Classic Schedule Layout Project Start : 12-Feb-13

Initial Planning Baseline of Rama Office Building East Project Data Date : 12-Feb-13
Andi Fernandez/91151473ZY Project Finish : 28-Oct-13
Tanggal Cetak : 29-Jul-21 14:47
Activity ID Activity Name Original Remaining Schedule % Start Finish Resources Budgeted Total Cost Total F March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 S October 2013 N D January 2014 F April 2014
March 2014
Duration Duration Complete Float
27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06
194 194 0% 12-Feb-13 09:00 14-Nov-13 18:00 Rp0 0 14-Nov-13 18:00, Rama East Rama Office Building East
Rama East Rama Office Building East
67 67 0% 12-Feb-13 09:00 20-May-13 18:00 Rp0 0 20-May-13 18:00, Rama East.1 Fondation
Rama East.1 Fondation
A1000 Begin Construction 0 0 100% 12-Feb-13 09:00 Rp0 0 Begin Construction
A1010 Site Preparation 20 20 0% 12-Feb-13 09:00 11-Mar-13 18:00 Rp0 0 Site Preparation
A1020 Excavation 10 10 0% 13-Mar-13 09:00 26-Mar-13 18:00 Rp0 0 Excavation
A1030 Install Underground Water Lines 10 10 0% 27-Mar-13 09:00 10-Apr-13 18:00 Rp0 0 Install Underground Water Lines
A1040 Install Underground Electrical Conduit 10 10 0% 27-Mar-13 09:00 10-Apr-13 18:00 Rp0 0 Install Underground Electrical Conduit
A1050 Form/Pour Concrete Footings 10 10 0% 11-Apr-13 09:00 24-Apr-13 18:00 Rp0 0 Form/Pour Concrete Footings
A1060 Form/Pour Concrete Walls 10 10 0% 25-Apr-13 09:00 08-May-13 18:00 Rp0 0 Form/Pour Concrete Walls
A1070 Form/Pour Concrete Slab 5 5 0% 10-May-13 09:00 16-May-13 18:00 Rp0 0 Form/Pour Concrete Slab
A1080 Bcakfill And Compact Fills 2 2 0% 17-May-13 09:00 20-May-13 18:00 Rp0 0 Bcakfill And Compact Fills
69 69 0% 21-May-13 09:00 26-Aug-13 18:00 Rp0 10 26-Aug-13 18:00, Rama East.2 Structure
Rama East.2 Structure
A1090 Erect Structural Frame 20 20 0% 21-May-13 09:00 18-Jun-13 18:00 Rp0 0 Erect Structural Frame
A1100 Floor Decking 14 14 0% 19-Jun-13 09:00 08-Jul-13 18:00 Rp0 0 Floor Decking
A1110 Form/Pour Basement Slab And Floors 25 25 0% 09-Jul-13 09:00 12-Aug-13 18:00 Rp0 0 Form/Pour Basement Slab And Floors
A1130 Install Interior Wall Frame 15 15 0% 23-Jul-13 09:00 12-Aug-13 18:00 Rp0 0 Install Interior Wall Frame
A1120 Erect Stairwall And Elevator Walls 10 10 0% 13-Aug-13 09:00 26-Aug-13 18:00 Rp0 10 Erect Stairwall And Elevator Walls
53 53 0% 18-Jul-13 09:00 30-Sep-13 18:00 Rp0 0 30-Sep-13 18:00, Rama East.3 M/E Sytem
Rama East.3 M/E Sytem
Rama East.3.1 Plumbing & Electrical 48 48 0% 18-Jul-13 09:00 23-Sep-13 18:00 Rp0 0 23-Sep-13 18:00, Rama East.3.1 Plumbing & Electrical
A1140 Set Mechanical And Electrical Equipment 15 15 0% 18-Jul-13 09:00 07-Aug-13 18:00 Rp0 3 Set Mechanical And Electrical Equipment
