BILL OF QUANTITIES
Item No. Description Qty. Unit Unit Cost Amount Wt.
A. General Requirements ₱16,584,229.76 4.22%
1 Mobilization and Demobilization 1.00 Lot ₱2,331,302.40 ₱2,331,302.40
2 Temporary facilities 1.00 Lot ₱2,331,302.40 ₱2,331,302.40
3 Occupational Safety and Health Program 1.00 Lot ₱680,624.00 ₱680,624.00
4 Site Supervision 1.00 Lot ₱11,241,000.96 ₱11,241,000.96
B. Demolition and Clearing Works ₱3,330,432.00 0.85%
1 Demolition of Existing Market Building 1.00 Lot ₱3,330,432.00 ₱3,330,432.00
C. Temporary Selling Facilities ₱11,979,137.03 3.05%
1 Construction of Temporary Selling Facilities 1.00 lot ₱11,979,137.03 ₱11,979,137.03
D. Site Works ₱1,925,743.01 0.49%
1 Construction of Temporary Fence 500.00 L.m. ₱2,825.05 ₱1,412,526.08
2 Site Layout 10,230.71 Sq.m. ₱24.74 ₱253,086.40
3 Pest Control 6,561.00 Sq.m. ₱39.65 ₱260,130.53
E. Earthworks ₱21,629,942.96 5.51%
1 Excavation 20,855.45 Cu.m. ₱180.63 ₱3,767,210.23
2 Item 105 3,879.34 Sq.m. ₱50.89 ₱197,418.49
3 Item 200 3,150.94 Cu.m. ₱1,164.26 ₱3,668,526.70
4 Item 104 24,906.84 Cu.m. ₱542.35 ₱13,508,244.88
5 Gravel Bedding G1 75mm 663.40 Cu.m. ₱736.42 ₱488,542.66
6 Dewatering 1.00 Lot ₱77,313.60 ₱77,313.60
F. Civil/Structural ₱177,275,290.68 45.13%
1 Concrete 4000psi 5,932.74 Cu.m. ₱7,807.84 ₱46,321,853.78
2 Concrete Blinding 176.10 Cu.m. ₱4,407.30 ₱776,123.79
3 Concrete 3000psi 1,673.79 Cu.m. ₱7,675.40 ₱12,847,019.52
4 Reinforcing Steel Bars 503,402.88 kg ₱127.00 ₱63,931,657.33
5 Concrete Curb 1,074.59 L.m. ₱229.68 ₱246,810.94
6 Formworks Including Scaffoldings 35,717.56 Sq.m. ₱564.65 ₱20,167,742.87
9 Masonry 5,366.07 Sq.m. ₱1,410.01 ₱7,566,230.04
10 Steel Truss 175,284.85 kg ₱145.01 ₱25,417,852.40
G. Architectural ₱50,678,566.85 12.90%
1 Flooring 3,312.93 Sq.m. ₱576.02 ₱1,908,315.05
2 Wet Area 34.00 Unit ₱52,315.22 ₱1,778,717.61
3 Food Stall 18.00 Unit ₱72,421.04 ₱1,303,578.74
4 Dry Goods Stall 252.00 Unit ₱4,630.96 ₱1,167,002.13
5 Ceiling 24,156.36 Sq.m. ₱663.54 ₱16,028,697.84
6 Wall Painting 3,018.91 Sq.m. ₱5,698.84 ₱17,204,274.28
7 Roofing 4,165.53 Sq.m. ₱2,420.20 ₱10,081,414.65
8 Doors 29.00 Sets ₱8,294.18 ₱240,531.20
9 Windows 11.83 Sq.m. ₱5,305.96 ₱62,742.96
10 Grilles & Gates 178.90 Sq.m. ₱3,941.04 ₱705,052.38
11 Signage 1.00 Lot ₱198,240.00 ₱198,240.00
H. Mechanical System ₱3,645,698.36 0.93%
1 Installation of Mechanical Equipments 1.00 Lot ₱3,645,698.36 ₱3,645,698.36
-
-
-
-
TOTAL MATERIALS COST, ₱0.00
MATERIALS UNIT COST, P ₱0.00
B. EQUIPMENT COST
DESCRIPTION OF EQUIPMENTS No. DUR. (DAYS) RATE/DAY AMOUNT
1 Dump Truck 2 25 ₱13,200.00 ₱660,000.00
2 Backhoe 2 25 ₱32,880.00 ₱1,644,000.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
TOTAL MATERIALS COST, ₱2,056,549.00
MATERIALS UNIT COST, P ₱2,056,549.00
B. EQUIPMENT COST
DESCRIPTION OF EQUIPMENTS No. DUR. (DAYS) RATE/DAY AMOUNT
₱0.00