King Faisal Air Academy

Activity ID Activity Name Start Original Duration Finish 2021


Mar Apr May Jun Jul
King Faisal Air Academy 20-Mar-21 110 07-Jul-21

SUBSTRUCTURE 20-Mar-21 36 24-Apr-21


A1000 RC Foundation-RA42 20-Mar-21 10 29-Mar-21
A1010 Grade Beam-RA42 30-Mar-21 10 08-Apr-21
A1020 Blinding and Damproofing under SOG-RA42 09-Apr-21 6 14-Apr-21
A1030 RC Slab on Grade-RA42 15-Apr-21 10 24-Apr-21
SUPERSTRUCTURE 25-Apr-21 74 07-Jul-21

A1040 Concrete Vertical GF-RA42 25-Apr-21 7 01-May-21


A1050 Concrete Horizontal GF-RA42 02-May-21 10 11-May-21
A1060 Concrete Vertical FF-RA42 12-May-21 7 18-May-21
A1070 Concrete Horizontal FF-RA42 19-May-21 10 28-May-21
A1080 Concrete Vertical SF-RA42 29-May-21 7 04-Jun-21
A1090 Concrete Horizontal SF-RA42 05-Jun-21 10 14-Jun-21
A1100 Concrete Vertical 3F-RA42 15-Jun-21 7 21-Jun-21
A1110 Concrete Horizontal 3F-RA42 22-Jun-21 10 01-Jul-21
A1120 Concrete Vertical LR-RA42 02-Jul-21 2 03-Jul-21
A1130 Concrete Horizontal LR-RA42 04-Jul-21 4 07-Jul-21

Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities