150-SPEC-BF-100 Toilet Accessories - Basement Floor 10 10-Mar-15 21-Mar-15 01-Apr-15 12-Apr-15 19
Ground Floor 44 05-Mar-15 25-Apr-15 14-Mar-15 06-May-15 10
Wet Areas 21 22-Mar-15 14-Apr-15 13-Apr-15 06-May-15 19
53150-SPEC-GF-100 Toilet Accessories Ground Floor 21 22-Mar-15 14-Apr-15 13-Apr-15 06-May-15 19
Dry Areas 44 05-Mar-15 25-Apr-15 14-Mar-15 28-Apr-15 3
53150-SPEC-GF-101 Interior Signage Ground Floor 21 05-Mar-15 29-Mar-15 14-Mar-15 06-Apr-15 7
53150-SPEC-GF-102 Visual Display Units Ground Floor 6 19-Apr-15 25-Apr-15 22-Apr-15 28-Apr-15 3
First Floor 30 02-Apr-15 06-May-15 16-Apr-15 18-May-15 10
Wet Areas 21 02-Apr-15 26-Apr-15 25-Apr-15 18-May-15 19
53150-SPEC-FF-100 Toilet Accessories First Floor 21 02-Apr-15 26-Apr-15 25-Apr-15 18-May-15 19
Dry Areas 25 08-Apr-15 06-May-15 16-Apr-15 10-May-15 3
53150-SPEC-FF-101 Interior Signage First Floor 21 08-Apr-15 02-May-15 16-Apr-15 10-May-15 7
53150-SPEC-FF-102 Visual Display Units and Smoke Curtain First Floor 10 26-Apr-15 06-May-15 29-Apr-15 10-May-15 3
SPECIAL CONSTRUCTION 12 19-Nov-14 03-Dec-14 07-Dec-14 20-Dec-14 14
Radiation Protection 12 19-Nov-14 03-Dec-14 07-Dec-14 20-Dec-14 14
53150-SPCO-00-100 Radiation Protection to walls and ceilings 12 19-Nov-14 03-Dec-14 07-Dec-14 20-Dec-14 14
COMUNICATIONS 177 21-Sep-14 20-Apr-15 08-Oct-14 04-May-15 12
Basement Floor 163 21-Sep-14 04-Apr-15 08-Oct-14 22-Apr-15 16
53150-00IT-BF -100 IT/Telephone 1st Fix, Conduits Basement Floor 21 21-Sep-14 18-Oct-14 08-Oct-14 02-Nov-14 12
53150-00IT-BF -101 IT/Telephone 2nd Fix, high level Basement Floor 18 20-Nov-14 11-Dec-14 27-Nov-14 18-Dec-14 6
53150-00IT-BF -102 IT/Telephone Final Fix, Fittings Basement Floor 15 23-Feb-15 11-Mar-15 14-Mar-15 30-Mar-15 16
53150-00IT-BF -103 IT/Telephone Equipements installation Basement Floor 20 12-Mar-15 04-Apr-15 31-Mar-15 22-Apr-15 16
Ground Floor 120 19-Nov-14 08-Apr-15 03-Dec-14 22-Apr-15 12
53150-00IT-G F-100 IT/Telephone 1st Fix, Conduits Ground Floor 14 19-Nov-14 06-Dec-14 03-Dec-14 18-Dec-14 11

Actual Work Critical Remaining Work Summary Page 25 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-00IT-G F-101 IT/Telephone 2nd Fix, high level Ground Floor 18 13-Dec-14 01-Jan-15 20-Dec-14 08-Jan-15 6
53150-00IT-G F-102 IT/Telephone Final Fix, Fittings Ground Floor 15 28-Feb-15 16-Mar-15 14-Mar-15 30-Mar-15 12
53150-00IT-G F-103 IT/Telephone Equipements installation Ground Floor 20 17-Mar-15 08-Apr-15 31-Mar-15 22-Apr-15 12
First Floor 103 04-Dec-14 02-Apr-15 04-Dec-14 22-Apr-15 17
53150-00IT-FF -100 IT/Telephone 1st Fix, Conduits First Floor 18 04-Dec-14 24-Dec-14 04-Dec-14 24-Dec-14 0
53150-00IT-FF -101 IT/Telephone 2nd Fix, high level First Floor 18 03-Jan-15 22-Jan-15 10-Jan-15 29-Jan-15 6
53150-00IT-FF -102 IT/Telephone Final Fix, Fittings First Floor 15 28-Feb-15 16-Mar-15 19-Mar-15 05-Apr-15 17
53150-00IT-FF -103 IT/Telephone Equipements installation First Floor 15 17-Mar-15 02-Apr-15 06-Apr-15 22-Apr-15 17
General 10 09-Apr-15 20-Apr-15 23-Apr-15 04-May-15 12
53150-00IT-00-104 Third Party Testing and c ommis sionin g 10 09-Apr-15 20-Apr-15 23-Apr-15 04-May-15 12
ELECTRICAL WORKS 177 21-Sep-14 20-Apr-15 08-Oct-14 04-May-15 12
Basement Floor 157 21-Sep-14 28-Mar-15 08-Oct-14 28-Apr-15 27
53150-ELEC-BF-100 Electrical 1st Fix, Conduits - Basement Floor 21 21-Sep-14 18-Oct-14 08-Oct-14 02-Nov-14 12
53150-ELEC-BF-101 Electrical 2nd Fix, high level - Basement Floor 21 20-Nov-14 15-Dec-14 20-Dec-14 12-Jan-15 24
53150-ELEC-BF-102 Electrical Final Fix, Fittings - Basement Floor 21 14-Feb-15 09-Mar-15 22-Feb-15 17-Mar-15 7
53150-ELEC-BF-103 Electrical Equipements installation - Basement Floor 16 10-Mar-15 28-Mar-15 11-Apr-15 28-Apr-15 27
Ground Floor 122 19-Nov-14 11-Apr-15 25-Nov-14 28-Apr-15 15
53150-ELEC-GF-100 Electrical 1st Fix, Conduits Ground Floor 21 19-Nov-14 14-Dec-14 25-Nov-14 20-Dec-14 5
53150-ELEC-GF-101 Electrical 2nd Fix, high level Ground Floor 21 15-Dec-14 07-Jan-15 24-Dec-14 17-Jan-15 8
53150-ELEC-GF-102 Electrical Final Fix, Fittings Ground Floor 21 28-Feb-15 23-Mar-15 11-Mar-15 04-Apr-15 10
53150-ELEC-GF-103 Electrical Equipements installation Ground Floor 16 24-Mar-15 11-Apr-15 11-Apr-15 28-Apr-15 15
First Floor 113 04-Dec-14 14-Apr-15 04-Dec-14 28-Apr-15 12
53150-ELEC-FF-100 Electrical 1st Fix, Conduits First Floor 18 04-Dec-14 24-Dec-14 04-Dec-14 24-Dec-14 0
53150-ELEC-FF-101 Electrical 2nd Fix, high level First Floor 21 25-Dec-14 18-Jan-15 06-Jan-15 29-Jan-15 10
53150-ELEC-FF-102 Electrical Final Fix, Fittings First Floor 20 28-Feb-15 22-Mar-15 02-Mar-15 24-Mar-15 2
53150-ELEC-FF-103 Electrical Equipements installation First Floor 20 23-Mar-15 14-Apr-15 06-Apr-15 28-Apr-15 12
General 5 15-Apr-15 20-Apr-15 29-Apr-15 04-May-15 12
53150-ELEC-00-104 Third Party Testing and c ommis sionin g 5 15-Apr-15 20-Apr-15 29-Apr-15 04-May-15 12
FIXTURES, FURNISHINGS AND EQUIPMENT 133 21-Dec-14 24-May-15 24-Dec-14 08-Jun-15 13
FURNITURE, FIXTURES & EQUIPMENT 44 31-Mar-15 20-May-15 08-Apr-15 07-Jun-15 15
Exterior 13 06-May-15 20-May-15 24-May-15 07-Jun-15 15
53150-FURF-00-112 SIte Furnishing - Exterior 13 06-May-15 20-May-15 24-May-15 07-Jun-15 15
Interior 37 31-Mar-15 12-May-15 08-Apr-15 07-Jun-15 22
53150-FURF-00-100 Furniture Basement Floor 14 31-Mar-15 15-Apr-15 08-Apr-15 23-Apr-15 7
53150-FURF-00-101 Furniture Ground Floor 21 19-Apr-15 12-May-15 14-May-15 07-Jun-15 22
53150-FURF-00-102 Furniture First Floor 14 20-Apr-15 05-May-15 25-Apr-15 10-May-15 4
EQUIPMENT 10 25-Apr-15 05-May-15 07-May-15 18-May-15 11
Residential Equipments and Projection Screen 10 25-Apr-15 05-May-15 07-May-15 18-May-15 11
53150-00EQ-00-100 Residential Appliances 10 25-Apr-15 05-May-15 07-May-15 18-May-15 11
53150-00EQ-00-101 Projection Screen 10 25-Apr-15 05-May-15 07-May-15 18-May-15 11
CONVEYING EQUIPMENT 111 21-Dec-14 28-Apr-15 24-Dec-14 04-May-15 5
Elevators 111 21-Dec-14 28-Apr-15 24-Dec-14 04-May-15 5
53150-ELEV-00-100 Scaffolding in lift shaft 18 21-Dec-14 10-Jan-15 24-Dec-14 13-Jan-15 3
53150-ELEV-00-101 Rails 18 11-Jan-15 31-Jan-15 14-Jan-15 03-Feb-15 3
53150-ELEV-00-102 Machine 18 01-Feb-15 21-Feb-15 04-Feb-15 24-Feb-15 3
53150-ELEV-00-103 Cabin 18 22-Feb-15 14-Mar-15 25-Feb-15 17-Mar-15 3
53150-ELEV-00-104 Doors 18 15-Mar-15 04-Apr-15 18-Mar-15 07-Apr-15 3
53150-ELEV-00-105 Third Party Testing and c ommis sionin g 21 05-Apr-15 28-Apr-15 11-Apr-15 04-May-15 5
MEDICAL & LABORATORY EQUIPMENT 42 06-Apr-15 24-May-15 06-Apr-15 08-Jun-15 13
Medical Equipment 42 06-Apr-15 24-May-15 06-Apr-15 08-Jun-15 13
53150-MDEQ-00-100 Install Medical equipments Installation Part1 16 06-Apr-15 23-Apr-15 06-Apr-15 23-Apr-15 0
53150-MDEQ-00-110 Install Medical equipments Installation Part 2 16 25-Apr-15 12-May-15 25-Apr-15 12-May-15 0

Actual Work Critical Remaining Work Summary Page 26 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-MDEQ-00-115 Third Party Testing and c ommis sionin g 10 13-May-15 24-May-15 28-May-15 08-Jun-15 13
MECHANICAL AND PLUMBING 190 15-Sep-14 29-Apr-15 08-Oct-14 04-May-15 4
FIRE SUPPRESSION SYSTEM 137 20-Nov-14 29-Apr-15 07-Dec-14 04-May-15 4
Basement Floor 93 20-Nov-14 09-Mar-15 07-Dec-14 28-Mar-15 16
53150-00FF-BF-100 F.F 1st Fix, high level Basement 18 20-Nov-14 11-Dec-14 07-Dec-14 27-Dec-14 13
53150-00FF-BF-101 F.F 2nd Fix, risers Basement 21 13-Dec-14 05-Jan-15 06-Jan-15 29-Jan-15 21
53150-00FF-BF-102 F.F Final Fix, Fittings Basement 21 26-Jan-15 18-Feb-15 14-Feb-15 09-Mar-15 16
53150-00FF-BF-103 F.F Equipements installation Basement 16 19-Feb-15 09-Mar-15 10-Mar-15 28-Mar-15 16
Ground Floor 103 13-Dec-14 11-Apr-15 28-Dec-14 15-Apr-15 4
53150-00FF-GF-100 F.F 1st Fix, high level Ground Floor 18 13-Dec-14 01-Jan-15 28-Dec-14 17-Jan-15 13
53150-00FF-GF-101 F.F 2nd Fix, risers Ground Floor 16 27-Jan-15 14-Feb-15 31-Jan-15 17-Feb-15 3
53150-00FF-GF-102 F.F Final Fix, Fittings Ground Floor 21 28-Feb-15 23-Mar-15 04-Mar-15 28-Mar-15 4
53150-00FF-GF-103 F.F Equipements installation Ground Floor 16 24-Mar-15 11-Apr-15 29-Mar-15 15-Apr-15 4
First Floor 112 21-Dec-14 29-Apr-15 28-Dec-14 04-May-15 4
53150-00FF-FF-100 F.F 1st Fix, high level First Floor 15 21-Dec-14 06-Jan-15 28-Dec-14 13-Jan-15 6
