PROCUREMENT TRACKING CHART
Project Name: Woody 2000
Material Submittal Date Material Approval Date PO Issued Manufacture Started Shipment Date Clearance Delivery to Site / Store
Sub. No Activity ID Description Delivery Period Remarks
Forecast/
Required Required Forecast/ Actual Required Forecast/ Actual Required Fore cast/ Actual Required Fore cast/ Actual Required Fore cast/ Actual Required Fore cast/ Actual
Actual
1 A1080 P.C Concrete materials 21-Feb-14 3-Mar-14 13-Mar-14 23-Mar-14 7-Apr-14 9-Apr-14 19-Apr-14
2 A1090 R.C concrete materials 21-Mar-14 31-Mar-14 10-Apr-14 20-Apr-14 5-May-14 7-May-14 17-May-14
3 A1100 Waterproofing materials 2-May-14 12-May-14 22-May-14 1-Jun-14 16-Jun-14 18-Jun-14 28-Jun-14
4 A1110 Backfilling materials 16-May-14 26-May-14 5-Jun-14 15-Jun-14 30-Jun-14 2-Jul-14 12-Jul-14
5 A1120 Slab On Grade materials 20-Jun-14 30-Jun-14 10-Jul-14 20-Jul-14 4-Aug-14 6-Aug-14 16-Aug-14
6 A1130 Columns Works materials 19-Jun-14 29-Jun-14 9-Jul-14 19-Jul-14 18-Aug-14 20-Aug-14 30-Aug-14
7 A1140 Slabs Works materials 14-Aug-14 24-Aug-14 3-Sep-14 13-Sep-14 13-Oct-14 15-Oct-14 25-Oct-14
8 A1150 Masonry Works materials 7-Nov-14 17-Nov-14 27-Nov-14 7-Dec-14 22-Dec-14 24-Dec-14 3-Jan-15
9 A1160 Plaster Works materials 19-Dec-14 29-Dec-14 8-Jan-15 18-Jan-15 2-Feb-15 4-Feb-15 14-Feb-15
10 A1170 Painting Works materials 8-Jan-15 18-Jan-15 28-Jan-15 7-Feb-15 9-Mar-15 11-Mar-15 21-Mar-15
11 A1180 MEP 1st Fix materials 13-Nov-14 23-Nov-14 3-Dec-14 13-Dec-14 12-Jan-15 14-Jan-15 24-Jan-15
12 A1190 MEP 2nd and Final Fix materials 22-Jan-15 1-Feb-15 11-Feb-15 21-Feb-15 23-Mar-15 25-Mar-15 4-Apr-15
13 A1200 Install the Train Hardware materials 28-Oct-14 7-Nov-14 17-Nov-14 27-Nov-14 26-Jan-15 28-Jan-15 7-Feb-15
14 A1220 Repair Works materials 9-Oct-14 19-Oct-14 29-Oct-14 8-Nov-14 8-Dec-14 10-Dec-14 20-Dec-14
15 A1230 Finishes Works materials 23-Oct-14 2-Nov-14 12-Nov-14 22-Nov-14 22-Dec-14 24-Dec-14 3-Jan-15