Date:
Plan / Forecast Aug-21 Sep-21 Oct-21
W2 W3 W4 W1 W2 W3 W4 W5 W1
S.N Tag No Remarks Finish Total Balance Dur. Comp
Start Date
Date Q'ty (T) Q'ty (T) Day % 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8
1 011F0001 First layer Ongoing for South chamber North and East wall 10/Aug/21 7/Sep/21 14.20 14.10 24 10.00%
2 018F0002 Cell A & Cell B north south, arch pannel balance 5/Sep/21 12/Sep/21 9.21 4.40 7 52.25%
3 018F1001 Cell A east & west & north Wall & Cell B east & west, arch pannel balance 7/Sep/21 19/Sep/21 13.11 7.26 12 44.62%
4 018F0001 North and south wall, Arch pannel ongoing 13/Sep/21 20/Sep/21 4.23 2.00 6 52.75%
Manpower Alocation 10 10 10 10 10 10 10 10 10 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13