05-Sep-22

AMUMA Page 1 of 3
CONCEPCION, ILOILO
Activity ID Activity Name Start Finish Original Total Float Activity
Duration Typ e 2022 2023
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
22-Jul-22 07:00 AM 08-Sep-23 04:00 PM 414d 0d 08-Sep-23 04:00 PM, IP 43 AMUMA CONCEPCIO
IP 43 AMUMA CONCEPCION
IP 43.1 MILESTONES 22-Jul-22 07:00 AM 08-Sep-23 04:00 PM 414d 0d 08-Sep-23 04:00 PM, IP 43.1 MILESTONES

M0995 KICKOFF MEETING - JULY 22, 2022 22-Jul-22 07:00 AM 0d 414d Start Milestone KICKOFF MEETING - JULY 22, 2022, 22-Jul-22 07:00 AM
M1000 CONSTRUCTION START 22-Jul-22 07:00 AM 0d 0d Start Milestone CONSTRUCTION START, 22-Jul-22 07:00 AM
M1005 PREPARATION OF PERMITS 22-Jul-22 07:00 AM 0d 414d Start Milestone PREPARATION OF PERMITS, 22-Jul-22 07:00 AM
M1010 MOBILIZATION 22-Jul-22 07:00 AM 0d 414d Start Milestone MOBILIZATION, 22-Jul-22 07:00 AM
M1020 FIRST CONCRETE POURING 24-Nov-22 07:00 AM 0d 289d Start Milestone FIRST CONCRETE POURING, 24-Nov-22 07:00 AM
M1040 STRUCTURAL COMPLETION 19-Mar-23 04:00 PM 0d 173d Finish Milestone STRUCTURAL COMPLETION,
M1050 START OF HANDOVER TO OWNER 08-Sep-23 07:00 AM 0d 1d Start Milestone START OF HANDOVER TO OWNER, 08-Sep-23
M1060 DEMOBILIZATION 28-Aug-23 04:00 PM 0d 11d Finish Milestone DEMOBILIZATION,
M1070 PROJECT COMPLETION 08-Sep-23 04:00 PM 0d 0d Finish Milestone PROJECT COMPLETION,
IP 43.1.1 STRUCTURAL MILESTONES 19-Mar-23 04:00 PM 08-Apr-23 04:00 PM 20d 153d 08-Apr-23 04:00 PM, IP 43.1.1 STRUCTURAL MILESTONES
SM1010 MAIN BUILDING STRUCTURAL TOPPING OFF 19-Mar-23 04:00 PM 0d 173d Finish Milestone MAIN BUILDING STRUCTURAL TOPPING OFF,
SM1015 SITE DEVELOPMENT STRUCTURAL 08-Apr-23 04:00 PM 0d 153d Finish SITE DEVELOPMENT STRUCTURAL TOPPING OFF,
TOPPING OFF Milestone
IP 43.2 GENERAL PRELIMINARIES 22-Jul-22 07:00 AM 08-Sep-23 04:00 PM 414d 0d 08-Sep-23 04:00 PM, IP 43.2 GENERAL PRELIM

IP 43.2.2 PRELIMINARY FOR DESIGN DEVELOPMENT 22-Jul-22 07:00 AM 19-Sep-22 04:00 PM 60d 30d 19-Sep-22 04:00 PM, IP 43.2.2 PRELIMINARY FOR DESIGN DEVELOPMENT
A2130 GEOTECHNICAL INVESTIGATION 22-Jul-22 07:00 AM 24-Aug-22 04:00 PM 34d 56d Task Dependent GEOTECHNICAL INVESTIGATION
A2140 SITE TOPOGRAPHY SURVEY 22-Jul-22 07:00 AM 19-Sep-22 04:00 PM 60d 30d Task Dependent SITE TOPOGRAPHY SURVEY
A2150 SITE STAKING AND LAYOUT AND SURVEYS 22-Jul-22 07:00 AM 19-Sep-22 04:00 PM 60d 30d Task SITE STAKING AND LAYOUT AND SURVEYS OF PROPERTY
OF PROPERTY Dependent
A2250 DESIGN STAGE 22-Jul-22 07:00 AM 19-Sep-22 04:00 PM 60d 30d Task Dependent DESIGN STAGE
IP 43.2.1 PRELIMINARY FOR PERMITS & CONSTRUCTION 22-Jul-22 07:00 AM 08-Sep-23 04:00 PM 414d 0d 08-Sep-23 04:00 PM, IP 43.2.1 PRELIMINARY FO
GP0994 MOBILIZATION 22-Jul-22 07:00 AM* 19-Oct-22 04:00 PM 90d 0d Task Dependent MOBILIZATION
GP0995 PERMITS & LOCAL CLEARANCES 22-Jul-22 07:00 AM 19-Oct-22 04:00 PM 90d 0d Task Dependent PERMITS & LOCAL CLEARANCES
GP0996 CONSTRUCTION SURVEY, LIN E & GRADE 22-Jul-22 07:00 AM 08-Sep-23 04:00 PM 414d 0d Task Dependent CONSTRUCTION SURVEY, LINE & GRADE
GP0998 TEMPORARYFACILITIES 07-Sep-22 07:00 AM* 08-Sep-23 04:00 PM 367d 0d Task TEMPORARYFACILITIES
Dependent
GP0999 MANAGEMENT OF THE WORKS 07-Sep-22 07:00 AM* 08-Sep-23 04:00 PM 367d 0d Task MANAGEMENT OF THE WORKS
Dependent
GP1000 SECURITY, SAFETY& PROTEC TION 20-Oct-22 07:00 AM 08-Sep-23 04:00 PM 324d 0d Task Dependent SECURITY, SAFETY& PROTECTION
GP1001 TEMPORARYPLANT & EQUIPMENT 20-Oct-22 07:00 AM 08-Sep-23 04:00 PM 324d 0d Task Dependent TEMPORARYPLANT & EQUIPMENT
GP1020 MAINTENANCE, DEWATERING, & DISPOSAL 20-Oct-22 07:00 AM 08-Sep-23 04:00 PM 324d 0d Task Dependent MAINTENANCE, DEWATERING, & DISPOSAL

IP 43.3 SITE PREPARATION 07-Sep-22 07:00 AM 08-Jan-23 04:00 PM 124d 0d 08-Jan-23 04:00 PM, IP 43.3 SITE PREPARATION

A1410 EXCAVATION 20-Oct-22 07:00 AM 09-Nov-22 04:00 PM 21d 0d Task Dependent EXCAVATION
A1420 SURFACE PREPARATION 10-Nov-22 07:00 AM 17-Nov-22 04:00 PM 8d 0d Task Dependent SURFACE PREPARATION
A1430 BACKFILLING 16-Dec-22 07:00 AM 27-Dec-22 04:00 PM 12d 0d Task Dependent BACKFILLING
A1440 FILLING & COMPACTION 07-Sep-22 07:00 AM* 08-Jan-23 04:00 PM 124d 0d Task FILLING & COMPACTION
Dependent
IP 43.12 MAIN BUILDING 18-Nov-22 07:00 AM 18-Aug-23 04:00 PM 274d 0d 18-Aug-23 04:00 PM, IP 43.12 MAIN BUILDING

IP 43.12.9 STRUCTURAL 18-Nov-22 07:00 AM 19-Mar-23 04:00 PM 122d 125d 19-Mar-23 04:00 PM, IP 43.12.9 STRUCTURAL
IP 43.12.9.1 FOUNDATION 18-Nov-22 07:00 AM 15-Dec-22 04:00 PM 28d 0d 15-Dec-22 04:00 PM, IP 43.12.9.1 FOUNDATION
IP 43.12.9.1.1 FOOTING 18-Nov-22 07:00 AM 24-Nov-22 04:00 PM 7d 0d 24-Nov-22 04:00 PM, IP 43.12.9.1.1 FOOTING
A1020 REBAR FABRICATION & INSTALLATION 18-Nov-22 07:00 AM 23-Nov-22 04:00 PM 6d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A1030 FORMWORKS INSTALLATION 18-Nov-22 07:00 AM 23-Nov-22 04:00 PM 6d 0d Task Dependent FORMWORKS INSTALLATION
A1040 CONCRETE POURING 24-Nov-22 07:00 AM 24-Nov-22 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.1.2 COLUMNS 24-Nov-22 07:00 AM 06-Dec-22 04:00 PM 13d 0d 06-Dec-22 04:00 PM, IP 43.12.9.1.2 COLUMNS
A1050 REBAR FABRICATION & INSTALLATION 24-Nov-22 07:00 AM 05-Dec-22 04:00 PM 12d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A1060 FORMWORKS INSTALLATION 24-Nov-22 07:00 AM 05-Dec-22 04:00 PM 12d 0d Task Dependent FORMWORKS INSTALLATION
A1070 CONCRETE POURING 06-Dec-22 07:00 AM 06-Dec-22 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.1.3 TIE BEAMS 06-Dec-22 07:00 AM 15-Dec-22 04:00 PM 10d 0d 15-Dec-22 04:00 PM, IP 43.12.9.1.3 TIE BEAMS
A1080 REBAR FABRICATION & INSTALLATION 06-Dec-22 07:00 AM 14-Dec-22 04:00 PM 9d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A1090 FORMWORKS INSTALLATION 06-Dec-22 07:00 AM 14-Dec-22 04:00 PM 9d 0d Task Dependent FORMWORKS INSTALLATION
A1100 CONCRETE POURING 15-Dec-22 07:00 AM 15-Dec-22 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.2 GROUND FLOOR 15-Dec-22 07:00 AM 28-Jan-23 04:00 PM 45d 14d 28-Jan-23 04:00 PM, IP 43.12.9.2 GROUND FLOOR
IP 43.12.9.2.1 SLAB ON GRADE 15-Dec-22 07:00 AM 14-Jan-23 04:00 PM 31d 0d 14-Jan-23 04:00 PM, IP 43.12.9.2.1 SLAB ON GRADE
A1110 REBAR FABRICATION & INSTALLATION 15-Dec-22 07:00 AM 22-Dec-22 04:00 PM 8d 1d Task Dependent REBAR FABRICATION & INSTALLATION
A1120 FORMWORKS INSTALLATION 09-Jan-23 07:00 AM 13-Jan-23 04:00 PM 5d 0d Task Dependent FORMWORKS INSTALLATION
A1130 CONCRETE POURING 14-Jan-23 07:00 AM 14-Jan-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.2.2 COLUMNS 23-Dec-22 07:00 AM 27-Jan-23 04:00 PM 36d 0d 27-Jan-23 04:00 PM, IP 43.12.9.2.2 COLUMNS
