TIMELINES FOR CGS HOSPITAL WORKS

SL No. DESCRIPTION START DATE END DATE


1 Dismentalling of stores adjascent to Cat IPD 15-Sep-23 22-Sep-23
2 Dismentalling of Swimming pool 20-Sep-23 30-Sep-23
3 Dismentalling of Pavers 22-Sep-23 26-Sep-23
4 Excavation for Walls & PCC 22-Sep-23 30-Sep-23
5 Brick work of Cat IPD and Toilets 25-Sep-23 5-Oct-23
6 Excavation for Column & PCC 1-Oct-23 6-Oct-23
7 PCC and steel work for Column 3-Oct-23 11-Oct-23
8 RCC works 7-Oct-23 14-Oct-23
9 MEP works of toilet and shifting of existing lines 30-Sep-23 8-Oct-23
10 Gypsum Plaster works and tiling 7-Oct-23 27-Oct-23
11 Roofing 16-Oct-23 15-Nov-23
12 Pool structure and MEP works 30-Sep-23 14-Nov-23
13 False ceiling works 10-Nov-23 27-Nov-23
14 Pool Tiling works 15-Nov-23 5-Dec-23
15 Cat IPD flooring 26-Nov-23 16-Dec-23
16 Skylight work 15-Dec-23 25-Dec-23
17 Door and window work 15-Dec-23 25-Dec-23
18 Painting works 20-Dec-23 10-Jan-24
19 Wood works- Complete 25-Dec-23 5-Jan-24
20 Pathways development works 15-Dec-23 10-Jan-24
21 Final Handing over 5-Jan-24 14-Jan-24
Total days
No. of Days for Activity
7
10
4
8
10
5
8
7
8
20
30
45
17
20
20
10
10
21
11
26
9
121
CGS- Execution Timelines

Start Date

17/Nov/23 Week-10

24/Nov/23 Week-11

01/Dec/23 Week-12

08/Dec/23 Week-13

15/Dec/23 Week-14

22/Dec/23 Week-15

29/Dec/23 Week-16

05/Jan/24 Week-17
15/Sep/23 Week-1

22/Sep/23 Week-2

29/Sep/23 Week-3

06/Oct/23 Week-4

13/Oct/23 Week-5

20/Oct/23 Week-6

27/Oct/23 Week-7

03/Nov/23 Week-8

10/Nov/23 Week-9
Duration (In
S.no. Activity Description Date of Start- End Date Weeks)
LOI+1 Day

Dismentalling of stores adjascent to Cat


1 IPD 15-Sep-23 22-Sep-23 1 X X

2 Dismentalling of Swimming pool 20-Sep-23 30-Sep-23 1.6 X X

3 Dismentalling of Pavers 22-Sep-23 26-Sep-23 0.6 X

4 Excavation for walls & PCC 22-Sep-23 30-Sep-23 1.3 X X

5 Brick work of Cat IPD and toilets 25-Sep-23 5-Oct-23 1.6 X

6 Excavation for column & PCC 1-Oct-23 6-Oct-23 0.7 X

7 PCC and steel work for Column 3-Oct-23 11-Oct-23 1.1 X

8 Casting 7-Oct-23 14-Oct-23 1.0 X


MEP works of toilet and shifting of
9 existing lines 30-Sep-23 8-Oct-23 1.1 X

10 Gypsum Plaster works and tiling 7-Oct-23 27-Oct-23 2.9 X X X

11 Roofing 16-Oct-23 15-Nov-23 4.4 X X X X

12 Pool structure and MEP works 30-Sep-23 14-Nov-23 6.0 X X X X X X

13 False ceiling works 10-Nov-23 27-Nov-23 1.4 X X X

14 Pool Tiling works 15-Nov-23 5-Dec-23 2.9 X X X

15 Cat IPD flooring 26-Nov-23 16-Dec-23 2.9 X X X

16 Skylight work 15-Dec-23 25-Dec-23 1.4 X X

17 Door and window work 15-Dec-23 25-Dec-23 1.4 X X

18 Painting works 20-Dec-23 10-Jan-24 3.0 X X X

19 Wood works- Complete 25-Dec-23 5-Jan-24 1.6 X X

20 Pathways development works 15-Dec-23 10-Jan-24 4.3 X X X X

21 Final Handing over 5-Jan-24 14-Jan-24 1.4 X