RATE ANALYSIS 1

TASK WORK –
• It is also called as “ Turn out work”.
• It is the quantity of work which can be done by an artisan or skilled
labour of the trade working for 8 hrs. a day.
• It is approximate.

• It is worked out by following standard rate analysis of rates.


• It does not mean that it is completed by a single person.
• It is helped by other types of labourers or helpers those are engaged
too to complete the work.
SR.NO. DESCRIPTION OF WORK QUANTITY OF WORK PER
DAY (8 HRS./DAY)
1 Earthwork in excavation in foundation trenches in 2.27 cu.m. per Mazdoors
ordinary soil, lead up to 50 cm and lift up to 1.5m
2 Earthwork in excavation in foundation trenches in 2.10 cu.m. per Mazdoors
hard soil, lead up to 50 cm and lift up to 1.5m
3 Excavation in soft or decomposed rock by blasting 0.55 cu.m. per Mazdoors
, lead up to 50 cm and lift up to 1.5m
4 Sand filling in plinth, consolidating & dressing 4.00 cu.m. per Mazdoors
5 Cement concrete 5.00 cu.m. per mason
6 C.C.(1:2:4) for R.C.C. work 3.00 cu.m. per mason
7 Brickwork in foundation and plinth 1.25 cu.m. per mason
8 Brickwork in super str. Ground floor 1.10 cu.m. per mason
9 Half brickwork in partition wall 7.00 sq.m. per mason
10 Brickwork in plain arches 1 cu.m. per mason
11 2.5 cm thick cement conc. D.P.C. 12.50 sq.m. per mason
12 20 mm thick D.P.C.with cement mortar 12.50 sq.m. per mason
13 Random Rubble masonry in foundation & plinth 1 cu.m. per mason
SR.NO. DESCRIPTION OF WORK QUANTITY OF WORK PER
DAY (8 HRS./DAY)
1 Random Rubble masonry in superstructure 0.90 cu.m. per mason
2 Ashlar masonry in superstructure 0.40 cu.m. per mason
3 Coursed rubble stone masonry in susper 0.67 cu.m. per mason
structure
4 Brick on edge floor with cement mortar 1.00 sq.m. per mason
5 Neat cement punning (1.5 mm thick) 40 sq.m. per mason
6 12 mm thick cement plaster on brickwork 10 sq.m. per mason
7 6 mm thick cement plaster to R . C. ceiling 10 sq.m. per mason
8 Rule pointing on brickwork 10 sq.m. per mason
9 Water proofing cement paint to new cement 20 sq.m. painter
plaster
10 Wall painting with plastic emulsion paint for even 28 sq.m. per painter
shade
11 Primer coat with ready mixed primer on wood or 40 sq.m.Per painter
steel work
12 Painting two coats ( excluding primer coat) with 18 sq.m. per painter
ready mixed paint for wood work
SR.NO. DESCRIPTION OF WORK QUANTITY OF WORK PER
DAY (8 HRS./DAY)
1 Painting two coats (excluding primer coat) ready 28 sq. per painter
mixed paint on old wood work
2 Single coat white washing over old white washed 133 sq.. per painter
surface
3 White washing two coats on a coat of primer 66.70 sq.. per painter
4 Distempering two coats to new cement plaster 17 sq.. per painter
with a coat of primer
5 Lime punning over interior plaster . 10 sq.. per mason
6 Corrugated Galvanized Iron Sheet roofing 10 sq.. per carpenter
7 Breaking of over burnt brick to ballast 40 mm 0.75 cu.m. per mazdoor
down
8 Breaking of over burnt brick to ballast 25 mm 0.55 cu.m. per mazdoor
down
EXCAVATION ( EARTHWORK) –

SR.NO. DESCRIPTION OF AN ITEM UNIT LABOUR IN DAYS ( 8


WORKING HRS.)
1 Excavation in trenches for 10
foundation not exceeding 1.5 m in cu.m.
width , lift up to 1.5 m and lead up
to 0.3cm
a) In ordinary soil Mazdoor 3¼
b) In dense or hard soil Mazdoor 7¾
1. Calculate no. of labours required to excavate ordinary soil of 100
cu.m. ? How many labours will require to finish this work in a week?
2. Calculate no. of labours required to excavate dense soil of 300 cu.m. ?
How many labours will require to finish this work in a week?
FILLING OF EARTH –

SR.NO. DESCRIPTION OF AN ITEM UNIT LABOUR IN DAYS ( 8


WORKING HRS.)
1 Filling excavated earth in trenches , 10 mazdoor 2 1/3
plinth, sides of foundation in layers cu.m.
not exceeding 20 cm in depth
1. Calculate no. of labours required to do filling of plinth by earth for an
area of 180 sq. m.? How many labours will require to finish this work
in a week?