REVISED PERT/CPM TIME-SCALED NETWORK DIAGRAM

BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - MARCOS BRIDGE (BO1752LZ) ALONG MARCOS HIGHWAY (PHASE II)
(DUE TO TIME EXTENSION NO. 1)

12
232240

8
177191

L E G E N D:
S 1 1 2 3 4 5 6 9 10 14
CRITICAL PATH 0 0 2 2 2 2 9 9 39 39 70 70 100100 116116 191 191 222222 240 240

ACTIVITY
11 13
232232 237240

DUMMY

7
EVENT NO. - N 162191

N
EARLY START - ES
ES LF

LATE FINISH - LF

PREPARED BY: PROJECT AND LOCATION: CHECKED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED: SHEET CONTENTS: SHEET No.:
REPUBLIC OF THE PHILIPPINES
REVISED PERT - CPM DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BRIDGE - REHABILITATION/MAJOR REPAIR OF
PERMANENT BRIDGES - MARCOS BRIDGE (BO1752LZ)
NATIONAL CAPITAL REGION REVISED PERT-CPM DIAGRAM 1
CEFERINO A. LONDINA ALONG MARCOS HIGHWAY (PHASE II) CONSTRUCTION DIVISION EDGARDO S. RAMOS EDWIN M. LUZON JUBY B. CORDON, CEO ADOR G. CANLAS, CESO IV BAR CHART
AUTHORIZED MANAGING OFFICER 2ND STREET, PORT AREA MANILA ENGINEER III CHIEF, CONSTRUCTION DIVISION ASSISTANT REGIONAL DIRECTOR REGIONAL DIRECTOR S-CURVE 1
PROJECT ENGINEER III