Maulana Mukhtar Ahmad Nadvi Technical campus

Department Of Civil Engineering


Micro Project:- EAC
Estimate of Water Tank of Size 4M X 3M
Measurement Sheet
Sr. Num Particular Num Length Breadth Depth Quantity Unit Note
1 Earthwork in Excavation 1 4.46 3.46 2.95 45.52322 Cu.M
2 PCC 1 4.46 3.46 0.15 2.31474 Cu.M
3 BBM 0
Long Wall 2 4.46 0.23 2.7 5.53932 Cu.M
Short Wall 2 3 0.23 2.7 3.726 Cu.M 9.26532
4 RCC Slab 1 4.46 3.46 0.1 1.54316 Cu.M 3.8579
5 Internal Plaster 1 14 2.7 37.8 M. Sq
Ceiling plaster 1 4 3 12 M. Sq 49.8
Rate Analysis for RCC Work

A-Concrete work
Dry volume is 52 % more of wet volume

Wet volume of concrete = 3.8579


Dry Volume of Concrete = 5.864

B-Cement Calculation
Volume of Cement = Dry Volume/ Sum of Proportion X Content of cement in Proportion
Proportion = 1:2:4 as Cement Sand and Aggregate
Volume of Cement = 0.838 Cu.M
Number of Cement Bags = Volume of Cement / Volume of one Cement bag
Number of Cement Bags = 23.93 Bags

C-Sand Calculation
Volume of Sand = Dry Volume/ Sum of Proportion X Content of Sand in Proportion
Volume of Sand = 1.675 Cu. M

D-Aggregate Calculation
Volume of aggregate = Dry Volume/ Sum of Proportion X Content of Aggregate in Proportion
Volume of Aggregate = 3.351 Cu. M

E- Steel Calculation
Assume Volume of steel 1% to the volume of Concrete
Volume of Steel = 0.039 Cu. M
Weight of Steel per Cu.M = 7850 Kg
Weight of Steel Required = 302.85 Kg
Rate Analysis for BBM Work

A-Brick Calculation
Total Quantity of Brick Work = 9.26532 Cu.M
Size of one brick = 19X9X9 CM

Size of One Brick with Mortar thickness = 20x10x10 CM


Number of Brick = Volume of Masonary/ volume of one brick with mortar
Numbe rof Brick = 4632.66 Numbers
Assume 5 % Wastage = 231.633 Numbers
Total Quantity of Brick = 4864.293 Numbers

B-Mortar Calculation
Dry volume is 35 % volume of Masonary
Volume of Masonary = 9.2653
Dry Volume of Mortar = 3.243

C-Cement Calculation
Volume of Cement = Dry Volume/ Sum of Proportion X Content of cement in Proportion
Proportion = 1:6 as Cement Sand and Aggregate
Volume of Cement = 0.463 Cu.M
Number of Cement Bags = Volume of Cement / Volume of one Cement bag
Number of Cement Bags = 13.236 Bags

D-Sand Calculation
Volume of Sand = Dry Volume/ Sum of Proportion X Content of Sand in Proportion
Volume of Sand = 2.780 Cu. M
Rate Analysis for Plastering Work

A-Mortar Calculation
Thickness of Plaster = 12 mm
Area of Palstering = 49.8 Sq.M
Volume of Mortar = 0.60 Cu.M
Add 30% more to fill in joint = 0.78 Cu.M
Dry volume is 25 % more of total wet volume = 0.97 Cu.M

B-Cement Calculation
Volume of Cement = Dry Volume/ Sum of Proportion X Content of cement in Proportion
Proportion = 1:6 as Cement Sand and Aggregate
Volume of Cement = 0.139 Cu.M
Number of Cement Bags = Volume of Cement / Volume of one Cement bag
Number of Cement Bags = 3.964 Bags

C-Sand Calculation
Volume of Sand = Dry Volume/ Sum of Proportion X Content of Sand in Proportion
Volume of Sand = 0.832 Cu. M
Estimate of Water Tank of Size 4M X 3M
Abstract Sheet
A-Cost of Material:-

Sr. Num Description of Material Quantity Unit Rate Per Amount


1 Cement 41 Number 290 Number 11929.03
2 Sand 5.3 Cu.M 2000 Cu.M 10574.8
3 Aggregate 3.35 Cu.M 1500 Cu.M 5026.293
4 Steel 302.85 Kg 32 Kg 9691.045
5 Brick 4864.29 Number 5 Number 24321.46
Total Amount 61542.62 Rs

B-Cost of Labour :-
Sr. Num Description of Material Quantity Unit Rate Per Amount
1 Head Mason 1 Number 500 Number 500
2 Mason 8 Number 350 Number 2800
3 Mail Mazdoor 12 Number 300 Number 3600
4 Femail Mazdoor 4 Number 250 Number 1000
5 Bhisti 10 Number 150 Number 1500
Total Amount 9400 Rs

Total of Material & Labour 70942.62 Rs

Add Water Charges @ 1.5 % = 1064.139 Rs


Add Contractor Profit @ 10 % = 7094.262 Rs
Grand Total = 79101.03 Rs
Rate per Cu.M = 2441.39 Rs