A1140 REBAR FABRICATION & INSTALLATION 23-Dec-22 07:00 AM 05-Jan-23 04:00 PM 14d 1d Task Dependent REBAR FABRICATION & INSTALLATION
A1150 FORMWORKS INSTALLATION 15-Jan-23 07:00 AM 26-Jan-23 04:00 PM 12d 0d Task Dependent FORMWORKS INSTALLATION
A1160 CONCRETE POURING 27-Jan-23 07:00 AM 27-Jan-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.2.3 STAIRS 06-Jan-23 07:00 AM 20-Jan-23 04:00 PM 15d 22d 20-Jan-23 04:00 PM, IP 43.12.9.2.3 STAIRS
A1170 REBAR FABRICATION & INSTALLATION 06-Jan-23 07:00 AM 19-Jan-23 04:00 PM 14d 22d Task Dependent REBAR FABRICATION & INSTALLATION
A1180 FORMWORKS INSTALLATION 06-Jan-23 07:00 AM 19-Jan-23 04:00 PM 14d 22d Task Dependent FORMWORKS INSTALLATION
A1190 CONCRETE POURING 20-Jan-23 07:00 AM 20-Jan-23 04:00 PM 1d 22d Task Dependent CONCRETE POURING
IP 43.12.9.2.4 2F SUSPENDED BEAMS 06-Jan-23 07:00 AM 28-Jan-23 04:00 PM 23d 0d 28-Jan-23 04:00 PM, IP 43.12.9.2.4 2F SUSPENDED BEAMS
A1200 REBAR FABRICATION & INSTALLATION 06-Jan-23 07:00 AM 26-Jan-23 04:00 PM 21d 1d Task Dependent REBAR FABRICATION & INSTALLATION
A1210 FORMWORKS INSTALLATION 06-Jan-23 07:00 AM 26-Jan-23 04:00 PM 21d 1d Task Dependent FORMWORKS INSTALLATION
A1220 CONCRETE POURING 28-Jan-23 07:00 AM 28-Jan-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.2.5 2F SUSPENDED SLABS 06-Jan-23 07:00 AM 28-Jan-23 04:00 PM 23d 0d 28-Jan-23 04:00 PM, IP 43.12.9.2.5 2F SUSPENDED SLABS
A1230 REBAR FABRICATION & INSTALLATION 06-Jan-23 07:00 AM 23-Jan-23 04:00 PM 18d 4d Task Dependent REBAR FABRICATION & INSTALLATION
A1240 FORMWORKS INSTALLATION 06-Jan-23 07:00 AM 23-Jan-23 04:00 PM 18d 4d Task Dependent FORMWORKS INSTALLATION
A1250 CONCRETE POURING 28-Jan-23 07:00 AM 28-Jan-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.3 SECOND FLOOR 29-Jan-23 07:00 AM 26-Feb-23 04:00 PM 29d 3d 26-Feb-23 04:00 PM, IP 43.12.9.3 SECOND FLOOR
IP 43.12.9.3.2 COLUMNS 29-Jan-23 07:00 AM 10-Feb-23 04:00 PM 13d 0d 10-Feb-23 04:00 PM, IP 43.12.9.3.2 COLUMNS
A1260 REBAR FABRICATION & INSTALLATION 29-Jan-23 07:00 AM 09-Feb-23 04:00 PM 12d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A1270 FORMWORKS INSTALLATION 29-Jan-23 07:00 AM 09-Feb-23 04:00 PM 12d 0d Task Dependent FORMWORKS INSTALLATION
A1280 CONCRETE POURING 10-Feb-23 07:00 AM 10-Feb-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.3.3 STAIRS 10-Feb-23 07:00 AM 16-Feb-23 04:00 PM 7d 13d 16-Feb-23 04:00 PM, IP 43.12.9.3.3 STAIRS
A1290 REBAR FABRICATION & INSTALLATION 10-Feb-23 07:00 AM 15-Feb-23 04:00 PM 6d 13d Task Dependent REBAR FABRICATION & INSTALLATION
A1300 FORMWORKS INSTALLATION 10-Feb-23 07:00 AM 15-Feb-23 04:00 PM 6d 13d Task Dependent FORMWORKS INSTALLATION
A1310 CONCRETE POURING 16-Feb-23 07:00 AM 16-Feb-23 04:00 PM 1d 13d Task Dependent CONCRETE POURING
IP 43.12.9.3.4 3F SUSPENDED BEAMS 10-Feb-23 07:00 AM 26-Feb-23 04:00 PM 17d 3d 26-Feb-23 04:00 PM, IP 43.12.9.3.4 3F SUSPENDED BEAMS

