118th st.

ES - As Planned Schedule + Causes 1 CCEP 12-Jun-15


Activity ID Activity Name Start Finish Total 2015 2016
May
Float Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJun
Work done by WNG
A1000 Approved start date by AAA 12-Jun-15 0 Approved start date by AAA
A1020 Install Cabinets 12-Jun-15 25-Jun-15 67 Install Cabinets
A1010 Install pathways for all systems 13-Jun-15 22-Jul-15 0 Install pathways for all systems
A1030 Pull Copper Cables 23-Jul-15 31-Aug-15 0 Pull Copper Cables
A1040 Pull Fiber 01-Sep-15 03-Sep-15 4 Pull Fiber
A1060 Terminate Copper 01-Sep-15 11-Sep-15 0 Terminate Copper
A1050 Terminate Fiber 04-Sep-15 07-Sep-15 4 Terminate Fiber
A1070 Labeling 12-Sep-15 16-Sep-15 0 Labeling
A1080 Testing by WNG 17-Sep-15 21-Sep-15 0 Testing by WNG
A1090 Install Finish Equipment 22-Sep-15 26-Sep-15 0 Install Finish Equipment
A1100 Provide Final Test Report 22-Sep-15 22-Sep-15 4 Provide Final Test Report
A1110 WNG Scope Complete 26-Sep-15 0 WNG Scope Complete
Work to be done by AAA
A1130 Provide Back Boxes 12-Jun-15 12-Jun-15 0 Provide Back Boxes
Impacting work by AAA
A1140 Provide WAP's Design 12-Jun-15 18-Sep-15 8 Provide WAP's Design
A1150 WAP's MDF Cabinets 12-Jun-15 15-Dec-15 -80 WAP's MDF Cabinets
A1160 Clocks Provide Design and Back Boxes 12-Jun-15 28-Jul-15 60 Clocks Provide Design and Back Boxes
A1170 Provide Clocks 12-Jun-15 06-Nov-15 -41 Provide Clocks
A1180 Speakers - Provide Boxes 12-Jun-15 28-Jul-15 60 Speakers - Provide Boxes
A1190 Speakers - Provide Speakers 12-Jun-15 20-Nov-15 -55 Speakers - Provide Speakers
A1200 Details horns and cages 12-Jun-15 28-Jul-15 60 Details horns and cages
A1210 Phones - Provide Design 12-Jun-15 15-Jul-15 73 Phones - Provide Design
A1220 Provide Phones 12-Jun-15 06-Nov-15 -41 Provide Phones
A1230 Flex Horns - Provide Design, back boxes, mounting
12-Jun-15
details06-Nov-15 -41 Flex Horns - Provide Design, back boxes, mounting details
A1240 Flex Horns - Provide Flex Horns 12-Jun-15 06-Nov-15 -41 Flex Horns - Provide Flex Horns
A1270 Test and Acceptance 12-Jun-15 05-May-16 -222 Test and

Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation