Professional Documents
Culture Documents
FACULTY OF ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING
Group Members-
Samarakoon H.M.M.P. - EN18364934
Thanthrige G.T.N.I. - EN18357486
Rajapaksha R.A.B.P.B. - EN18384116
Acknowledgement
With pleasure, we were able to complete our task within the given time period. Most importantly, this
is a group work. Our group members worked for this success with a great spirit of unity. And our biggest
thank goes to our lecturer Eng. Felix Weerakkody for guiding us correctly to this completion
successfully and for teaching us this module. Our last but not least thank goes to our batch reps, friends
and respondents who supported us willingly, specially by spending their valuable time to educate us
with our questionnaires.
2
List of Figures
3
List of Tables
Table 1 – Data Collection 6
4
Table of Content
1. Introduction 5
2. Data Collection 6
12.2 Materials 13
13. Conclusion 16
14. References 17
5
1. Introduction
The designated assignment was focused on investigating and designing various parameters in
executing a concerting process. Different mix design specifications such as finding the volumes,
quantities required, the cost and time estimated, different required resources and the method
statement for the process are included in this report.
Further optimization will be done on the design specifications from the given design parameters.
Some of the parameters will be assumed with accordance to the local standards.
Finally the report will be contained with a substantial practical characteristic which will conquer
the civil engineering aspects.
6
2. Data Collection
This report includes all the costs involved in the process of laying a raft foundation, from the
operation of batching plant up to the placing of concrete for the foundation.
BASIC PARAMETERS
The mix design parameters for concrete (grade 25-35) to be placed for a raft foundation;
7
3. Mixed design for the raft foundation
Fine Aggregate
= 0.35
Coarse Aggregate
8
3.2 Mass Calculations per cubic meter
= 148liters
= 148 kg
Total weight = (471.7+1354.15+370+148) Kg
= 2343.85kg
9
4. Total Quantity of Cement Required
= 44.4 m3
= 44.4 ×1000
= 44400 Kg
10
Total time for the truck mixer cycle = 10 + 47.1 +20
= 77.1minutes
= 300m3/ 6m3
=50 times
Time required for placing concrete = No of times× Time for single placement
= 50×20
= 1000 minutes
=16.66 hours
= 50 / 20
= 2.5, therefore 3 trucks
11
10. Cost per cubic meter of Concrete at the Batching Plant
12
11. Cost of Transporting and Placing the Concrete
13
12. Method statement for executing the entire operation
The main purpose of the method statement is to explain the proper and systematic process of how to
construct a raft foundation that is highly complaint with standard engineering practices.
12.2 Materials
Batching plant
Truck mixers
Concrete pump
Concrete vibrators
Wheel barrow
Rubber hammer
Surveying instruments
Concrete cylinders/cubes
Shovels
Slump tray
Slump cone and other tools
14
12.4 Working Procedure
Batching Plant
Materials
Cement
Cement should be in an enclosed shell or building with dry weather. But, in the batching plants,
the cement is stored in the silos. The silos should be clean and the cement should be fresh to
avoid the lowering of quality of cement.
Aggregates
Make sure that the coarse and fine aggregates are clean. Prevent from segregation and store in a
hard clean base with free drainage. If the ambient temperature is high, water should be sprayed
on the aggregates. Aggregate must be clean and conform to the required grading curve.
Water
The water should be drinking water. If water is stored, it should be kept cool. The water should
be prevented from mixing with debris and chemicals.
15
Admixtures
Store the other materials like admixtures and pigments separately in order to identify easily and
do not become mixed together or contaminated.
Procedure
Batching should be done according to the mixing plan given in the mix design. The right
materials should be always be selected. Cement and aggregates are to be batched by mass and
mass by volume. Adding admixtures should follow the instructions given by its manufacturer.
Always work for accurate measurements. The batching plant should be cleaned after each use.
The same sequence should be followed for each batch otherwise the consistency of the concrete
produced may vary.
If the coarse aggregate is put into the hopper firstly, this prevents the cement and sand caking on
the hopper surface.
Mixing time is 1.5 - 2 minutes.
Concrete mixing should be done at the batching plant approved by the engineer and it should be
transported by truck mixer as per the specifications, codes and approved design mixing
requirements.
Laboratory tests will be carried on the concrete mix materials for classification as defined in the
specification and ensure that during the course of concrete mixing and preparation.
Pumping
Procedure
First, it is to be ensured that formwork and reinforcement are completed before concreting.
All pieces must be inspected before laying pipes.
Support and protection must be provided.
Then the clamps must be inspected.
After checking formwork concreting can be conducted.
Before that the temperature and slump should be checked and approved.
when the concrete is being supplied to the pump, two truck are allowed to supply concrete to the
pump. the reason is that one truck can discharge concrete continuously even though other truck
can't discharge concrete due to finishing of concrete. according to that, the concreteing can be
done without a brake the continuity.
Pump should be operated according to the manufacturer’s guidelines.
17
Placing
Make sure that the faces are stable and accurate before placing the foundation against the faces of
excavations.
Finishing
Finishing of exposed surfaces must be done before the concrete has hardened.
18
12.5 Health and Safety
19
13. Conclusion
Through this assignment we were able to gain a better understanding of mix design for a raft foundation.
A mix design includes a variety of materials, such as volume, quantity of materials required, estimated
cost, and calculation of time spent on various processes.
Our main task in the future is to complete the task assigned to us as professional engineers accurately,
systematically, efficiently and sustainably. Therefore, this assignment helped us a lot to design the
required specifications correctly. It helps us to complete the whole process sustainably with less
environmental impact.
Finally, through this assignment, we will be able to enhance our skills, knowledge and technology in
the field of civil engineering, as well as enhance our communication skills and work together as a team
to further our professional work in the field of civil engineering in the future.
20
14. References
C. Works, "Construction Method Statement For Concrete Works", Sites.google.com, 2020. [Online].
Available: https://sites.google.com/view/yhnmawiwxm/Construction-Method-Statement-For-
Concrete-Works. [Accessed: 04- Aug- 2020].
M. Pdf, "Method Statement Raft Foundation Pdf", Sites.google.com, 2020. [Online]. Available:
https://sites.google.com/view/czchfzygbw/Method-Statement-Raft-Foundation-Pdf. [Accessed: 07-
Aug- 2020].
K. Guzder and K. Guzder, "What is a Method Statement? | Free Downloadable Template", The Hub
| High Speed Training, 2020. [Online]. Available: https://www.highspeedtraining.co.uk/hub/what-is-
a-method-statement/. [Accessed: 10- Aug- 2020].
21