Sl. Measurements
Descripltion of Item No. Qty Rate Per Amount
No. L B D
1 2 3 4 5 6 7 8 9 10
Earthwork work excavation for foundations and depositing on bank for all
lifts and with an initial lead of 10m including all operational, labour
1 charges such as shoring sheeting, planking, strutting, etc,. Complete for
finished item of work including seigniorage excluding dewatring charges
etc., as per SS-20B (APSS308)
Long Walls 1 x 2 4.00 0.30 0.90 2.16
Cross Walls 1 x 2 4.00 0.30 0.90 2.16
Varandah Walls 1 x 2 1.70 0.30 0.90 0.92
5.24 189.28 1 Cum 991.00
Plastering 20mm thick in two coats with base coat of 16mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, sand, water
etc., to site, on all materials,all operational, incidental and labour charges
7
such as mixing mortar, scaffolding charges, lift charges, including cutting
of Grooves wherever necessary as directed by Engineer - in - charge,
finishing, curing, etc., complete for Even Surfaces of Wall for finished
item of work. (APSS 901,903 & 904) for External walls
Inside 1 x 2 4.00 3.05 24.40
1 x 2 4.00 3.05 24.40
Vaarandah 1 x 2 1.20 3.00 7.20
Outside alround 1 x 2 5.20 3.05 31.72
1 x 1 4.00 3.00 12.00
Deduct for Doors 1 x 1 2.00 1.00 -2.00
Windows 1 x 2 1.20 1.20 -2.88
94.84 373.77 Rmt 35448.00
Flooring with Vetrified ceramic tiles, set over base coat of cement mortar
(1:8), 12 mm thick over CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm &
8 jointed neatly with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement, sand water
and tiles etc., complete, including etc., complete for finished item of work,
but excluding the cost of conveyance of all materials.
1 x 5 4.00 20.00
20.00 457.00 1 Sqm 9140.00
Rate as per SSR 2022-23, Item No. TBSP-G.I-05
Total 300000.00
Name of the work:Construction of Fire Control Room at Vempally
Seigniorage Charges
Sl Item Qty Factor Metal Factor Sand Gravel Earth Brick
No
1 Earth work 5.24 1 5.24
417.00
LEAD CHART (S.S.R 2022-23)
Name of the work:Construction of Fire Control Room at Vempally
Sl Description of Item Name of the Lead in KM Conveyance Initial Cost Add Add 25% Nett Unit Per
No quarry charges of material Blasting Extra on Amount
excluding Charges Crushed
13.615% over Metal
C.T. M.R. Total
heads
1 2 3 4 5 6 7 8 10 11 12 13
1 10mm Gauge HGB Metal Machine crushed Muthampet 20.00 20.00 324.43 950.00 90.00 237.50 1601.93 1 Cum
2 12mm Gauge HGB Metal Machine crushed Muthampet 20.00 20.00 324.43 1050.00 90.00 262.50 1726.93 1 Cum
3 20mm Gauge HGB Metal Machine crushed Muthampet 20.00 20.00 324.43 1100.00 90.00 275.00 1789.43 1 Cum
4 40mm Gauge HGB Metal Machine crushed Muthampet 20.00 20.00 324.43 903.00 90.00 225.75 1543.18 1 Cum
5 Sand for Filling and Blindage Local 10.00 10.00 174.80 630.00 804.80 1 Cum
6 Sand for Concrette Local 10.00 10.00 174.80 630.00 804.80 1 Cum
Sand for mortar, plastering, ceiling coat including washing
7 Local 10.00 10.00 174.80 830.00 1004.80 1 Cum
screening etc.,
8 Gravel Local 10.00 10.00 174.80 108.00 282.80 1 Cum
9 Bricks 2nd class TBSC.A.I.01 Easgaon 35.00 35.00 863.97 9000.00 9863.97 1000 Nos
10 Fly Ash bricks of 290 x 140 x 225 mm TSBSC.A.II.01 Easgaon 35.00 35.00 863.97 30000.00 30863.97 1000 Nos
11 Cement (Rate as per March 2023) 0.00 5200.00 5200.00 1 MT
12 Steel 60000.00 60000.00 1 MT
Certificates:-
1. Certified that the leads provided in the estimate is correct to the best of my knowledge and the stone used Hard granite
2. The Rates for unloading of material except earth, sand, gravel, coarse aggregate, rubble size stone and cut stone are inclusive of stocking
4. The metal rates are including blasting charges of Rs 70.00 , Machine Crushing charges 25% , Seigniorage charges 50.00
Telangana Standard Data - Buildings SSR-2022-23
Total
Index- S
Description Unit Qty Amount unit
code No Rate Rs.
Rs.
