You are on page 1of 4

St.

Jude_Escubinas Classic Schedule Layout 19-Jan-24 14:23


Activity ID Activity Name Original Actual Start Finish Predecessors Activity Type Resources Actual Total Cost Budgeted Total Schedule % Performance
Duration Duration Cost Complete % Complete

St. Jude_Escubinas 232 0 16-Jan-24 22-Oct-24 ₱0.00 ₱0.00 0% 0%

MILESTONE 232 0 16-Jan-24 22-Oct-24 ₱0.00 ₱0.00 0% 0%


A1000 Kick Off Meeting 0 0 16-Jan-24 Start Milestone ₱0.00 ₱0.00 0% 0%
A1010 Ground Breaking Ceremony 0 0 16-Jan-24 Start Milestone ₱0.00 ₱0.00 0% 0%
A1020 Excavation Complete 0 0 02-Mar-24 A1100 Finish Milestone ₱0.00 ₱0.00 0% 0%
A1030 Concrete Topping Off 0 0 12-Jul-24 A1310 Finish Milestone ₱0.00 ₱0.00 0% 0%
A1040 Project Complete 0 0 22-Oct-24 A1350 Finish Milestone ₱0.00 ₱0.00 0% 0%
PRE CONSTRUCTION 14 0 16-Jan-24 31-Jan-24 ₱0.00 ₱0.00 0% 0%

General Requirements 14 0 16-Jan-24 31-Jan-24 ₱0.00 ₱0.00 0% 0%


A1050 Securing Permits 7 0 16-Jan-24 23-Jan-24 Task Dependent ₱0.00 ₱0.00 0% 0%
A1060 Mobilization Works 3 0 24-Jan-24 26-Jan-24 A1050 Task Dependent ₱0.00 ₱0.00 0% 0%
A1070 Construction of Temporary Facilities and Utilities 4 0 27-Jan-24 31-Jan-24 A1060 Task Dependent ₱0.00 ₱0.00 0% 0%
CONSTRUCTION 202 0 27-Jan-24 28-Sep-24 ₱0.00 ₱0.00 0% 0%

