1.8 Preperation of Specifications, initial ITPs 30 2 to 5 man days for each specification
1.9 Material Takeoffs 60 3 Base model (3D Model) is required to generate MTO and GA drawings
1.10 Datasheets 30 2 Process informations required from process department
2 Civil Activities
2.1 Simple Structures (e.g. Pump House, Control rooms etc) Average 15 days
2.2 Complex Structure (e.g. ESP, Dewatering bldg. etc.) Average 15 days
2.9 Tanks
2.10 Pumps
2.11 Silos
2.15 Tanks
2.16 Pumps
2.17 Silos
3 Structural Activities
Preperation of Super Structure Drawings for simple structures
3.1 Preperation of Model 90
3.2 Extraction of 2D drawings 20
3.5 Tanks 20
3.6 Silos 50
3.7 Pumps 30
4 Architectural Activities
5 Mechanical Activities
5.1 Preperation/Updation of Model
5.2 Piping Layouts 120
5.3 Isometric Layouts 45
5.4 Stress Analysis 10 Stress analysis is required only for Steam and Oxidation air piping
6 Electrical Activities
6.1 Preperation of Design criterias
6.2 Specifications
6.3 Load Flow calculations
6.4 Lux Calculation
6.5 X-former/UPS/Cable Sizing
6.6 FE/PE Calculation
6.7 Preperation of SLD *approx estimate
6.8 Cable tray/Conduits Layout
6.9 Control Room Layouts
6.10 Lighting Layouts
6.11 FE/PE Layouts
7 C&I Activities
7.1 Preperation of Design criterias
7.2 Specifications
7.3 ITPs
7.4 I/O List
7.5 Hook up drawings
7.6 Elementry Wiring diagrams
7.8 System Description