VGO PROJECT BASELINE SCHEDULE

Activity ID Activity Name Original Start Finish 3 2014 2015


Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
VGO PROJECT
PROJE BASELINE SCHEDULE 841 12-Jul-13 31-Oct-15 31-

MH-BEGIN-10 Site Hand over date 0 12-Jul-13 Site Hand over date
MH-BEGIN-10.5 Mobilization works 0 12-Jul-13 Mobilization works
MH-BEGIN-11 Work Commencement date 0 03-Aug-13* Work Commencement date
MH-BEGIN-20 Delivery of IFC Drawings 140 08-Aug-13 25-Dec-13 Delivery of IFC Drawings
MH-BEGIN-50 Works Kick off 0 12-Jul-13* Works Kick off
MILD HYDROCRACKING
HYDRO UNIT-CIVIL WORKS 389 13-Jul-13 05-Aug-14 05-Aug-14, MILD HYDROCRACKING UNIT-CIVIL WORKS
SITE CIVIL WORKS
WOR 389 13-Jul-13 05-Aug-14 05-Aug-14, SITE CIVIL WORKS
TEMPORARY SITE
SI FACILITIES 90 13-Jul-13 10-Oct-13 10-Oct-13, TEMPORARY SITE FACILITIES
MH-CW-659 Providing of Equipment & Material 20 13-Jul-13 01-Aug-13 Providing of Equipment & Material
MH-CW-691 Preparation of camp and site office area 23 13-Jul-13 04-Aug-13 Preparation of camp and site office area
MH-CW-692 Foundation works 35 18-Jul-13 21-Aug-13 Foundation works
MH-CW-694 Building construction works 65 20-Jul-13 22-Sep-13 Building construction works
MH-CW-695 Landscape works 81 22-Jul-13 10-Oct-13 Landscape works
TEMPORARY DRAINAGE
D WORKS 39 05-Aug-13 13-Sep-13 13-Sep-13, TEMPORARY DRAINAGE WORKS
MH-CW-10 Temporaray Drainage Works 39 05-Aug-13 13-Sep-13 Temporaray Drainage Works
BACKFILLING W
WORKS UPTO BOTTOM OF FOUNDATION(Contractual Granular M 81 09-Aug-13 28-Oct-13 28-Oct-13, BACKFILLING WORKS UPTO BOTTOM OF FOUNDATION(Contractual Granular Material)
MH-CW-30 Backfilling upto bottom of foundation(m3) 81 09-Aug-13 28-Oct-13 Backfilling upto bottom of foundation(m3)
PILING WORKS 149 23-Sep-13 18-Feb-14 18-Feb-14, PILING WORKS
PILE TESTS AND
AN RESULTS 39 23-Sep-13 31-Oct-13 31-Oct-13, PILE TESTS AND RESULTS
MH-CW-60 Installation of test piles 7 23-Sep-13 29-Sep-13 Installation of test piles
MH-CW-70 Testing- Area 1 ( Dynamic+ Static ) 12 01-Oct-13 12-Oct-13 Testing- Area 1 ( Dynamic+ Static )
MH-CW-80 Testing- Area 2 ( Dynamic+ Static ) 12 02-Oct-13 13-Oct-13 Testing- Area 2 ( Dynamic+ Static )
MH-CW-90 Saturation Test 18 08-Oct-13 25-Oct-13 Saturation Test
MH-CW-95 Evaluation Test results 5 27-Oct-13 31-Oct-13 Evaluation Test results
PILING & HEAD REMOVAL WORKS(Pieces) 111 31-Oct-13 18-Feb-14 18-Feb-14, PILING & HEAD REMOVAL WORKS(Pieces)
SECTION 9 P
PILING WORKS 15 31-Oct-13 14-Nov-13 14-Nov-13, SECTION 9 PILING WORKS
MH-CW-100 Piling Activities 15 31-Oct-13 14-Nov-13 Piling Activities
SECTION 3 P
PILING WORKS 26 31-Oct-13 25-Nov-13 25-Nov-13, SECTION 3 PILING WORKS
MH-CW-110 Piling Activities 26 31-Oct-13 25-Nov-13 Piling Activities
SECTION 7 P
PILING WORKS 35 12-Nov-13 16-Dec-13 16-Dec-13, SECTION 7 PILING WORKS
MH-CW-150 Piling Activities 35 12-Nov-13 16-Dec-13 Piling Activities
SECTION 8 P
PILING WORKS 45 12-Nov-13 26-Dec-13 26-Dec-13, SECTION 8 PILING WORKS
MH-CW-160 Piling Activities 45 12-Nov-13 26-Dec-13 Piling Activities
SECTION 2 P
PILING WORKS 45 22-Nov-13 05-Jan-14 05-Jan-14, SECTION 2 PILING WORKS
MH-CW-260 Piling Activities 45 22-Nov-13 05-Jan-14 Piling Activities
SECTION 5 P
PILING WORKS 33 12-Dec-13 13-Jan-14 13-Jan-14, SECTION 5 PILING WORKS
MH-CW-380 Piling Activities 33 12-Dec-13 13-Jan-14 Piling Activities
SECTION 6 P
PILING WORKS 50 26-Dec-13 13-Feb-14 13-Feb-14, SECTION 6 PILING WORKS
MH-CW-450 Piling Activities 50 26-Dec-13 13-Feb-14 Piling Activities
SECTION 1 PILING
PI WORKS 45 05-Jan-14 18-Feb-14 18-Feb-14, SECTION 1 PILING WORKS
MH-CW-230 Piling Activities 45 05-Jan-14 18-Feb-14 Piling Activities
SECTION 4 PILING
PI WORKS 35 13-Jan-14 16-Feb-14 16-Feb-14, SECTION 4 PILING WORKS
MH-CW-610 Piling Activities 35 13-Jan-14 16-Feb-14 Piling Activities
CONCRETE FOUNDATIONS-M3
FO 340 31-Aug-13 05-Aug-14 05-Aug-14, CONCRETE FOUNDATIONS-M3
FOUNDATION WORK-SECTIONS 265 14-Nov-13 05-Aug-14 05-Aug-14, FOUNDATION WORK-SECTIONS
PIPE RACK FOUNDAIONS
FO 79 18-Nov-13 04-Feb-14 04-Feb-14, PIPE RACK FOUNDAIONS
SECTION-3 5 18-Nov-13 22-Nov-13 22-Nov-13, SECTION-3
MH-CW-36 Pipe rack foundation work 5 18-Nov-13 22-Nov-13 Pipe rack foundation work
SECTION-8 18 18-Nov-13 05-Dec-13 05-Dec-13, SECTION-8
MH-CW-14 Pipe rack foundation work 18 18-Nov-13 05-Dec-13 Pipe rack foundation work
Primary Baseline Actual Work Critical Remaining Work Page 1 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
SECTION-2 28 27-Nov-13 24-Dec-13 24-Dec-13, SECTION-2
MH-CW-37 Pipe rack foundation work 28 27-Nov-13 24-Dec-13 Pipe rack foundation work
SECTION-3.2 8 27-Nov-13 04-Dec-13 04-Dec-13, SECTION-3.2
MH-CW-25 Pipe rack foundation work 8 27-Nov-13 04-Dec-13 Pipe rack foundation work
SECTION-1 23 09-Jan-14 31-Jan-14 31-Jan-14, SECTION-1
MH-CW-77 Pipe rack foundation work 23 09-Jan-14 31-Jan-14 Pipe rack foundation work
SECTION-6 22 10-Jan-14 31-Jan-14 31-Jan-14, SECTION-6
MH-CW-88 Pipe rack foundation work 22 10-Jan-14 31-Jan-14 Pipe rack foundation work
SECTION-7 4 01-Feb-14 04-Feb-14 04-Feb-14, SECTION-7
MH-CW-47 Pipe rack foundation work 4 01-Feb-14 04-Feb-14 Pipe rack foundation work
SECTION-4 8 13-Jan-14 20-Jan-14 20-Jan-14, SECTION-4
MH-CW-93 Pipe rack foundation work 8 13-Jan-14 20-Jan-14 Pipe rack foundation work
SECTION 9 - F
FOUNDATIONS 85 14-Nov-13 06-Feb-14 06-Feb-14, SECTION 9 - FOUNDATIONS
PILED FOUNDATION
FOUN 60 14-Nov-13 12-Jan-14 12-Jan-14, PILED FOUNDATION
BLOCK-40 FOUNDATIONS
F 50 14-Nov-13 02-Jan-14 02-Jan-14, BLOCK-40 FOUNDATIONS
EQUIPMENT 111-PB1 / 111-ME3 / 111-ME4
EQUIPMEN 50 14-Nov-13 02-Jan-14 02-Jan-14, EQUIPMENT 111-PB1 / 111-ME3 / 111-ME4
MH-CW-2 Foundation work 50 14-Nov-13 02-Jan-14 Foundation work
BLOCK-39 FOUNDATIONS
F 30 28-Nov-13 27-Dec-13 27-Dec-13, BLOCK-39 FOUNDATIONS
EQUIPMENT 111-E11 / 111-E12
EQUIPMEN 30 28-Nov-13 27-Dec-13 27-Dec-13, EQUIPMENT 111-E11 / 111-E12
MH-CW- Foundation work 30 28-Nov-13 27-Dec-13 Foundation work
BLOCK-38 FOUNDATIONS
F 15 29-Dec-13 12-Jan-14 12-Jan-14, BLOCK-38 FOUNDATIONS
OPEN PUM
PUMPING STATION NO:3 15 29-Dec-13 12-Jan-14 12-Jan-14, OPEN PUMPING STATION NO:3
MH-CW- Foundation work 15 29-Dec-13 12-Jan-14 Foundation work
NON-PILED F
FOUNDATION 24 14-Jan-14 06-Feb-14 06-Feb-14, NON-PILED FOUNDATION
BLOCK-38 FOUNDATIONS
F 24 14-Jan-14 06-Feb-14 06-Feb-14, BLOCK-38 FOUNDATIONS
EQUIPMENT 111-N6 A
EQUIPMEN 10 14-Jan-14 23-Jan-14 23-Jan-14, EQUIPMENT 111-N6 A
MH-CW-2 Foundation work 10 14-Jan-14 23-Jan-14 Foundation work
EQUIPMENT 111-N6 B
EQUIPMEN 10 17-Jan-14 26-Jan-14 26-Jan-14, EQUIPMENT 111-N6 B
MH-CW-3 Foundation work 10 17-Jan-14 26-Jan-14 Foundation work
EQUIPMENT 111-N7
EQUIPMEN 10 20-Jan-14 29-Jan-14 29-Jan-14, EQUIPMENT 111-N7
MH-CW-4 Foundation work 10 20-Jan-14 29-Jan-14 Foundation work
EQUIPMENT 111-N5 B
EQUIPMEN 10 23-Jan-14 01-Feb-14 01-Feb-14, EQUIPMENT 111-N5 B
MH-CW-2 Foundation work 10 23-Jan-14 01-Feb-14 Foundation work
EQUIPMENT 111-N5 A
EQUIPMEN 10 28-Jan-14 06-Feb-14 06-Feb-14, EQUIPMENT 111-N5 A
MH-CW- Foundation work 10 28-Jan-14 06-Feb-14 Foundation work
SECTION 3 - F
FOUNDATIONS 56 18-Nov-13 12-Jan-14 12-Jan-14, SECTION 3 - FOUNDATIONS
PILED FOUNDATION
FOUN 49 18-Nov-13 05-Jan-14 05-Jan-14, PILED FOUNDATION
BLOCK-12 FOUNDATIONS
F 45 18-Nov-13 01-Jan-14 01-Jan-14, BLOCK-12 FOUNDATIONS
EQUIPMENT 112-P1
EQUIPMEN 45 18-Nov-13 01-Jan-14 01-Jan-14, EQUIPMENT 112-P1
MH-CW-6 Foundation work 45 18-Nov-13 01-Jan-14 Foundation work
EQUIPMENT 111-P1
EQUIPMEN 30 25-Nov-13 24-Dec-13 24-Dec-13, EQUIPMENT 111-P1
MH-CW-8 Foundation work 30 25-Nov-13 24-Dec-13 Foundation work
BLOCK-13 FOUNDATIONS
F 38 29-Nov-13 05-Jan-14 05-Jan-14, BLOCK-13 FOUNDATIONS
STRUCTURE-K AND EQUIPMENTS 111-R1/R2
STRUCTUR 38 29-Nov-13 05-Jan-14 05-Jan-14, STRUCTURE-K AND EQUIPMENTS 111-R1/R2
MH-CW-9 Foundation work 38 29-Nov-13 05-Jan-14 Foundation work
NON-PILED F
FOUNDATION 5 08-Jan-14 12-Jan-14 12-Jan-14, NON-PILED FOUNDATION
BLOCK-14 FOUNDATIONS
F 5 08-Jan-14 12-Jan-14 12-Jan-14, BLOCK-14 FOUNDATIONS
EQUIPMENT 110-ME1
EQUIPMEN 5 08-Jan-14 12-Jan-14 12-Jan-14, EQUIPMENT 110-ME1
MH-CW-9 Foundation work 5 08-Jan-14 12-Jan-14 Foundation work
SECTION 8 - F
FOUNDATIONS 172 18-Nov-13 08-May-14 08-May-14, SECTION 8 - FOUNDATIONS
PILED FOUNDATION
FOUN 128 18-Nov-13 25-Mar-14 25-Mar-14, PILED FOUNDATION
BLOCK-36 FOUNDATIONS
F 90 18-Nov-13 15-Feb-14 15-Feb-14, BLOCK-36 FOUNDATIONS
STRUCTURE-R
STRUCTUR 60 18-Nov-13 16-Jan-14 16-Jan-14, STRUCTURE-R

Primary Baseline Actual Work Critical Remaining Work Page 2 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-CW-4 Foundation work 60 18-Nov-13 16-Jan-14 Foundation work
EQUIPMENT 112-E4
EQUIPMEN 75 03-Dec-13 15-Feb-14 15-Feb-14, EQUIPMENT 112-E4
MH-CW-5 Foundation work 75 03-Dec-13 15-Feb-14 Foundation work
BLOCK-37 FOUNDATIONS
F 60 18-Dec-13 15-Feb-14 15-Feb-14, BLOCK-37 FOUNDATIONS
EQUIPMENT 112-K4
EQUIPMEN 60 18-Dec-13 15-Feb-14 15-Feb-14, EQUIPMENT 112-K4
MH-CW-3 Foundation work 60 18-Dec-13 15-Feb-14 Foundation work
EQUIPMENT 112-K5 / 112-K7
EQUIPMEN 10 01-Jan-14 10-Jan-14 10-Jan-14, EQUIPMENT 112-K5 / 112-K7
MH-CW-4 Foundation work 10 01-Jan-14 10-Jan-14 Foundation work
EQUIPMENT 112-E3
EQUIPMEN 12 14-Jan-14 25-Jan-14 25-Jan-14, EQUIPMENT 112-E3
MH-CW-5 Foundation work 12 14-Jan-14 25-Jan-14 Foundation work
BLOCK-35 FOUNDATIONS
F 45 27-Jan-14 12-Mar-14 12-Mar-14, BLOCK-35 FOUNDATIONS
EQUIPMENT 112-K1/K3
EQUIPMEN 45 27-Jan-14 12-Mar-14 12-Mar-14, EQUIPMENT 112-K1/K3
MH-CW-5 Foundation work 45 27-Jan-14 12-Mar-14 Foundation work
EQUIPMENT 112-K2 & K8 STAIRCASE
EQUIPMEN 18 06-Feb-14 23-Feb-14 23-Feb-14, EQUIPMENT 112-K2 & K8 STAIRCASE
MH-CW- Foundation work 18 06-Feb-14 23-Feb-14 Foundation work
EQUIPMENT 112-K8
EQUIPMEN 12 13-Feb-14 24-Feb-14 24-Feb-14, EQUIPMENT 112-K8
MH-CW- Foundation work 12 13-Feb-14 24-Feb-14 Foundation work
EQUIPMENT 112-K2
EQUIPMEN 10 20-Feb-14 01-Mar-14 01-Mar-14, EQUIPMENT 112-K2
MH-CW- Foundation work 10 20-Feb-14 01-Mar-14 Foundation work
EQUIPMENT 112-K6
EQUIPMEN 10 27-Feb-14 08-Mar-14 08-Mar-14, EQUIPMENT 112-K6
MH-CW- Foundation work 10 27-Feb-14 08-Mar-14 Foundation work
BLOCK-33 FOUNDATIONS
F 16 10-Mar-14 25-Mar-14 25-Mar-14, BLOCK-33 FOUNDATIONS
STRUCTURE-E
STRUCTUR 16 10-Mar-14 25-Mar-14 25-Mar-14, STRUCTURE-E
MH-CW- Foundation work 16 10-Mar-14 25-Mar-14 Foundation work
NON-PILED F
FOUNDATION 43 27-Mar-14 08-May-14 08-May-14, NON-PILED FOUNDATION
BLOCK-36 FOUNDATIONS
F 34 27-Mar-14 29-Apr-14 29-Apr-14, BLOCK-36 FOUNDATIONS
EQUIPMENT 112-T9
EQUIPMEN 3 27-Mar-14 29-Mar-14 29-Mar-14, EQUIPMENT 112-T9
MH-CW-9 Foundation work 3 27-Mar-14 29-Mar-14 Foundation work
EQUIPMENT 112-ME4,ME5
EQUIPMEN 3 31-Mar-14 02-Apr-14 02-Apr-14, EQUIPMENT 112-ME4,ME5
MH-CW-6 Foundation work 3 31-Mar-14 02-Apr-14 Foundation work
EQUIPMENT 112-T10
EQUIPMEN 3 04-Apr-14 06-Apr-14 06-Apr-14, EQUIPMENT 112-T10
MH-CW-9 Foundation work 3 04-Apr-14 06-Apr-14 Foundation work
EQUIPMENT 112-T11
EQUIPMEN 6 13-Apr-14 18-Apr-14 18-Apr-14, EQUIPMENT 112-T11
MH-CW- Foundation work 6 13-Apr-14 18-Apr-14 Foundation work
EQUIPMENT 112-T7
EQUIPMEN 4 08-Apr-14 11-Apr-14 11-Apr-14, EQUIPMENT 112-T7
MH-CW-7 Foundation work 4 08-Apr-14 11-Apr-14 Foundation work
EQUIPMENT 112-Kh10
EQUIPMEN 10 20-Apr-14 29-Apr-14 29-Apr-14, EQUIPMENT 112-Kh10
MH-CW- Foundation work 10 20-Apr-14 29-Apr-14 Foundation work
BLOCK-33 FOUNDATIONS
F 8 01-May-14 08-May-14 08-May-14, BLOCK-33 FOUNDATIONS
EQUIPMENT 112-T12
EQUIPMEN 3 01-May-14 03-May-14 03-May-14, EQUIPMENT 112-T12
MH-CW- Foundation work 3 01-May-14 03-May-14 Foundation work
EQUIPMENT 112-Kh2
EQUIPMEN 4 05-May-14 08-May-14 08-May-14, EQUIPMENT 112-Kh2
MH-CW- Foundation work 4 05-May-14 08-May-14 Foundation work
SECTION 7 - F
FOUNDATIONS 242 23-Nov-13 22-Jul-14 22-Jul-14, SECTION 7 - FOUNDATIONS
PILED FOUNDATION
FOUN 50 23-Nov-13 11-Jan-14 11-Jan-14, PILED FOUNDATION
BLOCK-31 FOUNDATIONS
F 45 23-Nov-13 06-Jan-14 06-Jan-14, BLOCK-31 FOUNDATIONS
STRUCTURE-Zh
STRUCTUR 45 23-Nov-13 06-Jan-14 06-Jan-14, STRUCTURE-Zh
MH-CW-3 Foundation work 45 23-Nov-13 06-Jan-14 Foundation work
BLOCK-30 FOUNDATIONS
F 35 08-Dec-13 11-Jan-14 11-Jan-14, BLOCK-30 FOUNDATIONS
STRUCTURE-N
STRUCTUR 35 08-Dec-13 11-Jan-14 11-Jan-14, STRUCTURE-N
MH-CW-2 Foundation work 35 08-Dec-13 11-Jan-14 Foundation work
NON-PILED F
FOUNDATION 191 13-Jan-14 22-Jul-14 22-Jul-14, NON-PILED FOUNDATION
BLOCK-31 FOUNDATIONS
F 125 13-Jan-14 17-May-14 17-May-14, BLOCK-31 FOUNDATIONS

Primary Baseline Actual Work Critical Remaining Work Page 3 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
EQUIPMENT 112-N26
EQUIPMEN 5 13-Jan-14 17-Jan-14 17-Jan-14, EQUIPMENT 112-N26
MH-CW- Foundation work 5 13-Jan-14 17-Jan-14 Foundation work
EQUIPMENT 112-N6 A
EQUIPMEN 5 19-Jan-14 23-Jan-14 23-Jan-14, EQUIPMENT 112-N6 A
MH-CW-7 Foundation work 5 19-Jan-14 23-Jan-14 Foundation work
EQUIPMENT 112-N6 B
EQUIPMEN 5 25-Jan-14 29-Jan-14 29-Jan-14, EQUIPMENT 112-N6 B
MH-CW-8 Foundation work 5 25-Jan-14 29-Jan-14 Foundation work
EQUIPMENT 112-N4 A
EQUIPMEN 5 31-Jan-14 04-Feb-14 04-Feb-14, EQUIPMENT 112-N4 A
MH-CW-5 Foundation work 5 31-Jan-14 04-Feb-14 Foundation work
EQUIPMENT 112-N4 B
EQUIPMEN 5 06-Feb-14 10-Feb-14 10-Feb-14, EQUIPMENT 112-N4 B
MH-CW-6 Foundation work 5 06-Feb-14 10-Feb-14 Foundation work
EQUIPMENT 112-N9 A
EQUIPMEN 5 12-Feb-14 16-Feb-14 16-Feb-14, EQUIPMENT 112-N9 A
MH-CW- Foundation work 5 12-Feb-14 16-Feb-14 Foundation work
EQUIPMENT 112-N9 B
EQUIPMEN 5 18-Feb-14 22-Feb-14 22-Feb-14, EQUIPMENT 112-N9 B
MH-CW- Foundation work 5 18-Feb-14 22-Feb-14 Foundation work
EQUIPMENT 112-N8 A
EQUIPMEN 5 24-Feb-14 28-Feb-14 28-Feb-14, EQUIPMENT 112-N8 A
MH-CW-9 Foundation work 5 24-Feb-14 28-Feb-14 Foundation work
EQUIPMENT 112-N8 B
EQUIPMEN 5 02-Mar-14 06-Mar-14 06-Mar-14, EQUIPMENT 112-N8 B
MH-CW-9 Foundation work 5 02-Mar-14 06-Mar-14 Foundation work
EQUIPMENT 112-N10 A
EQUIPMEN 5 08-Mar-14 12-Mar-14 12-Mar-14, EQUIPMENT 112-N10 A
MH-CW- Foundation work 5 08-Mar-14 12-Mar-14 Foundation work
EQUIPMENT 112-N10 B
EQUIPMEN 5 14-Mar-14 18-Mar-14 18-Mar-14, EQUIPMENT 112-N10 B
MH-CW- Foundation work 5 14-Mar-14 18-Mar-14 Foundation work
EQUIPMENT 112-N7 A
EQUIPMEN 5 20-Mar-14 24-Mar-14 24-Mar-14, EQUIPMENT 112-N7 A
MH-CW-8 Foundation work 5 20-Mar-14 24-Mar-14 Foundation work
EQUIPMENT 112-N7 B
EQUIPMEN 5 26-Mar-14 30-Mar-14 30-Mar-14, EQUIPMENT 112-N7 B
MH-CW-8 Foundation work 5 26-Mar-14 30-Mar-14 Foundation work
EQUIPMENT 112-N11 A
EQUIPMEN 5 01-Apr-14 05-Apr-14 05-Apr-14, EQUIPMENT 112-N11 A
MH-CW- Foundation work 5 01-Apr-14 05-Apr-14 Foundation work
EQUIPMENT 112-N11 B
EQUIPMEN 5 07-Apr-14 11-Apr-14 11-Apr-14, EQUIPMENT 112-N11 B
MH-CW- Foundation work 5 07-Apr-14 11-Apr-14 Foundation work
EQUIPMENT 112-N12 A
EQUIPMEN 5 13-Apr-14 17-Apr-14 17-Apr-14, EQUIPMENT 112-N12 A
MH-CW- Foundation work 5 13-Apr-14 17-Apr-14 Foundation work
EQUIPMENT 112-N12 B
EQUIPMEN 5 19-Apr-14 23-Apr-14 23-Apr-14, EQUIPMENT 112-N12 B
MH-CW- Foundation work 5 19-Apr-14 23-Apr-14 Foundation work
EQUIPMENT 112-N20 A
EQUIPMEN 5 25-Apr-14 29-Apr-14 29-Apr-14, EQUIPMENT 112-N20 A
MH-CW- Foundation work 5 25-Apr-14 29-Apr-14 Foundation work
EQUIPMENT 112-N20 B
EQUIPMEN 5 01-May-14 05-May-14 05-May-14, EQUIPMENT 112-N20 B
MH-CW- Foundation work 5 01-May-14 05-May-14 Foundation work
EQUIPMENT 112-N18 A
EQUIPMEN 5 07-May-14 11-May-14 11-May-14, EQUIPMENT 112-N18 A
MH-CW- Foundation work 5 07-May-14 11-May-14 Foundation work
EQUIPMENT 112-N18 B
EQUIPMEN 5 13-May-14 17-May-14 17-May-14, EQUIPMENT 112-N18 B
MH-CW- Foundation work 5 13-May-14 17-May-14 Foundation work
BLOCK-30 FOUNDATIONS
F 65 19-May-14 22-Jul-14 22-Jul-14, BLOCK-30 FOUNDATIONS
EQUIPMENT 112-N3 A
EQUIPMEN 5 19-May-14 23-May-14 23-May-14, EQUIPMENT 112-N3 A
MH-CW-3 Foundation work 5 19-May-14 23-May-14 Foundation work
EQUIPMENT 112-N3 B
EQUIPMEN 5 25-May-14 29-May-14 29-May-14, EQUIPMENT 112-N3 B
MH-CW-4 Foundation work 5 25-May-14 29-May-14 Foundation work
EQUIPMENT 112-N2 A
EQUIPMEN 5 31-May-14 04-Jun-14 04-Jun-14, EQUIPMENT 112-N2 A
MH-CW-2 Foundation work 5 31-May-14 04-Jun-14 Foundation work
EQUIPMENT 112-N2 B
EQUIPMEN 5 06-Jun-14 10-Jun-14 10-Jun-14, EQUIPMENT 112-N2 B
MH-CW-2 Foundation work 5 06-Jun-14 10-Jun-14 Foundation work
EQUIPMENT 112-N1 A
EQUIPMEN 5 12-Jun-14 16-Jun-14 16-Jun-14, EQUIPMENT 112-N1 A

Primary Baseline Actual Work Critical Remaining Work Page 4 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-CW- Foundation work 5 12-Jun-14 16-Jun-14 Foundation work
EQUIPMENT 112-N1 B
EQUIPMEN 5 18-Jun-14 22-Jun-14 22-Jun-14, EQUIPMENT 112-N1 B
MH-CW- Foundation work 5 18-Jun-14 22-Jun-14 Foundation work
EQUIPMENT 112-N13 A
EQUIPMEN 5 24-Jun-14 28-Jun-14 28-Jun-14, EQUIPMENT 112-N13 A
MH-CW-7 Foundation work 5 24-Jun-14 28-Jun-14 Foundation work
EQUIPMENT 112-N13 B
EQUIPMEN 5 30-Jun-14 04-Jul-14 04-Jul-14, EQUIPMENT 112-N13 B
MH-CW-8 Foundation work 5 30-Jun-14 04-Jul-14 Foundation work
EQUIPMENT 112-N5 A/N5 B
EQUIPMEN 6 06-Jul-14 11-Jul-14 11-Jul-14, EQUIPMENT 112-N5 A/N5 B
MH-CW-4 Foundation work 6 06-Jul-14 11-Jul-14 Foundation work
EQUIPMENT 111-ME7
EQUIPMEN 10 13-Jul-14 22-Jul-14 22-Jul-14, EQUIPMENT 111-ME7
MH-CW-5 Foundation work 10 13-Jul-14 22-Jul-14 Foundation work
SECTION 2 - F
FOUNDATIONS 251 28-Nov-13 05-Aug-14 05-Aug-14, SECTION 2 - FOUNDATIONS
PILED FOUNDATION
FOUN 230 28-Nov-13 15-Jul-14 15-Jul-14, PILED FOUNDATION
BLOCK-11 FOUNDATIONS
F 33 28-Nov-13 30-Dec-13 30-Dec-13, BLOCK-11 FOUNDATIONS
STRUCTURE-V
STRUCTUR 25 28-Nov-13 22-Dec-13 22-Dec-13, STRUCTURE-V
MH-CW-4 Foundation work 25 28-Nov-13 22-Dec-13 Foundation work
EQUIPMENT 111-T3
EQUIPMEN 8 12-Dec-13 19-Dec-13 19-Dec-13, EQUIPMENT 111-T3
MH-CW-4 Foundation work 8 12-Dec-13 19-Dec-13 Foundation work
EQUIPMENT 111-T5 A/B
EQUIPMEN 8 14-Dec-13 21-Dec-13 21-Dec-13, EQUIPMENT 111-T5 A/B
MH-CW-5 Foundation work 8 14-Dec-13 21-Dec-13 Foundation work
EQUIPMENT 111-T6 A/B
EQUIPMEN 8 23-Dec-13 30-Dec-13 30-Dec-13, EQUIPMENT 111-T6 A/B
MH-CW-7 Foundation work 8 23-Dec-13 30-Dec-13 Foundation work
BLOCK-8 FOUNDATIONS
F 20 01-Jan-14 20-Jan-14 20-Jan-14, BLOCK-8 FOUNDATIONS
STRUCTURE-T
STRUCTUR 10 01-Jan-14 10-Jan-14 10-Jan-14, STRUCTURE-T
MH-CW- Foundation work 10 01-Jan-14 10-Jan-14 Foundation work
EQUIPMENT 111-E2/E3
EQUIPMEN 15 06-Jan-14 20-Jan-14 20-Jan-14, EQUIPMENT 111-E2/E3
MH-CW- Foundation work 15 06-Jan-14 20-Jan-14 Foundation work
BLOCK-10 FOUNDATIONS
F 54 22-Jan-14 16-Mar-14 16-Mar-14, BLOCK-10 FOUNDATIONS
STRUCTURE-G
STRUCTUR 45 22-Jan-14 07-Mar-14 07-Mar-14, STRUCTURE-G
MH-CW-4 Foundation work 45 22-Jan-14 07-Mar-14 Foundation work
EQUIPMENT 111-E4
EQUIPMEN 8 09-Mar-14 16-Mar-14 16-Mar-14, EQUIPMENT 111-E4
MH-CW- Foundation work 8 09-Mar-14 16-Mar-14 Foundation work
BLOCK-9 FOUNDATIONS
F 25 18-Mar-14 11-Apr-14 11-Apr-14, BLOCK-9 FOUNDATIONS
STRUCTURE-A
STRUCTUR 13 18-Mar-14 30-Mar-14 30-Mar-14, STRUCTURE-A
MH-CW- Foundation work 13 18-Mar-14 30-Mar-14 Foundation work
EQUIPMENT 111-T7
EQUIPMEN 8 23-Mar-14 30-Mar-14 30-Mar-14, EQUIPMENT 111-T7
MH-CW- Foundation work 8 23-Mar-14 30-Mar-14 Foundation work
EQUIPMENT 111-T8 A/B
EQUIPMEN 8 26-Mar-14 02-Apr-14 02-Apr-14, EQUIPMENT 111-T8 A/B
MH-CW- Foundation work 8 26-Mar-14 02-Apr-14 Foundation work
EQUIPMENT 111-T10 A/B
EQUIPMEN 8 04-Apr-14 11-Apr-14 11-Apr-14, EQUIPMENT 111-T10 A/B
MH-CW- Foundation work 8 04-Apr-14 11-Apr-14 Foundation work
BLOCK-7 FOUNDATIONS
F 12 13-Apr-14 24-Apr-14 24-Apr-14, BLOCK-7 FOUNDATIONS
EQUIPMENT 111-E5 & STEEL MAINTENANCE PLATFORM
EQUIPMEN 12 13-Apr-14 24-Apr-14 24-Apr-14, EQUIPMENT 111-E5 & STEEL MAINTENANCE PLATFORM
MH-CW- Foundation work 12 13-Apr-14 24-Apr-14 Foundation work
BLOCK-5 FOUNDATIONS
F 32 26-Apr-14 27-May-14 27-May-14, BLOCK-5 FOUNDATIONS
OPEN PUMPING
PUM STATITON NO:2 20 26-Apr-14 15-May-14 15-May-14, OPEN PUMPING STATITON NO:2
MH-CW- Foundation work 20 26-Apr-14 15-May-14 Foundation work
EQUIPMENT 111-N1 A/B
EQUIPMEN 25 03-May-14 27-May-14 27-May-14, EQUIPMENT 111-N1 A/B
MH-CW- Foundation work 25 03-May-14 27-May-14 Foundation work
BLOCK-6 FOUNDATIONS
F 20 29-May-14 17-Jun-14 17-Jun-14, BLOCK-6 FOUNDATIONS
STRUCTURE-B, 111-K1 & 111-KH1
STRUCTUR 20 29-May-14 17-Jun-14 17-Jun-14, STRUCTURE-B, 111-K1 & 111-KH1
MH-CW- Foundation work 20 29-May-14 17-Jun-14 Foundation work
BLOCK-3 FOUNDATIONS
F 8 18-Jun-14 25-Jun-14 25-Jun-14, BLOCK-3 FOUNDATIONS

Primary Baseline Actual Work Critical Remaining Work Page 5 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
OPEN PUMPING
PUM STATITON NO:1 8 18-Jun-14 25-Jun-14 25-Jun-14, OPEN PUMPING STATITON NO:1
MH-CW- Foundation work 8 18-Jun-14 25-Jun-14 Foundation work
BLOCK-4 FOUNDATIONS
F 20 26-Jun-14 15-Jul-14 15-Jul-14, BLOCK-4 FOUNDATIONS
EQUIPMENT 111-E1/E10
EQUIPMEN 20 26-Jun-14 15-Jul-14 15-Jul-14, EQUIPMENT 111-E1/E10
MH-CW- Foundation work 20 26-Jun-14 15-Jul-14 Foundation work
NON-PILED F
FOUNDATION 21 16-Jul-14 05-Aug-14 05-Aug-14, NON-PILED FOUNDATION
BLOCK-3 FOUNDATIONS
F 21 16-Jul-14 05-Aug-14 05-Aug-14, BLOCK-3 FOUNDATIONS
EQUIPMENT 111-N2 A/B
EQUIPMEN 5 16-Jul-14 20-Jul-14 20-Jul-14, EQUIPMENT 111-N2 A/B
MH-CW- Foundation work 5 16-Jul-14 20-Jul-14 Foundation work
EQUIPMENT 111-N3 A/B
EQUIPMEN 5 22-Jul-14 26-Jul-14 26-Jul-14, EQUIPMENT 111-N3 A/B
MH-CW- Foundation work 5 22-Jul-14 26-Jul-14 Foundation work
EQUIPMENT 111-N4 A/B
EQUIPMEN 5 28-Jul-14 01-Aug-14 01-Aug-14, EQUIPMENT 111-N4 A/B
MH-CW- Foundation work 5 28-Jul-14 01-Aug-14 Foundation work
EQUIPMENT 111-N9
EQUIPMEN 5 01-Aug-14 05-Aug-14 05-Aug-14, EQUIPMENT 111-N9
MH-CW- Foundation work 5 01-Aug-14 05-Aug-14 Foundation work
SECTION 5 - F
FOUNDATIONS 67 27-Dec-13 03-Mar-14 03-Mar-14, SECTION 5 - FOUNDATIONS
PILED FOUNDATION
FOUN 22 27-Dec-13 17-Jan-14 17-Jan-14, PILED FOUNDATION
BLOCK-18 FOUNDATIONS
F 22 27-Dec-13 17-Jan-14 17-Jan-14, BLOCK-18 FOUNDATIONS
STRUCTURE-D
STRUCTUR 22 27-Dec-13 17-Jan-14 17-Jan-14, STRUCTURE-D
MH-CW- Foundation work 22 27-Dec-13 17-Jan-14 Foundation work
NON-PILED F
FOUNDATION 44 19-Jan-14 03-Mar-14 03-Mar-14, NON-PILED FOUNDATION
BLOCK-18 FOUNDATIONS
F 35 19-Jan-14 22-Feb-14 22-Feb-14, BLOCK-18 FOUNDATIONS
EQUIPMENT 112-N15 A/B
EQUIPMEN 5 19-Jan-14 23-Jan-14 23-Jan-14, EQUIPMENT 112-N15 A/B
MH-CW- Foundation work 5 19-Jan-14 23-Jan-14 Foundation work
EQUIPMENT 112-N16 A/B
EQUIPMEN 5 25-Jan-14 29-Jan-14 29-Jan-14, EQUIPMENT 112-N16 A/B
MH-CW- Foundation work 5 25-Jan-14 29-Jan-14 Foundation work
EQUIPMENT 112-N17 A/B
EQUIPMEN 5 31-Jan-14 04-Feb-14 04-Feb-14, EQUIPMENT 112-N17 A/B
MH-CW- Foundation work 5 31-Jan-14 04-Feb-14 Foundation work
EQUIPMENT 112-N14 A/B
EQUIPMEN 5 06-Feb-14 10-Feb-14 10-Feb-14, EQUIPMENT 112-N14 A/B
MH-CW- Foundation work 5 06-Feb-14 10-Feb-14 Foundation work
EQUIPMENT 112-N19 A/B
EQUIPMEN 5 12-Feb-14 16-Feb-14 16-Feb-14, EQUIPMENT 112-N19 A/B
MH-CW- Foundation work 5 12-Feb-14 16-Feb-14 Foundation work
EQUIPMENT 110-N7 A/B
EQUIPMEN 5 18-Feb-14 22-Feb-14 22-Feb-14, EQUIPMENT 110-N7 A/B
MH-CW- Foundation work 5 18-Feb-14 22-Feb-14 Foundation work
BLOCK-17 FOUNDATIONS
F 8 24-Feb-14 03-Mar-14 03-Mar-14, BLOCK-17 FOUNDATIONS
EQUIPMENT 111-ME1
EQUIPMEN 5 24-Feb-14 28-Feb-14 28-Feb-14, EQUIPMENT 111-ME1
MH-CW- Foundation work 5 24-Feb-14 28-Feb-14 Foundation work
EQUIPMENT 111-F1 A/B
EQUIPMEN 5 27-Feb-14 03-Mar-14 03-Mar-14, EQUIPMENT 111-F1 A/B
A10100 Foundation work 5 27-Feb-14 03-Mar-14 Foundation work
SECTION 4 - F
FOUNDATIONS 25 27-Jan-14 20-Feb-14 20-Feb-14, SECTION 4 - FOUNDATIONS
PILED FOUNDATION
FOUN 25 27-Jan-14 20-Feb-14 20-Feb-14, PILED FOUNDATION
BLOCK-16 FOUNDATIONS
F 22 27-Jan-14 17-Feb-14 17-Feb-14, BLOCK-16 FOUNDATIONS
GAS COMP
COMPRESSOR 113-DK1 22 27-Jan-14 17-Feb-14 17-Feb-14, GAS COMPRESSOR 113-DK1
MH-CW- Foundation work 22 27-Jan-14 17-Feb-14 Foundation work
BLOCK-15 FOUNDATIONS
F 20 01-Feb-14 20-Feb-14 20-Feb-14, BLOCK-15 FOUNDATIONS
PSA UNIT 20 01-Feb-14 20-Feb-14 20-Feb-14, PSA UNIT
MH-CW- Foundation work 20 01-Feb-14 20-Feb-14 Foundation work
SECTION 6 - F
FOUNDATIONS 123 15-Jan-14 17-May-14 17-May-14, SECTION 6 - FOUNDATIONS
PILED FOUNDATION
FOUN 83 15-Jan-14 07-Apr-14 07-Apr-14, PILED FOUNDATION
BLOCK-29 FOUNDATIONS
F 7 15-Jan-14 21-Jan-14 21-Jan-14, BLOCK-29 FOUNDATIONS
EQUIPMENT 112-K9
EQUIPMEN 7 15-Jan-14 21-Jan-14 21-Jan-14, EQUIPMENT 112-K9
MH-CW- Foundation work 7 15-Jan-14 21-Jan-14 Foundation work
BLOCK-28 FOUNDATIONS
F 7 23-Jan-14 29-Jan-14 29-Jan-14, BLOCK-28 FOUNDATIONS
EQUIPMENT 112-K10
EQUIPMEN 7 23-Jan-14 29-Jan-14 29-Jan-14, EQUIPMENT 112-K10
Primary Baseline Actual Work Critical Remaining Work Page 6 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-CW- Foundation work 7 23-Jan-14 29-Jan-14 Foundation work
BLOCK-26 FOUNDATIONS
F 15 28-Jan-14 11-Feb-14 11-Feb-14, BLOCK-26 FOUNDATIONS
STRUCTURE-I
STRUCTUR 15 28-Jan-14 11-Feb-14 11-Feb-14, STRUCTURE-I
MH-CW- Foundation work 15 28-Jan-14 11-Feb-14 Foundation work
BLOCK-24 FOUNDATIONS
F 11 13-Feb-14 23-Feb-14 23-Feb-14, BLOCK-24 FOUNDATIONS
EQUIPMENT 112-K11
EQUIPMEN 5 13-Feb-14 17-Feb-14 17-Feb-14, EQUIPMENT 112-K11
MH-CW- Foundation work 5 13-Feb-14 17-Feb-14 Foundation work
EQUIPMENT 110-E11
EQUIPMEN 5 19-Feb-14 23-Feb-14 23-Feb-14, EQUIPMENT 110-E11
MH-CW- Foundation work 5 19-Feb-14 23-Feb-14 Foundation work
BLOCK-21 FOUNDATIONS
F 15 26-Feb-14 12-Mar-14 12-Mar-14, BLOCK-21 FOUNDATIONS
EQUIPMENT 110-E7
EQUIPMEN 15 26-Feb-14 12-Mar-14 12-Mar-14, EQUIPMENT 110-E7
MH-CW- Foundation work 15 26-Feb-14 12-Mar-14 Foundation work
BLOCK-22 FOUNDATIONS
F 7 14-Mar-14 20-Mar-14 20-Mar-14, BLOCK-22 FOUNDATIONS
STRUCTURE-M
STRUCTUR 7 14-Mar-14 20-Mar-14 20-Mar-14, STRUCTURE-M
MH-CW- Foundation work 7 14-Mar-14 20-Mar-14 Foundation work
BLOCK-20 FOUNDATIONS
F 7 16-Mar-14 22-Mar-14 22-Mar-14, BLOCK-20 FOUNDATIONS
OPEN PUM
PUMPING STATION NO:4 5 16-Mar-14 20-Mar-14 20-Mar-14, OPEN PUMPING STATION NO:4
MH-CW- Foundation work 5 16-Mar-14 20-Mar-14 Foundation work
EQUIPMENT 110-N6 A/B
EQUIPMEN 5 18-Mar-14 22-Mar-14 22-Mar-14, EQUIPMENT 110-N6 A/B
MH-CW- Foundation work 5 18-Mar-14 22-Mar-14 Foundation work
BLOCK-19 FOUNDATIONS
F 15 24-Mar-14 07-Apr-14 07-Apr-14, BLOCK-19 FOUNDATIONS
STRUCTURE-U
STRUCTUR 12 24-Mar-14 04-Apr-14 04-Apr-14, STRUCTURE-U
MH-CW- Foundation work 12 24-Mar-14 04-Apr-14 Foundation work
EQUIPMENT 110-E5 A/B, E6
EQUIPMEN 15 24-Mar-14 07-Apr-14 07-Apr-14, EQUIPMENT 110-E5 A/B, E6
MH-CW- Foundation work 15 24-Mar-14 07-Apr-14 Foundation work
NON-PILED F
FOUNDATION 39 09-Apr-14 17-May-14 17-May-14, NON-PILED FOUNDATION
BLOCK-27 FOUNDATIONS
F 3 09-Apr-14 11-Apr-14 11-Apr-14, BLOCK-27 FOUNDATIONS
EQUIPMENT FOUNDATION 112-T13
EQUIPMEN 3 09-Apr-14 11-Apr-14 11-Apr-14, EQUIPMENT FOUNDATION 112-T13
MH-CW- Foundation work 3 09-Apr-14 11-Apr-14 Foundation work
BLOCK-29 FOUNDATIONS
F 3 13-Apr-14 15-Apr-14 15-Apr-14, BLOCK-29 FOUNDATIONS
EQUIPMENT 112-T14
EQUIPMEN 3 13-Apr-14 15-Apr-14 15-Apr-14, EQUIPMENT 112-T14
MH-CW- Foundation work 3 13-Apr-14 15-Apr-14 Foundation work
BLOCK-26 FOUNDATIONS
F 10 17-Apr-14 26-Apr-14 26-Apr-14, BLOCK-26 FOUNDATIONS
EQUIPMENT 112-KH5
EQUIPMEN 3 17-Apr-14 19-Apr-14 19-Apr-14, EQUIPMENT 112-KH5
MH-CW- Foundation work 3 17-Apr-14 19-Apr-14 Foundation work
EQUIPMENT 112-KH6
EQUIPMEN 3 21-Apr-14 23-Apr-14 23-Apr-14, EQUIPMENT 112-KH6
MH-CW- Foundation work 3 21-Apr-14 23-Apr-14 Foundation work
EQUIPMENT 112-KH8
EQUIPMEN 2 25-Apr-14 26-Apr-14 26-Apr-14, EQUIPMENT 112-KH8
MH-CW- Foundation work 2 25-Apr-14 26-Apr-14 Foundation work
BLOCK-22 FOUNDATIONS
F 4 28-Apr-14 01-May-14 01-May-14, BLOCK-22 FOUNDATIONS
EQUIPMENT 110-E13
EQUIPMEN 4 28-Apr-14 01-May-14 01-May-14, EQUIPMENT 110-E13
MH-CW- Foundation work 4 28-Apr-14 01-May-14 Foundation work
BLOCK-23 FOUNDATIONS
F 7 03-May-14 09-May-14 09-May-14, BLOCK-23 FOUNDATIONS
ANALYZER SHELTER 7 03-May-14 09-May-14 09-May-14, ANALYZER SHELTER
MH-CW- Foundation work 7 03-May-14 09-May-14 Foundation work
BLOCK-20 FOUNDATIONS
F 7 11-May-14 17-May-14 17-May-14, BLOCK-20 FOUNDATIONS
EQUIPMENT 110-N5 A/B/C/D
EQUIPMEN 7 11-May-14 17-May-14 17-May-14, EQUIPMENT 110-N5 A/B/C/D
MH-CW- Foundation work 7 11-May-14 17-May-14 Foundation work
SECTION 1 - F
FOUNDATIONS 80 18-Jan-14 07-Apr-14 07-Apr-14, SECTION 1 - FOUNDATIONS
PILED FOUNDATION
FOUN 75 18-Jan-14 02-Apr-14 02-Apr-14, PILED FOUNDATION
BLOCK-1 FOUNDATIONS
F 75 18-Jan-14 02-Apr-14 02-Apr-14, BLOCK-1 FOUNDATIONS
COMPRESSOR STATION WITH TRANSFORMER SUBSTATION AND LOCAL CO
COMPRES 75 18-Jan-14 02-Apr-14 02-Apr-14, COMPRESSOR STATION WITH TRANSFORMER SUBSTATION AND LOCAL CONTROL RO
MH-CW-3 Foundation work 75 18-Jan-14 02-Apr-14 Foundation work

Primary Baseline Actual Work Critical Remaining Work Page 7 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
EQUIPMENT 111-TsK1
EQUIPMEN 40 28-Jan-14 08-Mar-14 08-Mar-14, EQUIPMENT 111-TsK1
MH-CW-8 Foundation work 40 28-Jan-14 08-Mar-14 Foundation work
EQUIPMENT 111-DK1 A/B
EQUIPMEN 40 31-Jan-14 11-Mar-14 11-Mar-14, EQUIPMENT 111-DK1 A/B
MH-CW-8 Foundation work 40 31-Jan-14 11-Mar-14 Foundation work
PLATFORM 111-TsK1 4 10-Mar-14 13-Mar-14 13-Mar-14, PLATFORM 111-TsK1
MH-CW- Foundation work 4 10-Mar-14 13-Mar-14 Foundation work
BLOCK-2 FOUNDATIONS
F 4 15-Mar-14 18-Mar-14 18-Mar-14, BLOCK-2 FOUNDATIONS
EQUIPMENT 111-E6
EQUIPMEN 4 15-Mar-14 18-Mar-14 18-Mar-14, EQUIPMENT 111-E6
MH-CW-7 Foundation work 4 15-Mar-14 18-Mar-14 Foundation work
NON-PILED F
FOUNDATION 19 20-Mar-14 07-Apr-14 07-Apr-14, NON-PILED FOUNDATION
BLOCK-1 FOUNDATIONS
F 13 20-Mar-14 01-Apr-14 01-Apr-14, BLOCK-1 FOUNDATIONS
EQUIPMENT 111-ME9
EQUIPMEN 3 20-Mar-14 22-Mar-14 22-Mar-14, EQUIPMENT 111-ME9
MH-CW- Foundation work 3 20-Mar-14 22-Mar-14 Foundation work
EQUIPMENT 111-E7/E8
EQUIPMEN 3 24-Mar-14 26-Mar-14 26-Mar-14, EQUIPMENT 111-E7/E8
MH-CW- Foundation work 3 24-Mar-14 26-Mar-14 Foundation work
EQUIPMENT 111-E6 STEEL MAINTENANCE PLATFORM
EQUIPMEN 4 28-Mar-14 31-Mar-14 31-Mar-14, EQUIPMENT 111-E6 STEEL MAINTENANCE PLATFORM
A10110 Foundation work 4 28-Mar-14 31-Mar-14 Foundation work
EQUIPMENT 111-N10A/N10B
EQUIPMEN 4 29-Mar-14 01-Apr-14 01-Apr-14, EQUIPMENT 111-N10A/N10B
A10120 Foundation work 4 29-Mar-14 01-Apr-14 Foundation work
BLOCK-2 FOUNDATIONS
F 8 31-Mar-14 07-Apr-14 07-Apr-14, BLOCK-2 FOUNDATIONS
EQUIPMENT 111-AVO3
EQUIPMEN 3 31-Mar-14 02-Apr-14 02-Apr-14, EQUIPMENT 111-AVO3
MH-CW-6 Foundation work 3 31-Mar-14 02-Apr-14 Foundation work
EQUIPMENT 111-Kh3
EQUIPMEN 3 01-Apr-14 03-Apr-14 03-Apr-14, EQUIPMENT 111-Kh3
MH-CW-6 Foundation work 3 01-Apr-14 03-Apr-14 Foundation work
EMERGENCY GENERATOR
EMERGEN 4 04-Apr-14 07-Apr-14 07-Apr-14, EMERGENCY GENERATOR
A10150 Foundation work 4 04-Apr-14 07-Apr-14 Foundation work
PIT FOR EQUIPMENT
EQUIP 63 31-Aug-13 01-Nov-13 01-Nov-13, PIT FOR EQUIPMENT
EQUIPMENT PPIT 110-E1/E2/E3/E4 63 31-Aug-13 01-Nov-13 01-Nov-13, EQUIPMENT PIT 110-E1/E2/E3/E4
MH-CW-580 Foundation work 63 31-Aug-13 01-Nov-13 Foundation work
UNDERGROUN WORKS
UNDERGROUND 213 18-Oct-13 18-May-14 18-May-14, UNDERGROUND WORKS
OILY WATER + STORM WATER SYSTEM DRAINAGE WORKS 65 18-Oct-13 21-Dec-13 21-Dec-13, OILY WATER + STORM WATER SYSTEM DRAINAGE WORKS
MH-CW-520 Excavation of Trenches & Manholes 15 18-Oct-13 01-Nov-13 Excavation of Trenches & Manholes
MH-CW-620 Precast manhole preparation 20 25-Oct-13 13-Nov-13 Precast manhole preparation
MH-CW-760 Manhole Installation works 25 03-Nov-13 27-Nov-13 Manhole Installation works
MH-CW-820 Pipe laying works 35 08-Nov-13 12-Dec-13 Pipe laying works
MH-CW-825 Backfilling of trenches 25 27-Nov-13 21-Dec-13 Backfilling of trenches
FIRE FIGHTING SYSTEM DRAINAGE WORKS 72 28-Oct-13 07-Jan-14 07-Jan-14, FIRE FIGHTING SYSTEM DRAINAGE WORKS
MH-CW-800 Excavation of Trenches 20 28-Oct-13 16-Nov-13 Excavation of Trenches
MH-CW-920 Manhole Installation works 35 07-Nov-13 11-Dec-13 Manhole Installation works
MH-CW-950 Pipe laying works(Kg) 45 17-Nov-13 31-Dec-13 Pipe laying works(Kg)
MH-CW-955 Backfilling of trenches 35 04-Dec-13 07-Jan-14 Backfilling of trenches
SEWAGE SYSTEM
SYST DRAINAGE WORKS 65 02-Nov-13 05-Jan-14 05-Jan-14, SEWAGE SYSTEM DRAINAGE WORKS
MH-CW-1650 Excavation of Trenches 20 02-Nov-13 21-Nov-13 Excavation of Trenches
MH-CW-1700 Manhole Installation works 35 12-Nov-13 16-Dec-13 Manhole Installation works
MH-CW-1750 Pipe laying works 45 17-Nov-13 31-Dec-13 Pipe laying works
MH-CW-1790 Backfilling of trenches 30 07-Dec-13 05-Jan-14 Backfilling of trenches
GROUNDING G
GRID WORKS 31 18-Apr-14 18-May-14 18-May-14, GROUNDING GRID WORKS
MH-CW-1840 Grounding Grid works below the pavement 31 18-Apr-14 18-May-14 Grounding Grid works below the pavement
BACKFILLING W
WORKS 234 15-Dec-13 05-Aug-14 05-Aug-14, BACKFILLING WORKS
MH-CW-320 Backfilling upto Level +14.20,16.20 (m3) 234 15-Dec-13 05-Aug-14 Backfilling upto Level +14.20,16.20 (m3)
MILD HYDROCRACKING
HYDRO UNIT-BUILDING WORKS 202 19-Nov-13 09-Jun-14 09-Jun-14, MILD HYDROCRACKING UNIT-BUILDING WORKS

Primary Baseline Actual Work Critical Remaining Work Page 8 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-BLD-10 Compressor Building I/D & O/D,HVAC,S/S 174 19-Nov-13 12-May-14 Compressor Building I/D & O/D,HVAC,S/S
MH-BLD-20 Control Room 202 19-Nov-13 09-Jun-14 Control Room
MILD HYDROCRACKING
HYDRO UNIT-MECHANICAL WORKS 670 26-Oct-13 26-Aug-15 26-Aug-15, MIL
STEEL STRUCTURE-TON
STRUCT 309 01-Jan-14 05-Nov-14 05-Nov-14, STEEL STRUCTURE-TON
SECTION-8 302 01-Jan-14 29-Oct-14 29-Oct-14, SECTION-8
BLOCK NUMBER
NUMB 711/041 PIPE RACK 176 01-Jan-14 25-Jun-14 25-Jun-14, BLOCK NUMBER 711/041 PIPE RACK
PIPE RACK STRUCTURAL
ST STEEL ERECTION 176 01-Jan-14 25-Jun-14 25-Jun-14, PIPE RACK STRUCTURAL STEEL ERECTION
MH-ME-10 Pipe rack structural steel preassembly 110 01-Jan-14 20-Apr-14 Pipe rack structural steel preassembly
MH-ME-40 Structural Steel Erection 150 27-Jan-14 25-Jun-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/036 STRUCTURE-R 204 08-Mar-14 27-Sep-14 27-Sep-14, BLOCK NUMBER 711/036 STRUC TURE-R
STRUCTURE-R ERECTION
STRUCTURE- 142 09-May-14 27-Sep-14 27-Sep-14, STRUCTURE-R ERECTION
MH-ME-730 Structural steel erection-1st Level 50 09-May-14 27-Jun-14 Structural steel erection-1st Level
MH-ME-731 Structural steel erection-2nd Level 45 29-Jun-14 12-Aug-14 Structural steel erection-2nd Level
MH-ME-740 Structural steel erection-3rd Level 45 14-Aug-14 27-Sep-14 Structural steel erection-3rd Level
112-E4 STEEL MAINTENANCE PLATFORM ERECTION 10 08-Mar-14 17-Mar-14 17-Mar-14, 112-E4 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-910 Structural steel Platform erection 10 08-Mar-14 17-Mar-14 Structural steel Platform erection
BLOCK NUMBER
NUMB 711/033 STRUCTURE-E 59 21-May-14 18-Jul-14 18-Jul-14, BLOCK NUMBER 711/033 STRUC TURE-E
PLATFORM +4,800
+ ERECTION 35 21-May-14 24-Jun-14 24-Jun-14, PLATFORM +4,800 ERECTION
MH-ME-690 Structural steel Platform erection 35 21-May-14 24-Jun-14 Structural steel Platform erection
PLATFORM +12,600
+ ERECTION (FINAL ERECTION) 30 09-Jun-14 08-Jul-14 08-Jul-14, PLATFORM +12,600 ERECTION (FINAL ERECTION)
MH-ME-126 Structural steel Platform erection 30 09-Jun-14 08-Jul-14 Structural steel Platform erection
112-E1 STEEL MAINTENANCE PLATFORM ERECTION 10 09-Jul-14 18-Jul-14 18-Jul-14, 112-E1 STEEL MAINTENANCE PLATFORM ERECTION
A10170 Structural steel Platform erection 10 09-Jul-14 18-Jul-14 Structural steel Platform erection
BLOCK NUMB
NUMBER 711/035 ABSORBER & STRIPPER BLOCK 75 10-May-14 23-Jul-14 23-Jul-14, BLOCK NUMBER 711/035 ABSORBER & STRIPPER BLOCK
112-K2 & K8 PLATFORM
P ERECTION 49 10-May-14 27-Jun-14 27-Jun-14, 112-K2 & K8 PLATFORM ERECTION
MH-ME-560 Structural steel Platform pre assembly 15 10-May-14 24-May-14 Structural steel Platform pre assembly
MH-ME-920 Structural steel Platform erection 30 29-May-14 27-Jun-14 Structural steel Platform erection
112-K1,3,6 PLATFORM
PLA ERECTION 60 25-May-14 23-Jul-14 23-Jul-14, 112-K1,3,6 PLATFORM ERECTION
MH-ME-148 Structural steel Platform pre assembly 23 25-May-14 16-Jun-14 Structural steel Platform pre assembly
MH-ME-170 Structural steel Platform erection 55 30-May-14 23-Jul-14 Structural steel Platform erection
BLOCK NUMBER
NUMB 711/037 PRODUCT FRACTIONATOR COLUMN BLOCK 152 31-May-14 29-Oct-14 29-Oct-14, BLOCK NUMBER 711/037 PRODUCT FRACTIONATOR
112-K5 & K7 PLATFORM
P ERECTION 65 31-May-14 03-Aug-14 03-Aug-14, 112-K5 & K7 PLATFORM ERECTION
MH-ME-280 Structural steel Platform pre assembly 45 31-May-14 14-Jul-14 Structural steel Platform pre assembly
MH-ME-530 Structural steel Platform erection 60 05-Jun-14 03-Aug-14 Structural steel Platform erection
112-K4 PLATFORM
PLATF ERECTION 151 01-Jun-14 29-Oct-14 29-Oct-14, 112-K4 PLATFORM ERECTION
MH-ME-540 Structural steel Platform pre assembly 60 01-Jun-14 30-Jul-14 Structural steel Platform pre assembly
MH-ME-570 Structural steel Platform erection 90 01-Aug-14 29-Oct-14 Structural steel Platform erection
112-E3 PLATF
PLATFORM ERECTION 55 06-Jun-14 30-Jul-14 30-Jul-14, 112-E3 PLATFORM ERECTION
MH-ME-123 Structural steel Platform pre assembly 30 06-Jun-14 05-Jul-14 Structural steel Platform pre assembly
MH-ME-158 Structural steel Platform erection 45 16-Jun-14 30-Jul-14 Structural steel Platform erection
SECTION-3 302 01-Jan-14 29-Oct-14 29-Oct-14, SECTION-3
BLOCK NUMBER
NUMB 711/042 PIPE RACK 111 01-Jan-14 21-Apr-14 21-Apr-14, BLOCK NUMBER 711/042 PIPE RACK
STRUCTURAL STEEL ERECTION 111 01-Jan-14 21-Apr-14 21-Apr-14, STRUCTURAL STEEL ERECTION
MH-ME-070 Pipe rack structural steel preassembly 70 01-Jan-14 11-Mar-14 Pipe rack structural steel preassembly
MH-ME-160 Structural Steel Erection 90 22-Jan-14 21-Apr-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/013 STRUCTURE-K 190 23-Apr-14 29-Oct-14 29-Oct-14, BLOCK NUMBER 711/013 STRUC TURE-K
STRUCTURAL STEEL ERECTION 190 23-Apr-14 29-Oct-14 29-Oct-14, STRUCTURAL STEEL ERECTION
MH-ME-120 Structural steel erection 190 23-Apr-14 29-Oct-14 Structural steel erection
SECTION-2 304 01-Jan-14 31-Oct-14 31-Oct-14, SECTION-2
BLOCK NUMBER
NUMB 711/042 PIPE RACK 144 01-Jan-14 24-May-14 24-May-14, BLOCK NUMBER 711/042 PIPE R ACK
STRUCTURAL STEEL ERECTION 144 01-Jan-14 24-May-14 24-May-14, STRUCTURAL STEEL ERECTION
MH-ME-30 Pipe rack structural steel preassembly 95 01-Jan-14 05-Apr-14 Pipe rack structural steel preassembly

