Woody 2000 Landscape 10-Dec-13 16:05

Activity ID Activity Name

Woody 2000
General Milestones
Milesto
A1260 Project Start Date
A1270 Design Start
A1280 Design Finish
A1290 Shop drawings Start

A1300 Shop drawings finish


A1310 Materials Delivery start
A1320 Materials Delivery Finish
A1330 Construction Start
A1340 Construction Finish

A1350 Closeout Start


A1360 Project Finish

Design Phase
A1000 Project Design

Engineering
Shop Drawigs
A1010 Shop Drawings Submittal
A1020 Shop drawings Approval
Materials
A1030 Materials submittal
A1040 Materials Approval
A1050 Materials Procurement
A1060 Materials Delivery

Construction Phase
P
Extention of existing
exist floor area
Substructure
A1070 Excavation Works
A1080 P.C Concrete
A1090 R.C concrete
A1100 Waterproofing
A1110 Backfilling
A1120 Slab On Grade
Superstructure
A1130 Columns Works
A1140 Slabs Works
Finishes
A1150 Masonry Works
A1160 Plaster Works
A1170 Painting Works
Elctro-Mechanic (MEP)
Elctro-Mechanical
A1180 MEP 1st Fix
A1190 MEP 2nd and Final Fix
Semi-automatic woodworking
w production train
A1200 Install the Train Hardware
A1210 Perform the Train Software Development
Renovate the Pre
President and Executive Vice Presidents' offices
A1220 Repair Works
A1230 Finishes Works

Close out Phase


A1240 Testing and Commissioning
A1250 Closeout the project documentation

Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities