Progress Report Cut‐off Date :15‐05‐2021
Activity Name Performance % Complete Schedule % Complete
GACA BUILDINGS 45.25% 96.67%
  B01 42.17% 96.19%
    Concrete Works 100.00% 100.00%
    Doors & Windows 53.33% 100.00%
    Electrical Works 23.45% 100.00%
    Elevators Works 0.00% 97.73%
    Equipment Works 0.00% 100.00%
    Finishes Works 7.87% 100.00%
    Furniture 0.00% 46.00%
    Masonry Works 100.00% 100.00%
    Mechanical Works 37.98% 100.00%
    Metal Works 0.00% 96.87%
    Site Works 100.00% 100.00%
    Smart Buildings Works 13.88% 100.00%
    Snagging 0.00% 0.00%
    Specialities Works 0.00% 25.96%
    Thermal & Moisture Protection 12.18% 100.00%
    Wood & Plastic Works 0.00% 97.51%
  B03 28.07% 90.92%
    Concrete Works 99.91% 100.00%
    Doors & Windows 40.96% 100.00%
    Electrical Works 11.93% 100.00%
    Elevators Works 0.00% 100.00%
    Equipment Works 0.00% 100.00%
    Finishes Works 4.36% 99.92%
    Furniture 0.00% 60.00%
    Masonry Works 100.00% 100.00%
    Mechanical Works 13.87% 98.10%
    Metal Works 0.00% 97.88%
    Site Works 100.00% 100.00%
    Smart Buildings Works 0.08% 84.76%
    Snagging 0.00% 0.00%
    Specialities Works 0.00% 0.00%
    Thermal & Moisture Protection 8.28% 100.00%
    Wood & Plastic Works 0.00% 100.00%
  B04 26.35% 99.36%
    Concrete Works 99.88% 100.00%
    Doors & Windows 35.98% 100.00%
    Electrical Works 12.27% 99.79%
    Elevators Works 0.00% 100.00%
    Equipment Works 0.00% 100.00%
    Finishes Works 8.62% 100.00%
    Furniture 0.00% 100.00%
    Masonry Works 100.00% 100.00%
    Mechanical Works 12.52% 99.87%
    Metal Works 0.00% 100.00%
    Site Works 100.00% 100.00%
    Smart Buildings Works 0.06% 99.06%
    Snagging 0.00% 0.00%
    Specialities Works 0.00% 31.24%
    Thermal & Moisture Protection 9.68% 100.00%

Page 1 of 3
Progress by Division 15‐05‐2021.xlsx 19/05/2021

Progress Report Cut‐off Date :15‐05‐2021
Activity Name Performance % Complete Schedule % Complete
    Wood & Plastic Works 0.00% 100.00%
  B05 35.52% 99.33%
    Concrete Works 99.91% 100.00%
    Doors & Windows 47.65% 100.00%
    Electrical Works 19.15% 100.00%
    Elevators Works 0.00% 100.00%
    Equipment Works 0.00% 100.00%
    Finishes Works 14.24% 97.13%
    Furniture 0.00% 100.00%
    Masonry Works 100.00% 100.00%
    Mechanical Works 40.29% 100.00%
    Metal Works 0.00% 100.00%
    Site Works 100.00% 100.00%
    Smart Buildings Works 13.92% 100.00%
    Snagging 0.00% 0.00%
    Specialities Works 0.00% 50.91%
    Thermal & Moisture Protection 6.49% 100.00%
    Wood & Plastic Works 0.00% 100.00%
  B06 34.30% 87.32%
    Concrete Works 99.90% 100.00%
    Doors & Windows 50.85% 100.00%
    Electrical Works 18.03% 100.00%
    Elevators Works 0.00% 100.00%
    Equipment Works 0.00% 100.00%
    Finishes Works 13.73% 100.00%
    Furniture 0.00% 29.04%
    Masonry Works 100.00% 100.00%
    Mechanical Works 42.58% 100.00%
    Metal Works 0.00% 100.00%
    Site Works 100.00% 100.00%
    Smart Buildings Works 14.25% 100.00%
    Snagging 0.00% 0.00%
    Specialities Works 0.00% 57.52%
    Thermal & Moisture Protection 12.32% 100.00%
    Wood & Plastic Works 0.00% 100.00%
  Car Parking 80.30% 100.00%
    Concrete Works 99.42% 100.00%
    Doors & Windows 0.00% 100.00%
    Electrical Works 69.92% 100.00%
    Finishes Works 12.19% 100.00%
    Masonry Works 73.00% 100.00%
    Mechanical Works 59.27% 100.00%
    Metal Works 52.03% 100.00%
    Site Works 85.67% 100.00%
    Smart Buildings Works 26.32% 100.00%
    Snagging 0.00% 0.00%
    Termite Control 100.00% 100.00%
    Thermal & Moisture Protection 73.46% 100.00%
  Roads 7.50% 99.31%
    Site Works 7.50% 99.31%
    Snagging 0.00% 0.00%

Page 2 of 3
Progress by Division 15‐05‐2021.xlsx 19/05/2021

Progress Report Cut‐off Date :15‐05‐2021
Activity Name Performance % Complete Schedule % Complete
  Service Buildings 59.84% 99.87%
    Concrete Works 94.56% 100.00%
    Doors & Windows 0.00% 100.00%
    Electrical Works 62.38% 100.00%
    Finishes Works 55.05% 100.00%
    Furniture 0.00% 100.00%
    Masonry Works 75.00% 100.00%
    Mechanical Works 69.59% 100.00%
    Metal Works 0.00% 83.12%
    Site Works 100.00% 100.00%
    Smart Buildings Works 1.97% 100.00%
    Snagging 0.00% 0.00%
    Thermal & Moisture Protection 10.83% 100.00%
  Site Layout 31.88% 100.00%
    Doors & Windows 0.00% 100.00%
    Fence Works 72.00% 100.00%
    Metal Works 0.00% 100.00%
    Site Works 26.07% 100.00%
    Snagging 0.00% 0.00%
    Termite Control 72.00% 100.00%
    Wood & Plastic Works 0.00% 100.00%
  Site Networks 35.33% 100.00%
    Mechanical Works 35.33% 100.00%
  STP 0.00% 100.00%
    Concrete Works 0.00% 100.00%
    Mechanical Works 0.00% 100.00%
    Metal Works 0.00% 100.00%
    Site Works 0.00% 100.00%
    Thermal & Moisture Protection 0.00% 100.00%
  Water Tank 78.79% 100.00%
    Concrete Works 100.00% 100.00%
    Metal Works 0.00% 100.00%
    Site Works 70.59% 100.00%
    Thermal & Moisture Protection 19.54% 100.00%
  Workshop 11.51% 99.11%
    Concrete Works 85.65% 100.00%
    Doors & Windows 0.00% 100.00%
    Electrical Works 0.00% 100.00%
    Equipment Works 0.00% 100.00%
    Finishes Works 0.00% 100.00%
    Furniture 0.00% 90.00%
    Masonry Works 90.00% 100.00%
    Mechanical Works 0.00% 100.00%
    Metal Works 0.00% 100.00%
    Site Works 10.72% 100.00%
    Smart Buildings Works 0.00% 100.00%
    Snagging 0.00% 0.00%
    Specialities Works 0.00% 100.00%
    Thermal & Moisture Protection 50.59% 100.00%