RATE ANALYSIS PART 2

•RATE
  ANALYSIS FOR STONE MASONRY-
1. RANDOM RUBBLE MASONRY IN C.M. (1:6) IN FOUNDATION &
PLINTH –
• Consider first 10 cu.m.

• CALUCLATION OF MATERIALS-

a) Volume of mortar per 10 cu.m. = 4.2 cu.m.


• Cement =
• Sand = 0.60 x 6 = 3.60 cu.m.
PARTICULARS QUANTITY RATE AMOUNT
A) MATERIALS
Stone (Undressed) 11.7 cu.m. -----------
Through /Headers 0.8 cu.m. ------------
Cement 18 bags -------------
Sand ( medium) 3.36 cu.m. --------------

B) Labour
Head mason ½ no. ----------------
Mason 10 no. -----------------
Mazdoor 19 no. -----------------

Contingencies, T.&P.etc. @ ½ %(A+B) ----------------

Total 1 ------------
C) Water charges @1% of total --------------
Total 2 --------------
D) Profit & overhead @ 10% of Total 2 ---------------
Grand Total ---------------
Rate per cu.m. = Grand Total / 10 cu.m. = --------------
•RATE
  ANALYSIS FOR STONE MASONRY-
1. RANDOM RUBBLE MASONRY IN C.M. (1:6) IN SUPERSTRCTURE
• Consider first 10 cu.m.
• CALUCLATION OF MATERIALS-
a) Volume of mortar per 10 cu.m. = 4.2 cu.m.
• Cement =
• Sand = 0.60 x 6 = 3.60 cu.m.
b) Add scaffolding as per local supply.
c) In case of labour, increase it by 1 no. mason & mazdoor .
PARTICULARS QUANTITY RATE AMOUNT
A) MATERIALS
Stone (Undressed) 11.7 cu.m.
Through /Headers 0.8 cu.m.
Cement 18 bags
Sand ( medium) 3.36 cu.m.

B) Labour
Head mason ½ no.
Mason 11no.
Mazdoor 20 no.
Scaffolding L.S.

Contingencies, T.&P . etc. ½ %(A+B)


Total 1
C) Water charges @1% of total
Total 2
D) Profit & overhead @ 10% of Total 2
Grand Total
Rate per cu.m. = Grand Total / 10 cu.m. = --------------
•Calculation
  of mortar for Random Rubble Masonry -
1. RANDOM RUBBLE MASONRY IN C.M. (1:3)
• Consider first 10 cu.m.
• CALUCLATION OF MATERIALS-
a) Volume of mortar per 10 cu.m. = 4.2 cu.m.
• Cement =
• Sand = --- x ------ = --- cu.m.
2) Similarly calculate material for R.R. Masonry in C.M. 1:4, 1:5, &1:6
•RATE
  ANALYSIS FOR STONE MASONRY-
1. COURSED RUBBLE MASONRY IN C.M. (1:6) IN FOUNDATION &
GROUND FLOOR
• Consider first 10 cu.m.

• CALUCLATION OF MATERIALS-

a) Volume of mortar per 10 cu.m. = 4.0 cu.m.


• Cement =
• Sand = 0.57 x 6 = 3.42 cu.m.
PARTICULARS QUANTITY RATE AMOUNT
A) MATERIALS
Stone (Undressed) 11.7 cu.m.
Through /Headers 0.8 cu.m.
Cement 17 bags
Sand ( medium) 3.40 cu.m.

B) Labour
Head mason ½ no.
Mason 13no.
Mazdoor 20 no.
Scaffolding L.S.

Contingencies, T.&P . etc. ½ %(A+B)

Total 1
C) Water charges @1% of total
Total 2
D) Profit & overhead @ 10% of Total 2
Grand Total
Rate per cu.m. = Grand Total / 10 cu.m. = --------------
•RATE
  ANALYSIS FOR BRICKWORK
• Consider first 10 cu.m.
A) CALUCLATION OF MATERIALS-
i. Size of brick with mortar = 10 cm x 10cm x 20 cm
ii. No. of brick =
iii. Size of brick without mortar = 9 cm x 9 cm x 19 cm
iv. Mortar required per 10 cu.m. = 10 – 5000 ( 0.09 x 0.09 x 0.19 ) = 2.3 cu.m.
v. Vol. of wet mortar ( increase by 15 %) = 2.3 + 2.3 (0.15) = 2.64 cu.m.
vi. For dry mortar, increase it by 33% = vol. = 2.64 x 1.33 = 3.51 cu.m. ( It is for first
class brick)
For second class brick volume of cement mortar = 4.0 cu.m.
(Note – for traditional brick size 10” x 5” x3”, no. of brick required 4100 nos. and
volume of mortar will remain same as above )
RATE ANALYSIS FOR BRICKWORK
• Consider first 10 cu.m.

B) LABOUR CONSTANT ( LABOUR REQUIRED ) –

SR.NO. PARTICULARS PER LABOUR CONSTANTS


1 Brickwork in foundation & plinth 10 cu.m. Head mason = ½
Mason = 8
Mazdoor = 14
Bhisti = 2
2 First class brickwork in superstructure 10 cu.m. Head mason = ½
ground floor Mason = 8
Mazdoor = 15
Bhisti = 2
3 First class brickwork for first floor 10 cu.m. Head mason = ½
Mason = 9
Mazdoor = 18
Bhisti = 2
•RATE
  ANALYSIS FOR HALF BRICKWORK IN C.M. (1:3) WITH H.B. NETTING
IN EVERY THIRD LAYER (GROUND FLOOR)
• Consider first 100 sq . m.
A) CALUCLATION OF MATERIALS-
i. Size of brick with mortar = 10 cm x 10cm x 20 cm
ii. No. of brick =
iii. Vol. of mortar increase by 35% of volume of work = 0.35 ( 100 x 0.1) = 3.5 cu.m.
iv. Due to half tk. Brick work, vol. of mortar becomes 10% less than 3.5 cu.m.
= 0.9 x 3.5 = 3.15 cu.m.
v. Cement = 3.15 / 4 = 0.79 cu.m. = 0.79 x 30 = 23.7 24 bags
sand = 0.79 x 3 = 2.37 cu.m.
vi. Wire netting for every third layer i.e. 30 cm intervals ( Wall L= 10 m & H = 10 m)
= 10 x 10/0. = 334 m

width of wire net = 10 cm


Area of netting = 334 x 0.1 = 33.4 sq. m.

B) LABOUR CONSTANT ( LABOUR REQUIRED ) –


•RATE
  ANALYSIS FOR D.P.C. OF 2.5 CM THICKNESS C.C.1:2:4
• Consider first 100 sq . m.

A) CALUCLATION OF MATERIALS-

i. Vol. of conc. =
ii. Dry volume of conc. = 2.5 x 15.4 / 10 = 3.85 cu.m.

iii. Cement =
iv. Sand = 0.55 x 2 = 1.1 cu.m.

v. Aggregate = 0.55 x 4 = 2.2 cu.m.


vi. Water proofing compound will be 3% by wt. of cement

= 3 x 0.55/100 = 0.0165 cu.m.


OR = 0.03 X 0.55 X 30X50 Kg = 24.75 25 Kg.
RATE ANALYSIS FOR BRICKWORK
• Consider first 100 sq. m.

B) LABOUR CONSTANT ( LABOUR REQUIRED ) –

SR.NO. PARTICULARS PER LABOUR CONSTANTS


1 2.5 cm thick D.P.C. with C.C.1:2:4 10 0 sq.m. Head mason =0.05
Mason = 0.8
Mazdoor = 0.8
Bhisti = 0.01
•RATE
  ANALYSIS FOR D.P.C. OF 2.5 CM THICKNESS C.M.(1:2)
• Consider first 100 sq . m.
A) CALUCLATION OF MATERIALS-
i. Vol. of wet mortar =
ii. Dry volume of mortar ( increase by 33%) = 2 + (0.33 x 2) = 2.66 cu.m.
iii. Cement =
iv. Sand = 0.9 x 2 = 1.8 cu.m.
v. Water proofing compound will be 2 % by wt. of cement
= 0.02 X 0.9 X 30X50 Kg = 26 Kg
vi. Formwork – as Lump sum
RATE ANALYSIS FOR BRICKWORK
• Consider first 100 sq. m.

B) LABOUR CONSTANT ( LABOUR REQUIRED ) –

SR.NO. PARTICULARS PER LABOUR CONSTANTS


1 2.0 cm thick D.P.C. with C.C.1:2:4 10 0 sq.m. Mason = 5
Mazdoor = 5
Bhisti = 1