Activity ID Activity Name Original Planned Planned Finish Budgeted Total Calendar 2015

Duration Start Cost


Feb Mar Apr May
S
PROJECT NAME Baseline Programme Rev. 00 53d 03-Feb-15 16-Apr-15 $0.00

MILESTONES
MILESTON 63d 03-Feb-15 16-Apr-15 $0.00 6-Day Workweek
A1000 (NTP) Notice to Proceed - Day 1 0d 03-Feb-15 $0.00 6-Day Workweek (NTP) Notice to Proceed - Day 1
A1005 Site Access Handover 0d 16-Feb-15* $0.00 6-Day Workweek Site Access Handover
A1180 Physical Completion 0d 08-Apr-15 $0.00 6-Day Workweek Physical Completion
A1190 Handover 0d 16-Apr-15 $0.00 6-Day Workweek Handover

PRELIMINARIES
PRELIMIN 63d 03-Feb-15 16-Apr-15 $0.00 6-Day Workweek
A1010 Prelims 63d 03-Feb-15 16-Apr-15 $0.00 6-Day Workweek

ENGINEERING
ENGINEE 21d 03-Feb-15 26-Feb-15 $0.00 6-Day Workweek
A1020 Shopdrawing Submittal/Approval 7d 03-Feb-15 10-Feb-15 $0.00 6-Day Workweek
A1030 Material Submittal/Approval 7d 11-Feb-15 18-Feb-15 $0.00 6-Day Workweek
A1040 Other Submittals 7d 19-Feb-15 26-Feb-15 $0.00 6-Day Workweek

PROCUREMENT
PROCURE 14d 19-Feb-15 06-Mar-15 $0.00 6-Day Workweek

Contractor Supplied
S Materials 14d 19-Feb-15 06-Mar-15 $0.00 6-Day Workweek
A1050 Contractor Supplied Material Procurement 7d 19-Feb-15 26-Feb-15 $0.00 6-Day Workweek
A1060 Contractor Supplied Material Long-Lead items 14d 19-Feb-15 06-Mar-15 $0.00 6-Day Workweek
Owner Supp
Supplied Materials 14d 19-Feb-15 06-Mar-15 $0.00 6-Day Workweek
A1070 Owner Supplied Material Procurement 7d 19-Feb-15 26-Feb-15 $0.00 6-Day Workweek
A1080 Owner Supplied Material Long-Lead items 14d 19-Feb-15 06-Mar-15 $0.00 6-Day Workweek

CONSTRUCTION
CONSTRU 38d 16-Feb-15 08-Apr-15 $0.00

FITOUT WORKS
WOR 21d 16-Feb-15 11-Mar-15 $0.00 6-Day Workweek
Ceiling Finishes
Finis 7d 16-Feb-15 23-Feb-15 $0.00 6-Day Workweek
A1090 Ceiling Finishes 7d 16-Feb-15 23-Feb-15 $0.00 6-Day Workweek
Wall & Column
Colu Finishes 7d 24-Feb-15 03-Mar-15 $0.00 6-Day Workweek
A1100 Wall & Coulumn Finishes 7d 24-Feb-15 03-Mar-15 $0.00 6-Day Workweek
Floor Finishes
Finish 7d 04-Mar-15 11-Mar-15 $0.00 6-Day Workweek
A1110 Floor Finishes (Paver & Epoxy Floor Finish) 7d 04-Mar-15 11-Mar-15 $0.00 6-Day Workweek
MEPF / AUXILLARY
AUX / ELV 35d 16-Feb-15 27-Mar-15 $0.00 6-Day Workweek
Plumbing W Works 21d 16-Feb-15 11-Mar-15 $0.00 6-Day Workweek
1st & 2nd FFix 7d 16-Feb-15 23-Feb-15 $0.00 6-Day Workweek
Final Fix 7d 24-Feb-15 03-Mar-15 $0.00 6-Day Workweek
Testing & CCommissioning 7d 04-Mar-15 11-Mar-15 $0.00 6-Day Workweek
Fire Protection
Protect Works 21d 16-Feb-15 11-Mar-15 $0.00 6-Day Workweek
1st & 2nd FFix 7d 16-Feb-15 23-Feb-15 $0.00 6-Day Workweek
Final Fix 7d 24-Feb-15 03-Mar-15 $0.00 6-Day Workweek
Testing & CCommissioning 7d 04-Mar-15 11-Mar-15 $0.00 6-Day Workweek
Electrical W
Works 21d 24-Feb-15 19-Mar-15 $0.00 6-Day Workweek
1st & 2nd FFix 7d 24-Feb-15 03-Mar-15 $0.00 6-Day Workweek
Final Fix 7d 04-Mar-15 11-Mar-15 $0.00 6-Day Workweek
Testing & CCommissioning 7d 12-Mar-15 19-Mar-15 $0.00 6-Day Workweek
ELV Works 21d 04-Mar-15 27-Mar-15 $0.00 6-Day Workweek
1st & 2nd FFix 7d 04-Mar-15 11-Mar-15 $0.00 6-Day Workweek
Final Fix 7d 12-Mar-15 19-Mar-15 $0.00 6-Day Workweek
Testing & CCommissioning 7d 20-Mar-15 27-Mar-15 $0.00 6-Day Workweek
SKITCHEN
SIGNA WINSTALLATION 7d 20-Mar-15 30-Mar-15 $0.00 Standard 6 Day Workweek
A1290 Kitchen Installation 7d 20-Mar-15 30-Mar-15
EX751$ WORKS
EXTERNAL
EXTERNAL WORKS 7d 31-Mar-15 08-Apr-15 $0.00 Standard 6 Day Workweek
A1300 Landscaping Works 7d 31-Mar-15 08-Apr-15 $0.00

PUNCHLISTING
PUNCHLIS 7d 09-Apr-15 16-Apr-15 $0.00 6-Day Workweek
A1170 Punchlisting & Rectification Works 7d 09-Apr-15 16-Apr-15 $0.00 6-Day Workweek

Remaining Level of Effort Actual Work Critical Remaining Work S. Work Package Baseline Program
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
'PROJECT NAME' Baseline Programme Revision 00

Note :
This template is serve only for the purpose of giving you idea on how to structure the baseline programme but not necessarily shows your actual baseline programme schedule.
(Contractor to breakdown WBS activities). WPM_PF_PJW_0089