Professional Documents
Culture Documents
REPORT
The estimate has been prepared as per PWD. Building 2013-14, Assam ( 12 %
GST added) &S.R.of C.E.Irri.Dep. 2017-18, Assam.
All works will be carried out as per A.P.W.D. specifications and departmental
norms.
Name of Work :- Construction of Plastic Recycling Plant at Goalpara.
ABSTRUCT OF COST
Item No : 1
[6.7 (a)]
Earth work in excavation trenches of walls, retaining walls, footing of walls,steps & septic tank including refilling (return
filling) the quantity as necessary after completetion of works, breaking clods in return filling, dressing, ramming, watering
etc.and removal of surplus earth with all lead and lift upto 2.00 metre as directed and specified in following classification
of soils, including bailing out of water where necessary upto depth below the existing ground level as mentioned in the
approved drawing and complete as directed and classified.
(A) In ordinary soil
Footing 28 x 1.80 mx 1.80 mx 1.50 m = 136.08 m3
Tie beam 3 x 18.00 mx 0.30 mx 0.25 m = 4.05 m3
8 x 10.00 mx 0.30 mx 0.25 m = 6.00 m3
Total = 146.13 m3
@ Rs. 375.93 / m3 (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 54,935.00
Item No : 2
[24.6 (i)]
Soling in foundation and under floor including filling interstices, ramming etc, completed as directed and as specified
thickness
(a) 9 cm brick on fllat including sand packing.
Footing 28 x 1.80 mx 1.80 m = 90.72 m2
Tie beam 3 x 18.00 mx 0.25 m = 13.50 m2
8 x 10.00 mx 0.25 m = 20.00 m2
Floor 1 x 10.00 mx 18.00 m = 180.00 m2
Total = 304.22 m2
@ Rs. 502.08 / m3 (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 152,743.00
Item No: 3
[24.4(c)]
Plain cement concrete floor base of thickness 100 mm in proportion 1:3:6 with coarse aggregate of size 13 mm to 38 mm
including curing etc, complete as specified.
Footing 28 x 1.80 m x 1.80 m = 90.72 m2
Tie beam 3 x 18.00 m x 0.25 m = 13.50 m2
8 x 10.00 m x 0.25 m = 20.00 m2
Floor 1 x 10.00 mx 18.00 m = 180.00 m2
Total = 304.22 m2
@ Rs. 656.33 / m2 (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 199,669.00
Item No: 4
[24.13]
Cement Concrete work in topping in proportion 1:1:2 with 6mm to 9mm size aggregate over CC floor and RCC floors,
tread and rise ding finishing the surface smooth neat cement and curing etc, complete as directed. ( 19 mm thick)
Floor 1 x 10.00 mx 18.00 m = 180.00 m2
@ Rs. 321.28 / m2 (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 57,830.00
Item No: 5
[12.1(A) (ii)]
RCC work in slab , abutment cap and above abutment, pier cap, pedestal, dirt wall etc. in proportion 1:1.5:3 with hard
broken stone aggregate of size 6mm to 20mm with proper renforcement as per design including necessary curing,
dewatering etc. completed as directed with necessary timber shutterring, scaffolding etc. where necessary, completed as
directed.(Shuttering, scaffolding cost will be separetly)
Footing base 28 x 1.80 mx 1.80 mx 0.10 m = 9.07 m3
Column 28 x 0.30 mx 0.30 mx 9.80 m = 24.70 m3
Deduct for tie 28 x 0.30 mx 0.30 mx 0.25 m = -0.63 m3
Beam 3 x 18.00 mx 0.40 mx 0.30 m = 6.48 m3
2 x 10.00 mx 0.40 mx 0.30 m = 2.40 m3
Lintel 2 x 2 x 18.00 mx 0.20 mx 0.20 m = 2.88 m3
2 x 2 x 10.00 mx 0.20 mx 0.20 m = 1.60 m3
Tie beam 3 x 18.00 mx 0.30 mx 0.25 m = 4.05 m3
8 x 10.00 mx 0.30 mx 0.25 m = 6.00 m3
Total = 56.55 m3
@ Rs. 9033.25 / m3 (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 510,830.00
Item No: 6 `
[6.16 (A)]
Earth work in filling in all soils in plinth, canal embankmentand back filling as per design section and grade by truck
carriage for a minimum distance of 4 KM including paying compensation of earth obtained from private land if any
loading, unloading, spreading the same including light jungle,removing trees upto 15 cm dia and uprooting roots and
stumps etc. from the seat of the embankment, breaking clods not more than 10mm cube, ramming, profillingetc. with alll
lift, completed as directed. ( Payment will be made after deduction of 12.50% shrinkage allowance from the gross
quantity).
Item No: 7
Providing form work of ordinary timber planking so as to give a rough finish including centering, shuttering, strutting and
propping etc, height of propping and centering below supportion floor to ceiling not exceeding 4.0m. and removal of the
same for in-situ reinforced concrete and plain concrete work in:
1 .Foundation, footings, bases of columns, pile cap, raft and mass concrete works etc.
Using 25mm thick plank
Footing 28 x 4 x 1.80 m x 0.100 m = 20.16 m2
Column upto PL 28 x 4 x 0.30 m x 2.10 m = 70.56 m2
Total = 90.72 m2
@ Rs. 269.90 / m2 (As per S.R.of PWD.Bldg 2013-14) = Rs. 24,485.00
2. Sides of tie beams, plinth beams, grade beams etc. at or below plinth level
Using 25mm thick plank
Tie beam 3 x 2 x 18.00 mx 0.40 m = 43.20 m2
8 x 2 x 10.00 mx 0.40 m = 64.00 m2
Total = 107.20 m2
@ Rs. 389.49 / m2 (As per S.R.of PWD.Bldg 2013-14) = Rs. 41,753.00
3. Columns, pillars, posts & strut
(a) Square, Rectangular, Polygonal in plan or anyshape like Tee/L etc. having plan vertical face
Using 25mm thick plank
Column above PL 28 x 4 x 0.30 mx 7.63 m = 256.27 m2
@ Rs. 216.61 / m2 (As per S.R.of PWD.Bldg 2013-14) = Rs. 55,511.00
4. Sides and soffits of beam, beam haunchings, cantilever girders, bressumers, lintels and horizontal ties.
Using 25mm thick plank
Beam 3 x 2 x 18.00 mx 0.40 m = 43.20 m2
3 x 1 x 18.00 mx 0.30 m = 16.20 m2
2 x 2 x 10.00 mx 0.40 m = 16.00 m2
2 x 1 x 10.00 mx 0.30 m = 6.00 m2
Lintel 2 x 2 x 18.00 mx 0.20 m = 14.40 m2
2 x 2 x 10.00 mx 0.20 m = 8.00 m2
2 x 3 x 18.00 mx 0.20 m = 21.60 m2
2 x 3 x 10.00 mx 0.20 m = 12.00 m2
Total = 137.40 m2
@ Rs. 247.17 / m2 (As per S.R.of PWD.Bldg 2013-14) = Rs. 33,961.00
Item No: 8
[24.8 (A) (ii)]
Brtick work in cement morter with 1st class brick as directed in foundation, retaining walls, plinth & steps including
racking out joints & curing.(ii) In proportion 1:4
Item No: 9
[24.10 (ii)]
125mm thick 1st class brick nogged wall in cement morter in proportion 1:4 including racking out joints curing etc,
complete as directed. (ii) 125 mm thick
2 x 18.00 mx 1.80 m = 64.80 m2
2 x 10.00 mx 1.80 m = 36.00 m2
Total = 100.80 m2
@ Rs. 903.89 / m2 (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 91,112.00
Item No: 10
[14.2 (ii)]
12 mm cement plastering including clearing surface and curing, complted as directed.
(ii) In proportion 1:4
Plinth wall 2 x 18.00 mx 0.60 m = 21.60 m2
2 x 10.00 mx 0.60 m = 12.00 m2
Column 28 x 4 x 5.60 mx 0.30 m = 188.16 m2
wall 2 x 2 x 18.00 mx 1.80 m = 129.60 m2
2 x 2 x 10.00 mx 1.80 m = 72.00 m2
Total = 423.36 m2
@ Rs. 182.49 / m2 (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 77,259.00
Item No : 11
[12.3]
Supplying, fitting fixing and laying reinforcement (TATA) in position in RCC work including cutting, bending, cranking
with two piles 0.91 M (20 BWG) annealed wire hooking tying, complete as directed.