Remaining Work
Critical Remaining Work MASTER PROJECT CONSTRUCTION
Milestone
summary SCHEDULE
PLANNING STAGE - REV 03
05-Sep-22
AMUMA Page 2 of 3
CONCEPCION, ILOILO
Activity ID Activity Name Start Finish Original Total Float Activity
Duration Typ e 2022 2023
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A1320 REBAR FABRICATION & INSTALLATION 10-Feb-23 07:00 AM 25-Feb-23 04:00 PM 16d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A1330 FORMWORKS INSTALLATION 10-Feb-23 07:00 AM 25-Feb-23 04:00 PM 16d 3d Task Dependent FORMWORKS INSTALLATION
A1340 CONCRETE POURING 26-Feb-23 07:00 AM 26-Feb-23 04:00 PM 1d 3d Task Dependent CONCRETE POURING
IP 43.12.9.3.5 3F SUSPENDED SLABS 10-Feb-23 07:00 AM 26-Feb-23 04:00 PM 17d 3d 26-Feb-23 04:00 PM, IP 43.12.9.3.5 3F SUSPENDED SLABS
A1350 REBAR FABRICATION & INSTALLATION 10-Feb-23 07:00 AM 25-Feb-23 04:00 PM 16d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A1360 FORMWORKS INSTALLATION 10-Feb-23 07:00 AM 25-Feb-23 04:00 PM 16d 3d Task Dependent FORMWORKS INSTALLATION
A1370 CONCRETE POURING 26-Feb-23 07:00 AM 26-Feb-23 04:00 PM 1d 3d Task Dependent CONCRETE POURING
IP 43.12.9.4 THIRD FLOOR 26-Feb-23 07:00 AM 19-Mar-23 04:00 PM 22d 18d 19-Mar-23 04:00 PM, IP 43.12.9.4 THIRD FLOOR
IP 43.12.9.4.1 COLUMNS 26-Feb-23 07:00 AM 02-Mar-23 04:00 PM 5d 0d 02-Mar-23 04:00 PM, IP 43.12.9.4.1 COLUMNS
A1380 REBAR FABRICATION & INSTALLATION 26-Feb-23 07:00 AM 01-Mar-23 04:00 PM 4d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A1390 FORMWORKS INSTALLATION 26-Feb-23 07:00 AM 01-Mar-23 04:00 PM 4d 0d Task Dependent FORMWORKS INSTALLATION
A1400 CONCRETE POURING 02-Mar-23 07:00 AM 02-Mar-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.4.4 RD SUSPENDED BEAMS 03-Mar-23 07:00 AM 19-Mar-23 04:00 PM 17d 0d 19-Mar-23 04:00 PM, IP 43.12.9.4.4 RD SUSPENDED BEAMS
A2190 REBAR FABRICATION & INSTALLATION 03-Mar-23 07:00 AM 18-Mar-23 04:00 PM 16d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A2200 FORMWORKS INSTALLATION 03-Mar-23 07:00 AM 18-Mar-23 04:00 PM 16d 0d Task Dependent FORMWORKS INSTALLATION
A2210 CONCRETE POURING 19-Mar-23 07:00 AM 19-Mar-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.4.5 RD SUSPENDED SLABS 03-Mar-23 07:00 AM 19-Mar-23 04:00 PM 17d 0d 19-Mar-23 04:00 PM, IP 43.12.9.4.5 RD SUSPENDED SLABS
A2220 REBAR FABRICATION & INSTALLATION 03-Mar-23 07:00 AM 18-Mar-23 04:00 PM 16d 0d Task Dependent REBAR FABRICATION & INSTALLATION
A2230 FORMWORKS INSTALLATION 03-Mar-23 07:00 AM 18-Mar-23 04:00 PM 16d 0d Task Dependent FORMWORKS INSTALLATION
A2240 CONCRETE POURING 19-Mar-23 07:00 AM 19-Mar-23 04:00 PM 1d 0d Task Dependent CONCRETE POURING
IP 43.12.9.4.3 STAIRS 02-Mar-23 07:00 AM 08-Mar-23 04:00 PM 7d 29d 08-Mar-23 04:00 PM, IP 43.12.9.4.3 STAIRS
A2160 REBAR FABRICATION & INSTALLATION 02-Mar-23 07:00 AM 07-Mar-23 04:00 PM 6d 29d Task Dependent REBAR FABRICATION & INSTALLATION
A2170 FORMWORKS INSTALLATION 02-Mar-23 07:00 AM 07-Mar-23 04:00 PM 6d 29d Task Dependent FORMWORKS INSTALLATION
A2180 CONCRETE POURING 08-Mar-23 07:00 AM 08-Mar-23 04:00 PM 1d 29d Task Dependent CONCRETE POURING
IP 43.12.9.5 STRUCTURAL STEEL & ROOFING 03-Mar-23 07:00 AM 16-Mar-23 04:00 PM 14d 3d 16-Mar-23 04:00 PM, IP 43.12.9.5 STRUCTURAL STEEL & ROOFING
A1810 FABRICATION & INSTALLATION OF 03-Mar-23 07:00 AM 16-Mar-23 04:00 PM 14d 3d Task FABRICATION & INSTALLATION OF STRUCTURAL STEEL
STRUCTURAL STEEL Dependent
IP 43.12.9.6 SWIMMING POOL 09-Jan-23 07:00 AM 24-Jan-23 04:00 PM 16d 179d 24-Jan-23 04:00 PM, IP 43.12.9.6 SWIMMING POOL
A1850 REBAR FABRICATION & INSTALLATION 09-Jan-23 07:00 AM 22-Jan-23 04:00 PM 14d 179d Task Dependent REBAR FABRICATION & INSTALLATION
A1860 FORMWORKS INSTALLATION 09-Jan-23 07:00 AM 22-Jan-23 04:00 PM 14d 179d Task Dependent FORMWORKS INSTALLATION
A1870 CONCRETE POURING 23-Jan-23 07:00 AM 24-Jan-23 04:00 PM 2d 179d Task Dependent CONCRETE POURING
IP 43.12.10 ARCHITECTURAL 25-Jan-23 07:00 AM 18-Aug-23 04:00 PM 206d 0d 18-Aug-23 04:00 PM, IP 43.12.10 ARCHITECTURAL
IP 43.12.10.1 MASONRY WORKS 29-Jan-23 07:00 AM 06-Apr-23 04:00 PM 68d 0d 06-Apr-23 04:00 PM, IP 43.12.10.1 MASONRY WORKS
A1450 GROUND FLOOR 29-Jan-23 07:00 AM 15-Feb-23 04:00 PM 18d 14d Task Dependent GROUND FLOOR
A1460 SECOND FLOOR 27-Feb-23 07:00 AM 16-Mar-23 04:00 PM 18d 3d Task Dependent SECOND FLOOR
A1470 THIRD FLOOR 20-Mar-23 07:00 AM 06-Apr-23 04:00 PM 18d 0d Task Dependent THIRD FLOOR
IP 43.12.10.2 PLASTERING 16-Feb-23 07:00 AM 18-Apr-23 04:00 PM 62d 0d 18-Apr-23 04:00 PM, IP 43.12.10.2 PLASTERING
A1480 GROUND FLOOR 16-Feb-23 07:00 AM 27-Feb-23 04:00 PM 12d 50d Task Dependent GROUND FLOOR
A1490 SECOND FLOOR 17-Mar-23 07:00 AM 28-Mar-23 04:00 PM 12d 21d Task Dependent SECOND FLOOR
A1500 THIRD FLOOR 07-Apr-23 07:00 AM 18-Apr-23 04:00 PM 12d 0d Task Dependent THIRD FLOOR
IP 43.12.10.3 CEILING WORKS 28-Feb-23 07:00 AM 02-May-23 04:00 PM 64d 22d 02-May-23 04:00 PM, IP 43.12.10.3 CEILING WORKS
A1510 GROUND FLOOR 28-Feb-23 07:00 AM 13-Mar-23 04:00 PM 14d 72d Task Dependent GROUND FLOOR
A1520 SECOND FLOOR 29-Mar-23 07:00 AM 11-Apr-23 04:00 PM 14d 43d Task Dependent SECOND FLOOR
A1530 THIRD FLOOR 19-Apr-23 07:00 AM 02-May-23 04:00 PM 14d 22d Task Dependent THIRD FLOOR
IP 43.12.10.13 WATERPROOFING 25-Jan-23 07:00 AM 26-Apr-23 04:00 PM 92d 94d 26-Apr-23 04:00 PM, IP 43.12.10.13 WATERPROOFING
A1820 GROUND FLOOR 28-Feb-23 07:00 AM 07-Mar-23 04:00 PM 8d 50d Task Dependent GROUND FLOOR
A1830 SECOND FLOOR 29-Mar-23 07:00 AM 05-Apr-23 04:00 PM 8d 21d Task Dependent SECOND FLOOR
A1840 THIRD FLOOR 19-Apr-23 07:00 AM 26-Apr-23 04:00 PM 8d 0d Task Dependent THIRD FLOOR
A1880 SWIMMING POOL 25-Jan-23 07:00 AM 31-Jan-23 04:00 PM 7d 179d Task Dependent SWIMMING POOL
IP 43.12.10.4 CONCRETE TOPPING 01-Feb-23 07:00 AM 08-May-23 04:00 PM 97d 88d 08-May-23 04:00 PM, IP 43.12.10.4 CONCRETE TOPPING
A1540 GROUND FLOOR 08-Mar-23 07:00 AM 19-Mar-23 04:00 PM 12d 50d Task Dependent GROUND FLOOR
A1550 SECOND FLOOR 06-Apr-23 07:00 AM 17-Apr-23 04:00 PM 12d 21d Task Dependent SECOND FLOOR
A1560 THIRD FLOOR 27-Apr-23 07:00 AM 08-May-23 04:00 PM 12d 0d Task Dependent THIRD FLOOR
A1720 SWIMMING POOL 01-Feb-23 07:00 AM 06-Feb-23 04:00 PM 6d 179d Task Dependent SWIMMING POOL
IP 43.12.10.5 TILING WORKS 09-Mar-23 07:00 AM 24-May-23 04:00 PM 77d 86d 24-May-23 04:00 PM, IP 43.12.10.5 TILING WORKS
A1570 GROUND FLOOR 20-Mar-23 07:00 AM 04-Apr-23 04:00 PM 16d 50d Task Dependent GROUND FLOOR
A1580 SECOND FLOOR 18-Apr-23 07:00 AM 03-May-23 04:00 PM 16d 21d Task Dependent SECOND FLOOR
A1590 THIRD FLOOR 09-May-23 07:00 AM 24-May-23 04:00 PM 16d 0d Task Dependent THIRD FLOOR
A1730 SWIMMING POOL 09-Mar-23 07:00 AM 22-Mar-23 04:00 PM 14d 149d Task Dependent SWIMMING POOL
IP 43.12.10.6 SKIMCOATING 05-Apr-23 07:00 AM 05-Jun-23 04:00 PM 62d 0d 05-Jun-23 04:00 PM, IP 43.12.10.6 SKIMCOATING
A1600 GROUND FLOOR 05-Apr-23 07:00 AM 16-Apr-23 04:00 PM 12d 50d Task Dependent GROUND FLOOR
A1610 SECOND FLOOR 04-May-23 07:00 AM 15-May-23 04:00 PM 12d 21d Task Dependent SECOND FLOOR
A1620 THIRD FLOOR 25-May-23 07:00 AM 05-Jun-23 04:00 PM 12d 0d Task Dependent THIRD FLOOR
IP 43.12.10.7 PAINTING WORKS 17-Apr-23 07:00 AM 26-Jun-23 04:00 PM 71d 0d 26-Jun-23 04:00 PM, IP 43.12.10.7 PAINTING WORKS
A1630 GROUND FLOOR 17-Apr-23 07:00 AM 07-May-23 04:00 PM 21d 50d Task Dependent GROUND FLOOR
A1640 SECOND FLOOR 16-May-23 07:00 AM 05-Jun-23 04:00 PM 21d 21d Task Dependent SECOND FLOOR
A1650 THIRD FLOOR 06-Jun-23 07:00 AM 26-Jun-23 04:00 PM 21d 0d Task Dependent THIRD FLOOR
IP 43.12.10.8 WALL FINISHES 08-May-23 07:00 AM 14-Jul-23 04:00 PM 68d 0d 14-Jul-23 04:00 PM, IP 43.12.10.8 WALL FINISHES
A1660 GROUND FLOOR 08-May-23 07:00 AM 25-May-23 04:00 PM 18d 50d Task Dependent GROUND FLOOR
A1670 SECOND FLOOR 06-Jun-23 07:00 AM 23-Jun-23 04:00 PM 18d 21d Task Dependent SECOND FLOOR
A1680 THIRD FLOOR 27-Jun-23 07:00 AM 14-Jul-23 04:00 PM 18d 0d Task Dependent THIRD FLOOR
IP 43.12.10.9 OPENINGS (DOORS/WINDOWS/CURTAIN WALL) 17-Apr-23 07:00 AM 09-Jun-23 04:00 PM 54d 35d 09-Jun-23 04:00 PM, IP 43.12.10.9 OPENINGS (DOORS/WINDOWS/CURTAIN WALL)
A1690 GROUND FLOOR 17-Apr-23 07:00 AM 20-Apr-23 04:00 PM 4d 85d Task Dependent GROUND FLOOR
A1700 SECOND FLOOR 16-May-23 07:00 AM 19-May-23 04:00 PM 4d 56d Task Dependent SECOND FLOOR
A1710 THIRD FLOOR 06-Jun-23 07:00 AM 09-Jun-23 04:00 PM 4d 35d Task Dependent THIRD FLOOR
IP 43.12.10.10 SKYLIGHTS 15-Jul-23 07:00 AM 17-Jul-23 04:00 PM 3d 32d 17-Jul-23 04:00 PM, IP 43.12.10.10 SKYLIGHTS
A1740 THIRD FLOOR 15-Jul-23 07:00 AM 17-Jul-23 04:00 PM 3d 32d Task Dependent THIRD FLOOR
IP 43.12.10.11 LOUVERS 08-May-23 07:00 AM 17-Jul-23 04:00 PM 71d 32d 17-Jul-23 04:00 PM, IP 43.12.10.11 LOUVERS
A1750 GROUND FLOOR 08-May-23 07:00 AM 28-May-23 04:00 PM 21d 82d Task Dependent GROUND FLOOR
A1760 SECOND FLOOR 06-Jun-23 07:00 AM 26-Jun-23 04:00 PM 21d 53d Task Dependent SECOND FLOOR
A1770 THIRD FLOOR 27-Jun-23 07:00 AM 17-Jul-23 04:00 PM 21d 32d Task Dependent THIRD FLOOR
IP 43.12.10.12 RAILINGS 17-Apr-23 07:00 AM 19-Jun-23 04:00 PM 64d 60d 19-Jun-23 04:00 PM, IP 43.12.10.12 RAILINGS
A1780 GROUND FLOOR 17-Apr-23 07:00 AM 30-Apr-23 04:00 PM 14d 110d Task Dependent GROUND FLOOR
A1790 SECOND FLOOR 16-May-23 07:00 AM 29-May-23 04:00 PM 14d 81d Task Dependent SECOND FLOOR
A1800 THIRD FLOOR 06-Jun-23 07:00 AM 19-Jun-23 04:00 PM 14d 60d Task Dependent THIRD FLOOR

Remaining Work
Critical Remaining Work MASTER PROJECT CONSTRUCTION
Milestone
summary SCHEDULE
PLANNING STAGE - REV 03
05-Sep-22
AMUMA Page 3 of 3
CONCEPCION, ILOILO
Activity ID Activity Name Start Finish Original Total Float Activity
Duration Typ e 2022 2023
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
IP 43.12.10.14 INTERIOR DESIGN 26-May-23 07:00 AM 18-Aug-23 04:00 PM 85d 0d 18-Aug-23 04:00 PM, IP 43.12.10.14 INTERIOR DESIGN
A2100 GROUND FLOOR 26-May-23 07:00 AM 29-Jun-23 04:00 PM 35d 50d Task Dependent GROUND FLOOR
A2110 SECOND FLOOR 24-Jun-23 07:00 AM 28-Jul-23 04:00 PM 35d 21d Task Dependent SECOND FLOOR
A2120 THIRD FLOOR 15-Jul-23 07:00 AM 18-Aug-23 04:00 PM 35d 0d Task Dependent THIRD FLOOR

IP 43.9 SITE DEVELOPMENT 10-Nov-22 07:00 AM 08-May-23 04:00 PM 180d 102d 08-May-23 04:00 PM, IP 43.9 SITE DEVELOPMENT

IP 43.9.1 PARKING, DRIVEWAY & ANCILLARY STRUCTURES 10-Nov-22 07:00 AM 08-May-23 04:00 PM 180d 102d 08-May-23 04:00 PM, IP 43.9.1 PARKING, DRIVEWAY& ANCILLARY STRUCTURES
A2015 GROUTED RIPRAP 10-Nov-22 07:00 AM 30-Nov-22 04:00 PM 21d 147d Task Dependent GROUTED RIPRAP
A2020 SUBBASE AND BASE COURSE 15-Jan-23 07:00 AM 04-Feb-23 04:00 PM 21d 102d Task SUBBASE AND BASE COURSE PREPARATION
PREPARATION Dependent
A2030 SUBBASE AND BASE COURSE FIL LING 05-Feb-23 07:00 AM 25-Feb-23 04:00 PM 21d 102d Task SUBBASE AND BASE COURSE FIL LING AND COMPACTION
AND COMPACTION Dependent
A2040 FORMS AND REBAR FABRICATION & 26-Feb-23 07:00 AM 18-Mar-23 04:00 PM 21d 102d Task FORMS AND REBAR FABRICATION & INSTALLATION
INSTALLATION Dependent
A2050 CONCRETE POURING 19-Mar-23 07:00 AM 08-Apr-23 04:00 PM 21d 102d Task CONCRETE POURING
Dependent
A2060 CONCRETE CURBS AND LANDSCAPING 09-Apr-23 07:00 AM 08-May-23 04:00 PM 30d 102d Task Dependent CONCRETE CURBS AND LANDSCAPING
IP 43.9.1.2 KITCHEN 09-Jan-23 07:00 AM 07-Mar-23 04:00 PM 58d 157d 07-Mar-23 04:00 PM, IP 43.9.1.2 KITCHEN
A2070 SITE PREPARATION 09-Jan-23 07:00 AM 15-Jan-23 04:00 PM 7d 157d Task Dependent SITE PREPARATION
A2080 STRUCTURAL 16-Jan-23 07:00 AM 05-Feb-23 04:00 PM 21d 157d Task Dependent STRUCTURAL
A2090 ARCHITECTURAL 06-Feb-23 07:00 AM 07-Mar-23 04:00 PM 30d 157d Task Dependent ARCHITECTURAL

IP 43.11 MEPF 03-Oct-22 07:00 AM 06-Jul-23 04:00 PM 277d 43d 06-Jul-23 04:00 PM, IP 43.11 MEPF

