Rate AnaIysis of Various Construction Component MateriaIs

Density of Sand 1 = 1466.00 Kg/m


Density of Kapachi 2 = 1401.00 Kg/m
Densiry of Cement = 1440.00 Kg/M3
Prize of Cement in Bag Pc = 265.00 Per Bag
Prize of Reti in Volume Pr = 350.00 Per Brass
Prize of Kapachi in Volume Pk = 750.00 Per Brass
Desired Concrete Volume Vol = 1.00 m
Brick Size Length L = 225.00 mm
Brick Size Breadth B = 100.00 mm
Brick Size Height H = 75.00 mm
Prize of Brick Pbr = 5.00 No
Plaster Labour per 100 Sq Ft plc = 650.00 Rs per Brass
Brick Masonary Labour bml = 6.50 Rs per SqFt
1 Rate AnaIysis of Concrete Quantity 1 Cubic Meter
VoIumatric Ratio Cu = 1.00
VoIumatric Ratio Ru = 1.50
VoIumatric Ratio Ku = 3.00
TotaI VoIume Vu = Cu + Ru + Ku = 5.50
SoIid 1 CuMt has Dry Concrete Mix in M20 is 1.52 CuMt
Cement Contains Cu =
( ) Cu * 1.52 VoI
( ) Vu
= 0.28 m
Reti Contains Ru =
Ru * 1.52 Vol
Vu
= 0.41 m
Kapachi Contains Ku =
Ku * 1.52 Vol
( ) Vu
=
3.00 * 1.52 1.00
( ) 5.50
= 0.83 m
Densiry of Cement = 1440.00 Kg/M3
Each Cement Bag Wt = 50.00 Kg
Cement Volume Bg = Cu * / / / /Wt = 8.06 Bags
Reti Volume = Ru = 0.41 m
Reti by Weight = Ru * 1 = 601.06 Kg
Kapachi Volume = Ku = 0.83 m
Kapachi by Weight = Ku * 2 = 1162.83 Kg
Desired Concrete VoIume Prize CaIcuIation
Cement Consumed R1 = Bg * Pc = 2135.90 Rs
Reti Consumed R2 = *
( )
* Ru
3.281
3
100
Pr = 50.68 Rs
Kapachi Consumed R3 = *
( )
* Ku
3.281
3
100
Pk = 219.87 Rs
Total Concrete Expenditure = R1 + R2 + R3
= 2406.45 Rs

Adding Labour Charge
10% of above = +
( )
* ( ) + R1 + R2 R3
10
100
( ) + R1 + R2 R3 = 2647.09 Rs
////////////////////////////////////////////////////////////CONCRETE COMPLETE///////////////////////////////
2 Rate AnaIysis of Masonary Quantity Bt mm thick and BI Mt by Bb Mt Height
and Width
Length of Masonary Work BI = 3.00 m
Breadth of Masonary Work Bb = 3.00 m
Thickness of Msonary Work Bt = 115.00 mm
TotaI Masonary VoIume Mbu = *
( )
Bt
1000
* BI Bb = 1.03 m
One Brick Volume Bvol =
* L * B H
* 1000 * 1000 1000
= 0.001688 m
Mortar 1% of Total Masonary Volume Bmtr = * Mbu
23
100
= 0.236900 m
No of Bricks Bno =
Mbu
Bvol
= 610.19 No
Considering Mix

Cement Portion cp = 1
and Reti Portion rp = 6
Total tl = cp + rp = 7.0
Cement Volume Mbg =
1
tl
= 0.1429
Cement Bags Bcbg = * ( ) ( ) Bmtr

Wt tl
= 0.97 Bags
Reti Br = Bmtr * 6/7 = 0.20 m
Cement Consumed CC = Bcbg * Pc = 257.05 Rs Per Bag
Reti Consumed RC = Br * Pr = 70.00 Rs
Bricks Consumed BC = Bno * Pbr = 3050.95 Rs
Brick Masonary Labour Charge BLC = * bml *
( )
3.282
2
* Mbu
1000
Bt
= 627.09 Rs
Total Cost Tc = BLC+BC + Bcbg*Pc + Br* Pr = 4005.09 Rs
Total Cost Tc =
Tc
Mbu 3.281^3
= 110.09 Rs Per CuFt
/////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////
3 Rate AnaIysis of PIaster
PIaster Thickness Pth = 12.50 mm
Plaster Length Pl = 3.00 m
Plaster Height Ph = 3.00 m
Plaster Quatity Pqt = * Pl * Ph
Pth
1000
= 0.11 m
n Plaster Cement Contain Pcement =
1.00
n Plaster Reti Contain Preti = 4.00
Total Mortar Pmortar = Pcement + Preti = 5.00
Cement Bags Pbags = (Pqt *Pcement / Pmortar) * / / / /Wt = 0.63 Bags
Reti Pqty = * Pqt
Preti
Pmortar
= 0.09 m

Say in CuFt = Pqty * 3.282^3 = 3.18 CuFt
By Weight = Pqty * 1 1 1 1 = 131.94 kg
Prize CaIcuIation
Cement Consumed PCC = Pbags * Pc = 166.95 Rs
Reti Consumed PRC = Pqty * Pr = 31.50 Rs
Labour Charge PLC = * ( ) * Pl Ph * plc
3.282
2
100
= 630.13 Rs
Total Plaster Cost = PCC + PRC + PLC = 828.58 Rs
Total Cost Per SqFt =
+ PCC + PRC PLC
* Pl * Ph 3.281
2
= 8.55 Rs Per SqFt