10m
m dia
Footing 28 x 2 x 19 x 1.80 m = 1915.20 m
@ 0.62 Kg / m = 1915.20 x 0.62 = 1187.42 Kg
12mm dia
Column 28 x 6 x 10.25 m = 1722.00 m
Beam 3 x 6 x 18.00 m = 324.00 m
2 x 6 x 10.00 m = 120.00 m
Lintel 2 x 2 x 4 x 18.00 m = 288.00 m
2 x 2 x 4 x 10.00 m = 160.00 m
Tie beam 3 x 4 x 18.00 m = 216.00 m
8 x 4 x 10.00 m = 320.00 m
Total = 3150.00 m
@ 0.89 Kg / m = 3150.00 x 0.89 = 2803.50 Kg
8mm dia
Column 28 x 66 x 1.10 m = 2032.80 m
Tie beam 3 x 121 x 1.00 m = 363.00 m
8 x 67 x 1.00 m = 536.00 m
Beam 3 x 121 x 0.86 m = 312.18 m
2 x 67 x 1.20 m = 160.80 m
Linte 2 x 2 x 121 x 0.79 m = 382.36 m
l
2 x 2 x 67 x 0.79 m = 211.72 m
Total = 3998.86 m
@ 0.22 Kg / m = 3998.86 x 0.22 = 879.75 Kg
TOTAL = 4870.67 Kg
Add 5 % for wastage and lapping = 243.53 Kg
Grand Total = 5114.20 Kg
= 51.14 Qntl.
@ Rs. 8003.00 / Qntl. (As per S.R.of C.E.Irri.Dep. 2017-18) = Rs. 409,273.00
Item No: 12
Providing, fitting , hoisting and fixing of roof trusses including purlins fabricated out of MS black tube conforming to
relevant IS code , as per approved design and drawing including providing MS cleats, base plate, bolts, nuts and one coat
of red oxide zinc chromate primer and two coats of approved enamel paints complete including fitting necessary cleats etc.
for fixing ceiling joist as per design and drawing as directed.
42.20 mm OD
Truss 2 x 18 x 0.45 m = 16.20 m
2 x 17 x 0.57 m = 19.35 m
Total = 35.55 m
@ 3.15 Kg / m = 35.55 x 3.15 = 111.98 Kg
48.30 mm OD
Rafter 2 x 8 x 1 x 5.02 m = 80.32 m
Bottom Runner 2 x 8 x 1 x 5.02 m = 80.32 m
Purlin 2 x 4 x 11.20 m = 89.60 m
Total = 250.24 m
@ 3.61Kg / m = 250.24 x 3.61 = 903.37 Kg
TOTAL = 1015.35 Kg
Add 10% for wastage etc. = 101.53 Kg
GRAND TOTAL = 1116.88 Kg
= 11.17 Qntl
@ Rs. 9404.70 / Qntl (As per S.R.of PWD.Bldg 2013-14) = Rs. 105,050.00
Item No: 13
[8.1.33]
Providing Pre Painted Galvanized Iron Sheet Roofing (PPGI) at all levels including fitting and fixing with self drilling,
self tapping screws complete. (Roof trusses, purlins etc. to be measured and paid separately.)
TATA Blue scope/ Dyna roof / Durakolor /Wonder Roof or equivalent as directed by the Departement
(iv) 0.60 mm thick
Truss 2 x 5.60 mx 19.20 m = 215.04 m2
Outside of Warehouse 2 x 10.00 mx 5.80 m = 116.00 m2
2 x 18.00 mx 5.80 m = 208.80 m2
= 539.84 m2
@ Rs. 1033.73 / m2 (As per S.R.of PWD.Bldg 2013-14) = Rs. 558,048.00
Item No: 13
[8.1.34]
Providing Pre Painted Galvanized Iron Sheet (PPGI) accessories (Ridges / Valley / Gutter /Flashing) at all levels
including fitting and fixing self drilling, self tapping screws complete complete.
TATA Blue scope/ Dyna roof / Durakolor /Wonder Roof or equivalent as directed by the Departement
(iv) 0.60 mm thick
Qnty- = 19.20 RM
@ Rs. 1033.73 / RM (As per S.R.of PWD.Bldg 2013-14) = Rs. 19,848.00
Item No: 14
[24.39 (ii)]
Distemper with approved distempering materials. (two coats)
Item No: 5
RCC work in ...
