You are on page 1of 2

2-Storey Residential Building Classic Schedule Layout 28-Mar-21 21:57

Activity ID Activity Name Original Remaining Schedule % Start Finish Total Float Budgeted
Duration Duration Complete Total Cost

RB Project 2-Storey Residential Building 58 58 0% 31-Mar-21 28-Jun-21 0 $0.00

A01 Move and Clearing 4 4 0% 31-Mar-21 05-Apr-21 0 $0.00


A02 Procurement and Delivery of Materials 6 6 0% 31-Mar-21 08-Apr-21 4 $0.00
A03 Layout_Excavation of Footing and Zocalo 8 8 0% 06-Apr-21 19-Apr-21 0 $0.00
A04 Tables, Chairs, Desks 12 12 0% 08-Apr-21 28-Apr-21 4 $0.00
A05 Concreting of Ftg & Zocalo, CHB Installation 12 12 0% 20-Apr-21 07-May-21 0 $0.00
A06 Fab'n of doors, jambs, jalouses, & trusses 12 12 0% 28-Apr-21 17-May-21 4 $0.00
A07 Ins'n of rebars & forms, pouring of Columns & Beams 10 10 0% 08-May-21 22-May-21 0 $0.00
A08 Backfilling of Footing, Zocalo, & Flooring 2 2 0% 22-May-21 25-May-21 12 $0.00
A09 Ins'n of doors, jambs, jalouses, & trusses 8 8 0% 22-May-21 03-Jun-21 0 $0.00
A10 Roofing, Gutter & Downspouts 6 6 0% 03-Jun-21 11-Jun-21 0 $0.00
A11 Plastering 7 7 0% 22-May-21 02-Jun-21 8 $0.00
A12 Rebars, Forms, & Pouring of Floor Slab 3 3 0% 14-Jun-21 17-Jun-21 0 $0.00
A13 Painting and Finishing 5 5 0% 17-Jun-21 24-Jun-21 0 $0.00
A14 Demobilazation and Clearing 2 2 0% 25-Jun-21 28-Jun-21 0 $0.00

Actual Work Critical Remaining Work Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
2-Storey Residential Building Classic Schedule Layout 28-Mar-21 21:57
d Total Qtr 2, 2021 Qtr 3, 2021
Cost
Apr May Jun Jul Aug
$0.00 28-Jun-21, RB Project 2-Storey Residential Building

$0.00 Move and Clearing


$0.00 Procurement and Delivery of Materials
$0.00 Layout_Excavation of Footing and Zocalo
$0.00 Tables, Chairs, Desks
$0.00 Concreting of Ftg & Zocalo, CHB Installation
$0.00 Fab'n of doors, jambs, jalouses, & trusses
$0.00 Ins'n of rebars & forms, pouring of Columns & Beams
$0.00 Backfilling of Footing, Zocalo, & Flooring
$0.00 Ins'n of doors, jambs, jalouses, & trusses
$0.00 Roofing, Gutter & Downspouts
$0.00 Plastering
$0.00 Rebars, Forms, & Pouring of Floor Slab
$0.00 Painting and Finishing
$0.00 Demobilazation and Clearing

Actual Work Critical Remaining Work Page 2 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation

You might also like