You are on page 1of 4

Project Name: Construction of DOH Drug Abuse Treatment and Rehabilitation Center (DATRC)

Project Location: Osorio Rd., Brgy. Osorio, Trece Martires City, Cavite
Subject: Actual BOQ for Patient Dormitory
BUILDING 14 PATIENT DORM

ITEM NO. PARTICULARS QTY UNIT UNIT COST AMOUNT

A. SITE PREPARATIONS ₱ 1,314,865.67


CLEARING AND GRUBBING 561.00 sq.m. 30.41 ₱ 17,058.87
DEMOLITION WORKS 1.00 lot 20,084.73 ₱ 20,084.73
DISPOSAL OF DEBRIS FROM DEMOLITION 55.00 cu.m. 1,214.04 ₱ 66,772.13
DAYWORKS 1.00 lot 318,123.58 ₱ 318,123.58
Sub-total ₱ 422,039.31
EARTHWORKS
Structural Excavation for Building Foundations 293.20 cu.m. 728.42 Php 213,574.67
Hauling and Disposal of excavated unsuitable 124.56 cu.m. 1,214.03 Php 151,219.71
material
Backfilling and Compaction cu.m. 1,214.04 Php -
Disposal of Water (Dewatering) 1.00 lot 214,582.29 Php 214,582.29
Trimming Works 293.20 sq.m. 607.02 Php 177,978.23
Soil Poisoning 77.96 sq.m. 121.40 Php 9,464.65
Gravel Bedding (100mm thk.) 51.90 cu.m. 2,428.06 Php 126,006.80
Sub-total Php 892,826.36
B. CONCRETE WORKS ₱ 6,456,542.78
3.0 Reinforcing Steel Bars; Grade 60
Foundations 553.35 kgs ₱ 74.06 Php 40,979.09
Columns 4,203.22 kgs ₱ 74.06 Php 311,274.85
Concrete Walls kgs ₱ 74.06 Php -
Beams and Girders 12,735.94 kgs ₱ 74.06 Php 943,177.68
Reinforcing Steel Bars; Grade 40 Php -
Suspended Slabs; Slabs on-grade 5,473.95 kgs Php 72.62 Php 397,531.70
Stairs 1,468.12 kgs Php 72.62 Php 106,618.48
Sewage and Sump pits kgs Php 72.62 Php -
Sub-total Php 1,799,581.80
Formworks; including shoring and bracing work
Foundations 37.36 sq.m. 2,655.73 Php 99,218.21
Columns 154.81 sq.m. 2,655.73 Php 411,134.12
Concrete Walls sq.m. 2,655.73 Php -
Beams and Girders 585.07 sq.m. 2,655.73 Php 1,553,790.05
Suspended Slabs; Slabs on-grade 449.40 sq.m. 2,655.73 Php 1,193,486.25
Stairs 18.91 sq.m. 2,655.73 Php 50,226.30
Sub-total Php 3,307,854.92
Cast-in-place Concrete
Foundations 14.07 cu.m. 6,552.89 Php 92,199.21
Columns 17.58 cu.m. 6,552.89 Php 115,170.01
Concrete Walls cu.m. 6,552.89 Php -
Beams and Girders 67.20 cu.m. 6,552.89 Php 440,354.44
Suspended Slabs; Slabs on-grade 98.39 cu.m. 6,552.89 Php 644,765.40
Stairs 8.64 cu.m. 6,552.89 Php 56,617.00
Sewage and Sump pits cu.m. Php -
Sub-total Php 1,349,106.06
Concrete Accessories
Waterstops l.m. 1,042.45 Php -
Contraction Joints l.m. 623.65 Php -
Expansion Joints l.m. 623.65 Php -
Block-outs sets 303.51 Php -
Sub-total Php -
C. MASONRY ₱ 2,077,662.82
CHB Laying 150mm 373.20 sq.m 1,031.93 Php 385,116.28
CHB Laying 100mm 552.00 sq.m 849.83 Php 469,104.56
Exterior Plastering 373.20 sq.m 693.82 Php 258,934.79
Interior Plastering 1477.20 sq.m 616.73 Php 911,036.02
Roof Deck Topping 163.20 sq.m 327.64 Php 53,471.17
