A-Concrete work
Dry volume is 52 % more of wet volume
B-Cement Calculation
Volume of Cement = Dry Volume/ Sum of Proportion X Content of cement in Proportion
Proportion = 1:2:4 as Cement Sand and Aggregate
Volume of Cement = 0.838 Cu.M
Number of Cement Bags = Volume of Cement / Volume of one Cement bag
Number of Cement Bags = 23.93 Bags
C-Sand Calculation
Volume of Sand = Dry Volume/ Sum of Proportion X Content of Sand in Proportion
Volume of Sand = 1.675 Cu. M
D-Aggregate Calculation
Volume of aggregate = Dry Volume/ Sum of Proportion X Content of Aggregate in Proportion
Volume of Aggregate = 3.351 Cu. M
E- Steel Calculation
Assume Volume of steel 1% to the volume of Concrete
Volume of Steel = 0.039 Cu. M
Weight of Steel per Cu.M = 7850 Kg
Weight of Steel Required = 302.85 Kg
Rate Analysis for BBM Work
A-Brick Calculation
Total Quantity of Brick Work = 9.26532 Cu.M
Size of one brick = 19X9X9 CM
B-Mortar Calculation
Dry volume is 35 % volume of Masonary
Volume of Masonary = 9.2653
Dry Volume of Mortar = 3.243
C-Cement Calculation
Volume of Cement = Dry Volume/ Sum of Proportion X Content of cement in Proportion
Proportion = 1:6 as Cement Sand and Aggregate
Volume of Cement = 0.463 Cu.M
Number of Cement Bags = Volume of Cement / Volume of one Cement bag
Number of Cement Bags = 13.236 Bags
D-Sand Calculation
Volume of Sand = Dry Volume/ Sum of Proportion X Content of Sand in Proportion
Volume of Sand = 2.780 Cu. M
Rate Analysis for Plastering Work
A-Mortar Calculation
Thickness of Plaster = 12 mm
Area of Palstering = 49.8 Sq.M
Volume of Mortar = 0.60 Cu.M
Add 30% more to fill in joint = 0.78 Cu.M
Dry volume is 25 % more of total wet volume = 0.97 Cu.M
B-Cement Calculation
Volume of Cement = Dry Volume/ Sum of Proportion X Content of cement in Proportion
Proportion = 1:6 as Cement Sand and Aggregate
Volume of Cement = 0.139 Cu.M
Number of Cement Bags = Volume of Cement / Volume of one Cement bag
Number of Cement Bags = 3.964 Bags
C-Sand Calculation
Volume of Sand = Dry Volume/ Sum of Proportion X Content of Sand in Proportion
Volume of Sand = 0.832 Cu. M
Estimate of Water Tank of Size 4M X 3M
Abstract Sheet
A-Cost of Material:-
B-Cost of Labour :-
Sr. Num Description of Material Quantity Unit Rate Per Amount
1 Head Mason 1 Number 500 Number 500
2 Mason 8 Number 350 Number 2800
3 Mail Mazdoor 12 Number 300 Number 3600
4 Femail Mazdoor 4 Number 250 Number 1000
5 Bhisti 10 Number 150 Number 1500
Total Amount 9400 Rs