GENERAL AUTHORITY OF CIVIL AVIATION BUILDING

Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
139 20-May-21 28-Oct-21 30-Dec-20 13-Jun-21 -117 28-Oct-21, Construct
Construction
139 20-May-21 28-Oct-21 30-Dec-20 13-Jun-21 -117 28-Oct-21, B06
B06
Fire Alarm 16 24-Aug-21 11-Sep-21 07-Apr-21 26-Apr-21 -117 11-Sep-21, Fire Alarm
CN-B06-SB-BF-S-3-3 Fire Alarm System 16 24-Aug-21 11-Sep-21 07-Apr-21 26-Apr-21 0% -117 11-Sep-21

Furniture 35 14-Sep-21 24-Oct-21 28-Apr-21 08-Jun-21 -117 24-Oct-21, Furniture


CN-B06-SP-L1-FUR-1 Furniture 10 14-Sep-21 25-Sep-21 28-Apr-21 10-May-21 0% -117 25-Sep-21

CN-B06-SP-L2-FUR-1 Furniture 10 20-Sep-21 30-Sep-21 04-May-21 16-May-21 0% -117 30-Sep-21

CN-B06-SP-L3-FUR-1 Furniture 10 26-Sep-21 06-Oct-21 10-May-21 22-May-21 0% -117 06-Oct-21

CN-B06-SP-L4-FUR-1 Furniture 10 02-Oct-21 12-Oct-21 16-May-21 27-May-21 0% -117 12-Oct-21

CN-B06-SP-GF-FUR-1 Furniture 10 07-Oct-21 18-Oct-21 22-May-21 02-Jun-21 0% -117 18-Oct-21

CN-B06-SP-L5-FUR-1 Furniture 5 07-Oct-21 12-Oct-21 22-May-21 27-May-21 0% -117 12-Oct-21

CN-B06-SP-L6-FUR-1 Furniture 5 07-Oct-21 12-Oct-21 22-May-21 27-May-21 0% -117 12-Oct-21

CN-B06-SUB-BF-FUR-1 Furniture 10 13-Oct-21 24-Oct-21 27-May-21 08-Jun-21 0% -117 24-Oct-21

Painting 2 12-Sep-21 13-Sep-21 26-Apr-21 28-Apr-21 -117 13-Sep-21, Painting


CN-B06-SUB-BF-FS-W-5 Final Coat Paint 2 12-Sep-21 13-Sep-21 26-Apr-21 28-Apr-21 0% -117 13-Sep-21

Raised Floor & Carpet Tiles 20 20-May-21 12-Jun-21 30-Dec-20 21-Jan-21 -117 12-Jun-21, Raised Floor & Carpet Tiles
CN-B06-SP-L1-FS-F-6 Carpet Tiles on Raised Floor 10 20-May-21 31-May-21 30-Dec-20 10-Jan-21 0% -117 31-May-21

CN-B06-SP-L2-FS-F-6 Carpet Tiles on Raised Floor 10 01-Jun-21 12-Jun-21 11-Jan-21 21-Jan-21 0% -117 12-Jun-21

Snagging 4 25-Oct-21 28-Oct-21 08-Jun-21 13-Jun-21 -117 28-Oct-21, Snagging


CN-B6-SUB-BF-SNG-1 Snagging (By Consultant) - Basement 2 25-Oct-21 26-Oct-21 08-Jun-21 10-Jun-21 0% -117 26-Oct-21
Floor
CN-B6-SUB-BF-SNG-2 Incorporate Snagging comments & 4 25-Oct-21 28-Oct-21 08-Jun-21 13-Jun-21 0% -117 28-Oct-21
De-Snagging- Basement Floor
Wooden Doors 62 13-Jun-21 23-Aug-21 23-Jan-21 04-Apr-21 -117 23-Aug-21, Wooden Doors
CN-B06-SP-L2-DW-1 Wooden Doors 10 13-Jun-21 23-Jun-21 23-Jan-21 02-Feb-21 0% -117 23-Jun-21

CN-B06-SP-L3-DW-1 Wooden Doors 10 24-Jun-21 05-Jul-21 03-Feb-21 14-Feb-21 0% -117 05-Jul-21

CN-B06-SP-L4-DW-1 Wooden Doors 10 06-Jul-21 17-Jul-21 15-Feb-21 25-Feb-21 0% -117 17-Jul-21

CN-B06-SP-L5-DW-1 Wooden Doors 6 18-Jul-21 24-Jul-21 27-Feb-21 04-Mar-21 0% -117 24-Jul-21

CN-B06-SP-L6-DW-1 Wooden Doors 6 25-Jul-21 31-Jul-21 06-Mar-21 11-Mar-21 0% -117 31-Jul-21

CN-B06-SP-GF-DW-1 Wooden Doors 10 01-Aug-21 11-Aug-21 13-Mar-21 23-Mar-21 0% -117 11-Aug-21

CN-B06-SUB-BF-DW-1 Wooden Doors 10 12-Aug-21 23-Aug-21 24-Mar-21 04-Apr-21 0% -117 23-Aug-21

7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 -117 03-Apr-21, Design


Design
7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 -117 03-Apr-21, B03 & B04
B03 & B04
Details 7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 -117 03-Apr-21, Details

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 1 of 3
13-Mar-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
ENG-B3&4-DD-AR-1100 12000-General Details Submission & 7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 0% -117 03-Apr-21
Approval
Flooring 7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 -117 03-Apr-21, Flooring
ENG-B3&4-DD-AR-1030 4000-Flooring Submission & Approval 7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 0% -117 03-Apr-21

Stairs 7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 -117 03-Apr-21, Stairs


ENG-B3&4-DD-AR-1080 9000-Stairs Submission & Approval 7 27-Mar-21 03-Apr-21 05-Nov-20 12-Nov-20 0% -117 03-Apr-21

30 20-Apr-21 19-May-21 30-Nov-20 29-Dec-20 -136 19-May-21, Material Delivery


Material Delivery
30 20-Apr-21 19-May-21 30-Nov-20 29-Dec-20 -136 19-May-21, General
General
No Sub-Trade 30 20-Apr-21 19-May-21 30-Nov-20 29-Dec-20 -136 19-May-21, No Sub-Trade
ENG-MP-AR-NLL-1140 1st Cementitious raised floor Batch to Site 30 20-Apr-21 19-May-21 30-Nov-20 29-Dec-20 0% -136 19-May-21

14 04-Apr-21 19-Apr-21 14-Nov-20 29-Nov-20 -117 19-Apr-21, Shop Drawings


Shop Drawings
14 04-Apr-21 19-Apr-21 14-Nov-20 29-Nov-20 -117 19-Apr-21, B03 & B04
B03 & B04
Ceramic & Porcelain 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 -117 11-Apr-21, Ceramic & Porcelain
EN-SD-B3&4-AR-FS-01 Building No. 3 & 4 Basement Floor Plan 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
Floor & Wall Tiling
EN-SD-B3&4-AR-FS-02 Building No. 3 & 4 Ground Floor Plan Floor 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
& Wall Tiling
EN-SD-B3&4-AR-FS-03 Building No. 3 & 4 First Floor Plan Floor & 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
Wall Tiling
EN-SD-B3&4-AR-FS-04 Building No. 3 & 4 Second Floor Plan Floor 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
& Wall Tiling
EN-SD-B3&4-AR-FS-05 Building No. 3 & 4 Third Floor Plan Floor & 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
Wall Tiling
EN-SD-B3&4-AR-FS-06 Building No. 3 & 4 Fourth Floor Plan Floor 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
& Wall Tiling
EN-SD-B3&4-AR-FS-07 Building No. 3 & 4 Fifth Floor Plan Floor & 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
Wall Tiling
EN-SD-B3&4-AR-FS-08 Building No. 3 & 4 Sixth Floor Plan Floor & 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
Wall Tiling
EN-SD-B3&4-AR-FS-09 Building No. 3 & 4 General Details Floor & 7 04-Apr-21 11-Apr-21 14-Nov-20 21-Nov-20 0% -117 11-Apr-21
Wall Tiling
False Ceiling 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 -117 19-Apr-21, False Ceiling
EN-SD-B3&4-AR-FS-17 Building No. 3 & 4 Basement Floor Plan 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
False Ceiling Works
EN-SD-B3&4-AR-FS-18 Building No. 3 & 4 Ground Floor Plan False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
EN-SD-B3&4-AR-FS-19 Building No. 3 & 4 First Floor Plan False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
EN-SD-B3&4-AR-FS-20 Building No. 3 & 4 Second Floor Plan False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
EN-SD-B3&4-AR-FS-21 Building No. 3 & 4 Third Floor Plan False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
EN-SD-B3&4-AR-FS-22 Building No. 3 & 4 Fourth Floor Plan False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
EN-SD-B3&4-AR-FS-23 Building No. 3 & 4 Fifth Floor Plan False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
EN-SD-B3&4-AR-FS-24 Building No. 3 & 4 Sixth Floor Plan False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
EN-SD-B3&4-AR-FS-25 Building No. 3 & 4 General Details False 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Ceiling Works
Raised Floor 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 -117 19-Apr-21, Raised Floor

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 2 of 3
13-Mar-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
EN-SD-B3&4-AR-FS-10 Building No. 3 & 4 First Floor Plan Raised 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Floor System
EN-SD-B3&4-AR-FS-11 Building No. 3 & 4 Second Floor Plan 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Raised Floor System
EN-SD-B3&4-AR-FS-12 Building No. 3 & 4 Third Floor Plan Raised 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Floor System
EN-SD-B3&4-AR-FS-13 Building No. 3 & 4 Fourth Floor Plan 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Raised Floor System
EN-SD-B3&4-AR-FS-14 Building No. 3 & 4 Fifth Floor Plan Raised 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Floor System
EN-SD-B3&4-AR-FS-15 Building No. 3 & 4 Sixth Floor Plan Raised 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Floor System
EN-SD-B3&4-AR-FS-16 Building No. 3 & 4 General Details Raised 7 12-Apr-21 19-Apr-21 22-Nov-20 29-Nov-20 0% -117 19-Apr-21
Floor System
12 15-Mar-20 A 25-Mar-21 15-Mar-20 28-Mar-20 -117 25-Mar-21, Zoning
Zoning
12 15-Mar-20 A 25-Mar-21 15-Mar-20 28-Mar-20 -117 25-Mar-21, B03 & B04
B03 & B04
Zoning 12 15-Mar-20 A 25-Mar-21 15-Mar-20 28-Mar-20 -117 25-Mar-21, Zoning
ENG-B3&4-ZON-1010 B03 & B04 Zoning Approval 12 15-Mar-20 A 25-Mar-21 15-Mar-20 28-Mar-20 0% -117 25-Mar-21

0 28-Oct-21 28-Oct-21 14-Jun-21 14-Jun-21 -117 28-Oct-21, No WBS-


No WBS-Action
0 28-Oct-21 28-Oct-21 14-Jun-21 14-Jun-21 -117 28-Oct-21, No Locat
No Location
No Sub-Trade 0 28-Oct-21 28-Oct-21 14-Jun-21 14-Jun-21 -117 28-Oct-21, No Sub-T
CNS-1010 Project Completion 0 28-Oct-21 14-Jun-21 0% -117 Project Completion

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 3 of 3
13-Mar-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone