Professional Documents
Culture Documents
MH-BEGIN-10 Site Hand over date 0 12-Jul-13 Site Hand over date
MH-BEGIN-10.5 Mobilization works 0 12-Jul-13 Mobilization works
MH-BEGIN-11 Work Commencement date 0 03-Aug-13* Work Commencement date
MH-BEGIN-20 Delivery of IFC Drawings 140 08-Aug-13 25-Dec-13 Delivery of IFC Drawings
MH-BEGIN-50 Works Kick off 0 12-Jul-13* Works Kick off
MILD HYDROCRACKING
HYDRO UNIT-CIVIL WORKS 389 13-Jul-13 05-Aug-14 05-Aug-14, MILD HYDROCRACKING UNIT-CIVIL WORKS
SITE CIVIL WORKS
WOR 389 13-Jul-13 05-Aug-14 05-Aug-14, SITE CIVIL WORKS
TEMPORARY SITE
SI FACILITIES 90 13-Jul-13 10-Oct-13 10-Oct-13, TEMPORARY SITE FACILITIES
MH-CW-659 Providing of Equipment & Material 20 13-Jul-13 01-Aug-13 Providing of Equipment & Material
MH-CW-691 Preparation of camp and site office area 23 13-Jul-13 04-Aug-13 Preparation of camp and site office area
MH-CW-692 Foundation works 35 18-Jul-13 21-Aug-13 Foundation works
MH-CW-694 Building construction works 65 20-Jul-13 22-Sep-13 Building construction works
MH-CW-695 Landscape works 81 22-Jul-13 10-Oct-13 Landscape works
TEMPORARY DRAINAGE
D WORKS 39 05-Aug-13 13-Sep-13 13-Sep-13, TEMPORARY DRAINAGE WORKS
MH-CW-10 Temporaray Drainage Works 39 05-Aug-13 13-Sep-13 Temporaray Drainage Works
BACKFILLING W
WORKS UPTO BOTTOM OF FOUNDATION(Contractual Granular M 81 09-Aug-13 28-Oct-13 28-Oct-13, BACKFILLING WORKS UPTO BOTTOM OF FOUNDATION(Contractual Granular Material)
MH-CW-30 Backfilling upto bottom of foundation(m3) 81 09-Aug-13 28-Oct-13 Backfilling upto bottom of foundation(m3)
PILING WORKS 149 23-Sep-13 18-Feb-14 18-Feb-14, PILING WORKS
PILE TESTS AND
AN RESULTS 39 23-Sep-13 31-Oct-13 31-Oct-13, PILE TESTS AND RESULTS
MH-CW-60 Installation of test piles 7 23-Sep-13 29-Sep-13 Installation of test piles
MH-CW-70 Testing- Area 1 ( Dynamic+ Static ) 12 01-Oct-13 12-Oct-13 Testing- Area 1 ( Dynamic+ Static )
MH-CW-80 Testing- Area 2 ( Dynamic+ Static ) 12 02-Oct-13 13-Oct-13 Testing- Area 2 ( Dynamic+ Static )
MH-CW-90 Saturation Test 18 08-Oct-13 25-Oct-13 Saturation Test
MH-CW-95 Evaluation Test results 5 27-Oct-13 31-Oct-13 Evaluation Test results
PILING & HEAD REMOVAL WORKS(Pieces) 111 31-Oct-13 18-Feb-14 18-Feb-14, PILING & HEAD REMOVAL WORKS(Pieces)
SECTION 9 P
PILING WORKS 15 31-Oct-13 14-Nov-13 14-Nov-13, SECTION 9 PILING WORKS
MH-CW-100 Piling Activities 15 31-Oct-13 14-Nov-13 Piling Activities
SECTION 3 P
PILING WORKS 26 31-Oct-13 25-Nov-13 25-Nov-13, SECTION 3 PILING WORKS
MH-CW-110 Piling Activities 26 31-Oct-13 25-Nov-13 Piling Activities
SECTION 7 P
PILING WORKS 35 12-Nov-13 16-Dec-13 16-Dec-13, SECTION 7 PILING WORKS
MH-CW-150 Piling Activities 35 12-Nov-13 16-Dec-13 Piling Activities
SECTION 8 P
PILING WORKS 45 12-Nov-13 26-Dec-13 26-Dec-13, SECTION 8 PILING WORKS
MH-CW-160 Piling Activities 45 12-Nov-13 26-Dec-13 Piling Activities
SECTION 2 P
PILING WORKS 45 22-Nov-13 05-Jan-14 05-Jan-14, SECTION 2 PILING WORKS
MH-CW-260 Piling Activities 45 22-Nov-13 05-Jan-14 Piling Activities
SECTION 5 P
PILING WORKS 33 12-Dec-13 13-Jan-14 13-Jan-14, SECTION 5 PILING WORKS
MH-CW-380 Piling Activities 33 12-Dec-13 13-Jan-14 Piling Activities
SECTION 6 P
PILING WORKS 50 26-Dec-13 13-Feb-14 13-Feb-14, SECTION 6 PILING WORKS
MH-CW-450 Piling Activities 50 26-Dec-13 13-Feb-14 Piling Activities
SECTION 1 PILING
PI WORKS 45 05-Jan-14 18-Feb-14 18-Feb-14, SECTION 1 PILING WORKS
MH-CW-230 Piling Activities 45 05-Jan-14 18-Feb-14 Piling Activities
SECTION 4 PILING
PI WORKS 35 13-Jan-14 16-Feb-14 16-Feb-14, SECTION 4 PILING WORKS
MH-CW-610 Piling Activities 35 13-Jan-14 16-Feb-14 Piling Activities
CONCRETE FOUNDATIONS-M3
FO 340 31-Aug-13 05-Aug-14 05-Aug-14, CONCRETE FOUNDATIONS-M3
FOUNDATION WORK-SECTIONS 265 14-Nov-13 05-Aug-14 05-Aug-14, FOUNDATION WORK-SECTIONS
PIPE RACK FOUNDAIONS
FO 79 18-Nov-13 04-Feb-14 04-Feb-14, PIPE RACK FOUNDAIONS
SECTION-3 5 18-Nov-13 22-Nov-13 22-Nov-13, SECTION-3
MH-CW-36 Pipe rack foundation work 5 18-Nov-13 22-Nov-13 Pipe rack foundation work
SECTION-8 18 18-Nov-13 05-Dec-13 05-Dec-13, SECTION-8
MH-CW-14 Pipe rack foundation work 18 18-Nov-13 05-Dec-13 Pipe rack foundation work
Primary Baseline Actual Work Critical Remaining Work Page 1 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 2 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 3 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 4 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 5 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 7 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 8 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 9 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 10 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 11 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 12 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 13 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 15 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 16 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 17 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 18 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 19 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 20 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 22 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 23 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 24 of 25 TASK filter: All Activities
Primary Baseline Actual Work Critical Remaining Work Page 25 of 25 TASK filter: All Activities