1

Quantity Considered earthwork


Sr. No Labour/Material/Others Quatity/10m
3
Rate Per Amount in Rs.
1 Labour
a) Mate 0.6 162 day 97.38
b) Mazdoor 6.2 166 day 1030.13
Sum 1127.51
2 Water @ 1.50% 16.91
Sum 1144.42
3 Contractor's Profit @ 10% 114.44
Total For 10m
3
1258.86
Therefore, Per m
3
126.00
2
Unreinforced concrete 1 : 4 : 8
consolidating and curing:
Quantity Considered concrete
Sr. No Labour/Material/Others Quatity/10m
3
Rate Per Amount in Rs.
1 Labour For 10 m
3
dry concrete = 15.5
a) Mason 1 182 day 181.80 15.5 / (1 + 4 + 8 )
b) Mazdoor 21.3 166 day 3539.00 1.19 m
3
c) Bhistie 7 162 day 1136.10 1440 kg/m3
2 Materials 1.19 x 1440
a) Cement bags 34.34 329 bag 11290.99 1717 kg
b) Sand 4.77 437 m
3
2083.54 1 50 kg
c) Coarse Aggregates 9.54 1071 m
3
10217.34 1717 / 50
Sum 28448.77 34.34 bags
3 Water @ 1.50% 426.73 4.77 m
3
4 Tools and Machinery Lump sum 500.00 9.54 m
3
Sum 29375.50
Density of Cement =
Coarse Aggregates Reqd. =
10 m
3
Therefore, Cement Required =
bag of cement =
No. of Cement bags reqd. =
Sand Required =
1
1
1
1
RATE ANALYSIS
a) Excavation over areas (Hard/dense soil ), depth up to I.5 m and removal
Therefore, cement required =
Therefore, cement required =
Cement Required =
Excavation and Earth Works
( up to one metre from edge )
in foundations including mixing, pouring,
1) Hand mixed cement concrete
Day
Day
10 m
3
Plain Cement Concrete
Calculation of Materials
m
3
wet concrete
1
Note: Labour Constants have been taken from IS: 7272 (Part I)
No. of Cement bags reqd. =
Page 1 of 6
5 Contractor's Profit @ 10% 2937.55
Total For 10m
3
32313.05
Therefore, Per m
3
3232.00
3
Reinf. cement concrete 1 : 1.5 : 3
Quantity Considered concrete
Sr. No Labour/Material/Others Quatity/10m
3
Rate Per Amount in Rs. For 10 m
3
dry concrete = 15.5
1 Labour 15.5 / (1+ 1.5 + 3 )
a) Mason 1.7 182 day 309.06 Cement = 2.82
b) Mazdoor 20 166 day 3323.00 1440
c) Bhistie 9 162 day 1460.70 2.82 x 1440
d) Mixer Operator 0.7 182 day 127.26 4058
e) Mixer 0.7 182 day 127.26 1 50
f) Vibrator 0.7 182 day 127.26 4058 / 50
2 Materials 81.16
a) Cement bags 81.16 329 bag 26685.41 4.23
b) Sand 4.23 437 m
3
1847.66 8.45
c) Coarse Aggregates 8.45 1071 m
3
9049.95
Sum 43057.56
3 Water @ 1.50% 645.86
4 Tools and Machinery Lump Sum 500.00
Sum 44203.42
5 Contractor's Profit @ 10% 4420.34
Total For 10m
3
48623.76
Therefore, Per m
3
4863.00
4
Size of Modular brick is 20 x 10 X 10 cms
cement mortar 1 : 4 In 1 m3, no of bricks = 1 / 0.2 / 0.1 / 0.1
Quantity Considered brickwork In 1 m3, no of bricks = 500 nos
Sr. No Labour/Material/Others Quatity/10m
3
Rate Per Amount in Rs. In 10 m3, no of bricks = 5000 nos
Concrete
Day
Day
Therefore, Cement Required =
1
1
1
bag of cement =
No. of Cement bags reqd. =
Sand Required =
Therefore, Cement required =
Density of Cement =
insitu in foundations, concrete footings
bases tor columns, etc excluding form work and reinforcement
10 m
3
1
1
1
Coarse Aggregates Reqd. =
10 m
3
a) Brick work in walls exceeding one brick thick, in
Brick work ( Straight Walls)
m
3
Cement Required =
No. of Cement bags reqd. =
Calculation of Materials
Calculation of Materials
m
3
wet concrete
m
3
kg/m3
kg
kg
bags
m
3
Page 2 of 6
1 Labour Size of Actual Brick is 19 x 9 x 9 cms
a) Mason 9.4 182 day 1708.92 For 1 m3,
b) Mazdoor 18 166 day 2990.70 Actual volume of by bricks= 500 x 0.19 x 0.09 x 0.09
c) Bhistie 2 162 day 324.60 Actual volume of by bricks= 0.77 m3
2 Materials Volume of cement mortar = 1 - 0.77
a) Bricks 5000 5.8 nos 29000.00 Volume of cement mortar = 0.23 m3
b) Cement bags 20.08 329 bag 6602.30 Add 10% for undulations = 0.25 m3
c) Sand 2.79 437 m
3
1218.67 Add 10% for frogs, wastage = 0.28 m3
Sum 41845.20 For 10 m3 of brickwork = 10 x 0.28 m3 of cement mortar
3 Water @ 1.50% 627.68 For 10 m3 of brickwork = 2.79 m3 of cement mortar
Sum 42472.88 For 10 m
3