Earthworks 70 0 27-Jan-24 23-Apr-24 ₱0.00 ₱0.00 0% 0%


A1080 Survey Works (Staking/Layout) 5 0 27-Jan-24 01-Feb-24 A1070 Task Dependent ₱0.00 ₱0.00 0% 0%
A1090 Clearing/Grubbing 10 0 02-Feb-24 14-Feb-24 A1080 Task Dependent ₱0.00 ₱0.00 0% 0%
A1100 Excavation 15 0 15-Feb-24 02-Mar-24 A1090 Task Dependent ₱0.00 ₱0.00 0% 0%
A1105 Gravel Bedding for Foundation and SOG 2 0 04-Mar-24 05-Mar-24 A1100 Task Dependent ₱0.00 ₱0.00 0% 0%
A1110 Hauling & Disposal 5 0 15-Feb-24 20-Feb-24 A1100 Task Dependent ₱0.00 ₱0.00 0% 0%
A1120 Backfilling & Compaction 7 0 16-Apr-24 23-Apr-24 A1210,A1110 Task Dependent ₱0.00 ₱0.00 0% 0%
Civil Works 137 0 04-Mar-24 16-Aug-24 ₱0.00 ₱0.00 0% 0%
Sub Structure 74 0 04-Mar-24 03-Jun-24 ₱0.00 ₱0.00 0% 0%
Footing Foundation 17 0 04-Mar-24 22-Mar-24 ₱0.00 ₱0.00 0% 0%
A1130 Installation of Rebar at Foundation 10 0 04-Mar-24 14-Mar-24 A1100 Task Dependent ₱0.00 ₱0.00 0% 0%
A1140 Installation of Formworks 4 0 15-Mar-24 19-Mar-24 A1130 Task Dependent ₱0.00 ₱0.00 0% 0%
A1150 Concrete Pouring 1 0 20-Mar-24 20-Mar-24 A1140 Task Dependent ₱0.00 ₱0.00 0% 0%
A1190 Formworks Stripping 1 0 22-Mar-24 22-Mar-24 A1150 Task Dependent ₱0.00 ₱0.00 0% 0%
Footing Tie Beam 18 0 23-Mar-24 17-Apr-24 ₱0.00 ₱0.00 0% 0%
A1160 Installation of Rebar 12 0 23-Mar-24 10-Apr-24 A1190 Task Dependent ₱0.00 ₱0.00 0% 0%
A1170 Installation of Formworks 2 0 11-Apr-24 12-Apr-24 A1160 Task Dependent ₱0.00 ₱0.00 0% 0%
A1180 Concrete Pouring 1 0 13-Apr-24 13-Apr-24 A1170 Task Dependent ₱0.00 ₱0.00 0% 0%
A1200 Formworks Stripping 2 0 16-Apr-24 17-Apr-24 A1180 Task Dependent ₱0.00 ₱0.00 0% 0%
Ground Floor 42 0 15-Apr-24 03-Jun-24 ₱0.00 ₱0.00 0% 0%
A1210 Subgrade Preparation 1 0 15-Apr-24 15-Apr-24 A1180 Task Dependent ₱0.00 ₱0.00 0% 0%
A1220 Installation of Vapor Barrier & Soil Termite Application 3 0 24-Apr-24 26-Apr-24 A1120 Task Dependent ₱0.00 ₱0.00 0% 0%
A1230 Installation of Rebar at GF 15 0 27-Apr-24 15-May-24 A1220 Task Dependent ₱0.00 ₱0.00 0% 0%
A1240 Installation of Formworks 2 0 16-May-24 17-May-24 A1230 Task Dependent ₱0.00 ₱0.00 0% 0%
A1250 Concrete Pouring SOG 1 0 18-May-24 18-May-24 A1240 Task Dependent ₱0.00 ₱0.00 0% 0%
A1260 Installation of Rebar, Formwork, 1st Lift Columns 12 0 20-May-24 01-Jun-24 A1250 Task Dependent ₱0.00 ₱0.00 0% 0%
A1270 Concrete Pouring 1st Lift Columns 1 0 03-Jun-24 03-Jun-24 A1260 Task Dependent ₱0.00 ₱0.00 0% 0%
Super Structure 63 0 04-Jun-24 16-Aug-24 ₱0.00 ₱0.00 0% 0%
2nd Floor 63 0 04-Jun-24 16-Aug-24 ₱0.00 ₱0.00 0% 0%
A1280 Installation of Scaffolding System 10 0 04-Jun-24 15-Jun-24 A1270 Task Dependent ₱0.00 ₱0.00 0% 0%
A1285 Installation of Rebar for Columns 5 0 17-Jun-24 21-Jun-24 A1280 Task Dependent ₱0.00 ₱0.00 0% 0%
A1295 Installation of Rebar for 2nd Floor Beams 5 0 22-Jun-24 27-Jun-24 A1285 Task Dependent ₱0.00 ₱0.00 0% 0%
A1300 Installation of Formwork, Rebar, Embedments for Slab 12 0 28-Jun-24 11-Jul-24 A1295 Task Dependent ₱0.00 ₱0.00 0% 0%
A1310 Concrete Pouring at 2nd Floor Slab and 2nd Lift Columns & Beams 1 0 12-Jul-24 12-Jul-24 A1300 Task Dependent ₱0.00 ₱0.00 0% 0%
A1440 Installation of Rebar Columns 5 0 13-Jul-24 18-Jul-24 A1310 Task Dependent ₱0.00 ₱0.00 0% 0%
A1450 Concrete Pouring Columns (Last Lift) 5 0 19-Jul-24 24-Jul-24 A1440 Task Dependent ₱0.00 ₱0.00 0% 0%
A1500 Stripping of Formworks 5 0 25-Jul-24 30-Jul-24 A1450 Task Dependent ₱0.00 ₱0.00 0% 0%

Page 1 of 2 TASK filter: All Activities


© Oracle Corporation
St. Jude_Escubinas Classic Schedule Layout 19-Jan-24 14:23
Activity ID Activity Name Original Actual Start Finish Predecessors Activity Type Resources Actual Total Cost Budgeted Total Schedule % Performance
Duration Duration Cost Complete % Complete