In Substracture
In footing
Square portion 28 x 1.5 mx 1.5 mx 0.15 m = 9.45 m3
Trapezoidal portion 28 x 2.25 mx 0.203 mx 0.35 m = 17.19 m3
Column upto G.L. 28 x 0.35 mx 0.35 mx 1.00 m = 3.43 m3
Tie beam 3 x 18.00 mx 0.30 mx 0.25 m = 4.05 m3
8 x 10.00 mx 0.30 mx 0.25 m = 6.00 m3
Page 25
NO. L B H/T QTY
Deduct for tie 28 x 0.30 mx 0.30 mx 0.25 m = -0.63 m3
39.49 m3
In Superstructure
Column above G.L. 28 x 0.30 mx 0.30 mx 8.22 m = 20.71 m3
Beam 3 x 18.00 mx 0.40 mx 0.30 m = 6.48 m3
2 x 10.00 mx 0.40 mx 0.30 m = 2.40 m3
Lintel 2 x 2 x 18.00 mx 0.20 mx 0.20 m = 2.88 m3
2 x 2 x 10.00 mx 0.20 mx 0.20 m = 1.60 m3
Total = 103.61 m3
Item No: 6 `
Earth work in filling…
Floor 1 x 18.00 mx 10.00 mx 0.60 m = 108.00 m3
Ramp 0.5 x 1.70 mx 1.70 mx 0.60 m = 1.73 m3
109.73 m3
Item No: 7
Providing form work of ordinary timber…
Footing 28 x 4 x 1.60 mx 0.10 m = 17.92 m2
28 x 4 x 1.50 mx 0.15 m 25.20 m2
Column upto PL 28 x 4 x 0.35 mx 1.00 m = 39.20 m2
Total = 82.32 m2
Sides of tie beams,.... at or below plinth level
Tie beam 3 x 2 x 18.00 mx 0.40 m = 43.20 m2
8 x 2 x 10.00 mx 0.40 m = 64.00 m2
Total = 107.20 m2
In superstructure
Columns, pillars, posts & strut
Column above PL 28 x 4 x 0.30 mx 7.63 m = 256.27 m2
beam haunchings, ...
Beam 3 x 2 x 18.00 mx 0.40 m = 43.20 m2
3 x 1 x 18.00 mx 0.30 m = 16.20 m2
2 x 2 x 10.00 mx 0.40 m = 16.00 m2
2 x 1 x 10.00 mx 0.30 m = 6.00 m2
Lintel 2 x 2 x 18.00 mx 0.20 m = 14.40 m2
2 x 2 x 10.00 mx 0.20 m = 8.00 m2
2 x 3 x 18.00 mx 0.20 m = 21.60 m2
2 x 3 x 10.00 mx 0.20 m = 12.00 m2
Total = 137.40 m2
Item No: 8
Brtick work in cement morter…
Page 26
NO. L B H/T QTY
125mm thick 1st class brick nogged wall….
Page 27
NO. L B H/T QTY
@ 0.39 Kg / m = 5187.80 x 0.22 = 1141.32 Kg
TOTAL = 4648.95 Kg
Add 5 % for wastage and lapping = 232.45 Kg
Grand Total = 4881.39 Kg
= 48.81 Qntl.
Item No: 13
Providing, fitting , hoisting and fixing of roof trusses…
42.20 mm OD
Truss 2 x 18 x 0.45 m = 16.20 m
2 x 17 x 0.57 m = 19.35 m
Total = 35.55 m
@ 3.15 Kg / m = 35.55 x 3.15 = 111.98 Kg
48.30 mm OD
Rafter 2 x 8 x 1 x 5.02 m = 80.32 m
Bottom Runner 2 x 8 x 1 x 5.02 m = 80.32 m
Purlin 2 x 4 x 11.20 m = 89.60 m
Total = 250.24 m
@ 3.61Kg / m = 250.24 x 3.61 = 903.37 Kg
TOTAL = 1015.35 Kg
Add 10% for wastage etc. = 101.53 Kg
GRAND TOTAL = 1116.88 Kg
= 11.17 Qntl
Item No: 14
Providing Pre Painted Galvanized Iron Sheet Roofing (PPGI)…
Truss 2 x 5.60 mx 19.20 m = 215.04 m2
Outside of Warehouse 2 x 10.00 mx 5.80 m = 116.00 m2
2 x 18.00 mx 5.80 m = 208.80 m2
= 539.84 m2
Item No: 15
Providing Pre Painted Galvanized Iron Sheet (PPGI) accessories (Ridges / Valley / Gutter /Flashing)…
Item No: 16
Distemper with approved distempering materials. (two coats)
Primary Coat
wall 2 x 18.00 mx 1.80 m = 64.80 m2
2 x 10.00 mx 1.80 m = 36.00 m2
Column 28 3 x 5.80 mx 0.30 m = 146.16 m2
Total = 246.96 m2
Page 28
NO. L B H/T QTY
Toap coat
Qnty- = 246.96 m2
Item No: 17
Rolling Shutter… 1 x 2.30 mx 3.00 m = 6.90 m2
Page 29
(As per S.R.of PWD.Bldg 2013-14)
148.99 148.99
299.25 299.25
299.25 299.25
184.83 184.83
Page 30
5
39.49 39.49
103.61 103.61
109.73 109.73
82.32 82.32
107.20 107.20
256.27
137.40 137.40
6.00 6.00
Page 31
100.80 100.80
356.16 356.16
134.40 134.40
Page 32
48.81 48.81
11.17 11.17
539.84 539.84
38.40
246.96 246.96
Page 33
246.96 246.96
6.90 6.90
3504.74 3504.74
Page 34
NAME OF WORK : DETAIL ESTIMATE FOR CONSTRUCTION OF WAREHOUSE OF PLASTIC RECYCLING
PLANT.
