Chapter 2 Project Management

Section 2.1 Critical Path Method (CPM) using Activity on Arrow

Example 2.1 Black Eyed Peas (I)

Table 2.1 Data Summary

Prede- Time t
Activity Description
cessor/s (days)
A 16 Process permits
B A 10 Organize team
C B 18 Book performers
D A 24 Reserve venue
E C 20 Schedule rehearsals
F C 12 Advertise
G D,F 22 Sell tickets
H D 8 Subcontract staging
I E,G,H 14 Conduct & evaluate concert

Figure 2.1 Project Network

A B C
1 2 3 4
F E
I
D G
6 7 8

H
5

Table 2.2 Critical Path

Prede- Time t Earliest Earliest Latest Start Latest Critical


Activity Idle Time
cessor(s) (days) Start (ES) Finish (EF) (LS) Finish (LF) Path?
A 16 0 16 0 16 0 YES
B A 10 16 26 16 26 0 YES
C B 18 26 44 26 44 0 YES
D A 24 16 40 32 56 16 NO
E C 20 44 64 58 78 14 NO
F C 12 44 56 44 56 0 YES
G D,F 22 56 78 56 78 0 YES
H D 8 40 48 70 78 30 NO
I E,G,H 14 78 92 78 92 0 YES

Figure 2.2 Critical Project Network

1 2 3 4

6 7 8

Section 2.2 Manual Crashing

Example 2.2 Black Eyed Peas (II)

Table 2.3 Data Summary

Prede- Time t (days) Cost ($000)


Activity
cessor/s Normal Crashed Normal Crashed
A 16 14 13 15
B A 10 9 17 20
C B 18 17 10 12
D A 24 22 16 18
E C 20 18 11 15
F C 12 11 15 18
G D,F 22 20 12 14
H D 8 5 14 20
I E,G,H 14 13 14 15
Due Date (days) 86

Table 2.4 Crashed Time

Time Cost Crash Critical Crash Time Crash Cost Time t (days)
Activity (days) ($000)
Allowed Increase Cost/Day Path? Normal Crashed
A
B
C
D
E
F
G
H
I
Total (Critical Path)

Section 2.3 Crashing with Solver

Example 2.3 Black Eyed Peas (III)

Table 2.5 Data Summary

Col\Row B C D E F G
116 Prede- Time t (days) Cost ($000)
Activity
117 cessor/s Normal Crashed Normal Crashed
118 A 16 14 13 15
119 B A 10 9 17 20
120 C B 18 17 10 12
121 D A 24 22 16 18
122 E C 20 18 11 15
123 F C 12 11 15 18
124 G D,F 22 20 12 14
125 H D 8 5 14 20
126 I E,G,H 14 13 14 15
127 Due Date (days) 86

Table 2.6 Minimum Crash Cost

Col\Row B C D E F G H
134 Time Cost Crash Crash Time Crash Cost Slack
Activity (days) ($000) (Allowed)
135 Allowed Increase Cost/Day
136 A
137 B
138 C
139 D
140 E
141 F
142 G
143 H
144 I
145 Total

Table 2.7 Crashed Critical Path


Col\Row B C D E F G H I
152 Prede- Crashed t Earliest Earliest Latest Start Latest
Activity Idle Time
153 cessor(s) (days) Start (ES) Finish (EF) (LS) Finish (LF)
154 A 0
155 B A
156 C B
157 D A
158 E C
159 F C
160 G D,F
161 H D
162 I E,G,H

Table 2.8 Answer Report