Primary Baseline Actual Work Critical Remaining Work Page 9 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-ME-60 Structural Steel Erection 120 25-Jan-14 24-May-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/010 STRUCTURE-G 82 06-May-14 26-Jul-14 26-Jul-14, BLOCK NUMBER 711/010 STRUC TURE-G
STRUCTURAL STEEL ERECTION (AXES 4-10) 50 06-May-14 24-Jun-14 24-Jun-14, STRUCTURAL STEEL ERECTION (AXES 4-10)
MH-ME-220 Structural steel erection 50 06-May-14 24-Jun-14 Structural steel erection
STRUCTURAL STEEL ERECTION (AXES 1-4) 30 27-Jun-14 26-Jul-14 26-Jul-14, STRUCTURAL STEEL ERECTION (AXES 1-4)
MH-ME-990 Structural steel erection 30 27-Jun-14 26-Jul-14 Structural steel erection
111-E4 STEEL MAINTENANCE PLATFORM ERECTION 15 28-Jun-14 12-Jul-14 12-Jul-14, 111-E4 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-630 Structural steel Platform erection 15 28-Jun-14 12-Jul-14 Structural steel Platform erection
BLOCK NUMBER
NUMB 711/006 STRUCTURE-V 45 26-May-14 09-Jul-14 09-Jul-14, BLOCK NUMBER 711/006 STRUC TURE-V
STRUCTURAL STEEL ERECTION 45 26-May-14 09-Jul-14 09-Jul-14, STRUCTURAL STEEL ERECTION
MH-ME-104 Structural Steel Erection 45 26-May-14 09-Jul-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/008 STRUCTURE-T 45 01-Jun-14 15-Jul-14 15-Jul-14, BLOCK NUMBER 711/008 STRUC TURE-T
STRUCTURAL STEEL ERECTION 45 01-Jun-14 15-Jul-14 15-Jul-14, STRUCTURAL STEEL ERECTION
MH-ME-900 Structural Steel Erection 45 01-Jun-14 15-Jul-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/009 STRUCTURE-A 30 15-Jun-14 14-Jul-14 14-Jul-14, BLOCK NUMBER 711/009 STRUC TURE-A
STRUCTURAL STEEL ERECTION 30 15-Jun-14 14-Jul-14 14-Jul-14, STRUCTURAL STEEL ERECTION
MH-ME-410 Structural Steel Erection 30 15-Jun-14 14-Jul-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/005 OPEN PUMP STATION-2 45 16-Jul-14 29-Aug-14 29-Aug-14, BLOCK NUMBER 711/005 OPEN PUMP STATION-2
STRUCTURAL STEEL ERECTION 45 16-Jul-14 29-Aug-14 29-Aug-14, STRUCTURAL STEEL ERECTION
MH-ME-102 Structural Steel Erection 45 16-Jul-14 29-Aug-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/003 OPEN PUMP STATION-1 61 01-Sep-14 31-Oct-14 31-Oct-14, BLOCK NUMBER 711/003 OPEN PUMP STATION-1
STRUCTURAL STEEL ERECTION 61 01-Sep-14 31-Oct-14 31-Oct-14, STRUCTURAL STEEL ERECTION
MH-ME-103 Structural Steel Erection 61 01-Sep-14 31-Oct-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/007 COLD SEPARATOR 36 09-Jun-14 14-Jul-14 14-Jul-14, BLOCK NUMBER 711/007 COLD SEPARATOR
111-E5 STEEL MAINTENANCE PLATFORM ERECTION 36 09-Jun-14 14-Jul-14 14-Jul-14, 111-E5 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-640 Structural steel Platform pre assembly 10 09-Jun-14 18-Jun-14 Structural steel Platform pre assembly
MH-ME-680 Structural steel Platform erection 25 20-Jun-14 14-Jul-14 Structural steel Platform erection
BLOCK NUMBER
NUMB 711/011 STRUCTURE-B 75 18-Jun-14 31-Aug-14 31-Aug-14, BLOCK NUMBER 711/011 STRUCTURE-B
STRUCTURAL STEEL ERECTION 75 18-Jun-14 31-Aug-14 31-Aug-14, STRUCTURAL STEEL ERECTION
MH-ME-290 Structural Steel Erection 75 18-Jun-14 31-Aug-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/004 BLENDED RAW MATERIAL TANK 32 15-Jul-14 15-Aug-14 15-Aug-14, BLOCK NUMBER 711/004 BLENDED RAW MATERIAL TANK
111-E1 STEEL MAINTENANCE PLATFORM ERECTION 30 15-Jul-14 13-Aug-14 13-Aug-14, 111-E1 STEEL M AINTENANCE PLATFORM ERECTION
MH-ME-610 Structural steel Platform erection 30 15-Jul-14 13-Aug-14 Structural steel Platform erection
111-E10 STEEL
STEE MAINTENANCE PLATFORM ERECTION 30 17-Jul-14 15-Aug-14 15-Aug-14, 111-E10 STEEL M AINTENANCE PLATFORM ERECTION
MH-ME-620 Structural steel Platform erection 30 17-Jul-14 15-Aug-14 Structural steel Platform erection
SECTION-6 267 07-Feb-14 31-Oct-14 31-Oct-14, SECTION-6
BLOCK NUMBER
NUMB 711/041 PIPE RACK 153 07-Feb-14 09-Jul-14 09-Jul-14, BLOCK NUMBER 711/041 PIPE RACK
MH-ME-120 Pipe rack structural steel preassembly 100 07-Feb-14 17-May-14 Pipe rack structural steel preassembly
MH-ME-180 Structural Steel Erection 140 20-Feb-14 09-Jul-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/026 STRUCTURE-I 77 02-Jun-14 17-Aug-14 17-Aug-14, BLOCK NUMBER 711/026 STRUC TURE-I
STRUCTURAL STEEL ERECTION(1ST LEVEL) 30 02-Jun-14 01-Jul-14 01-Jul-14, STRUCTURAL STEEL ERECTION(1ST LEVEL)
MH-ME-145 Structural Steel Erection 30 02-Jun-14 01-Jul-14 Structural Steel Erection
STRUCTURAL STEEL ERECTION (2ND LEVEL) 30 03-Jul-14 01-Aug-14 01-Aug-14, STRUCTURAL STEEL ERECTION (2ND LEVEL)
MH-ME-153 Structural Steel Erection 30 03-Jul-14 01-Aug-14 Structural Steel Erection
PLATFORM +13,200
+ ERECTION 15 03-Aug-14 17-Aug-14 17-Aug-14, PLATFORM +13,200 ERECTION
MH-ME-172 Platform Erection 15 03-Aug-14 17-Aug-14 Platform Erection
BLOCK NUMB
NUMBER 711/019 FLARE KNOCK OUT UNIT 92 03-Jun-14 02-Sep-14 02-Sep-14, BLOCK NUMBER 711/019 FLARE KNOCK OUT UNIT
STRUCTURE-U 110-E5 A/B,E6 STRUCTURAL STEEL ERECTION
STRUCTURE- 46 03-Jun-14 18-Jul-14 18-Jul-14, STRUCTURE-U 110-E5 A/B,E6 STRUCTURAL STEEL ERECTION
MH-ME-097 Structural steel Platform pre assembly 20 03-Jun-14 22-Jun-14 Structural steel Platform pre assembly
MH-ME-136 Structural steel Platform erection 42 07-Jun-14 18-Jul-14 Structural steel Platform erection
STRUCTURE-U 2nd LEVEL ERECTION
STRUCTURE- 45 20-Jul-14 02-Sep-14 02-Sep-14, STRUCTURE-U 2nd LEVEL EREC TION
MH-ME-137 Structural Steel Erection 45 20-Jul-14 02-Sep-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/020 OPEN PUMP STATION-4 30 04-Jun-14 03-Jul-14 03-Jul-14, BLOCK NUMBER 711/020 OPEN PUMP STATION-4

Primary Baseline Actual Work Critical Remaining Work Page 10 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-ME-500 Structural Steel Erection 30 04-Jun-14 03-Jul-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/022 STRUCTURE-M 76 05-Jun-14 19-Aug-14 19-Aug-14, BLOCK NUMBER 711/022 STRUC TURE-M
MH-ME-0510 Structure-M upto 110-E8,9,10 30 05-Jun-14 04-Jul-14 Structure-M upto 110-E8,9,10
MH-ME-1140 Structure-M Final Erection 45 06-Jul-14 19-Aug-14 Structure-M Final Erection
BLOCK NUMBER
NUMB 711/028 DEBUTANIZER COLUMN 30 10-Jun-14 09-Jul-14 09-Jul-14, BLOCK NUMBER 711/028 DEBUTANIZER COLUM N
112-K10 STEEL
STEE MAINTENANCE PLATFORM ERECTION 30 10-Jun-14 09-Jul-14 09-Jul-14, 112-K10 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-182 Platform Erection 30 10-Jun-14 09-Jul-14 Platform Erection
BLOCK NUMBER
NUMB 711/029 DEPROPANIZER COLUMN 45 11-Jun-14 25-Jul-14 25-Jul-14, BLOCK NUMBER 711/029 DEPROPANIZER COLUMN
112-K9 STEEL MAINTENANCE PLATFORM ERECTION 45 11-Jun-14 25-Jul-14 25-Jul-14, 112-K9 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-181 Platform Erection 45 11-Jun-14 25-Jul-14 Platform Erection
BLOCK NUMBER
NUMB 711/024 PROPANE AMINE TREATER(ABSORBER) 148 06-Jun-14 31-Oct-14 31-Oct-14, BLOCK NUMBER 711/024 PROPANE AMINE TREATER
110-E11 STEEL
STEE MAINTENANCE PLATFORM ERECTION 58 03-Sep-14 30-Oct-14 30-Oct-14, 110-E11 STEEL M AINTENANCE PLATFORM ERECTION
MH-ME-074 Platform Erection 58 03-Sep-14 30-Oct-14 Platform Erection
110-E7 STEEL MAINTENANCE PLATFORM ERECTION 58 04-Sep-14 31-Oct-14 31-Oct-14, 110-E7 STEEL MAINTENANCE PLATFORM ERECTION
A10160 Platform Erection 58 04-Sep-14 31-Oct-14 Platform Erection
112-K11 STEEL
STEE MAINTENANCE PLATFORM ERECTION 64 06-Jun-14 08-Aug-14 08-Aug-14, 112-K11 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-112 Platform Erection 64 06-Jun-14 08-Aug-14 Platform Erection
BLOCK NUMBER
NUMB 711/025 INHIBITOR FEED EQUIPMENT 1 27 10-Aug-14 05-Sep-14 05-Sep-14, BLOCK NUMBER 711/025 INHIBITOR FEED EQUIPMENT 1
112-T14 STEEL
STEE MAINTENANCE PLATFORM ERECTION 27 10-Aug-14 05-Sep-14 05-Sep-14, 112-T14 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-154 Platform Erection 27 10-Aug-14 05-Sep-14 Platform Erection
SECTION-1 175 07-Feb-14 31-Jul-14 31-Jul-14, SECTION-1
BLOCK NUMBER
NUMB 711/042 PIPE RACK 95 07-Feb-14 12-May-14 12-May-14, BLOCK NUMBER 711/042 PIPE R ACK
STRUCTURAL STEEL ERECTION 95 07-Feb-14 12-May-14 12-May-14, STRUCTURAL STEEL ERECTION
MH-ME-20 Pipe rack structural steel preassembly 60 07-Feb-14 07-Apr-14 Pipe rack structural steel preassembly
MH-ME-50 Structural Steel Erection 75 27-Feb-14 12-May-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/002 SEPARATOR BLOCK NO:1 28 24-Mar-14 20-Apr-14 20-Apr-14, BLOCK NUMBER 711/002 SEPARATOR BLOCK NO:1
111-E6 STEEL MAINTENANCE PLATFORM ERECTION 28 24-Mar-14 20-Apr-14 20-Apr-14, 111-E6 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-190 Structural steel Platform erection 28 24-Mar-14 20-Apr-14 Structural steel Platform erection
BLOCK NUMB
NUMBER 711/001 COMPRESSOR STATION 115 08-Apr-14 31-Jul-14 31-Jul-14, BLOCK NUMBER 711/001 COMPR ESSOR STATION
COMPRESSOR STATION STRUCTURAL ERECTION
COMPRESSO 115 08-Apr-14 31-Jul-14 31-Jul-14, COMPRESSOR STATION STRUCTURAL ERECTION
MH-ME-170 Structural steel erection 115 08-Apr-14 31-Jul-14 Structural steel erection
111-DK1 A/B STEEL
S MAINTENANCE PLATFORM ERECTION 60 23-Apr-14 21-Jun-14 21-Jun-14, 111-DK1 A/B STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-350 Structural steel Platform erection 60 23-Apr-14 21-Jun-14 Structural steel Platform erection
111-TSK1 STEEL
STE MAINTENANCE PLATFORM ERECTION 60 25-Apr-14 23-Jun-14 23-Jun-14, 111-TSK1 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-360 Structural steel Platform erection 60 25-Apr-14 23-Jun-14 Structural steel Platform erection
111-E7 STEEL MAINTENANCE PLATFORM ERECTION 30 26-Apr-14 25-May-14 25-May-14, 111-E7 STEEL M AINTENANCE PLATFORM ERECTION
MH-ME-200 Structural steel Platform erection 30 26-Apr-14 25-May-14 Structural steel Platform erection
111-E8 STEEL MAINTENANCE PLATFORM ERECTION 30 27-Apr-14 26-May-14 26-May-14, 111-E8 STEEL M AINTENANCE PLATFORM ERECTION
MH-ME-210 Structural steel Platform erection 30 27-Apr-14 26-May-14 Structural steel Platform erection
SECTION-7 250 01-Mar-14 05-Nov-14 05-Nov-14, SECTION-7
BLOCK NUMBER
NUMB 711/044 PIPE RACK 91 01-Mar-14 30-May-14 30-May-14, BLOCK NUMBER 711/044 PIPE R ACK
STRUCTURAL STEEL ERECTION 91 01-Mar-14 30-May-14 30-May-14, STRUCTURAL STEEL ERECTION
MH-ME-100 Pipe rack structural steel preassembly 30 01-Mar-14 30-Mar-14 Pipe rack structural steel preassembly
MH-ME-130 Structural Steel Erection 60 01-Apr-14 30-May-14 Structural Steel Erection
BLOCK NUMBER
NUMB 711/031 STRUCTURE-ZH 180 01-May-14 27-Oct-14 27-Oct-14, BLOCK NUMBER 711/031 STRUC TURE-ZH
STRUCTURAL STEEL ERECTION 180 01-May-14 27-Oct-14 27-Oct-14, STRUCTURAL STEEL ERECTION
MH-ME-150 Structural steel erection 180 01-May-14 27-Oct-14 Structural steel erection
BLOCK NUMBER
NUMB 711/030 STRUCTURE-N 160 30-May-14 05-Nov-14 05-Nov-14, BLOCK NUMBER 711/030 STRUC TURE-N
STRUCTURAL STEEL ERECTION 160 30-May-14 05-Nov-14 05-Nov-14, STRUCTURAL STEEL ERECTION
MH-ME-140 Structural steel erection 160 30-May-14 05-Nov-14 Structural steel erection
SECTION-5 46 01-Mar-14 15-Apr-14 15-Apr-14, SECTION-5
BLOCK NUMBER
NUMB 711/018 STRUCTURE-D 46 01-Mar-14 15-Apr-14 15-Apr-14, BLOCK NUMBER 711/018 STRUCTURE-D
MH-ME-110 Structural Steel Erection 46 01-Mar-14 15-Apr-14 Structural Steel Erection

