Sr. No Labour/Material/Others Quatity/10m 3 Rate Per Amount in Rs. 1 Labour a) Mate 0.6 162 day 97.38 b) Mazdoor 6.2 166 day 1030.13 Sum 1127.51 2 Water @ 1.50% 16.91 Sum 1144.42 3 Contractor's Profit @ 10% 114.44 Total For 10m 3 1258.86 Therefore, Per m 3 126.00 2 Unreinforced concrete 1 : 4 : 8 consolidating and curing: Quantity Considered concrete Sr. No Labour/Material/Others Quatity/10m 3 Rate Per Amount in Rs. 1 Labour For 10 m 3 dry concrete = 15.5 a) Mason 1 182 day 181.80 15.5 / (1 + 4 + 8 ) b) Mazdoor 21.3 166 day 3539.00 1.19 m 3 c) Bhistie 7 162 day 1136.10 1440 kg/m3 2 Materials 1.19 x 1440 a) Cement bags 34.34 329 bag 11290.99 1717 kg b) Sand 4.77 437 m 3 2083.54 1 50 kg c) Coarse Aggregates 9.54 1071 m 3 10217.34 1717 / 50 Sum 28448.77 34.34 bags 3 Water @ 1.50% 426.73 4.77 m 3 4 Tools and Machinery Lump sum 500.00 9.54 m 3 Sum 29375.50 Density of Cement = Coarse Aggregates Reqd. = 10 m 3 Therefore, Cement Required = bag of cement = No. of Cement bags reqd. = Sand Required = 1 1 1 1 RATE ANALYSIS a) Excavation over areas (Hard/dense soil ), depth up to I.5 m and removal Therefore, cement required = Therefore, cement required = Cement Required = Excavation and Earth Works ( up to one metre from edge ) in foundations including mixing, pouring, 1) Hand mixed cement concrete Day Day 10 m 3 Plain Cement Concrete Calculation of Materials m 3 wet concrete 1 Note: Labour Constants have been taken from IS: 7272 (Part I) No. of Cement bags reqd. = Page 1 of 6 5 Contractor's Profit @ 10% 2937.55 Total For 10m 3 32313.05 Therefore, Per m 3 3232.00 3 Reinf. cement concrete 1 : 1.5 : 3 Quantity Considered concrete Sr. No Labour/Material/Others Quatity/10m 3 Rate Per Amount in Rs. For 10 m 3 dry concrete = 15.5 1 Labour 15.5 / (1+ 1.5 + 3 ) a) Mason 1.7 182 day 309.06 Cement = 2.82 b) Mazdoor 20 166 day 3323.00 1440 c) Bhistie 9 162 day 1460.70 2.82 x 1440 d) Mixer Operator 0.7 182 day 127.26 4058 e) Mixer 0.7 182 day 127.26 1 50 f) Vibrator 0.7 182 day 127.26 4058 / 50 2 Materials 81.16 a) Cement bags 81.16 329 bag 26685.41 4.23 b) Sand 4.23 437 m 3 1847.66 8.45 c) Coarse Aggregates 8.45 1071 m 3 9049.95 Sum 43057.56 3 Water @ 1.50% 645.86 4 Tools and Machinery Lump Sum 500.00 Sum 44203.42 5 Contractor's Profit @ 10% 4420.34 Total For 10m 3 48623.76 Therefore, Per m 3 4863.00 4 Size of Modular brick is 20 x 10 X 10 cms cement mortar 1 : 4 In 1 m3, no of bricks = 1 / 0.2 / 0.1 / 0.1 Quantity Considered brickwork In 1 m3, no of bricks = 500 nos Sr. No Labour/Material/Others Quatity/10m 3 Rate Per Amount in Rs. In 10 m3, no of bricks = 5000 nos Concrete Day Day Therefore, Cement Required = 1 1 1 bag of cement = No. of Cement bags reqd. = Sand Required = Therefore, Cement required = Density of Cement = insitu in foundations, concrete footings bases tor columns, etc excluding form work and reinforcement 10 m 3 1 1 1 Coarse Aggregates Reqd. = 10 m 3 a) Brick work in walls exceeding one brick thick, in Brick work ( Straight Walls) m 3 Cement Required = No. of Cement bags reqd. = Calculation of Materials Calculation of Materials m 3 wet concrete m 3 kg/m3 kg kg bags m 3 Page 2 of 6 1 Labour Size of Actual Brick is 19 x 9 x 9 cms a) Mason 9.4 182 day 1708.92 For 1 m3, b) Mazdoor 18 166 day 2990.70 Actual volume of by bricks= 500 x 0.19 x 0.09 x 0.09 c) Bhistie 2 162 day 324.60 Actual volume of by bricks= 0.77 m3 2 Materials Volume of cement mortar = 1 - 0.77 a) Bricks 5000 5.8 nos 29000.00 Volume of cement mortar = 0.23 m3 b) Cement bags 20.08 329 bag 6602.30 Add 10% for undulations = 0.25 m3 c) Sand 2.79 437 m 3 1218.67 Add 10% for frogs, wastage = 0.28 m3 Sum 41845.20 For 10 m3 of brickwork = 10 x 0.28 m3 of cement mortar 3 Water @ 1.50% 627.68 For 10 m3 of brickwork = 2.79 m3 of cement mortar Sum 42472.88 For 10 m 3 dry mortar = 12.5 m 3 wet