dry mortar = 12.5 m
3
wet mortar
4 Contractor's Profit @ 10% 4247.29 For 10 m3 of c.m, Cement = 2.5 m
3
Total For 10m
3
46720.17 For 2.79 m3 of c.m. = 2.79 x 2.5 / 10
Therefore, Per m
3
4673.00 For 2.79 m3 of c.m. = 0.7 m3 of cement
1440 kg/m3
1004 kg
1 50 kg
20.08 bags
2.79 m
3
5
Cement plaster 15 On 10 m2, the quantity of cement mortar in bottom layer,
mixing of mortar c.m. in bottom Layer= 10 x 0.01
Assume: Bottom Layer c.m. in bottom Layer= 0.1 m3
in cement mortar 1 : 5 Add 10% for undulations = 0.11 m3
the top Layer being Add 10% for wastage, etc. = 0.12 m3
in cement mortar 1 : 3 For 10 m
3
dry mortar = 12.5 m
3
wet mortar
Quantity Considered surface area, over which plaster is applied. For 10 m3 of c.m, Cement = 2.08 m
3
Sr. No Labour/Material/Others Quatity/10m
3
Rate Per Amount in Rs. For 0.12 m3 of c.m. = 0.12 x 2.083 / 10
1 Labour For 0.12 m3 of c.m. = 0.03 m3 of cement
a) Mason 0.6 182 day 181.80 1440 kg/m3
b) Mazdoor 1 166 day 166.15 36.3 kg
c) Bhistie 1 162 day 162.30 1 50 kg
2 Materials 0.73 bags
a) Cement bags 1.23 329 bag 404.42 0.13 m
3
Density of Cement =
Cement Required =
10
5
10 m
2
mm thick
1
1
mm thick over brick walls ( exterior ) including
External Plastering:
1
1
1
bag of cement =
No. of Cement bags reqd. =
Sand Required =
and
mm thick
Day
1
bag of cement =
No. of Cement bags reqd. =
Calculation of Materials
Sand Required =
Density of Cement =
Cement Required =
Page 3 of 6
b) Sand 0.18 437 m
3
78.62 On 10 m2, the quantity of cement mortar in top layer,
Sum 993.29 c.m. in top Layer= 10 x 0.005
3 Water @ 1.50% 14.90 c.m. in top Layer= 0.050 m3
Sum 1008.19 Add 1% for undulations = 0.051 m3
4 Contractor's Profit @ 10% 100.82 Add 10% for wastage, etc. = 0.056 m3
Total For 10m
2
1109.01 For 10 m
3
dry mortar = 12.5 m
3
wet mortar
Therefore, Per m
2
111.00 For 10 m3 of c.m, Cement = 3.13 m
3
For 0.06 m3 of c.m. = 0.056 x 3.125 / 10
For 0.06 m3 of c.m. = 0.017 m3 of cement
1440 kg/m3
25 kg
1 50 kg
0.5 bags
0.05 m
3
6 Flooring:
Precast terrazo tile flooring 10
thick cement mortar: 1 : 4
Size of a Terrazo tile is 250 x 250
Quantity Considered surface area, over which flooring is laid. In 1 m2, no of tiles = 1 / 0.25 / 0.25
Sr. No Labour/Material/Others Quatity/10m
3
Rate Per Amount in Rs. In 1 m2, no of tiles = 16 nos
1 Labour In 10 m2, no of tiles = 160 nos
a) Mason 1.2 182 day 218.16 Volume of c. m. over 1 m2 = 1 x 0.01
b) Mazdoor 2 166 day 332.30 Volume of cement mortar = 0.010 m3
c) Bhistie 1 162 day 162.30 Add 10% for undulations = 0.011 m3
d) Mazdoor 5 166 day 830.75 Add 10% for wastage = 0.012 m3
e) Machine 4 182 day 727.20 For 10 m2 of terrazo tiling = 10 x 0.012 m3 of cement mortar
2 Materials For 10 m2 of terrazo tiling = 0.12 m3 of cement mortar
a) Tiles 160 75 nos 12000.00 For 10 m
3
dry mortar = 12.5 m
3
wet mortar
b) Cement bags 0.87 329 bag 286.06 For 10 m3 of c.m, Cement = 2.5 m
3
c) Sand 0.12 437 m
3
52.42 For 0.12 m3 of c.m. = 0.12 x 2.5 / 10
Sum 14609.18 For 0.12 m3 of c.m. = 0.03 m3 of cement
3 Water @ 1.50% 219.14 1440 kg/m3
Sum 14828.32 43.6 kg
4 Contractor's Profit @ 10% 1482.83 1 50 kg
Total For 10m2 16311.15 0.87 bags
20 mm thick laid over
including Laying, cutting, grinding and polishing
Density of Cement =
Cement Required =
bag of cement =
No. of Cement bags reqd. =
Day
1
1
1
1
Sand Required =
bag of cement =
No. of Cement bags reqd. =
10 m
2
Density of Cement =
Cement Required =
mm
1
Calculation of Materials
Page 4 of 6
Therefore, Per m
2
1632.00 0.12 m
3
Following has been assumed:
329
437
1071
5.8
75
Austin S. Rodrigues, Lecturer, Government
Polytechnic Panaji
162.3
181.8
166.15
Cement
Sand
Coarse Aggregates
Sand Required =
Labour
Mate
Mason
Mazdoor
Bhistie
Mixer Operator
Mixer
Vibrator
Rate/day
m3
no
no
Rate Material Rate Per Unit
162.3
181.8
181.8
181.8
Machine Operator 181.8
Bricks
Terrazo Tiles
bag
m3