Primary Baseline Actual Work Critical Remaining Work Page 11 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
SECTION-9 98 01-Jun-14 06-Sep-14 06-Sep-14, SECTION-9
BLOCK NUMBER
NUMB 711/003 OPS-3 45 01-Jun-14 15-Jul-14 15-Jul-14, BLOCK NUMBER 711/003 OPS-3
STRUCTURAL STEEL ERECTION 45 01-Jun-14 15-Jul-14 15-Jul-14, STRUCTURAL STEEL ERECTION
MH-ME-550 Structural Steel Erection 45 01-Jun-14 15-Jul-14 Structural Steel Erection
TANKS STEEL MAINTENANCE PLATFORM 93 06-Jun-14 06-Sep-14 06-Sep-14, TANKS STEEL MAINTENANCE PLATFORM
TANKS STEEL MAINTENANCE PLATFORM ERECTION 93 06-Jun-14 06-Sep-14 06-Sep-14, TANKS STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-197 Structural steel Platform erection 93 06-Jun-14 06-Sep-14 Structural steel Platform erection
BLOCK NUMB
NUMBER 711/039 FLUSHING / START UP OIL BLOCK 35 11-Jun-14 15-Jul-14 15-Jul-14, BLOCK NUMBER 711/039 FLUSHING / START UP OIL BLOCK
111-E11 STEEL
STEE MAINTENANCE PLATFORM ERECTION 30 11-Jun-14 10-Jul-14 10-Jul-14, 111-E11 STEEL MAINTENANCE PLATFORM ERECTION
MH-ME-760 Structural steel Platform erection 30 11-Jun-14 10-Jul-14 Structural steel Platform erection
111-E12 STEEL
STEE MAINTENANCE PLATFORM ERECTION 30 16-Jun-14 15-Jul-14 15-Jul-14, 111-E12 STEEL M AINTENANCE PLATFORM ERECTION
MH-ME-770 Structural steel Platform erection 30 16-Jun-14 15-Jul-14 Structural steel Platform erection
SECTION-4 60 28-Aug-14 26-Oct-14 26-Oct-14, SECTION-4
BLOCK NUMBER
NUMB 711/043 PIPE RACK 60 28-Aug-14 26-Oct-14 26-Oct-14, BLOCK NUMBER 711/043 PIPE R ACK
PIPE RACK STRUCTURAL
ST STEEL STRUCTION 60 28-Aug-14 26-Oct-14 26-Oct-14, PIPE RACK STRUCTURAL STEEL STRUCTION
MH-ME-80 Pipe rack structural steel preassembly 30 28-Aug-14 26-Sep-14 Pipe rack structural steel preassembly
MH-ME-90 Structural Steel Erection 50 07-Sep-14 26-Oct-14 Structural Steel Erection
EQUIPMENT ERECTION-TON
ER 450 01-Apr-14 24-Jun-15 24-Jun-15, EQUIPMENT E
SECTION-3 342 01-Apr-14 08-Mar-15 08-Mar-15, SECTION-3
HEATER ERECTION
EREC 342 01-Apr-14 08-Mar-15 08-Mar-15, HEATER ERECTION
HEATERS 111-P1
111 & 112-P1 INSTALLATION 342 01-Apr-14 08-Mar-15 08-Mar-15, HEATERS 111-P1 & 112-P1 INSTA
MH-ME-023 Structural Steel Erection (Radiant Section) 60 01-Apr-14 30-May-14 Structural Steel Erection (Radiant Section)
MH-ME-042 Grouting,Furnace box prefabrication module 65 31-May-14 03-Aug-14 Grouting,Furnace box prefabrication module
MH-ME-155 Refractory lining vertical walls 55 04-Aug-14 27-Sep-14 Refractory lining vertical walls
MH-ME-156 Refractory lining radiant floor panels 65 09-Aug-14 12-Oct-14 Refractory lining radiant floor panels
MH-ME-194 Convection chamber & Steel stack completion works 55 13-Oct-14 06-Dec-14 Convection chamber & Steel stack completion works
MH-ME-202 Fan driver,Ducts Platform installation 55 12-Dec-14 04-Feb-15 Fan driver,Ducts Platform installation
MH-ME-203 Coils preassembly and Erection 50 17-Dec-14 04-Feb-15 Coils preassembly and Erection
MH-ME-204 Air preheating system installation 55 27-Dec-14 19-Feb-15 Air preheating system installation
MH-ME-205 Burners,Instrumentation,Dumpers installation 56 12-Jan-15 08-Mar-15 Burners,Instrumentation,Dumpers installation
STRUCTURE-K
STRUCTURE-K(111-R1 & 111-R2) 46 01-Jun-14 16-Jul-14 16-Jul-14, STRUCTURE-K(111-R1 & 111-R2)
111-R1 & R2 INSTALLATION
IN 46 01-Jun-14 16-Jul-14 16-Jul-14, 111-R1 & R2 INSTALLATION
MH-ME-030 111-R1 & R2 Main crane installation 26 01-Jun-14 26-Jun-14 111-R1 & R2 Main crane installation
MH-ME-078 111-R2 Lifting 1 29-Jun-14* 29-Jun-14 111-R2 Lifting
MH-ME-086 1 Gantry crane relocation 14 29-Jun-14 13-Jul-14 1 Gantry crane relocation
MH-ME-121 111-R1 Lifting 1 15-Jul-14* 16-Jul-14 111-R1 Lifting
110-ME1,T1,110-F1 A/B INSTALLATION
110-ME1,T1,110 10 16-Jul-14 26-Jul-14 26-Jul-14, 110-ME1,T1,110-F1 A/B INSTALLATION
A10040 Installations 10 16-Jul-14 26-Jul-14 Installations
SECTION-1 418 03-May-14 24-Jun-15 24-Jun-15, SECTION-1
BUILDINGS 418 03-May-14 24-Jun-15 24-Jun-15, BUILDINGS
111-TSK1 & 111-DK1
11 A/B PACKAGE ERECTION 120 03-May-14 30-Aug-14 30-Aug-14, 111-TSK1 & 111-DK1 A/B PACKAGE ERECTION
MH-ME-270 Installations 120 03-May-14 30-Aug-14 Installations
O/D EQUIPME
EQUIPMENT 111-E6,7,8 & 111-AV03 INSTALLATION 60 01-Jul-14 30-Aug-14 30-Aug-14, O/D EQUIPMENT 111-E6,7,8 & 111-AV03 INSTALLATION
MH-ME-240 Installations 60 01-Jul-14* 30-Aug-14 Installations
111-KH3,KH4, 111-ME5, ME6 A/B, ME 9,111-N 10A/B INSTALLATION 60 23-May-14 21-Jul-14 21-Jul-14, 111-KH3,KH4, 111-ME5, ME6 A/B, ME 9,111-N 10A/B INSTALLATION
A10070 Installations 60 23-May-14 21-Jul-14 Installations
COMP,CENTRIFUGAL,RECIPROGATING WORKS
COMP,CENTR 288 09-Sep-14 24-Jun-15 24-Jun-15, COMP,CENTRI
MH-ME-025 Mechanical works & Installation 210 09-Sep-14 07-Apr-15 Mechanical works & Installation
MH-ME-026 Piping works, connecting & Testing 210 04-Oct-14 02-May-15 Piping works, connecting & Testing
MH-ME-192 Electrical works connecting & Testing 177 05-Dec-14 31-May-15 Electrical works connecting & T
MH-ME-206 Instrumentation works connecting & Testing 177 29-Dec-14 24-Jun-15 Instrumentation works conn
SECTION-6 88 11-Jun-14 06-Sep-14 06-Sep-14, SECTION-6

Primary Baseline Actual Work Critical Remaining Work Page 12 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
COLUMNS 14 11-Jun-14 25-Jun-14 25-Jun-14, COLUMNS
112-K9 INSTALLATION
INSTA 14 11-Jun-14 24-Jun-14 24-Jun-14, 112-K9 INSTALLATION
MH-ME-480 Dressing 10 11-Jun-14 20-Jun-14 Dressing
MH-ME-880 Lifting 2 22-Jun-14* 24-Jun-14 Lifting
112-K10 INSTALLATION
INSTA 13 12-Jun-14 25-Jun-14 25-Jun-14, 112-K10 INSTALLATION
MH-ME-490 Dressing 10 12-Jun-14 21-Jun-14 Dressing
MH-ME-890 Lifting 2 23-Jun-14* 25-Jun-14 Lifting
112-K11 INSTALLATION
INSTA 3 20-Jun-14 23-Jun-14 23-Jun-14, 112-K11 INSTALLATION
MH-ME-190 Installations 3 20-Jun-14* 23-Jun-14 Installations
STRUCTURE-I 81 12-Jun-14 31-Aug-14 31-Aug-14, STRUCTURE-I
HEAT EXCHA
EXCHANGERS GRADE LEVEL:112-KH 5,6,8 INSTALLATION 5 12-Jun-14 16-Jun-14 16-Jun-14, HEAT EXCHANGERS GRADE LEVEL:112-KH 5,6,8 INSTALLATION
MH-ME-169 Installations 5 12-Jun-14 16-Jun-14 Installations
FIRST LEVEL:112-E7,KH3,E6,ME2
LEVEL INSTALLATION 6 03-Jul-14 08-Jul-14 08-Jul-14, FIRST LEVEL:112-E7,KH3,E6,ME2 INSTALLATION
MH-ME-166 Installations 6 03-Jul-14 08-Jul-14 Installations
SECOND LEVEL:112-KH
LEV 7,9 INSTALLATION 4 13-Jul-14 16-Jul-14 16-Jul-14, SECOND LEVEL:112-KH 7,9 INSTALLATION
MH-ME-185 Installations 4 13-Jul-14 16-Jul-14 Installations
TOP LEVEL:112-AV
LEVEL:1 04 AIR COOLER INSTALATION 24 08-Aug-14 31-Aug-14 31-Aug-14, TOP LEVEL:112-AV 04 AIR COOLER INSTALATION
MH-ME-174 Pre-assembly work 15 08-Aug-14 22-Aug-14 Pre-assembly work
MH-ME-195 Installations 4 28-Aug-14 31-Aug-14 Installations
STRUCTURE-M 68 16-Jun-14 22-Aug-14 22-Aug-14, STRUCTURE-M
110-E13 INSTALLATION
INSTA 2 16-Jun-14 17-Jun-14 17-Jun-14, 110-E13 INSTALLATION
MH-ME-176 Installations 2 16-Jun-14 17-Jun-14 Installations
VESSELS 110-E
110- 9,10,8 INSTALLATION 4 25-Jun-14 28-Jun-14 28-Jun-14, VESSELS 110-E 9,10,8 INSTALLATION
MH-ME-175 Installations 4 25-Jun-14 28-Jun-14 Installations
113-KH2 INSTALLATION
INST 2 21-Aug-14 22-Aug-14 22-Aug-14, 113-KH2 INSTALLATION
A10180 Installations 2 21-Aug-14 22-Aug-14 Installations
STRUCTURE-U 30 20-Jul-14 19-Aug-14 19-Aug-14, STRUCTURE-U
110-E5 A/B, E6 INSTALLATION 30 20-Jul-14 19-Aug-14 19-Aug-14, 110-E5 A/B, E6 INSTALLATION
MH-ME-184 Installations 30 20-Jul-14* 19-Aug-14 Installations
OPEN PUMP STATION
S -4 10 30-Jun-14 09-Jul-14 09-Jul-14, OPEN PUMP STATION -4
110-N 5A/B/C/D
5A/B/C/ , 110-N 6A/B INSTALLATION 10 30-Jun-14 09-Jul-14 09-Jul-14, 110-N 5A/B/C/D , 110-N 6A/B INSTALLATION
MH-ME-430 Installations 10 30-Jun-14 09-Jul-14 Installations
110-E11 INSTALLATION
INSTA 2 04-Sep-14 05-Sep-14 05-Sep-14, 110-E11 INSTALLATION
MH-ME-1770 Installations 2 04-Sep-14 05-Sep-14 Installations
112-T14 INSTALLATION
INSTA 4 11-Aug-14 14-Aug-14 14-Aug-14, 112-T14 INSTALLATION
MH-ME-1650 Installations 4 11-Aug-14 14-Aug-14 Installations
112-T13 INSTALLATION
INSTA 4 12-Aug-14 15-Aug-14 15-Aug-14, 112-T13 INSTALLATION
MH-ME-1960 Installations 4 12-Aug-14 15-Aug-14 Installations
110-E7 INSTALLATION
INSTAL 3 04-Sep-14 06-Sep-14 06-Sep-14, 110-E7 INSTALLATION
MH-ME-1890 Installations 3 04-Sep-14 06-Sep-14 Installations
112-N24A INSTALLATION
INST 3 04-Sep-14 06-Sep-14 06-Sep-14, 112-N24A INSTALLATION
A10050 Installations 3 04-Sep-14 06-Sep-14 Installations
112-N25A INSTALLATION
INST 3 04-Sep-14 06-Sep-14 06-Sep-14, 112-N25A INSTALLATION
A10060 Installations 3 04-Sep-14 06-Sep-14 Installations
SECTION-9 155 11-Jun-14 12-Nov-14 12-Nov-14, SECTION-9
111-RV1,111-ME3,111-ME4 INSTALATION
111-RV1,111-M 155 11-Jun-14 12-Nov-14 12-Nov-14, 111-RV1,111-ME3,111-ME4 INSTALATION
MH-ME-1430 Installations 155 11-Jun-14 12-Nov-14 Installations
111-E11,111-E12 INSTALLATION
111-E11,111-E1 90 26-Jun-14 23-Sep-14 23-Sep-14, 111-E11,111-E12 INSTALLATION
MH-ME-710 Installations 90 26-Jun-14 23-Sep-14 Installations
111-N5 A/B,6 A/B,7
A INSTALLATION 60 26-Jul-14 23-Sep-14 23-Sep-14, 111-N5 A/B,6 A/B ,7 INSTALLATION
MH-ME-670 Installations 60 26-Jul-14 23-Sep-14 Installations
SECTION-5 94 10-Jul-14 11-Oct-14 11-Oct-14, SECTION-5

Primary Baseline Actual Work Critical Remaining Work Page 13 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
STRUCTURE-D 94 10-Jul-14 11-Oct-14 11-Oct-14, STRUCTURE-D
PUMPS GRAD
GRADE LEVEL INSTALLATION:110-N7 A/B,14 A/B,15 A/B, 16 A/B 60 10-Jul-14 07-Sep-14 07-Sep-14, PUMPS GRADE LEVEL INSTALLATION:110-N7 A/B,14 A/B,15 A/B
MH-ME-105 Installations 60 10-Jul-14 07-Sep-14 Installations
AIR COOLERS
COOLER At level +6,000 for 110-AV1,112-AV3,5 INSTALLATION 34 08-Sep-14 11-Oct-14 11-Oct-14, AIR COOLERS At level +6,000 for 110-AV1,112-AV3,5 INSTAL
MH-ME-310 Pre-assembly work 15 08-Sep-14 22-Sep-14 Pre-assembly work
MH-ME-790 Installations 24 18-Sep-14 11-Oct-14 Installations
111-ME1,111-F1 A/B INSTALLATION
111-ME1,111-F 17 19-Sep-14 05-Oct-14 05-Oct-14, 111-ME1,111-F1 A/B INSTALLATION
MH-ME-106 Installations 17 19-Sep-14 05-Oct-14 Installations
SECTION-7 315 10-Jul-14 20-May-15 20-May-15, SECTION-7
STRUCTURE-ZH
STRUCTURE-Z 231 10-Jul-14 25-Feb-15 25-Feb-15, STRUCTURE-ZH
PUMP GRADE LEVEL INSTALLATION:112-N 4A/B,6A/B,7A/B,8A/B,9A/B10A/B,112 120 10-Jul-14 06-Nov-14 06-Nov-14, PUMP GRADE LEVEL INSTALLATION:112-N 4A/B,6A/
MH-ME-108 Installations 120 10-Jul-14 06-Nov-14 Installations
112-AV-07 INSTALLATION
INS 201 09-Aug-14 25-Feb-15 25-Feb-15, 112-AV-07 INSTALLATION
MH-ME-340 Pre-assembly work 90 09-Aug-14 06-Nov-14 Pre-assembly work
MH-ME-820 Installations 120 29-Oct-14 25-Feb-15 Installations
STRUCTURE-N 301 24-Jul-14 20-May-15 20-May-15, STRUCTURE-N
PUMP GRADE LEVEL INSTALLATION:112-N 5A/B,13A/B,1A/B,2A/B,3A/B,18A/B,20 120 24-Jul-14 20-Nov-14 20-Nov-14, PUMP GRADE LEVEL INSTALLATION:112-N 5A/B,1
MH-ME-107 Installations 120 24-Jul-14 20-Nov-14 Installations
112-AV01 INSTALLATION
INST 120 22-Nov-14 21-Mar-15 21-Mar-15, 112-AV01 INSTALLATION
MH-ME-320 Pre-assembly work 60 22-Nov-14 20-Jan-15 Pre-assembly work
MH-ME-800 Installations 90 22-Dec-14 21-Mar-15 Installations
112-AV06 INSTALLATION
INST 119 22-Jan-15 20-May-15 20-May-15, 112-AV06 INSTALLA
MH-ME-330 Pre-assembly work 60 22-Jan-15 22-Mar-15 Pre-assembly work
MH-ME-810 Installations 90 20-Feb-15 20-May-15 Installations
SECTION-2 118 14-Jul-14 09-Nov-14 09-Nov-14, SECTION-2
STRUCTURE-V 50 14-Jul-14 02-Sep-14 02-Sep-14, STRUCTURE-V
GRADE LEVEL:111-T3,T6
LEVE A/B,T5 A/B INSTALLATION 30 14-Jul-14 13-Aug-14 13-Aug-14, GRADE LEVEL:111-T3,T6 A/B,T5 A/B INSTALLATION
MH-ME-440 Installations 30 14-Jul-14* 13-Aug-14 Installations
LEVEL 2,+10,5 ml: 111-T4 A/B,T2 A/B,T1 INSTALLATION 45 19-Jul-14 02-Sep-14 02-Sep-14, LEVEL 2,+10,5 ml: 111-T4 A/B,T2 A/B,T1 INSTALLATION
MH-ME-870 Installations 45 19-Jul-14* 02-Sep-14 Installations
STRUCTURE-T 31 17-Jul-14 17-Aug-14 17-Aug-14, STRUCTURE-T
111-E2 INSTALLATION
INSTAL 30 17-Jul-14 16-Aug-14 16-Aug-14, 111-E2 INSTALLATION
MH-ME-101 Installations 30 17-Jul-14* 16-Aug-14 Installations
111-E3 INSTALLATION
INSTAL 30 18-Jul-14 17-Aug-14 17-Aug-14, 111-E3 INSTALLATION
MH-ME-109 Installations 30 18-Jul-14* 17-Aug-14 Installations
STRUCTURE-A 47 17-Jul-14 02-Sep-14 02-Sep-14, STRUCTURE-A
GRADE LEVEL:111-T7,111-T8A,111-T8B,T10
LEVE A/B INSTALLATION 30 17-Jul-14 16-Aug-14 16-Aug-14, GRADE LEVEL:111-T7,111-T8A,111-T8B,T10 A/B INSTALLATION
MH-ME-142 Installations 30 17-Jul-14* 16-Aug-14 Installations
UPPER LEVEL:111-T11,111-T9
LEVEL INSTALATION 45 19-Jul-14 02-Sep-14 02-Sep-14, UPPER LEVEL:111-T11,111-T9 INSTALATION
MH-ME-840 Installations 45 19-Jul-14* 02-Sep-14 Installations
STRUCTURE-G 31 15-Jul-14 15-Aug-14 15-Aug-14, STRUCTURE-G
111-E4 INSTALLATION
INSTAL 30 15-Jul-14 14-Aug-14 14-Aug-14, 111-E4 INSTALLATION
MH-ME-940 Installations 30 15-Jul-14* 14-Aug-14 Installations
AIR COOLERS
COOLER 111-AV-01 & AV-02 INSTALLATION 20 27-Jul-14 15-Aug-14 15-Aug-14, AIR COOLERS 111-AV-01 & AV-02 INSTALLATION
MH-ME-157 Installations 20 27-Jul-14 15-Aug-14 Installations
STRUCTURE-B 33 18-Jul-14 19-Aug-14 19-Aug-14, STRUCTURE-B
111-E9 INSTALLATION
INSTAL 10 18-Jul-14 27-Jul-14 27-Jul-14, 111-E9 INSTALLATION
A9990 Installations 10 18-Jul-14 27-Jul-14 Installations
111-K1 INSTALLATION
INSTA 30 20-Jul-14 19-Aug-14 19-Aug-14, 111-K1 INSTALLATION
MH-ME-125 Installations 30 20-Jul-14* 19-Aug-14 Installations
111-KH1 & 111-KH2
111 INSTALLATION 15 21-Jul-14 05-Aug-14 05-Aug-14, 111-KH1 & 111-KH2 INSTALLATION
A10000 Installations 15 21-Jul-14 05-Aug-14 Installations
111-E5 INSTALLATION
INSTAL 20 16-Jul-14 05-Aug-14 05-Aug-14, 111-E5 INSTALLATION
Primary Baseline Actual Work Critical Remaining Work Page 14 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-ME-1110 Installations 20 16-Jul-14* 05-Aug-14 Installations
111-E1 INSTALLATION
INSTAL 20 17-Jul-14 06-Aug-14 06-Aug-14, 111-E1 INSTALLATION
MH-ME-1130 Installations 20 17-Jul-14* 06-Aug-14 Installations
111-E10 INSTALLATION
INSTA 20 18-Jul-14 07-Aug-14 07-Aug-14, 111-E10 INSTALLATION
MH-ME-1160 Installations 20 18-Jul-14* 07-Aug-14 Installations
OPEN PUMP S
STATION-2 INSTALLATION:111-N1 A/B 25 14-Sep-14 08-Oct-14 08-Oct-14, OPEN PUMP STATION-2 INSTALLATION:111-N1 A/B
MH-ME-1220 Installations 25 14-Sep-14 08-Oct-14 Installations
OPEN PUMP S
STATION-1 INSTALLATION:111-N2 A/B,3 A/B,4 A/B,9 30 11-Oct-14 09-Nov-14 09-Nov-14, OPEN PUMP STATION-1 INSTALLATION:111-N2 A/B,3
MH-ME-1340 Installations 30 11-Oct-14 09-Nov-14 Installations
SECTION-8 116 14-Jul-14 06-Nov-14 06-Nov-14, SECTION-8
STRUCTURE-R 116 14-Jul-14 06-Nov-14 06-Nov-14, STRUCTURE-R
VESSELS & EX
EXCHANGERS GRADE LEVEL INSTALL:112-T 7,9,10,11,ME15,KH10 12 14-Jul-14 25-Jul-14 25-Jul-14, VESSELS & EXCHANGERS GRADE LEVEL INSTALL:112-T 7,9,10,11,ME1
MH-ME-580 Installations 12 14-Jul-14 25-Jul-14 Installations
FIRST LEVEL:112-T2,3,4,5,6;112-E4,E9,E8
LEVEL INSTALLATION 16 16-Jul-14 31-Jul-14 31-Jul-14, FIRST LEVEL:112-T2,3,4,5,6;112-E4,E9,E8 INSTALLATION
MH-ME-590 Installations 16 16-Jul-14* 31-Jul-14 Installations
SECOND LEVEL:112-ME
LEV 8,9,10,11,112-T8 INSTALLATION 5 01-Aug-14 05-Aug-14 05-Aug-14, SECOND LEVEL:112-ME 8,9,10,11,112-T8 INSTALLATION
MH-ME-129 Installations 5 01-Aug-14 05-Aug-14 Installations
THIRD LEVEL:
LEVEL AIR COOLERS 112-AV02 & 112-ME7 INSTALLATION 81 18-Aug-14 06-Nov-14 06-Nov-14, THIRD LEVEL: AIR COOLERS 112-AV02 & 112-ME7 IN
MH-ME-151 Pre-assembly work 25 18-Aug-14 11-Sep-14 Pre-assembly work
MH-ME-167 Installations 39 29-Sep-14 06-Nov-14 Installations
STRUCTURE-E 15 12-Sep-14 26-Sep-14 26-Sep-14, STRUCTURE-E
GRADE LEVEL:112-T12,T1,KH2
LEVE INSTALLATION 4 12-Sep-14 15-Sep-14 15-Sep-14, GRADE LEVEL:112-T12,T1,KH2 INSTALLATION
MH-ME-600 Installations 4 12-Sep-14 15-Sep-14 Installations
FIRST LEVEL:VESSELS
LEVEL 112-E5,E1,E2 INSTALATION 4 17-Sep-14 20-Sep-14 20-Sep-14, FIRST LEVEL:VESSELS 112-E5,E1,E2 INSTALATION
MH-ME-117 Installations 4 17-Sep-14 20-Sep-14 Installations
SECOND LEVEL:112-KH1,112-KH4
LEV (0402) INSTALLATION 5 22-Sep-14 26-Sep-14 26-Sep-14, SECOND LEVEL:112-KH1,112-KH4 (0402) INSTALLATION
MH-ME-159 Installations 5 22-Sep-14 26-Sep-14 Installations
COLUMN 106 16-Jul-14 30-Oct-14 30-Oct-14, COLUMN
112-K8 INSTALLATION
INSTA 30 16-Jul-14 15-Aug-14 15-Aug-14, 112-K8 INSTALLATION
MH-ME-390 Installations 30 16-Jul-14* 15-Aug-14 Installations
112-K2 INSTALLATION
INSTA 12 17-Jul-14 29-Jul-14 29-Jul-14, 112-K2 INSTALLATION
MH-ME-400 Installations 12 17-Jul-14* 29-Jul-14 Installations
112-K3 INSTALLATION
INSTA 12 18-Jul-14 30-Jul-14 30-Jul-14, 112-K3 INSTALLATION
MH-ME-370 Installations 12 18-Jul-14* 30-Jul-14 Installations
112-K6 INSTALLATION
INSTA 15 18-Jul-14 02-Aug-14 02-Aug-14, 112-K6 INSTALLATION
MH-ME-380 Installations 15 18-Jul-14* 02-Aug-14 Installations
112-K1 INSTALLATION
INSTA 25 18-Jul-14 12-Aug-14 12-Aug-14, 112-K1 INSTALLATION
MH-ME-130 Installations 25 18-Jul-14* 12-Aug-14 Installations
112-K5;112-K7 INSTALLATION 60 17-Jul-14 15-Sep-14 15-Sep-14, 112-K5;112-K7 INSTALLATION
MH-ME-450 Installations 60 17-Jul-14* 15-Sep-14 Installations
112-K4 INSTALLATION
INSTA 60 31-Aug-14 30-Oct-14 30-Oct-14, 112-K4 INSTALLATION
MH-ME-132 Installations 60 31-Aug-14* 30-Oct-14 Installations
U/G VESSELS & PUMPS 110-E3/N3,E4/N4,E2/N2,E1/N1 A/B INSTALL 10 28-Sep-14 07-Oct-14 07-Oct-14, U/G VESSELS & PUMPS 110-E3/N3,E4/N4,E2/N2,E1/N1 A/B I
MH-ME-1100 Installations 10 28-Sep-14 07-Oct-14 Installations
EJECTOR RECEIVER
REC 112-E8 INSTALLATION 7 08-Oct-14 14-Oct-14 14-Oct-14, EJECTOR RECEIVER 112-E8 INSTALLATION
MH-ME-1270 Installations 7 08-Oct-14 14-Oct-14 Installations
112-E3 INSTALLATION
INSTAL 2 18-Aug-14 20-Aug-14 20-Aug-14, 112-E3 INSTALLATION
MH-ME-1440 Installations 2 18-Aug-14 20-Aug-14* Installations
112-N22A INSTALLATION
INST 5 20-Aug-14 25-Aug-14 25-Aug-14, 112-N22A INSTALLATION
A10010 Installations 5 20-Aug-14 25-Aug-14 Installations
112-N23A INSTALLATION
INST 5 25-Aug-14 30-Aug-14 30-Aug-14, 112-N23A INSTALLATION
A10020 Installations 5 25-Aug-14 30-Aug-14 Installations

Primary Baseline Actual Work Critical Remaining Work Page 15 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
SECTION-4 115 16-Aug-14 08-Dec-14 08-Dec-14, SECTION-4
TAIL GAS COM
COMPRESSOR (40MTR) INSTALATION 47 16-Aug-14 01-Oct-14 01-Oct-14, TAIL GAS COMPRESSOR (40MTR) INSTALATION
MH-ME-700 Installations 47 16-Aug-14 01-Oct-14 Installations
PSA,VESSELS,DRUM & VALVE SKID(90MTR) INSTALLATION
PSA,VESSELS, 67 03-Oct-14 08-Dec-14 08-Dec-14, PSA,VESSELS,DRUM & VALVE SKID(90MTR) IN
MH-ME-1400 Installations 67 03-Oct-14 08-Dec-14 Installations
PIPING WORKS-KG
WORKS 670 26-Oct-13 26-Aug-15 26-Aug-15, PIPI
PIPE RACKS 211 12-Mar-14 08-Oct-14 08-Oct-14, PIPE RACKS
SECTION-8 90 12-Mar-14 09-Jun-14 09-Jun-14, SECTION-8
MH-ME-2130 Pipe Installation on Rack 90 12-Mar-14 09-Jun-14 Pipe Installation on Rack
SECTION-3 40 12-Mar-14 20-Apr-14 20-Apr-14, SECTION-3
MH-ME-2190 Pipe Installation on Rack 40 12-Mar-14 20-Apr-14 Pipe Installation on Rack
SECTION-2 80 25-May-14 12-Aug-14 12-Aug-14, SECTION-2
MH-ME-2180 Pipe Installation on Rack 80 25-May-14 12-Aug-14 Pipe Installation on Rack
SECTION-7 20 10-Jun-14 29-Jun-14 29-Jun-14, SECTION-7
MH-ME-2160 Pipe Installation on Rack 20 10-Jun-14 29-Jun-14 Pipe Installation on Rack
SECTION-1 90 09-Jul-14 06-Oct-14 06-Oct-14, SECTION-1
MH-ME-2150 Pipe Installation on Rack 90 09-Jul-14 06-Oct-14 Pipe Installation on Rack
SECTION-6 70 10-Jul-14 17-Sep-14 17-Sep-14, SECTION-6
MH-ME-2140 Pipe Installation on Rack 70 10-Jul-14 17-Sep-14 Pipe Installation on Rack
SECTION-4 20 19-Sep-14 08-Oct-14 08-Oct-14, SECTION-4
MH-ME-2170 Pipe Installation on Rack 20 19-Sep-14 08-Oct-14 Pipe Installation on Rack
SECTION-9 341 26-Oct-13 01-Oct-14 01-Oct-14, SECTION-9
MH-ME-2390 Piping Prefabrication 90 25-Feb-14 25-May-14 Piping Prefabrication
MH-ME-2400 U/G Piping Prefabrication 30 26-Oct-13 24-Nov-13 U/G Piping Prefabrication
MH-ME-2410 U/G Pipng Erection & test 30 01-Mar-14 30-Mar-14 U/G Pipng Erection & test
MH-ME-2420 A/G Pipng Erection & test 90 11-May-14 08-Aug-14 A/G Pipng Erection & test
MH-ME-2430 Equipment Connections 70 11-Jun-14 19-Aug-14 Equipment Connections
MH-ME-2440 Pipe & support installation in unit,valves,interconnection 60 09-Jul-14 06-Sep-14 Pipe & support installation in unit,valves,interconnection
MH-ME-2450 Lines hydrotest(100%) 55 08-Aug-14 01-Oct-14 Lines hydrotest(100%)
SECTION-8 367 25-Nov-13 26-Nov-14 26-Nov-14, SECTION-8
MH-ME-2530 Piping Prefabrication 110 17-Mar-14 04-Jul-14 Piping Prefabrication
MH-ME-2540 U/G Piping Prefabrication 30 25-Nov-13 24-Dec-13 U/G Piping Prefabrication
MH-ME-2550 U/G Pipng Erection & test 30 31-Mar-14 29-Apr-14 U/G Pipng Erection & test
MH-ME-2560 A/G Pipng Erection & test 120 31-May-14 27-Sep-14 A/G Pipng Erection & test
MH-ME-2570 Equipment Connections 120 15-Jun-14 12-Oct-14 Equipment Connections
MH-ME-2580 Pipe & support installation in unit,valves,interconnection 120 10-Jul-14 06-Nov-14 Pipe & support installation in unit,valves,interconnection
MH-ME-2590 Lines hydrotest(100%) 120 30-Jul-14 26-Nov-14 Lines hydrotest(100%)
SECTION-3 337 25-Dec-13 26-Nov-14 26-Nov-14, SECTION-3
MH-ME-2460 Piping Prefabrication 90 06-Apr-14 04-Jul-14 Piping Prefabrication
MH-ME-2470 U/G Piping Prefabrication 30 25-Dec-13 23-Jan-14 U/G Piping Prefabrication
MH-ME-2480 U/G Pipng Erection & test 30 30-Apr-14 29-May-14 U/G Pipng Erection & test
MH-ME-2490 A/G Pipng Erection & test 110 10-Jun-14 27-Sep-14 A/G Pipng Erection & test
MH-ME-2500 Equipment Connections 100 25-Jun-14 02-Oct-14 Equipment Connections
MH-ME-2510 Pipe & support installation in unit,valves,interconnection 100 10-Jul-14 17-Oct-14 Pipe & support installation in unit,valves,interconnection
MH-ME-2520 Lines hydrotest(100%) 110 09-Aug-14 26-Nov-14 Lines hydrotest(100%)
SECTION-2 242 16-May-14 13-Jan-15 13-Jan-15, SECTION-2
MH-ME-2200 Piping Prefabrication 100 16-May-14 23-Aug-14 Piping Prefabrication
MH-ME-2210 A/G Pipng Erection & test 120 05-Jul-14 01-Nov-14 A/G Pipng Erection & test
MH-ME-2220 Equipment Connections 110 01-Aug-14 19-Nov-14 Equipment Connections
MH-ME-2230 Pipe & support installation in unit,valves,interconnection 110 26-Aug-14 14-Dec-14 Pipe & support installation in unit,valves,interconnection

Primary Baseline Actual Work Critical Remaining Work Page 16 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-ME-2240 Lines hydrotest(100%) 120 15-Sep-14 13-Jan-15 Lines hydrotest(100%)
SECTION-7 364 24-Jan-14 23-Jan-15 23-Jan-15, SECTION-7
MH-ME-2600 Piping Prefabrication 80 30-Jun-14 17-Sep-14 Piping Prefabrication
MH-ME-2610 U/G Piping Prefabrication 45 24-Jan-14 09-Mar-14 U/G Piping Prefabrication
MH-ME-2620 U/G Pipng Erection & test 45 30-May-14 13-Jul-14 U/G Pipng Erection & test
MH-ME-2630 A/G Pipng Erection & test 100 19-Aug-14 26-Nov-14 A/G Pipng Erection & test
MH-ME-2640 Equipment Connections 90 13-Sep-14 11-Dec-14 Equipment Connections
MH-ME-2650 Pipe & support installation in unit,valves,interconnection 90 05-Oct-14 03-Jan-15 Pipe & support installation in unit,valves,interconnection
MH-ME-2660 Lines hydrotest(100%) 90 25-Oct-14 23-Jan-15 Lines hydrotest(100%)
SECTION-6 462 10-Mar-14 14-Jun-15 14-Jun-15, SECTION-6
MH-ME-2250 Piping Prefabrication 110 14-Aug-14 01-Dec-14 Piping Prefabrication
MH-ME-2260 U/G Piping Prefabrication 30 10-Mar-14 08-Apr-14 U/G Piping Prefabrication
MH-ME-2270 U/G Pipng Erection & test 30 14-Jul-14 12-Aug-14 U/G Pipng Erection & test
MH-ME-2280 A/G Pipng Erection & test 115 13-Oct-14 04-Feb-15 A/G Pipng Erection & test
MH-ME-2290 Equipment Connections 100 12-Dec-14 21-Mar-15 Equipment Connections
MH-ME-2300 Pipe & support installation in unit,valves,interconnection 105 26-Jan-15 10-May-15 Pipe & support installation in unit,v
MH-ME-2310 Lines hydrotest(100%) 105 02-Mar-15 14-Jun-15 Lines hydrotest(100%)
SECTION-1 447 09-Apr-14 29-Jun-15 29-Jun-15, SECTION-1
MH-ME-2320 Piping Prefabrication 110 08-Sep-14 26-Dec-14 Piping Prefabrication
MH-ME-2330 U/G Piping Prefabrication 58 09-Apr-14 05-Jun-14 U/G Piping Prefabrication
MH-ME-2340 U/G Pipng Erection & test 63 13-Aug-14 14-Oct-14 U/G Pipng Erection & test
MH-ME-2350 A/G Pipng Erection & test 130 09-Nov-14 18-Mar-15 A/G Pipng Erection & test
MH-ME-2360 Equipment Connections 110 29-Dec-14 17-Apr-15 Equipment Connections
MH-ME-2370 Pipe & support installation in unit,valves,interconnection 115 02-Feb-15 27-May-15 Pipe & support installation in un
MH-ME-2380 Lines hydrotest(100%) 110 12-Mar-15 29-Jun-15 Lines hydrotest(100%)
SECTION-5 447 06-Jun-14 26-Aug-15 26-Aug-15, SEC
MH-ME-2670 Piping Prefabrication 115 18-Sep-14 10-Jan-15 Piping Prefabrication
MH-ME-2680 U/G Piping Prefabrication 45 06-Jun-14 20-Jul-14 U/G Piping Prefabrication
MH-ME-2690 U/G Pipng Erection & test 45 02-Sep-14 16-Oct-14 U/G Pipng Erection & test
MH-ME-2700 A/G Pipng Erection & test 127 30-Nov-14 05-Apr-15 A/G Pipng Erection & test
MH-ME-2710 Equipment Connections 122 19-Jan-15 20-May-15 Equipment Connections
MH-ME-2720 Pipe & support installation in unit,valves,interconnection 122 02-Feb-15 03-Jun-15 Pipe & support installation in u
MH-ME-2730 Lines hydrotest(100%) 135 14-Apr-15 26-Aug-15 Lines hydrotest
SECTION-4 291 12-Jul-14 28-Apr-15 28-Apr-15, SECTION-4
MH-ME-2740 Piping Prefabrication 54 16-Oct-14 08-Dec-14 Piping Prefabrication
MH-ME-2750 U/G Piping Prefabrication 28 12-Jul-14 08-Aug-14 U/G Piping Prefabrication
MH-ME-2760 U/G Pipng Erection & test 28 25-Sep-14 22-Oct-14 U/G Pipng Erection & test
MH-ME-2770 A/G Pipng Erection & test 55 29-Dec-14 22-Feb-15 A/G Pipng Erection & test
MH-ME-2780 Equipment Connections 50 23-Jan-15 13-Mar-15 Equipment Connections
MH-ME-2790 Pipe & support installation in unit,valves,interconnection 45 08-Feb-15 24-Mar-15 Pipe & support installation in unit,valves,int
MH-ME-2800 Lines hydrotest(100%) 45 15-Mar-15 28-Apr-15 Lines hydrotest(100%)
PAINTING & INSULATION
INS (EQUIPMENT & PIPING) 299 06-Oct-14 01-Aug-15 01-Aug-15, PAINTIN
SECTION-9 97 06-Oct-14 10-Jan-15 10-Jan-15, SECTION-9
MH-ME-0830 111-E11,E12 Painting & Insulation works 20 06-Oct-14 25-Oct-14 111-E11,E12 Painting & Insulation works
MH-ME-1390 111-N5 A/B,6 A/B,7 Painting & Insulation works 29 08-Nov-14 06-Dec-14 111-N5 A/B,6 A/B,7 Painting & Insulation works
MH-ME-1990 111-RV1,ME3,ME4 Painting & Insulation works 28 06-Dec-14 03-Jan-15 111-RV1,ME3,ME4 Painting & Insulation works
MH-ME-2080 Piping Painting & Insulation works 15 26-Dec-14 10-Jan-15 Piping Painting & Insulation works
SECTION-8 161 10-Jan-15 20-Jun-15 20-Jun-15, SECTION-8
MH-ME-0470 112-K8,2,3,6 Painting & Insulation works 12 10-Jan-15 22-Jan-15 112-K8,2,3,6 Painting & Insulation works