mortar 4 Contractor's Profit @ 10% 4247.29 For 10 m3 of c.m, Cement = 2.5 m 3 Total For 10m 3 46720.17 For 2.79 m3 of c.m. = 2.79 x 2.5 / 10 Therefore, Per m 3 4673.00 For 2.79 m3 of c.m. = 0.7 m3 of cement 1440 kg/m3 1004 kg 1 50 kg 20.08 bags 2.79 m 3 5 Cement plaster 15 On 10 m2, the quantity of cement mortar in bottom layer, mixing of mortar c.m. in bottom Layer= 10 x 0.01 Assume: Bottom Layer c.m. in bottom Layer= 0.1 m3 in cement mortar 1 : 5 Add 10% for undulations = 0.11 m3 the top Layer being Add 10% for wastage, etc. = 0.12 m3 in cement mortar 1 : 3 For 10 m 3 dry mortar = 12.5 m 3 wet mortar Quantity Considered surface area, over which plaster is applied. For 10 m3 of c.m, Cement = 2.08 m 3 Sr. No Labour/Material/Others Quatity/10m 3 Rate Per Amount in Rs. For 0.12 m3 of c.m. = 0.12 x 2.083 / 10 1 Labour For 0.12 m3 of c.m. = 0.03 m3 of cement a) Mason 0.6 182 day 181.80 1440 kg/m3 b) Mazdoor 1 166 day 166.15 36.3 kg c) Bhistie 1 162 day 162.30 1 50 kg 2 Materials 0.73 bags a) Cement bags 1.23 329 bag 404.42 0.13 m 3 Density of Cement = Cement Required = 10 5 10 m 2 mm thick 1 1 mm thick over brick walls ( exterior ) including External Plastering: 1 1 1 bag of cement = No. of Cement bags reqd. = Sand Required = and mm thick Day 1 bag of cement = No. of Cement bags reqd. = Calculation of Materials Sand Required = Density of Cement = Cement Required = Page 3 of 6 b) Sand 0.18 437 m 3 78.62 On 10 m2, the quantity of cement mortar in top layer, Sum 993.29 c.m. in top Layer= 10 x 0.005 3 Water @ 1.50% 14.90 c.m. in top Layer= 0.050 m3 Sum 1008.19 Add 1% for undulations = 0.051 m3 4 Contractor's Profit @ 10% 100.82 Add 10% for wastage, etc. = 0.056 m3 Total For 10m 2 1109.01 For 10 m 3 dry mortar = 12.5 m 3 wet mortar Therefore, Per m 2 111.00 For 10 m3 of c.m, Cement = 3.13 m 3 For 0.06 m3 of c.m. = 0.056 x 3.125 / 10 For 0.06 m3 of c.m. = 0.017 m3 of cement 1440 kg/m3 25 kg 1 50 kg 0.5 bags 0.05 m 3 6 Flooring: Precast terrazo tile flooring 10 thick cement mortar: 1 : 4 Size of a Terrazo tile is 250 x 250 Quantity Considered surface area, over which flooring is laid. In 1 m2, no of tiles = 1 / 0.25 / 0.25 Sr. No Labour/Material/Others Quatity/10m 3 Rate Per Amount in Rs. In 1 m2, no of tiles = 16 nos 1 Labour In 10 m2, no of tiles = 160 nos a) Mason 1.2 182 day 218.16 Volume of c. m. over 1 m2 = 1 x 0.01 b) Mazdoor 2 166 day 332.30 Volume of cement mortar = 0.010 m3 c) Bhistie 1 162 day 162.30 Add 10% for undulations = 0.011 m3 d) Mazdoor 5 166 day 830.75 Add 10% for wastage = 0.012 m3 e) Machine 4 182 day 727.20 For 10 m2 of terrazo tiling = 10 x 0.012 m3 of cement mortar 2 Materials For 10 m2 of terrazo tiling = 0.12 m3 of cement mortar a) Tiles 160 75 nos 12000.00 For 10 m 3 dry mortar = 12.5 m 3 wet mortar b) Cement bags 0.87 329 bag 286.06 For 10 m3 of c.m, Cement = 2.5 m 3 c) Sand 0.12 437 m 3 52.42 For 0.12 m3 of c.m. = 0.12 x 2.5 / 10 Sum 14609.18 For 0.12 m3 of c.m. = 0.03 m3 of cement 3 Water @ 1.50% 219.14 1440 kg/m3 Sum 14828.32 43.6 kg 4 Contractor's Profit @ 10% 1482.83 1 50 kg Total For 10m2 16311.15 0.87 bags 20 mm thick laid over including Laying, cutting, grinding and polishing Density of Cement = Cement Required = bag of cement = No. of Cement bags reqd. = Day 1 1 1 1 Sand Required = bag of cement = No. of Cement bags reqd. = 10 m 2 Density of Cement = Cement Required = mm 1 Calculation of Materials Page 4 of 6 Therefore, Per m 2 1632.00 0.12 m 3 Following has been assumed: 329 437 1071 5.8 75 Austin S. Rodrigues, Lecturer, Government Polytechnic Panaji 162.3 181.8 166.15 Cement Sand Coarse Aggregates Sand Required = Labour Mate Mason Mazdoor Bhistie Mixer Operator Mixer Vibrator Rate/day m3 no no Rate Material Rate Per Unit 162.3 181.8 181.8 181.8 Machine Operator 181.8 Bricks Terrazo Tiles bag m3 Page 5 of 6