Sub-total Php 2,077,662.82
D. METALS ₱ 1,383,075.61
Structural Steel Framing sq.m 99.50
Roof Framing 13,703.30 sq.m 99.50 Php 1,363,456.70
Stair Railings 20.20 l.m. 971.23 Php 19,618.91
Stair Nosing l.m. 971.23
Sub-total Php 1,383,075.61
E. THERMAL AND MOISTURE PROTECTION ₱ 3,395,738.54
Polyethylene Sheet 441.80 sq.m 60.71 Php 26,819.52
Cementitious Waterproofing System 227.28 sq.m 1,820.92 Php 413,859.75
Rigid Thermal Insulation for Roofdecks sq.m 910.53 Php -
Roof Thermal Insulation 144.53 sq.m 176.04 Php 25,442.71
Roof Covering 1511.79 l.m 1,841.36 Php 2,783,749.97
Reinforced Concrete Gutter 80.10 l.m 1,821.06 Php 145,866.60
Sub-total Php 3,395,738.54
F. OPENINGS (DOORS AND WINDOWS) ₱ 1,164,200.49
0.7 x 2.4 Solid Core Wood Door 1.00 set(s) 13,982.58 Php 13,982.58
0.8 x 2.4 Solid Core Wood Door 1.00 set(s) 15,980.10 Php 15,980.10
0.9 x 2.4 Solid Core Wood Door 1.00 set(s) 17,977.61 Php 17,977.61
0.9 x 2.4 Hollow Metal Single Door 1.00 set(s) 23,437.30 Php 23,437.30
1.0 x 2.4 Hollow Metal Single Door 8.00 set(s) 26,041.45 Php 208,331.59
1.0 x 2.4 Hollow Metal Single Door 1.00 set(s) 26,041.45 Php 26,041.45
1.10 x 2.4 Hollow Metal Double Leaf Door 1.00 set(s) 57,291.20 Php 57,291.20
1.55 x 1.0 Aluminum Framed Awning Window 24.00 set(s) 11,513.06 Php 276,313.43
1.55 x 2.7 Aluminum Framed Fixed Corner Window 3.00 set(s) 31,085.27 Php 93,255.82
1.55 x 1.0 Aluminum Framed Fixed Window 18.00 set(s) 11,513.06 Php 207,235.08
3.30 x 4.90 Built-up Lattice Grilles 4.00 set(s) 56,088.58 Php 224,354.33
Sub-total Php 1,164,200.49
G. FLOOR FINISHES ₱ 911,293.08
F6 600 x 600 Homogenous Matte Floor Tiles 517.11 sq.m 1,347.78 Php 696,951.08
F7 600 x 600 Homogenous Non Skid Floor Tile 50.05 sq.m 1,352.38 Php 67,686.39
F8 300 x 300 Homogenous Non Skid Floor Tile 117.04 sq.m 1,253.04 Php 146,655.60
Sub-total Php 911,293.08
H. WALL FINISHES ₱ 1,894,440.91
W1 Textured Elastomeric Exterior Wall Coating 410.52 sq.m 839.68 Php 344,704.21
System
W2 Semi - Gloss Acrylic Latex Paint Finish 1,624.92 sq.m 503.80 Php 818,636.87
W5 300 x300 Ceramic Polish Tile 652.08 sq.m 1,121.18 Php 731,099.82
Sub-total Php 1,894,440.91
I. BASEBOARDS ₱ 28,750.70
B1 10mm High Baseboard Tile 236.83 l.m 121.40 Php 28,750.70
Sub-total Php 28,750.70
J. CEILING FINISHES ₱ 694,551.93
C3 12mm Thk Moisture Resistant Flat Latex Paint 622.80 sq.m 950.06 Php 591,698.57
Finish
C6 200mm wide powder coated wood 106.80 sq.m 789.13 Php 84,278.57
C7 Exposed underside of Slab/beam 61.20 sq.m 303.51 Php 18,574.79
Sub-total Php 694,551.93
K. SPECIALTIES ₱ 867,967.05
50mmx100mmx1.5mm thk Primed and Painted Steel 833.34 sq.m
622.77 Php 518,979.32
Vertical Slats
100mmx300mm Aluminum Powder Coated Tubular 339.63 sq.m
1,027.57 Php 348,987.74
Horizontal Louvers @ 250mm O.C