Primary Baseline Actual Work Critical Remaining Work Page 17 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-ME-0520 112-K5,7 Painting & Insulati on works 8 23-Jan-15 31-Jan-15 112-K5,7 Painting & Insulati on works
MH-ME-0650 112-T12,1,KH2 Painting & Insulation works 13 31-Jan-15 13-Feb-15 112-T12,1,KH2 Painting & Insulation works
MH-ME-0720 112-T2,3,4,5,6,112-E4 Painting & Insulation works 20 13-Feb-15 05-Mar-15 112-T2,3,4,5,6,112-E4 Painting & Insulation work
MH-ME-0750 112-T7,9,10,11,ME15,E9,KH10,ME5,ME4 Painting & Insulation w 20 18-Feb-15 10-Mar-15 112-T7,9,10,11,ME15,E9,KH10,ME5,ME4 Pain
MH-ME-1240 112-E5,1,2 Painting & Insulation works 16 23-Feb-15 11-Mar-15 112-E5,1,2 Painting & Insulation works
MH-ME-1280 110-E3/N3,E4/N4,E2/N2,E1/ N1 A/B Painting & Insulation works 19 25-Feb-15 16-Mar-15 110-E3/N3,E4/N4,E2/N2,E1/ N1 A/B Painting
MH-ME-1350 112-K1 Painting & Insulation works 13 17-Mar-15 29-Mar-15 112-K1 Painting & Insulation works
MH-ME-1380 112-ME8,9,10,11,112-T8 Painting & Insulation works 19 30-Mar-15 18-Apr-15 112-ME8,9,10,11,112-T8 Painting & Insu
MH-ME-1410 112-K4 Painting & Insulation works 22 20-Apr-15 11-May-15 112-K4 Painting & Insulation works
MH-ME-1460 112-E3 & E8 Painting & Insulation works 11 21-Apr-15 01-May-15 112-E3 & E8 Painting & Insulation w
MH-ME-1630 112-KH1,KH4(04,02) Painting & Insulation works 19 26-Apr-15 14-May-15 112-KH1,KH4(04,02) Painting & In
MH-ME-1635 112-AV02 Painting & Insulation works 10 01-May-15 10-May-15 112-AV02 Painting & Insulation wor
MH-ME-1655 112-N22A & N23A Painting & Insulation works 15 06-May-15 20-May-15 112-N22A & N23A Painting & Ins
MH-ME-1790 Piping Painting & Insulation works 30 22-May-15 20-Jun-15 Piping Painting & Insulation
SECTION-3 55 16-Feb-15 12-Apr-15 12-Apr-15, SECTION-3
MH-ME-0850 112-R2 Painting & Insulation works 45 16-Feb-15 02-Apr-15 112-R2 Painting & Insulation works
MH-ME-0870 110-ME1 Painting & Insulati on works 10 21-Feb-15 03-Mar-15 110-ME1 Painting & Insulati on works
MH-ME-1470 112-R1 Painting & Insulation works 45 26-Feb-15 12-Apr-15 112-R1 Painting & Insulation works
MH-ME-2100 Piping Painting & Insulation works 30 28-Feb-15 30-Mar-15 Piping Painting & Insulation works
SECTION-2 47 03-Apr-15 20-May-15 20-May-15, SECTION-2
MH-ME-0460 111-T3,T6 A/B, T5 A/B Painting & Insulation works 13 03-Apr-15 16-Apr-15 111-T3,T6 A/B, T5 A/B Painting & Insul
MH-ME-0930 111-T4 A/B, T2 A/B, T1 Painting & Insulation works 13 05-Apr-15 18-Apr-15 111-T4 A/B, T2 A/B, T1 Painting & Insu
MH-ME-0980 111-T11,111-T9 Painting & Insulation works 23 05-Apr-15 28-Apr-15 111-T11,111-T9 Painting & Insulation
MH-ME-1000 111-E4 Painting & Insulation works 14 07-Apr-15 21-Apr-15 111-E4 Painting & Insulation works
MH-ME-1150 111-E2,111-E3 Painting & Insulation works 19 09-Apr-15 28-Apr-15 111-E2,111-E3 Painting & Insulation w
MH-ME-1190 111-E1, E9 & 10 Painting & Insulation works 15 11-Apr-15 26-Apr-15 111-E1, E9 & 10 Painting & Insulation
MH-ME-1330 Open Pump Station-2 Painting & Insulation works 12 16-Apr-15 29-Apr-15 Open Pump Station-2 Painting & Insul
MH-ME-1490 111-T7,T8A, T8 B Painting & Insulation works 23 16-Apr-15 10-May-15 111-T7,T8A, T8 B Painting & Insula
MH-ME-1500 111-T10A, T10B Painting & Insulation works 21 16-Apr-15 08-May-15 111-T10A, T10B Painting & Insulati
MH-ME-1520 111-E5 Painting & Insulation works 18 18-Apr-15 06-May-15 111-E5 Painting & Insulation works
MH-ME-1610 OPS-1, 111-N2 A/B, 3 A/B, 4 A/B, 9 Painting & Insulation works 15 22-Apr-15 07-May-15 OPS-1, 111-N2 A/B, 3 A/B, 4 A/B, 9
MH-ME-1640 111-H1 & K1 Painting & Insulation works 12 24-Apr-15 06-May-15 111-H1 & K1 Painting & Insulation w
MH-ME-1645 111-AV01 & AV02 Painting & Insulation works 15 29-Apr-15 14-May-15 111-AV01 & AV02 Painting & Insul
MH-ME-1730 Piping Painting & Insulation works 20 30-Apr-15 20-May-15 Piping Painting & Insulation work
SECTION-7 54 16-May-15 08-Jul-15 08-Jul-15, SECTION-7
MH-ME-1620 112-N1 A/B,2 A/B,3 A/B,5 A/B,13 A/B Painting & Insulation work 12 16-May-15 28-May-15 112-N1 A/B,2 A/B,3 A/B,5 A/B,
MH-ME-1830 112-N4 A/B,6 A/B,7 A/B,8 A/B,9 A/B,10 A/B,11 A/B,12 A/B,18 A 20 18-May-15 07-Jun-15 112-N4 A/B,6 A/B,7 A/B,8 A/B
MH-ME-1935 112-AV01 & AV06 Painting & Insulation works 15 28-May-15 12-Jun-15 112-AV01 & AV06 Painting &
MH-ME-2090 Piping Painting & Insulation works 18 21-Jun-15 08-Jul-15 Piping Painting & Insula
SECTION-6 50 18-May-15 07-Jul-15 07-Jul-15, SECTION-6
MH-ME-0660 OPS-4, 110-N5 A,B,C,D, 110-N6 A/B Painting & Insulation works 15 18-May-15 02-Jun-15 OPS-4, 110-N5 A,B,C,D, 110-N6
MH-ME-0950 112-K10 Painting & Insulation works 14 20-May-15 03-Jun-15 112-K10 Painting & Insulation
MH-ME-0960 112-K9 Painting & Insulation works 2 03-Jun-15 05-Jun-15 112-K9 Painting & Insulation w
MH-ME-1680 112-T14 Painting & Insulation works 6 05-Jun-15 11-Jun-15 112-T14 Painting & Insulation
MH-ME-1710 112-E7,Kh3,E6,ME2 Painting & Insulation works 10 11-Jun-15 21-Jun-15 112-E7,Kh3,E6,ME2 Paintin
MH-ME-1780 112-Kh 5,6,8 Painting & Insulation works 6 13-Jun-15 19-Jun-15 112-Kh 5,6,8 Painting & Insu
MH-ME-1800 110-E 9,10,8,11,13,7 , 113-KH2Painting & Insulation works 10 17-Jun-15 27-Jun-15 110-E 9,10,8,11,13,7 , 113-K
MH-ME-1870 112-Kh 7,9 Painting & Insulation works 5 18-Jun-15 23-Jun-15 112-Kh 7,9 Painting & Insul

Primary Baseline Actual Work Critical Remaining Work Page 18 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-ME-1880 110-E5 A/B, E6 Painting & Insulation works 15 21-Jun-15 06-Jul-15 110-E5 A/B, E6 Painting
MH-ME-1910 112-K11 Painting & Insulation works 10 23-Jun-15 02-Jul-15 112-K11 Painting & Insula
MH-ME-1980 112-T13 Painting & Insulation works 9 25-Jun-15 04-Jul-15 112-T13 Painting & Insula
MH-ME-1985 112-N24A, 25A Painting & Insulation works 10 26-Jun-15 06-Jul-15 112-N24A, 25A Painting
MH-ME-2000 Piping Painting & Insulation works 10 27-Jun-15 07-Jul-15 Piping Painting & Insula
SECTION-1 41 20-May-15 30-Jun-15 30-Jun-15, SECTION-1
MH-ME-1600 BUILD O/D Equipment 111-E6,7,8 Painting & Insulation works 10 20-May-15 30-May-15 BUILD O/D Equipment 111-E6,
MH-ME-1860 Piping Electrical Tracing Painting & Insulation works 35 21-May-15 25-Jun-15 Piping Electrical Tracing P
MH-ME-1930 Piping Painting & Insulation works 35 26-May-15 30-Jun-15 Piping Painting & Insulati
SECTION-5 36 31-May-15 05-Jul-15 05-Jul-15, SECTION-5
MH-ME-1180 OPS Pumps Painting & Insulation works (Structure D) 20 31-May-15 20-Jun-15 OPS Pumps Painting & Insu
MH-ME-2070 Piping Painting & Insulation works 15 21-Jun-15 05-Jul-15 Piping Painting & Insulat
SECTION-4 24 08-Jul-15 01-Aug-15 01-Aug-15, SECTIO
A10130 Tail gas compressor Painting & Insulation works 10 08-Jul-15 18-Jul-15 Tail gas compressor Pa
A10140 PSA, Vessel, Drum & valve skid Painting & Insulation works 10 13-Jul-15 23-Jul-15 PSA, Vessel, Drum &
MH-ME-2010 Piping Painting & Insulation works 13 19-Jul-15 01-Aug-15 Piping Painting & In
MILD HYDROCRACKING
HYDRO UNIT-ELECTRICAL & TELECOM 415 13-May-14 02-Jul-15 02-Jul-15, MILD HYDRO
BUILDING ELECTRICAL
ELEC WORKS 366 13-May-14 14-May-15 14-May-15, BUILDING ELECTRI
SECTION-1 366 13-May-14 14-May-15 14-May-15, SECTION-1
MH-EL-350 S/S room hand over in cleaning condtions 0 13-May-14 S/S room hand over in cleaning condtions
MH-EL-370 Trays installation in SS building and CCR 43 14-May-14 25-Jun-14 Trays installation in SS building and CCR
MH-EL-380 S/S Switch gear & DB Erection 45 16-May-14 30-Jun-14 S/S Switch gear & DB Erection
MH-EL-520 MV/LV Cable laying 40 26-May-14 05-Jul-14 MV/LV Cable laying
MH-EL-530 Grounding Grid A/G 38 05-Jun-14 13-Jul-14 Grounding Grid A/G
MH-EL-630 Groundind grid connections A/G to Equipment 25 13-Jul-14 07-Aug-14 Groundind grid connections A/G to Equipment
MH-EL-640 Indoor & Outdoor Panels 28 23-Jul-14 20-Aug-14 Indoor & Outdoor Panels
MH-EL-760 Lighting Protection 28 15-Aug-14 12-Sep-14 Lighting Protection
MH-EL-770 Cable Connection S/S-MK/Panel-Equipment 35 25-Aug-14 29-Sep-14 Cable Connection S/S-MK/Panel-Equipment
MH-EL-830 Cable loop check 30 29-Sep-14 29-Oct-14 Cable loop check
MH-EL-860 KTP/SWG/Capacitor bank testing 30 29-Oct-14 28-Nov-14 KTP/SWG/Capacitor bank testing
MH-EL-870 Protection/Control system/Interlocks 64 08-Nov-14 11-Jan-15 Protection/Control system/Interlocks
MH-EL-910 MV link to 6.6KV Grid 56 26-Nov-14 21-Jan-15 MV link to 6.6KV Grid
MH-EL-920 MV cable sealing ends 60 06-Dec-14 04-Feb-15 MV cable sealing ends
MH-EL-960 6.6 KV Energization 30 04-Feb-15 06-Mar-15 6.6 KV Energization
MH-EL-970 0,4 KV Energization 30 06-Mar-15 05-Apr-15 0,4 KV Energization
MH-EL-980 Substation unit Energization 0 05-Apr-15 Substation unit Energization
MH-EL-990 DCS system readiness 39 05-Apr-15 14-May-15 DCS system readiness
FIELD ELECTRICAL
ELECTR WORKS 328 09-Aug-14 02-Jul-15 02-Jul-15, FIELD ELECT
SECTION-9 216 09-Aug-14 12-Mar-15 12-Mar-15, SECTION-9
MH-EL-360 Trays Installation in field 45 09-Aug-14 23-Sep-14 Trays Installation in field
MH-EL-430 Earthing works 56 19-Aug-14 13-Oct-14 Earthing works
MH-EL-431 Electrical Heat Tracing 37 28-Sep-14 03-Nov-14 Electrical Heat Tracing
MH-EL-550 Lighting protection 49 07-Oct-14 25-Nov-14 Lighting protection
MH-EL-700 HV/MV/LV cable laying 44 26-Oct-14 09-Dec-14 HV/MV/LV cable laying
MH-EL-780 Electrical Equipment installation 46 17-Nov-14 02-Jan-15 Electrical Equipment installation
MH-EL-900 Cable Terminations 42 05-Dec-14 16-Jan-15 Cable Terminations
MH-EL-940 Testing cables & Equipments 42 04-Jan-15 15-Feb-15 Testing cables & Equipments
MH-EL-950 Lighting works 45 26-Jan-15 12-Mar-15 Lighting works
SECTION-8 266 14-Aug-14 06-May-15 06-May-15, SECTION-8

Primary Baseline Actual Work Critical Remaining Work Page 19 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-EL-400 Trays Installation in field 60 14-Aug-14 13-Oct-14 Trays Installation in field
MH-EL-440 Earthing works 75 03-Sep-14 17-Nov-14 Earthing works
MH-EL-441 Electrical Heat Tracing 75 08-Oct-14 22-Dec-14 Electrical Heat Tracing
MH-EL-470 Lighting protection 75 18-Oct-14 01-Jan-15 Lighting protection
MH-EL-580 HV/MV/LV cable laying 80 07-Nov-14 26-Jan-15 HV/MV/LV cable laying
MH-EL-620 Electrical Equipment installation 90 27-Nov-14 25-Feb-15 Electrical Equipment installation
MH-EL-740 Cable Terminations 80 15-Dec-14 05-Mar-15 Cable Terminations
MH-EL-800 Testing cables & Equipments 90 14-Jan-15 14-Apr-15 Testing cables & Equipments
MH-EL-820 Lighting works 90 05-Feb-15 06-May-15 Lighting works
SECTION-3 235 29-Aug-14 21-Apr-15 21-Apr-15, SECTION-3
MH-EL-040 Trays Installation in field 55 29-Aug-14 23-Oct-14 Trays Installation in field
MH-EL-060 Earthing works 60 13-Sep-14 12-Nov-14 Earthing works
MH-EL-061 Electrical Heat Tracing 60 18-Oct-14 17-Dec-14 Electrical Heat Tracing
MH-EL-070 Lighting protection 64 28-Oct-14 31-Dec-14 Lighting protection
MH-EL-130 HV/MV/LV cable laying 67 17-Nov-14 23-Jan-15 HV/MV/LV cable laying
MH-EL-180 Electrical Equipment installation 62 07-Dec-14 06-Feb-15 Electrical Equipment installation
MH-EL-270 Cable Terminations 78 25-Dec-14 13-Mar-15 Cable Terminations
MH-EL-300 Testing cables & Equipments 53 24-Jan-15 18-Mar-15 Testing cables & Equipments
MH-EL-340 Lighting works 65 15-Feb-15 21-Apr-15 Lighting works
SECTION-2 261 08-Sep-14 26-May-15 26-May-15, SECTION-2
MH-EL-030 Trays Installation in field 90 08-Sep-14 07-Dec-14 Trays Installation in field
MH-EL-050 Earthing works 95 23-Sep-14 27-Dec-14 Earthing works
MH-EL-051 Electrical Heat Tracing 90 28-Oct-14 26-Jan-15 Electrical Heat Tracing
MH-EL-090 Lighting protection 90 07-Nov-14 05-Feb-15 Lighting protection
MH-EL-100 HV/MV/LV cable laying 92 27-Nov-14 27-Feb-15 HV/MV/LV cable laying
MH-EL-160 Electrical Equipment installation 88 12-Dec-14 10-Mar-15 Electrical Equipment installation
MH-EL-250 Cable Terminations 90 04-Jan-15 04-Apr-15 Cable Terminations
MH-EL-310 Testing cables & Equipments 92 03-Feb-15 06-May-15 Testing cables & Equipments
MH-EL-490 Lighting works 90 25-Feb-15 26-May-15 Lighting works
SECTION-7 251 03-Oct-14 10-Jun-15 10-Jun-15, SECTION-7
MH-EL-120 Trays Installation in field 85 03-Oct-14 27-Dec-14 Trays Installation in field
MH-EL-170 Earthing works 90 12-Oct-14 09-Jan-15 Earthing works
MH-EL-171 Electrical Heat Tracing 83 07-Nov-14 29-Jan-15 Electrical Heat Tracing
MH-EL-260 Lighting protection 92 12-Nov-14 12-Feb-15 Lighting protection
MH-EL-390 HV/MV/LV cable laying 89 07-Dec-14 06-Mar-15 HV/MV/LV cable laying
MH-EL-450 Electrical Equipment installation 75 17-Dec-14 02-Mar-15 Electrical Equipment installation
MH-EL-570 Cable Terminations 92 14-Jan-15 16-Apr-15 Cable Terminations
MH-EL-650 Testing cables & Equipments 93 13-Feb-15 17-May-15 Testing cables & Equipments
MH-EL-730 Lighting works 95 07-Mar-15 10-Jun-15 Lighting works
SECTION-6 237 23-Oct-14 16-Jun-15 16-Jun-15, SECTION-6
MH-EL-110 Trays Installation in field 90 23-Oct-14 21-Jan-15 Trays Installation in field
MH-EL-150 Earthing works 90 01-Nov-14 30-Jan-15 Earthing works
MH-EL-151 Electrical Heat Tracing 82 17-Nov-14 07-Feb-15 Electrical Heat Tracing
MH-EL-240 Lighting protection 84 20-Nov-14 11-Feb-15 Lighting protection
MH-EL-330 HV/MV/LV cable laying 78 17-Dec-14 05-Mar-15 HV/MV/LV cable laying
MH-EL-480 Electrical Equipment installation 70 22-Dec-14 02-Mar-15 Electrical Equipment installation
MH-EL-670 Cable Terminations 83 24-Jan-15 17-Apr-15 Cable Terminations
MH-EL-810 Testing cables & Equipments 83 23-Feb-15 17-May-15 Testing cables & Equipments