53150-00FF-FF-101 F.F 2nd Fix, risers First Floor 18 15-Feb-15 07-Mar-15 18-Feb-15 10-Mar-15 3
53150-00FF-FF-102 F.F Final Fix, Fittings First Floor 12 08-Mar-15 21-Mar-15 11-Mar-15 24-Mar-15 3
53150-00FF-FF-103 F.F Equipements installation First Floor 16 12-Apr-15 29-Apr-15 16-Apr-15 04-May-15 4
General 6 23-Apr-15 29-Apr-15 28-Apr-15 04-May-15 4
53150-00FF-00-104 Third Party Testing and c ommis sionin g 6 23-Apr-15 29-Apr-15 28-Apr-15 04-May-15 4
PLUMBING INSTALLATIONS 177 21-Sep-14 20-Apr-15 20-Oct-14 04-May-15 12
Basement Floor 162 21-Sep-14 02-Apr-15 20-Oct-14 04-May-15 27
53150-PLUM-BF-100 Plumbing 1st Fix, Conduits - Basement Floor 21 21-Sep-14 18-Oct-14 20-Oct-14 13-Nov-14 22
53150-PLUM-BF-101 Plumbing 2nd Fix, high level - Basement Floor 21 20-Nov-14 15-Dec-14 20-Dec-14 12-Jan-15 24
53150-PLUM-BF-102 Plumbing Final Fix, Fittings - Basement Floor 21 14-Feb-15 09-Mar-15 22-Feb-15 17-Mar-15 7
53150-PLUM-BF-103 Plumbing Equipements installation - Basement Floor 21 10-Mar-15 02-Apr-15 11-Apr-15 04-May-15 27
Ground Floor 121 26-Nov-14 16-Apr-15 29-Nov-14 04-May-15 15
53150-PLUM-GF-100 Plumbing 1st Fix, Conduits Ground Floor 18 26-Nov-14 17-Dec-14 29-Nov-14 20-Dec-14 2
53150-PLUM-GF-101 Plumbing 2nd Fix, high level Ground Floor 16 18-Dec-14 05-Jan-15 22-Dec-14 08-Jan-15 3
53150-PLUM-GF-102 Plumbing Final Fix, Fittings Ground Floor 21 28-Feb-15 23-Mar-15 11-Mar-15 04-Apr-15 10
53150-PLUM-GF-103 Plumbing Equipements installation Ground Floor 21 24-Mar-15 16-Apr-15 11-Apr-15 04-May-15 15
First Floor 112 04-Dec-14 13-Apr-15 04-Dec-14 27-Apr-15 12
53150-PLUM-FF-100 Plumbing 1st Fix, Conduits First Floor 18 04-Dec-14 24-Dec-14 04-Dec-14 24-Dec-14 0
53150-PLUM-FF-101 Plumbing 2nd Fix, high level First Floor 18 06-Jan-15 26-Jan-15 10-Jan-15 29-Jan-15 3
53150-PLUM-FF-102 Plumbing Final Fix, Fittings First Floor 18 28-Feb-15 19-Mar-15 04-Mar-15 24-Mar-15 4
53150-PLUM-FF-103 Plumbing Equipements installation First Floor 21 21-Mar-15 13-Apr-15 04-Apr-15 27-Apr-15 12
General 10 09-Apr-15 20-Apr-15 23-Apr-15 04-May-15 12
53150-PLUM-00-104 Third Party Testing and c ommis sionin g 10 09-Apr-15 20-Apr-15 23-Apr-15 04-May-15 12
HVAC SYSTEM 125 20-Nov-14 15-Apr-15 24-Nov-14 04-May-15 16
Basement Floor 107 20-Nov-14 25-Mar-15 24-Nov-14 29-Mar-15 3
53150-HVAC-BF-100 HVAC 1st Fix, ducts - Basement Floor 21 20-Nov-14 15-Dec-14 24-Nov-14 18-Dec-14 3
53150-HVAC-BF-101 HVAC 2nd Fix, FCUs/AHU - Basement Floor 21 16-Dec-14 08-Jan-15 20-Dec-14 12-Jan-15 3
53150-HVAC-BF-102 HVAC Final Fix, Fittings - Basement Floor 21 14-Feb-15 09-Mar-15 17-Feb-15 12-Mar-15 3
53150-HVAC-BF-103 HVAC Equipements installation (Chillers) - Basement Floor 14 10-Mar-15 25-Mar-15 14-Mar-15 29-Mar-15 3