Sub-total Php 867,967.05


L. PLUMBING ₱ 176,323.78
Catch basins 13.00 sets
13,563.37 Php 176,323.78

Php -

Php -
Sub-total Php 176,323.78
M. ELECTRICAL WORKS, AUXILIARIES, & ELECTRONICS ₱ 2,183,536.47
Pin Light 216.00 set(s) 1,113.67 Php 240,551.88
Square Light 12.00 set(s) 1,706.34 Php 20,476.14
Troffer Light 300 x 1200 332.00 set(s) 2,184.31 Php 725,191.74
Troffer Light 600 x 600 12.00 set(s) 2,313.36 Php 27,760.31
Flourescent Lamp 24.00 set(s) 1,194.92 Php 28,678.05
Exit Sign with Direction 12.00 set(s) 3,685.13 Php 44,221.58
1 x 25 watts LED Perimeter light complete with 40.00 set(s)
bracket and support 14,339.04 Php 573,561.56

One gang switch 48.00 pcs 167.29 Php 8,030.03


Two gang switch 44.00 pcs 257.16 Php 11,314.83
Duplex convenience outlet 16.00 pcs 445.47 Php 7,127.54
Junction Box 648.00 pcs 30.58 Php 19,818.42
Utility Box 360.00 pcs 28.68 Php 10,326.20
Pullbox w/ cover 8.00 pcs 7,073.92 Php 56,591.40
Flexible Conduit Connector 1944.00 pcs Php -
3-way two gang switch 32.00 pcs 257.16 Php 8,228.96
3-way one gang switch 12.00 pcs 167.29 Php 2,007.51
Special outlet (EF) 76.00 pcs 477.97 Php 36,325.57
Special outlet (OF) 128.00 pcs 477.97 Php 61,179.90
ECB 20AT, 1P 4.00 pcs 573.56 Php 2,294.25
Pull Box 8.00 pcs 191.19 Php 1,529.50
IMC Conduit 1188.00 pcs Php -
IMC Coupling 1188.00 pcs Php -
3.5mm THHN - 12113.00 m Php -
Flexible Conduit 972.00 pcs Php -
Php -
Addressable Manual Pull Station 20.00 pcs 2,389.84 Php 47,796.80
Fire Alarm Speaker w/ Strobe Light 20.00 pcs 2,389.84 Php 47,796.80
Smoke Detector 48.00 pcs 2,389.84 Php 114,712.32
Smoke Detector w/ base 16.00 pcs 2,389.84 Php 38,237.44
Addressable Output Module 8.00 pcs 2,389.84 Php 19,118.72
Addressable Input Module 4.00 pcs 2,389.84 Php 9,559.36
Evacuation Panel 4.00 pcs Php -
Pull Box 4.00 pcs 191.19 Php 764.75
IMC Conduit 260.00 pcs Php -
IMC Coupling 260.00 pcs Php -
Junction Box 104.00 pcs 43.02 Php 4,473.78
Square Box 55.00 pcs 81.25 Php 4,469.00
Utility Box 25.00 pcs 33.46 Php 836.44
Locknut + Bushing 25mm 552.00 pcs 19.12 Php 10,555.68

Sub-total Php 2,183,536.47

TOTAL PROJECT COST: Php 22,548,949.83