Primary Baseline Actual Work Critical Remaining Work Page 20 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-EL-880 Lighting works 90 18-Mar-15 16-Jun-15 Lighting works
SECTION-1 215 02-Nov-14 04-Jun-15 04-Jun-15, SECTION-1
MH-EL-010 Trays Installation in field 74 02-Nov-14 15-Jan-15 Trays Installation in field
MH-EL-020 Earthing works 74 11-Nov-14 24-Jan-15 Earthing works
MH-EL-021 Electrical Heat Tracing 59 27-Nov-14 24-Jan-15 Electrical Heat Tracing
MH-EL-080 Lighting protection 56 07-Dec-14 01-Feb-15 Lighting protection
MH-EL-140 HV/MV/LV cable laying 62 05-Jan-15 08-Mar-15 HV/MV/LV cable laying
MH-EL-190 Electrical Equipment installation 63 15-Jan-15 19-Mar-15 Electrical Equipment installation
MH-EL-230 Cable Terminations 59 03-Feb-15 03-Apr-15 Cable Terminations
MH-EL-280 Testing cables & Equipments 59 05-Mar-15 03-May-15 Testing cables & Equipments
MH-EL-290 Lighting works 60 05-Apr-15 04-Jun-15 Lighting works
SECTION-5 169 27-Nov-14 14-May-15 14-May-15, SECTION-5
MH-EL-320 Trays Installation in field 46 27-Nov-14 12-Jan-15 Trays Installation in field
MH-EL-420 Earthing works 46 06-Dec-14 21-Jan-15 Earthing works
MH-EL-421 Electrical Heat Tracing 35 21-Dec-14 25-Jan-15 Electrical Heat Tracing
MH-EL-510 Lighting protection 37 31-Dec-14 07-Feb-15 Lighting protection
MH-EL-560 HV/MV/LV cable laying 36 15-Jan-15 20-Feb-15 HV/MV/LV cable laying
MH-EL-610 Electrical Equipment installation 38 29-Jan-15 08-Mar-15 Electrical Equipment installation
MH-EL-720 Cable Terminations 37 21-Feb-15 30-Mar-15 Cable Terminations
MH-EL-790 Testing cables & Equipments 31 15-Mar-15 15-Apr-15 Testing cables & Equipments
MH-EL-890 Lighting works 38 06-Apr-15 14-May-15 Lighting works
SECTION-4 198 17-Dec-14 02-Jul-15 02-Jul-15, SECTION-4
MH-EL-410 Trays Installation in field 40 17-Dec-14 26-Jan-15 Trays Installation in field
MH-EL-460 Earthing works 40 27-Dec-14 05-Feb-15 Earthing works
MH-EL-461 Electrical Heat Tracing 25 20-Jan-15 14-Feb-15 Electrical Heat Tracing
MH-EL-500 Lighting protection 27 23-Jan-15 19-Feb-15 Lighting protection
MH-EL-600 HV/MV/LV cable laying 41 12-Feb-15 25-Mar-15 HV/MV/LV cable laying
MH-EL-660 Electrical Equipment installation 27 13-Feb-15 12-Mar-15 Electrical Equipment installation
MH-EL-750 Cable Terminations 26 30-Mar-15 24-Apr-15 Cable Terminations
MH-EL-850 Testing cables & Equipments 29 25-Apr-15 24-May-15 Testing cables & Equipments
MH-EL-930 Lighting works 35 28-May-15 02-Jul-15 Lighting works
MILD HYDROCRACKING
HYDRO UNIT-INSTRUMENTATION 385 08-Sep-14 28-Sep-15 28-Sep-15
SECTION-1 149 08-Sep-14 04-Feb-15 04-Feb-15, SECTION-1
CONTROL ROOM
ROO 149 08-Sep-14 04-Feb-15 04-Feb-15, CONTROL ROOM
MH-INT-130 CCR-Handover in cleaning conditions 0 08-Sep-14 CCR-Handover in cleaning conditions
MH-INT-140 CCR-DCS Room Instrumentation works 80 08-Sep-14 27-Nov-14 CCR-DCS Room Instrumentation works
MH-INT-150 CCR-Trays Installation 79 13-Sep-14 30-Nov-14 CCR-Trays Installation
MH-INT-260 CCR-Cable laying and connections 78 28-Sep-14 15-Dec-14 CCR-Cable laying and connections
MH-INT-410 CCR-Panels Installation 60 27-Nov-14 26-Jan-15 CCR-Panels Installation
MH-INT-430 CCR-Tests 60 06-Dec-14 04-Feb-15 CCR-Tests
FIELD INSTRUM
INSTRUMENTATION WORKS 385 08-Sep-14 28-Sep-15 28-Sep-15
SECTION-9 367 08-Sep-14 10-Sep-15 10-Sep-15, S
MH-INT-160 Trays Installation 100 08-Sep-14 17-Dec-14 Trays Installation
MH-INT-190 Cable laying and connections 140 08-Oct-14 25-Feb-15 Cable laying and connections
MH-INT-300 Valves and local Instrumentation Installation 165 01-Mar-15 13-Aug-15 Valves and local I
MH-INT-301 PCS/PLC/DCS/ECS/F&G/Analyser Installation 90 01-Mar-15 30-May-15 PCS/PLC/DCS/ECS/F&G/Ana
MH-INT-302 Control Board Installation 90 01-Mar-15 30-May-15 Control Board Installation
MH-INT-350 Wiring and piping connections 85 30-May-15 23-Aug-15 Wiring and pipin
MH-INT-520 Test & Loop Check (P.P) 80 22-Jun-15 10-Sep-15 Test & Loop
Primary Baseline Actual Work Critical Remaining Work Page 21 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
SECTION-8 367 18-Sep-14 20-Sep-15 20-Sep-15,
MH-INT-170 Trays Installation 120 18-Sep-14 16-Jan-15 Trays Installation
MH-INT-200 Cable laying and connections 160 02-Nov-14 11-Apr-15 Cable laying and connections
MH-INT-330 Valves and local Instrumentation Installation 185 11-Mar-15 12-Sep-15 Valves and l
MH-INT-331 PCS/PLC/DCS/ECS/F&G/Analyser Installation 95 11-Mar-15 14-Jun-15 PCS/PLC/DCS/ECS/F&G/A
MH-INT-332 Control Board Installation 95 11-Mar-15 14-Jun-15 Control Board Installation
MH-INT-360 Wiring and piping connections 90 09-Jun-15 07-Sep-15 Wiring and pi
MH-INT-510 Test & Loop Check (P.P) 85 27-Jun-15 20-Sep-15 Test & Loo
SECTION-3 352 28-Sep-14 15-Sep-15 15-Sep-15, S
MH-INT-030 Trays Installation 111 28-Sep-14 17-Jan-15 Trays Installation
MH-INT-060 Cable laying and connections 150 22-Nov-14 21-Apr-15 Cable laying and connections
MH-INT-110 Valves and local Instrumentation Installation 155 17-Mar-15 18-Aug-15 Valves and local
MH-INT-111 PCS/PLC/DCS/ECS/F&G/Analyser Installation 80 17-Mar-15 04-Jun-15 PCS/PLC/DCS/ECS/F&G/Ana
MH-INT-112 Control Board Installation 80 17-Mar-15 04-Jun-15 Control Board Installation
MH-INT-459 Wiring and piping connections 75 14-Jun-15 28-Aug-15 Wiring and pip
MH-INT-460 Test & Loop Check (P.P) 70 07-Jul-15 15-Sep-15 Test & Loop
SECTION-2 352 08-Oct-14 25-Sep-15 25-Sep-15
MH-INT-020 Trays Installation 140 08-Oct-14 25-Feb-15 Trays Installation
MH-INT-040 Cable laying and connections 160 02-Dec-14 11-May-15 Cable laying and connections
MH-INT-250 Valves and local Instrumentation Installation 165 01-Apr-15 12-Sep-15 Valves and l
MH-INT-251 PCS/PLC/DCS/ECS/F&G/Analyser Installation 85 01-Apr-15 24-Jun-15 PCS/PLC/DCS/ECS/F&G/
MH-INT-252 Control Board Installation 85 01-Apr-15 24-Jun-15 Control Board Installation
MH-INT-449 Wiring and piping connections 80 19-Jun-15 07-Sep-15 Wiring and pi
MH-INT-450 Test & Loop Check (P.P) 75 12-Jul-15 25-Sep-15 Test & Lo
SECTION-1 332 18-Oct-14 15-Sep-15 15-Sep-15, S
MH-INT-010 Trays Installation 100 18-Oct-14 26-Jan-15 Trays Installation
MH-INT-050 Cable laying and connections 145 12-Dec-14 06-May-15 Cable laying and connections
MH-INT-220 Valves and local Instrumentation Installation 150 06-Apr-15 02-Sep-15 Valves and loc
MH-INT-221 PCS/PLC/DCS/ECS/F&G/Analyser Installation 70 06-Apr-15 14-Jun-15 PCS/PLC/DCS/ECS/F&G/A
MH-INT-222 Control Board Installation 70 06-Apr-15 14-Jun-15 Control Board Installation
MH-INT-439 Wiring and piping connections 65 05-Jun-15 08-Aug-15 Wiring and piping
MH-INT-440 Test & Loop Check (P.P) 60 17-Jul-15 15-Sep-15 Test & Loop
SECTION-7 334 28-Oct-14 27-Sep-15 27-Sep-15
MH-INT-070 Trays Installation 125 28-Oct-14 02-Mar-15 Trays Installation
MH-INT-080 Cable laying and connections 160 22-Dec-14 31-May-15 Cable laying and connections
MH-INT-290 Valves and local Instrumentation Installation 165 11-Apr-15 22-Sep-15 Valves and
MH-INT-291 PCS/PLC/DCS/ECS/F&G/Analyser Installation 80 11-Apr-15 29-Jun-15 PCS/PLC/DCS/ECS/F&G
MH-INT-292 Control Board Installation 80 11-Apr-15 29-Jun-15 Control Board Installation
MH-INT-420 Wiring and piping connections 75 10-Jun-15 23-Aug-15 Wiring and pipin
MH-INT-500 Test & Loop Check (P.P) 70 19-Jul-15 27-Sep-15 Test & Lo
SECTION-6 325 07-Nov-14 28-Sep-15 28-Sep-15
MH-INT-090 Trays Installation 110 07-Nov-14 25-Feb-15 Trays Installation
MH-INT-120 Cable laying and connections 150 01-Jan-15 31-May-15 Cable laying and connections
MH-INT-280 Valves and local Instrumentation Installation 155 16-Apr-15 17-Sep-15 Valves and
MH-INT-281 PCS/PLC/DCS/ECS/F&G/Analyser Installation 70 16-Apr-15 24-Jun-15 PCS/PLC/DCS/ECS/F&G/
MH-INT-282 Control Board Installation 70 16-Apr-15 24-Jun-15 Control Board Installation
MH-INT-400 Wiring and piping connections 65 05-Jun-15 08-Aug-15 Wiring and piping
MH-INT-490 Test & Loop Check (P.P) 60 30-Jul-15 28-Sep-15 Test & L
SECTION-5 317 12-Nov-14 25-Sep-15 25-Sep-15

Primary Baseline Actual Work Critical Remaining Work Page 22 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-INT-210 Trays Installation 110 12-Nov-14 02-Mar-15 Trays Installation
MH-INT-270 Cable laying and connections 155 26-Jan-15 30-Jun-15 Cable laying and connecti
MH-INT-390 Valves and local Instrumentation Installation 150 21-Apr-15 17-Sep-15 Valves and
MH-INT-391 PCS/PLC/DCS/ECS/F&G/Analyser Installation 68 21-Apr-15 27-Jun-15 PCS/PLC/DCS/ECS/F&G
MH-INT-392 Control Board Installation 68 21-Apr-15 27-Jun-15 Control Board Installation
MH-INT-479 Wiring and piping connections 65 10-Jun-15 13-Aug-15 Wiring and piping
MH-INT-480 Test & Loop Check (P.P) 55 01-Aug-15 25-Sep-15 Test & Lo
SECTION-4 308 24-Nov-14 28-Sep-15 28-Sep-15
MH-INT-230 Trays Installation 102 24-Nov-14 06-Mar-15 Trays Installation
MH-INT-320 Cable laying and connections 125 09-Feb-15 14-Jun-15 Cable laying and connections
MH-INT-370 Valves and local Instrumentation Installation 140 30-Apr-15 16-Sep-15 Valves and
MH-INT-371 PCS/PLC/DCS/ECS/F&G/Analyser Installation 54 30-Apr-15 22-Jun-15 PCS/PLC/DCS/ECS/F&G/
MH-INT-372 Control Board Installation 54 30-Apr-15 22-Jun-15 Control Board Installation
MH-INT-469 Wiring and piping connections 64 19-Jul-15 21-Sep-15 Wiring and
MH-INT-470 Test & Loop Check (P.P) 56 03-Aug-15 28-Sep-15 Test & L
MILD HYDROCRACKING
HYDRO UNIT-HSE 572 23-Dec-13 17-Jul-15 17-Jul-15, MILD HYDR
SECTION-9 78 23-Dec-13 10-Mar-14 10-Mar-14, SECTION-9
MH-FF-070 Prefabrication & Installation of fire fighting above ground system 60 23-Dec-13 20-Feb-14 Prefabrication & Installation of fire fighting above ground system
MH-FF-100 Installation of fire Extinguishers 18 21-Feb-14 10-Mar-14 Installation of fire Extinguishers
SECTION-8 111 21-Feb-14 11-Jun-14 11-Jun-14, SECTION-8
MH-FF-080 Prefabrication & Installation of fire fighting above ground system 90 21-Feb-14 21-May-14 Prefabrication & Installation of fire fighting above ground system
MH-FF-140 Installation of fire Extinguishers 21 22-May-14 11-Jun-14 Installation of fire Extinguishers
SECTION-3 79 22-May-14 08-Aug-14 08-Aug-14, SECTION-3
MH-FF-160 Prefabrication & Installation of fire fighting above ground system 60 22-May-14 20-Jul-14 Prefabrication & Installation of fire fighting above ground system
MH-FF-180 Installation of fire Extinguishers 19 21-Jul-14 08-Aug-14 Installation of fire Extinguishers
SECTION-2 151 03-Jul-14 30-Nov-14 30-Nov-14, SECTION-2
MH-FF-130 Prefabrication & Installation of fire fighting above ground system 106 03-Jul-14 16-Oct-14 Prefabrication & Installation of fire fighting above ground system
MH-FF-170 Installation of fire Extinguishers 45 17-Oct-14 30-Nov-14 Installation of fire Extinguishers
SECTION-1 62 17-Oct-14 17-Dec-14 17-Dec-14, SECTION-1
MH-FF-10 Prefabrication & Installation of fire fighting above ground system 45 17-Oct-14 30-Nov-14 Prefabrication & Installation of fire fighting above ground system
MH-FF-20 Installation of fire Extinguishers 17 01-Dec-14 17-Dec-14 Installation of fire Extinguishers
SECTION-7 80 01-Dec-14 18-Feb-15 18-Feb-15, SECTION-7
MH-FF-120 Prefabrication & Installation of fire fighting above ground system 60 01-Dec-14 29-Jan-15 Prefabrication & Installation of fire fighting above grou
MH-FF-150 Installation of fire Extinguishers 20 30-Jan-15 18-Feb-15 Installation of fire Extinguishers
SECTION-6 80 01-Feb-15 21-Apr-15 21-Apr-15, SECTION-6
MH-FF-050 Prefabrication & Installation of fire fighting above ground system 60 01-Feb-15 01-Apr-15 Prefabrication & Installation of fire fighting
MH-FF-110 Installation of fire Extinguishers 20 02-Apr-15 21-Apr-15 Installation of fire Extinguishers
SECTION-5 81 07-Apr-15 26-Jun-15 26-Jun-15, SECTION-5
MH-FF-60 Prefabrication & Installation of fire fighting above ground system 60 07-Apr-15 05-Jun-15 Prefabrication & Installation o
MH-FF-90 Installation of fire Extinguishers 21 06-Jun-15 26-Jun-15 Installation of fire Extingui
SECTION-4 60 19-May-15 17-Jul-15 17-Jul-15, SECTION-4
MH-FF-30 Prefabrication & Installation of fire fighting above ground system 45 19-May-15 02-Jul-15 Prefabrication & Installat
MH-FF-40 Installation of fire Extinguishers 15 03-Jul-15 17-Jul-15 Installation of fire Exti
MILD HYDROCRACKING
HYDRO UNIT-FIREPROOFING 149 04-Jun-15 31-Oct-15 31-
SECTION-9 9 04-Jun-15 12-Jun-15 12-Jun-15, SECTION-9
MH-FP-590 Fire proofing-OPS3 Shelter 5 04-Jun-15 08-Jun-15 Fire proofing-OPS3 Shelter
MH-FP-610 Fire proofing-111-E11,111-E12 5 06-Jun-15 10-Jun-15 Fire proofing-111-E11,111-E12
MH-FP-620 Fire proofing-111-N6 A/B,111-N5 A/B 5 08-Jun-15 12-Jun-15 Fire proofing-111-N6 A/B,111

Primary Baseline Actual Work Critical Remaining Work Page 23 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
SECTION-8 47 12-Jun-15 29-Jul-15 29-Jul-15, SECTION
MH-FP-280 Fire proofing-Pipe Rack 5 12-Jun-15 17-Jun-15 Fire proofing-Pipe Rack
MH-FP-300 Fire proofing-Structure E 5 17-Jun-15 21-Jun-15 Fire proofing-Structure E
MH-FP-320 Fire proofing-Structure R 5 21-Jun-15 26-Jun-15 Fire proofing-Structure R
MH-FP-340 Fire proofing-112-T1,T12 5 26-Jun-15 01-Jul-15 Fire proofing-112-T1,T12
MH-FP-360 Fire proofing-112-T4,112-ME-15,KH10,T5,T6,T7 5 01-Jul-15 05-Jul-15 Fire proofing-112-T4,112-
MH-FP-380 Fire proofing-112-K6,1,3,2,8 5 05-Jul-15 10-Jul-15 Fire proofing-112-K6,1,3
MH-FP-400 Fire proofing-112-E2 5 10-Jul-15 15-Jul-15 Fire proofing-112-E2
MH-FP-420 Fire proofing-112-E3 5 15-Jul-15 19-Jul-15 Fire proofing-112-E3
MH-FP-440 Fire proofing-112-K4 5 19-Jul-15 24-Jul-15 Fire proofing-112-K4
MH-FP-460 Fire proofing-112-K5/K7 5 24-Jul-15 29-Jul-15 Fire proofing-112-K5
SECTION-3 23 29-Jul-15 21-Aug-15 21-Aug-15, SEC
MH-FP-390 Fire proofing-Pipe Rack 5 29-Jul-15 02-Aug-15 Fire proofing-Pipe R
MH-FP-410 Fire proofing-Structure K 5 02-Aug-15 07-Aug-15 Fire proofing-Struc
MH-FP-430 Fire proofing-Pipe Rack 3.2 5 07-Aug-15 12-Aug-15 Fire proofing-Pipe
MH-FP-450 Fire proofing-111-P1,112-P1 5 12-Aug-15 16-Aug-15 Fire proofing-111-
MH-FP-470 Fire proofing-111-R1,111-R2 5 16-Aug-15 21-Aug-15 Fire proofing-111
SECTION-2 92 31-Jul-15 31-Oct-15 31-
MH-FP-030 Fire proofing-OPS2 Shelter 9 31-Jul-15 09-Aug-15 Fire proofing-OPS2
MH-FP-040 Fire proofing-111-N1 A,111-N1 B 6 09-Aug-15 14-Aug-15 Fire proofing-111-
MH-FP-050 Fire proofing-Structure T 6 14-Aug-15 20-Aug-15 Fire proofing-Str
MH-FP-060 Fire proofing-Structure A 6 20-Aug-15 25-Aug-15 Fire proofing-St
MH-FP-070 Fire proofing-Structure G 6 25-Aug-15 31-Aug-15 Fire proofing-S
MH-FP-080 Fire proofing-Structure V 6 31-Aug-15 05-Sep-15 Fire proofing-
MH-FP-090 Fire proofing-OPS1 Shelter 6 05-Sep-15 11-Sep-15 Fire proofing
MH-FP-100 Fire proofing-Pipe Rack(R90) 6 11-Sep-15 17-Sep-15 Fire proofin
MH-FP-110 Fire proofing-Structure B 6 17-Sep-15 22-Sep-15 Fire proofi
MH-FP-120 Fire proofing-111-E2,111-E3 6 22-Sep-15 28-Sep-15 Fire proo
MH-FP-130 Fire proofing-Structure V 6 23-Sep-15 29-Sep-15 Fire proo
MH-FP-140 Fire proofing-111-T5 A/B,111-T6 A/B, 111-T3 5 29-Sep-15 03-Oct-15 Fire proo
MH-FP-150 Fire proofing-111-H9 5 03-Oct-15 08-Oct-15 Fire pro
MH-FP-160 Fire proofing-111-N3 A/B 5 08-Oct-15 13-Oct-15 Fire pr
MH-FP-170 Fire proofing-111-T8 A/B,111-T7, 111-T10 A/B 5 13-Oct-15 17-Oct-15 Fire p
MH-FP-180 Fire proofing-(R120) - Curb (Around 111-E10, 111-E1) 5 25-Oct-15 29-Oct-15 Fire
MH-FP-190 Fire proofing-(R120) - Curb (Around 111-E5) 5 26-Oct-15 31-Oct-15 Fir
MH-FP-520 Fire proofing-111-E4 5 26-Oct-15 30-Oct-15 Fir
SECTION-1 10 13-Oct-15 23-Oct-15 23-O
MH-FP-10 Fire proofing-(R90) Compressor Building 5 13-Oct-15 18-Oct-15 Fire p
MH-FP-20 Fire proofing-(R90) Pipe Rack 5 18-Oct-15 23-Oct-15 Fire
SECTION-7 12 18-Oct-15 30-Oct-15 30-
MH-FP-540 Fire proofing-Pipe Rack 5 18-Oct-15 22-Oct-15 Fire
MH-FP-550 Fire proofing-Structure ZH 5 20-Oct-15 24-Oct-15 Fire
MH-FP-560 Fire proofing-Structure N 5 22-Oct-15 26-Oct-15 Fire
MH-FP-570 Fire proofing-112-N3 A/B, 112-N2 A/B, 112-N1 A/B, 112-N13 A/B 5 24-Oct-15 29-Oct-15 Fire
MH-FP-600 Fire proofing-112-N26, 112-H6 A/B, 112-N4 A/B, 112-N9 A/B, 112- 5 25-Oct-15 30-Oct-15 Fir
SECTION-6 56 09-Aug-15 04-Oct-15 04-Oct-1
MH-FP-210 Fire proofing-Pipe Rack 5 09-Aug-15 14-Aug-15 Fire proofing-Pipe
MH-FP-220 Fire proofing-Structure I 5 14-Aug-15 19-Aug-15 Fire proofing-Str

Primary Baseline Actual Work Critical Remaining Work Page 24 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation


VGO PROJECT BASELINE SCHEDULE
Activity ID Activity Name Original Start Finish 3 2014 2015
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MH-FP-230 Fire proofing-Structure U 5 19-Aug-15 23-Aug-15 Fire proofing-St
MH-FP-240 Fire proofing-112-T13 5 23-Aug-15 28-Aug-15 Fire proofing-1
MH-FP-250 Fire proofing-112-K10,9 5 28-Aug-15 01-Sep-15 Fire proofing-1
MH-FP-260 Fire proofing-112-T14 5 01-Sep-15 06-Sep-15 Fire proofing-
MH-FP-270 Fire proofing-112-KH5, 112-KH6,112-KH8 5 06-Sep-15 11-Sep-15 Fire proofing
MH-FP-290 Fire proofing-112-K11 5 11-Sep-15 15-Sep-15 Fire proofin
MH-FP-310 Fire proofing-OPS4 Shelter 5 15-Sep-15 20-Sep-15 Fire proofi
MH-FP-330 Fire proofing-110-N5 A/B/C/D 5 20-Sep-15 25-Sep-15 Fire proof
MH-FP-350 Fire proofing-110-N6 A/B 5 25-Sep-15 29-Sep-15 Fire proo
MH-FP-370 Fire proofing-110-E5 B,110-E5 A,E6 5 29-Sep-15 04-Oct-15 Fire proo
SECTION-5 20 04-Oct-15 24-Oct-15 24-O
MH-FP-490 Fire proofing-Structure D 5 04-Oct-15 09-Oct-15 Fire pro
MH-FP-500 Fire proofing-111-F1 A/B 5 09-Oct-15 13-Oct-15 Fire pr
MH-FP-510 Fire proofing-111-ME1 5 13-Oct-15 18-Oct-15 Fire p
MH-FP-530 Fire proofing-110-N15 A/B, 112-N16 A/B, 112-N17 A/B, 112-N14 A 5 19-Oct-15 24-Oct-15 Fire
SECTION-4 5 25-Oct-15 29-Oct-15 29-
MH-FP-480 Fire proofing-Pipe Rack 5 25-Oct-15 29-Oct-15 Fire
MILD HYDROCRACKING
HYDRO UNIT-PRECOMMISSIONING 229 15-Mar-15 30-Oct-15 30-
MH-PRE-10 Precommissioning 229 15-Mar-15 30-Oct-15* Pre
MH-PRE-20 Finish project 0 30-Oct-15 Fin

Primary Baseline Actual Work Critical Remaining Work Page 25 of 25 TASK filter: All Activities

Second Baseline Remaining Work Milestone © Oracle Corporation