SL.
NO. S.O.R
. NO. DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT
1 1.1 Earthwork in excavation for foundation
trenches of walls, retaining walls, footings
of column, steps, septic tank etc. including
refilling (return filling) the quantity as
necessary after completion of work,
breaking clods in return filling, dressing,
watering and ramming etc. and removal of
surplus earth with all lead and lifts as
directed and specified in the following
classification of soils including bailing out
water where necessary as directed and
specified. (A) Up
to a depth of 2.00m below the existing
ground level. (a) In
ordinary soil
148.99 cum 108.82 16,213.09
2 4.1.1 Providing soling in foundation and under
floor with stone/ best quality picked jhama
brick, sand packed and laid to level and in
panel after preparing the subgrade as
directed including all labour and materials
and if necessary dewatering, complete.
(a).Brick on flat soling.
299.25 sqm 368.71 110,336.47
3 2.1.1 Plain cement concrete works with coarse
aggregate of sizes 13mm to 32mm in
foundation bed for footing steps, walls,
brick works etc. as directed and specified
including dewatering if necessary, and
curing complete (shuttering where
necessary shall be measured and paid
separately).
(a)
In prop 1cement: 3 sand :6 coarse
aggregate by volume 299.25 cum 4292.86 1,284,638.36
4 5.1.1 Cement concrete works in topping 1:1:2
(1cement :1sand :2 graded aggregates on
R.C.C floor, tread and rise of steps
finished with a floating coat of neat cement
using cement slurry for bond @ 2.75 kg.of
cement per sq. m. of floor to be laid in
panels including curing complete as
directed. (b) 20 mm thick
Page 35
SL.
NO. S.O.R
. NO. DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT
5 2.2.1 Providing and laying plain/reinforced
cement croncrete works cement, coarse
sand & 20mm down graded stone
aggregate including dewatering if
necessary, and curing complete but
excluding cost of form work and
reinforcement for reinforced cement
concrete work (form work and
reinforcement will be measured and paid
separately)
Page 36
SL.
NO. S.O.R
. NO. DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT
7 3.1.1 Providing form work of ordinary timber
planking so as to give a rough finish
including centering, shuttering, strutting
and propping etc., height of propping and
centering below supporting floor to ceiling
not exceeding 4.0M and removal of the
same for in-situ reinforced concrete and
plain concrete work in: (b) Using
25mm thick plank
Foundation, footings, bases of
columns, pile cap, raft and mass concrete
works etc.
Page 37
SL.
NO. S.O.R
. NO. DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT
11 6.2.2 15mm thick cement plaster in single coat on
sigle or brick wall for interior plastering up to 1st
floor level including arises, internal rounded
angles, not exceeding 80mm in girth and
finished even and smooth including curing
complete as directed
(b) In cement mortar 1:4
Page 38
SL.
NO. S.O.R
. NO. DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT
15 8.1.34 Providing Pre Painted Galvanized Iron Sheet
(PPGI) accessories (Ridges / Valley / Gutter
/Flashing) at all levels including fitting and
fixing self drilling, self tapping screws
complete complete.
TATA Blue scope/ Dyna roof / Durakolor
/Wonder Roof or equivalent as directed by the
Departement.
(iv) 0.60 mm thick
Executive Engineer,PWD
Dibrugarh NH Division
Dibrugarh.
Page 39
AMOUNT
16213.09
110336.5
1284638
49976.18
Page 40
AMOUNT
239472.9
655979.7
37925.17
Page 41
AMOUNT
20764.40
36651.68
93284.84
27815.26
35165.16
73584
41617.3
Page 42
AMOUNT
19787.71
346523.6 -9,594.98
93939.7
524481.6
Page 43
AMOUNT
22604.54
8534.938
12022.01
29293.95
3780613
Page 44
Name of Work :- Construction of Warehouse Plastic Recycling Plant at Dibrugarh under
Dibrugarh NH Division
ABSTRACT OF COST
Executive Engineer,PWD
Dibrugarh NH Division
Dibrugarh
under
###
###
eer,PWD
Name of Work :- Construction of Warehouse Plastic Recycling Plant at
Dibrugarh under Dibrugarh NH Division
Location :- Dibrugarh
REPORT
The estimate has been prepared as per S.O.R. PWD. Building 2013-14, Assam.
All works will be carried out as per A.P.W.D. specifications and departmental norms.