A1540 Installation of Roof Beams 5 0 31-Jul-24 05-Aug-24 A1500 Task Dependent ₱0.00 ₱0.00 0% 0%
A1550 Installation of Formworks 5 0 06-Aug-24 10-Aug-24 A1540 Task Dependent ₱0.00 ₱0.00 0% 0%
A1560 Concrete Pouring at Roof Beams 5 0 12-Aug-24 16-Aug-24 A1550 Task Dependent ₱0.00 ₱0.00 0% 0%
Plumbing 114 0 16-May-24 28-Sep-24 ₱0.00 ₱0.00 0% 0%
A1410 Installation of 1st Fix (Rough Ins) 5 0 16-May-24 21-May-24 A1230 Task Dependent ₱0.00 ₱0.00 0% 0%
A1420 Installation of 2nd Fix (Fittings) 5 0 24-Aug-24 30-Aug-24 A1360 Task Dependent ₱0.00 ₱0.00 0% 0%
A1430 Installation of 3rd Fix (Fixtures) 5 0 24-Sep-24 28-Sep-24 A1530 Task Dependent ₱0.00 ₱0.00 0% 0%
Architectural/Finishing Works 10 0 17-Aug-24 30-Aug-24 ₱0.00 ₱0.00 0% 0%
A1360 Laying of Concrete Hollow Blocks 5 0 17-Aug-24 23-Aug-24 A1560 Task Dependent ₱0.00 ₱0.00 0% 0%
A1370 Plastering & Floor Topping 5 0 24-Aug-24 30-Aug-24 A1360 Task Dependent ₱0.00 ₱0.00 0% 0%
Steel Works & Roofing 30 0 17-Aug-24 23-Sep-24 ₱0.00 ₱0.00 0% 0%
A1460 Fabrication of Steel Trusses 5 0 17-Aug-24 23-Aug-24 A1560 Task Dependent ₱0.00 ₱0.00 0% 0%
A1470 Installation of C-Purlins 5 0 24-Aug-24 30-Aug-24 A1460 Task Dependent ₱0.00 ₱0.00 0% 0%
A1475 Installation of G.I. Steel Matting 5 0 31-Aug-24 05-Sep-24 A1470 Task Dependent ₱0.00 ₱0.00 0% 0%
A1480 Installation of Roofing Insulation 5 0 06-Sep-24 11-Sep-24 A1475 Task Dependent ₱0.00 ₱0.00 0% 0%
A1490 Installation of Roofing Sheets 5 0 06-Sep-24 11-Sep-24 A1480 Task Dependent ₱0.00 ₱0.00 0% 0%
A1510 Installation of Bended Accessories 5 0 12-Sep-24 17-Sep-24 A1490 Task Dependent ₱0.00 ₱0.00 0% 0%
A1520 Installation of I-Beam for Canopy 5 0 03-Sep-24 07-Sep-24 A1360 Task Dependent ₱0.00 ₱0.00 0% 0%
A1530 Application of Water Proofing for Concrete Gutter 5 0 18-Sep-24 23-Sep-24 A1510 Task Dependent ₱0.00 ₱0.00 0% 0%
POST CONSTRUCTION 20 0 30-Sep-24 22-Oct-24 ₱0.00 ₱0.00 0% 0%
A1320 Punchlisting Works 5 0 30-Sep-24 04-Oct-24 A1430 Task Dependent ₱0.00 ₱0.00 0% 0%
A1330 Preparation & Submission of Close Out Documents 5 0 05-Oct-24 10-Oct-24 A1320 Task Dependent ₱0.00 ₱0.00 0% 0%
A1340 Demobilization 5 0 11-Oct-24 16-Oct-24 A1330 Task Dependent ₱0.00 ₱0.00 0% 0%
A1350 Project Complete 5 0 17-Oct-24 22-Oct-24 A1340 Task Dependent ₱0.00 ₱0.00 0% 0%

Page 2 of 2 TASK filter: All Activities


© Oracle Corporation
St. Jude_Escubinas Classic Schedule Layout 19-Jan-24 14:23
January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27
22-Oct-24, St. Jude_Escubinas

22-Oct-24, MILESTONE
Kick Off Meeting
Ground Breaking Ceremony
Excavation Complete
Concrete Topping Off
Project Complete
31-Jan-24, PRE CONSTRUCTION
31-Jan-24, General Requirements
Securing Permits
Mobilization Works
Construction of Temporary Facilities and Utilities
28-Sep-24, CONSTRUCTION
23-Apr-24, Earthworks
Survey Works (Staking/Layout)
Clearing/Grubbing
Excavation
Gravel Bedding for Foundation and SOG
Hauling & Disposal
Backfilling & Compaction
16-Aug-24, Civil Works
03-Jun-24, Sub Structure
22-Mar-24, Footing Foundation
Installation of Rebar at Foundation
Installation of Formworks
Concrete Pouring
Formworks Stripping
17-Apr-24, Footing Tie Beam
Installation of Rebar
Installation of Formworks
Concrete Pouring
Formworks Stripping
03-Jun-24, Ground Floor
Subgrade Preparation
Installation of Vapor Barrier & Soil Termite Application
Installation of Rebar at GF
Installation of Formworks
Concrete Pouring SOG
Installation of Rebar, Formwork, 1st Lift Columns
Concrete Pouring 1st Lift Columns
16-Aug-24, Super Structure
16-Aug-24, 2nd Floor
Installation of Scaffolding System
Installation of Rebar for Columns
Installation of Rebar for 2nd Floor Beams
Installation of Formwork, Rebar, Embedments for Slab
Concrete Pouring at 2nd Floor Slab and 2nd Lift Columns & Beams
Installation of Rebar Columns
Concrete Pouring Columns (Last Lift)
Stripping of Formworks

Actual Work Critical Remaining Work Summary Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
St. Jude_Escubinas Classic Schedule Layout 19-Jan-24 14:23
January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27
Installation of Roof Beams
Installation of Formworks
Concrete Pouring at Roof Beams
28-Sep-24, Plumbing
Installation of 1st Fix (Rough Ins)
Installation of 2nd Fix (Fittings)
Installation of 3rd Fix (Fixtures)
30-Aug-24,Architectural/Finishing Works
Laying of Concrete Hollow Blocks
Plastering & Floor Topping
23-Sep-24, Steel Works & Roofing
Fabrication of Steel Trusses
Installation of C-Purlins
Installation of G.I. Steel Matting
Installation of Roofing Insulation
Installation of Roofing Sheets
Installation of Bended Accessories
Installation of I-Beam for Canopy
Application of Water Proofing for Concrete Gutter
22-Oct-24, POST CONSTRUCTION
Punchlisting Works
Preparation & Submission of Close Out Docume
Demobilization
Project Complete

Actual Work Critical Remaining Work Summary Page 2 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation

You might also like