Professional Documents
Culture Documents
Activity ID Activity Name Original Duration Resources Budgeted Labor Budgeted Total Cost
Units
General Milestones
Milesto 0 0 $0.00
Construction Phase
P 60 7950 $9,030,000.00
Extention of existing
exist floor area 50 5050 $6,680,000.00
Substructure 40 1350 $1,830,000.00
A1070 Excavation Works 40 resources, Cost 200 $300,000.00
A1080 P.C Concrete 25 resources, Cost 200 $200,000.00
A1090 R.C concrete 30 resources, Cost 300 $1,000,000.00
A1100 Waterproofing 15 resources, Cost 150 $80,000.00
A1110 Backfilling 30 resources, Cost 400 $100,000.00
A1120 Slab On Grade 10 resources, Cost 100 $150,000.00
Superstructure 50 1350 $1,000,000.00
A1130 Columns Works 40 resources, Cost 600 $200,000.00
A1140 Slabs Works 50 resources, Cost 750 $800,000.00
Finishes 40 1600 $1,200,000.00
A1150 Masonry Works 40 resources, Cost 400 $500,000.00
A1160 Plaster Works 40 resources, Cost 400 $200,000.00
A1170 Painting Works 40 resources, Cost 800 $500,000.00
Elctro-Mechanic (MEP)
Elctro-Mechanical 40 750 $2,650,000.00
A1180 MEP 1st Fix 40 resources, Cost 400 $650,000.00
A1190 MEP 2nd and Final Fix 30 resources, Cost 350 $2,000,000.00
Semi-automatic woodworking
w production train 60 1400 $850,000.00
A1200 Install the Train Hardware 40 resources, Cost 800 $500,000.00
A1210 Perform the Train Software Development 60 resources, Cost 600 $350,000.00
Renovate the Pre
President and Executive Vice Presidents' offices 45 1500 $1,500,000.00
A1220 Repair Works 30 resources, Cost 600 $500,000.00
A1230 Finishes Works 45 resources, Cost 900 $1,000,000.00