Estimated Cost by items of work

% OF UNIT
SCOPE OF WORKS UNIT QUANTITY TOTAL AMOUNT
TOTAL PRICE

I General requirements 0.50% lot


1.00 10,408.24 10,408.24

II Project information sign 0.36% set


3.00 2,459.52 7,378.56

Personal protective
III 0.07% set
equipment 1.00 1,478.40 1,478.40

1 Earthworks 2.18% lot


1.00 45,076.17 45,076.17

2 Concreting Works 11.45% cu.m.


47.75 4,946.00 236,171.50

3 Rebar Works 13.44% kg.


3,401.14 81.51 277,226.92

4 Formworks 2.51% sq.m.


199.50 260.04 51,877.98

5 Masonry Works 10.52% sq.m.


726.21 298.72 216,933.45

6 Doors and Windows 8.96% set


18.00 10,265.82 184,784.76

7 Steel Works 12.69% lot


1.00 261,746.45 261,746.45

8 Roofing Works 12.32% lot


1.00 254,248.51 254,248.51

9 Carpentry Works 10.48% sq.m.


305.80 707.16 216,249.53

10 Electrical Works 4.25% lot


1.00 87,691.30 87,691.30

11 Painting Works 4.95% sq.m.


736.62 138.68 102,154.46

Window security grill


12 5.31% sq.m.
works 41.11 2,665.38 109,573.77

Estimated total cost of project: 100% 2,063,000.00

SAY PROJECT COST: 2,063,000.00