A1150 Rough-in Plumbing/Electrical/Mechanical 15 15 0% 13-Aug-13 09:00 02-Sep-13 18:00 Rp0 0 Rough-in Plumbing/Electrical/Mechanical
A1160 Install Wiring And Cable 15 15 0% 03-Sep-13 09:00 23-Sep-13 18:00 Rp0 0 Install Wiring And Cable
Rama East.3.2 Elevator 25 25 0% 27-Aug-13 09:00 30-Sep-13 18:00 Rp0 0 30-Sep-13 18:00, Rama East.3.2 Elevator
A1170 Install Elevator Rails And Equipment 10 10 0% 27-Aug-13 09:00 09-Sep-13 18:00 Rp0 10 Install Elevator Rails And Equipment
A1180 Install Elevator CabinetAnd Finishes 5 5 0% 24-Sep-13 09:00 30-Sep-13 18:00 Rp0 0 Install Elevator CabinetAnd Finishes
38 38 0% 19-Jun-13 09:00 09-Aug-13 18:00 Rp0 26 09-Aug-13 18:00, Rama East.4 Exterior
Rama East.4 Exterior
A1190 Brick Exterior Walls 28 28 0% 19-Jun-13 09:00 26-Jul-13 18:00 Rp0 26 Brick Exterior Walls
A1200 Installs Exterior Doors And Windows 10 10 0% 26-Jun-13 09:00 09-Jul-13 18:00 Rp0 39 Installs Exterior Doors And Windows
A1210 Insulation And Builtup Roofin g 10 10 0% 29-Jul-13 09:00 09-Aug-13 18:00 Rp0 26 Insulation And Builtup Roofin g
38 38 0% 17-Sep-13 09:00 07-Nov-13 18:00 Rp0 0 07-Nov-13 18:00, Rama East.5 Interior
Rama East.5 Interior
Rama East.5.1 Walls 35 35 0% 17-Sep-13 09:00 04-Nov-13 18:00 Rp0 0 04-Nov-13 18:00, Rama East.5.1 Walls
A1220 Drywall In Offices 15 15 0% 17-Sep-13 09:00 07-Oct-13 18:00 Rp0 0 Drywall In Offices
A1230 Paint Building Interior 20 20 0% 08-Oct-13 09:00 04-Nov-13 18:00 Rp0 0 Paint Building Interior
Rama East.5.2 Fixtures 3 3 0% 05-Nov-13 09:00 07-Nov-13 18:00 Rp0 0 07-Nov-13 18:00, Rama East.5.2 Fixtures
A1240 Install Plumbing Fixtures 2 2 0% 05-Nov-13 09:00 06-Nov-13 18:00 Rp0 1 Install Plumbing Fixtures
A1250 Install Lighting Fixtures 3 3 0% 05-Nov-13 09:00 07-Nov-13 18:00 Rp0 0 Install Lighting Fixtures
Rama East.5.3 Floors 7 7 0% 08-Oct-13 09:00 16-Oct-13 18:00 Rp0 16 16-Oct-13 18:00, Rama East.5.3 Floors
A1260 Install Carpeting 5 5 0% 08-Oct-13 09:00 14-Oct-13 18:00 Rp0 18 Install Carpeting
A1270 Install Floor Finishes 7 7 0% 08-Oct-13 09:00 16-Oct-13 18:00 Rp0 16 Install Floor Finishes
5 5 0% 08-Nov-13 09:00 14-Nov-13 18:00 Rp0 0 14-Nov-13 18:00, Rama East.6 Punch List
Rama East.6 Punch List
A1280 Punchlist/Touchup And Cleanup 5 5 0% 08-Nov-13 09:00 14-Nov-13 18:00 Rp0 0 Punchlist/Touchup And Cleanup
A1290 Complete Construction 0 0 0% 14-Nov-13 18:00 Rp0 0 Complete Construction

Remaining Level of Effort Tertiary Baseline Revision Box TASK filter: All Activities
Date Revision Checked Approved © PLN Corporate University
Actual Level of Effort Actual Work
Project Baseline Bar Remaining Work Supported by : Project Academy
Pembelajaran Primavera Project Planning P6
Primary Baseline Critical Remainin...
Secondary Baseline Start Constraint