Ground Floor 95 07-Dec-14 26-Mar-15 11-Dec-14 29-Mar-15 2
53150-HVAC-GF-100 HVAC 1st Fix, ducts Ground Floor 16 07-Dec-14 24-Dec-14 11-Dec-14 29-Dec-14 4
53150-HVAC-GF-101 HVAC 2nd Fix, FCUs/AHU Ground Floor 16 25-Dec-14 12-Jan-15 30-Dec-14 17-Jan-15 4
53150-HVAC-GF-102 HVAC Final Fix, Fittings Ground Floor 10 28-Feb-15 10-Mar-15 02-Mar-15 12-Mar-15 2
53150-HVAC-GF-103 HVAC Equipements installation (Chillers) Ground Floor 14 11-Mar-15 26-Mar-15 14-Mar-15 29-Mar-15 2
First Floor 85 21-Dec-14 29-Mar-15 24-Dec-14 29-Mar-15 0
53150-HVAC-FF-100 HVAC 1st Fix, ducts First Floor 16 21-Dec-14 07-Jan-15 24-Dec-14 11-Jan-15 3
53150-HVAC-FF-101 HVAC 2nd Fix, FCUs/AHU First Floor 16 08-Jan-15 26-Jan-15 12-Jan-15 29-Jan-15 3

Actual Work Critical Remaining Work Summary Page 27 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-HVAC-FF-102 HVAC Final Fix, Fittings First Floor 12 28-Feb-15 12-Mar-15 28-Feb-15 12-Mar-15 0
53150-HVAC-FF-103 HVAC Equipements installation (Chillers) First Floor 14 14-Mar-15 29-Mar-15 14-Mar-15 29-Mar-15 0
General 15 30-Mar-15 15-Apr-15 18-Apr-15 04-May-15 16
53150-HVAC-00-104 Third Party Testing and c ommis sionin g 15 30-Mar-15 15-Apr-15 18-Apr-15 04-May-15 16
FIRE ALARM WORKS 181 15-Sep-14 19-Apr-15 08-Oct-14 04-May-15 13
Basement Floor 160 15-Sep-14 25-Mar-15 08-Oct-14 09-Apr-15 13
53150-00FA- BF-100 F.A 1st Fix, Conduits - Basement Floor 21 15-Sep-14 12-Oct-14 08-Oct-14 02-Nov-14 17
53150-00FA- BF-101 F.A 2nd Fix, high level - Basement Floor 21 20-Nov-14 15-Dec-14 20-Dec-14 12-Jan-15 24
53150-00FA- BF-102 F.A Final Fix, Fittings - Basement Floor 21 14-Feb-15 09-Mar-15 22-Feb-15 17-Mar-15 7
53150-00FA- BF-103 F.A Equipements installation - Basement Floor 14 10-Mar-15 25-Mar-15 25-Mar-15 09-Apr-15 13
Ground Floor 120 19-Nov-14 08-Apr-15 25-Nov-14 04-May-15 22
53150-00FA- GF- 100 F.A 1st Fix, Conduits Ground Floor 21 19-Nov-14 14-Dec-14 25-Nov-14 20-Dec-14 5
53150-00FA- GF- 101 F.A 2nd Fix, high level Ground Floor 21 15-Dec-14 07-Jan-15 24-Dec-14 17-Jan-15 8
53150-00FA- GF- 102 F.A Final Fix, Fittings Ground Floor 21 28-Feb-15 23-Mar-15 11-Mar-15 04-Apr-15 10
53150-00FA- GF- 103 F.A Equipements installation Ground Floor 14 24-Mar-15 08-Apr-15 19-Apr-15 04-May-15 22
First Floor 103 04-Dec-14 02-Apr-15 04-Dec-14 18-Apr-15 13
53150-00FA- FF-100 F.A 1st Fix, Conduits First Floor 18 04-Dec-14 24-Dec-14 04-Dec-14 24-Dec-14 0
53150-00FA- FF-101 F.A 2nd Fix, high level First Floor 21 25-Dec-14 18-Jan-15 06-Jan-15 29-Jan-15 10
53150-00FA- FF-102 F.A Final Fix, Fittings First Floor 16 28-Feb-15 17-Mar-15 07-Mar-15 24-Mar-15 6
53150-00FA- FF-103 F.A Equipements installation First Floor 14 18-Mar-15 02-Apr-15 02-Apr-15 18-Apr-15 13
General 14 04-Apr-15 19-Apr-15 19-Apr-15 04-May-15 13
53150-00FA- FF-113 Third Party Testing and c ommis sionin g 14 04-Apr-15 19-Apr-15 19-Apr-15 04-May-15 13
EARTHWORK 351 27-Jan-14 21-Mar-15 27-Jan-14 18-Apr-15 24
53150-ERTH-00-100 Excavation upto 1.5 m depth from ground level 4 27-Jan-14 30-Jan-14 27-Jan-14 30-Jan-14 0
53150-ERTH-00-101 Shoring Secant Piles (Part 1) 12 15-Feb-14 27-Feb-14 15-Feb-14 27-Feb-14 0
53150-ERTH-00-103 Shoring Secant Piles (Part 2) 9 01-Mar-14 10-Mar-14 01-Mar-14 10-Mar-14 0
53150-ERTH-00-104 Structural Piles (Part 1) 15 11-Mar-14 27-Mar-14 11-Mar-14 27-Mar-14 0
53150-ERTH-00-105 Shoring Secant Piles (Part 3) 9 12-Mar-14 22-Mar-14 22-Mar-14 31-Mar-14 8
53150-ERTH-00-107 Shoring Secant Piles (Part 4) 9 23-Mar-14 01-Apr-14 01-Apr-14 10-Apr-14 8
53150-ERTH-00-106 Structural Piles (Part 2) 16 29-Mar-14 15-Apr-14 29-Mar-14 15-Apr-14 0
53150-ERTH-00-102 Dewatering 100 19-Apr-14 16-Aug-14 21-Apr-14 18-Aug-14 2
53150-ERTH-00-108 Excavation to final level 20 22-Apr-14 14-May-14 22-Apr-14 14-May-14 0
53150-ERTH-00-111 Pile Static Load tests 7 30-Apr-14 07-May-14 15-May-14 22-May-14 13
53150-ERTH-00-110 Piles head Cutting & Treatment 6 15-May-14 21-May-14 15-May-14 21-May-14 0
53150-ERTH-00-133 Anti Termite Treatment For Pile Caps/Polytherene Sheet 1 22-May-14 22-May-14 22-May-14 22-May-14 0
53150-ERTH-00-112 Integrity Pile tests 3 22-May-14 25-May-14 11-Jun-14 14-Jun-14 16
53150-ERTH-00-143 Anti Termite Treatment for Raft/Polytherene Sheet 1 14-Jun-14 14-Jun-14 14-Jun-14 14-Jun-14 0
53150-ERTH-00-109 Backfil (Dune Sand) behind the Basement walls 10 19-Aug-14 30-Aug-14 31-Aug-14 10-Sep-14 10
53150-ERTH-00-123 Anti Termite treatment Landscape 3 18-Mar-15 21-Mar-15 15-Apr-15 18-Apr-15 24
DEMOLITION 20 09-Dec-13 31-Dec-13 09-Dec-13 31-Dec-13 0
53150-DEMO-00-100 Demolition of existing buildings 20 09-Dec-13 31-Dec-13 09-Dec-13 31-Dec-13 0
UTILITIES 21 26-Mar-15 19-Apr-15 11-Apr-15 04-May-15 13
53150-UTIL-00-101 Water Distribution 21 26-Mar-15 19-Apr-15 11-Apr-15 04-May-15 13
53150-UTIL-00-102 Sanitary Sewerage 21 26-Mar-15 19-Apr-15 11-Apr-15 04-May-15 13
53150-UTIL-00-103 Storm Utility Drainage Piping and Sub-drainage 21 26-Mar-15 19-Apr-15 11-Apr-15 04-May-15 13
EXTERNAL WORKS 81 03-Feb-15 07-May-15 14-Feb-15 13-May-15 5
Landscape and Hardscape 81 03-Feb-15 07-May-15 14-Feb-15 13-May-15 5
53150-EXIM-00-100 Excavation for services 16 03-Feb-15 21-Feb-15 14-Feb-15 03-Mar-15 9
53150-EXIM-00-101 installation of services 16 10-Feb-15 28-Feb-15 21-Feb-15 10-Mar-15 9
53150-EXIM-00-102 Backfilling for service trenches 12 12-Feb-15 25-Feb-15 23-Feb-15 08-Mar-15 9
53150-EXIM-00-103 Excavation for soft/hard landscaping 12 12-Feb-15 25-Feb-15 23-Feb-15 08-Mar-15 9
53150-EXIM-00-105 Backfilling for soft landscaping 12 26-Feb-15 11-Mar-15 09-Mar-15 22-Mar-15 9

Actual Work Critical Remaining Work Summary Page 28 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone
Data Date : 22-Aug-13
MHCOST LOADINGPROJECT 53150 (AL MUSHRIF AMBULATORY
HEALTH CENTRE)
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2014 2015 2016
Duration Float
Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct N Dec Jan
53150-EXIM-00-104 Compaction 15 12-Mar-15 29-Mar-15 23-Mar-15 08-Apr-15 9
53150-EXIM-00-107 Final Utility conection to main 21 30-Mar-15 22-Apr-15 11-Apr-15 04-May-15 10
53150-EXIM-00-108 Subbase/Roadbase 20 04-Apr-15 26-Apr-15 09-Apr-15 02-May-15 5
53150-EXIM-00-106 Landscaping and Hard landscaping 20 15-Apr-15 07-May-15 21-Apr-15 13-May-15 5
53150-EXIM-00-109 Completion of Hard/Soft landscaping 0 07-May-15 13-May-15 5
TESTING AND COMMISSIONING 80 08-Mar-15 08-Jun-15 18-Mar-15 08-Jun-15 0
Testing and Commissioning 74 08-Mar-15 01-Jun-15 18-Mar-15 07-Jun-15 5
53150-HAND-00-121 Temporary Power conenction for testing and commissioning 10 08-Mar-15 18-Mar-15 18-Mar-15 29-Mar-15 9
53150-ELEV-00-116 Wild Air system for Medical Equipment 6 30-Mar-15 05-Apr-15 30-Mar-15 05-Apr-15 0
53150-HAND-00-100 Completion Inspections 12 05-May-15 18-May-15 05-May-15 18-May-15 0
53150-HAND-00-101 Testing & Commissioning 12 05-May-15 18-May-15 05-May-15 18-May-15 0
53150-HAND-00-105 Completion Testin g & C ommiss ioning 21 09-May-15 01-Jun-15 14-May-15 07-Jun-15 5
Authority Inspections 17 19-May-15 07-Jun-15 01-Jun-15 07-Jun-15 0
53150-HAND-00-111 HADD Inspection 6 19-May-15 25-May-15 01-Jun-15 07-Jun-15 11
53150-HAND-00-126 Power on 1 07-Jun-15 07-Jun-15 07-Jun-15 07-Jun-15 0
As built Preparation,Snagging and Handing over 46 16-Apr-15 08-Jun-15 27-Apr-15 08-Jun-15 0
53150-HAND-00-102 As built Documents/Operation Manauals 36 16-Apr-15 27-May-15 27-Apr-15 07-Jun-15 9
53150-HAND-00-103 Building Completion Certificate (BCC) 9 05-May-15 14-May-15 05-May-15 14-May-15 0
53150-HAND-00-104 Snagging 24 07-May-15 03-Jun-15 11-May-15 07-Jun-15 3
53150-HAND-00-107 Handing over BCC 1 16-May-15 16-May-15 16-May-15 16-May-15 0
53150-HAND-00-108 Permanent utilities available 10 19-May-15 30-May-15 27-May-15 07-Jun-15 7
53150-HAND-00-109 Handing over to the client 1 08-Jun-15 08-Jun-15 08-Jun-15 08-Jun-15 0
53150-HAND-00-110 Issue of Taking O ver C ertificate 0 08-Jun-15 08-Jun-15 0

Actual Work Critical Remaining Work Summary Page 29 of 29 Date Revision Checked Approved
Polensky & Zoellner Abu Dhabi WLL 13-May-14 Baseline Program ... MOKHTAR ALEX
Remaining Work Milestone

You might also like