1 2 3 4 5 6 7
Earthwork work excavation for foundations and depositing on bank for all lifts and with an initial
lead of 10m including all operational, labour charges such as shoring sheeting, planking, strutting,
1
etc,. Complete for finished item of work including seigniorage excluding dewatring charges etc.,
as per SS-20B (APSS308)
Ordinary soil - Manual Means - upto 3m depth
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64 520.00 1892.80
Cost for 10 cum = a+b+c 1892.80
Net Rate per cum 189.28 cum
Filling with Sand (excluding rock) in trenches, sides of foundations and basement with initial lead
in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming
2 including cost and Cost and Conveyance of water to site and all operational, incidental, labour
charges, Seigoirage charges, sales and other taxes etc, hire charges of T & P etc., complete for
finished item of work. (APSS NO. 309 & 310)
Unit = cum
Taking out put = 1cum
a) Labour
Mazdoor (Unskilled) as RSSR day 0.25 550.00 137.50
b) Material :
Sand cum 1.00 804.80 804.80
Total cost of 1.00 cum 942.30
Rate per cum Rs 942.30 1Cum
Plain Cement Concrete corresponding to (1:4:8) proportion nominal mix (cement: fine aggregate: Coarse
aggregate) using 40mm size Hard Broken Granite (IS383, 1970) metal from approved quarry including
BLD-
cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including
CSTN- 3
seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges
2-7 such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work for Foundations (APSS No. 402)
Unit = 1cum
A. MATERIALS:
Cement kg/MT 162.00 5200.00 842.40
Coarse aggregate 40 mm cum 0.90 1004.80 904.32
Fine aggregate (Sand) cum 0.45 804.80 362.16
B. MACHINERY
Concrete mixer 600/400 ltr 10/7 cft ( 0.2/0.80cum) capacity hr 1.00 1052.10 1052.10
C. LABOUR:
Mason 1st class day 0.10 605.00 60.50
Mazdoor (unskilled) day 2.36 520.00 1227.20
Total per 1 Cum 4448.68 1Cum
1 2 3 4 5 6 7
CR stone masonry, in CM (1:6) prop: (Cement: Sand) using hard
granite stones 2nd sort from approved quarry including cost and
conveyance of all materials like Granite stones, cement, sand,
BLD- water, etc., to site including seigniorage charges, sales & other
CSTN-6- 4 taxes on all materials, all operational, incidental, and labour
6 charges such as cutting stones to required size and shape,
mixing of cement mortar, constructing masonry, curing etc.,
complete for finished item of work for foundation basement
(APSS No. 601 )
unit = cum
a) Materials
Cement Kgs 76.80 5200.00 399.36
CR Stone Cum 0.94 675.33 634.81
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
Cum 0.16 1541.23 246.60
0.16cum
Fine aggregate ( Sand) cum 0.32 804.80 257.54
b) Labour
1st Class Mason Nos 1.50 605.00 907.50
Man Mazdoor (Un-Skilled) Nos 2.32 520.00 1206.40
Net Total per cum 3652.20 1Cum
Brick Masonry in superstructure with CM (1:8) prop with Flyash Cement solid blocks of size 290 x
BLD- 225 x 140 mm, for manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs.
CSTN-5- 6 Gypsum of 5 kgs. and stone dust with a compresive strength not lessthan 50 kg/sqm including
4 cost and conveyance of all materials, labour charges, seiniorage charges, scaffolding and curing
etc., for Superstructure Walls.
a.Material
No of blocks required for one cum of Masonry Nos 110.00 30863.97 3395.04
CM (1:8) Cum 0.10 2095.040 209.50
b.Labour
Mason 1st Class Day 0.420 605.00 254.10
Mason 2nd Class Day 0.920 550.00 506.00
Mazdoor (Unskilled) Day 2.800 520.00 1456.00
Rate per Cum 5820.64
1 2 3 4 5 6 7
Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc.,
BLD-
to site, on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding
CSTN-8- 7
charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in -
1 charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS
901,903 & 904) for External walls
Unit = 10 sqm
A. MATERIALS:
Base coat in CM (1:6), 16mm thick
Cement kgs/ MT 43.00 5200.00 223.60
Fine aggregate (Sand) cum 0.18 1004.80 180.86
Top coat in CM (1:4), 4mm Thick
Cement kgs/ MT 14.50 5200.00 75.40
Fine aggregate (Sand) cum 0.04 1004.80 40.19
b) Labour
Mason 1st class day 0.63 605.00 381.15
Mason 2nd class day 1.47 550.00 808.50
Mazdoor (unskilled) day 3.90 520.00 2028.00
Rate for 10 sqm 3737.71
Rate per sqm 373.77 per sqm
Unit = 10 sqm
A. MATERIALS:
TBSC-C.I-01 Ceramic tiles 7.3mm thick 1 st quality sqm 10.50 315.00 3307.50
Cement for CM (1:8) for base coat kg. 21.60 5200.00 112.32
Cement for slurry kg. 33.00 5200.00 171.60
TBSC-G.I-03 White cement kg. 2.00 41.00 82.00
Sand for CM (1:8) cum 0.12 1004.80 120.58
B. LABOUR
Mason 1st class day 0.96 605.00 580.80
Mason 2nd class day 2.24 550.00 1232.00
Mazdoor (unskiled) day 3.30 520.00 1716.00
Total 7322.80
per sqm 732.28 per sqm
1 2 3 4 5 6 7
Unit = 10 sqm
TBSC-G.I-01 Cost of Cement Primer kg 1.00 173.00 173.00
Ist class painter day 0.21 665.00 139.65
2nd class painter day 0.49 550.00 269.50
TBSC-G.II-04 Supply of Water proof Cement paint 1 kg 3.50 60.00 210.00