A1890 ELECTRICAL WORKS 07-Oct-22 07:00 AM 06-Jul-23 04:00 PM 273d 43d Task ELECTRICAL WORKS
Dependent
A1900 PLUMBING WORKS 03-Oct-22 07:00 AM* 02-Jul-23 04:00 PM 273d 47d Task PLUMBING WORKS
Dependent
A1910 MECHANICAL WORKS 03-Oct-22 07:00 AM* 02-Jul-23 04:00 PM 273d 47d Task MECHANICAL WORKS
Dependent
A1920 ELECTRONICS 03-Oct-22 07:00 AM* 02-Jul-23 04:00 PM 273d 47d Task ELECTRONICS
Dependent
A1930 FIRE PROTECTION 03-Oct-22 07:00 AM* 02-Jul-23 04:00 PM 273d 47d Task FIRE PROTECTION
Dependent
IP 43.6 PUNCHLISTING 02-Dec-22 07:00 AM 18-Aug-23 04:00 PM 260d 0d 18-Aug-23 04:00 PM, IP 43.6 PUNCHLISTING

IP 43.6.8 MAIN BUILDING 02-Dec-22 07:00 AM 18-Aug-23 04:00 PM 260d 0d 18-Aug-23 04:00 PM, IP 43.6.8 MAIN BUILDING
IP 43.6.8.2 STRUCTURAL 02-Dec-22 07:00 AM 02-Apr-23 04:00 PM 122d 138d 02-Apr-23 04:00 PM, IP 43.6.8.2 STRUCTURAL
A1935 FOUNDATION 02-Dec-22 07:00 AM 15-Dec-22 04:00 PM 14d 246d Task Dependent FOUNDATION
A1940 GROUND FLOOR 15-Jan-23 07:00 AM 28-Jan-23 04:00 PM 14d 202d Task Dependent GROUND FLOOR
A1950 SECOND FLOOR 13-Feb-23 07:00 AM 26-Feb-23 04:00 PM 14d 173d Task Dependent SECOND FLOOR
A1960 THIRD FLOOR 20-Mar-23 07:00 AM 02-Apr-23 04:00 PM 14d 138d Task Dependent THIRD FLOOR
IP 43.6.8.3 ARCHITECTURAL 09-Mar-23 07:00 AM 18-Aug-23 04:00 PM 163d 0d 18-Aug-23 04:00 PM, IP 43.6.8.3 ARCHITECTURAL
A1970 GROUND FLOOR 16-Jun-23 07:00 AM 29-Jun-23 04:00 PM 14d 50d Task Dependent GROUND FLOOR
A1980 SECOND FLOOR 15-Jul-23 07:00 AM 28-Jul-23 04:00 PM 14d 21d Task Dependent SECOND FLOOR
A1990 THIRD FLOOR 05-Aug-23 07:00 AM 18-Aug-23 04:00 PM 14d 0d Task Dependent THIRD FLOOR
A2010 SWIMMING POOL 09-Mar-23 07:00 AM 22-Mar-23 04:00 PM 14d 149d Task Dependent SWIMMING POOL
IP 43.6.8.4 MEPF 02-Jun-23 07:00 AM 06-Jul-23 04:00 PM 35d 43d 06-Jul-23 04:00 PM, IP 43.6.8.4 MEPF
A2000 PUNCHLISTING 02-Jun-23 07:00 AM 06-Jul-23 04:00 PM 35d 43d Task PUNCHLISTING
Dependent
IP 43.6.1 SITE DEVELOPMENT 26-Mar-23 07:00 AM 08-May-23 04:00 PM 44d 102d 08-May-23 04:00 PM, IP 43.6.1 SITE DEVELOPMENT
PL1000 STRUCTURAL 26-Mar-23 07:00 AM 08-Apr-23 04:00 PM 14d 132d Task Dependent STRUCTURAL
PL1020 ARCHITECTURAL 25-Apr-23 07:00 AM 08-May-23 04:00 PM 14d 102d Task Dependent ARCHITECTURAL
IP 43.6.2 KITCHEN 30-Jan-23 07:00 AM 14-Mar-23 04:00 PM 44d 157d 14-Mar-23 04:00 PM, IP 43.6.2 KITCHEN
PL1010 STRUCTURAL 30-Jan-23 07:00 AM 05-Feb-23 04:00 PM 7d 194d Task Dependent STRUCTURAL
PL1030 ARCHITECTURAL 08-Mar-23 07:00 AM 14-Mar-23 04:00 PM 7d 157d Task Dependent ARCHITECTURAL

IP 43.7 DEMOBILIZATION 19-Aug-23 07:00 AM 28-Aug-23 04:00 PM 10d 0d 28-Aug-23 04:00 PM, IP 43.7 DEMOBILIZATION

DEMOB1000 DISMANTLING OF TEMPORARY FACILITIES 19-Aug-23 07:00 AM 23-Aug-23 04:00 PM 5d 0d Task Dependent DISMANTLING OF TEMPORARY FACILITIES
DEMOB1010 HAULING OUT 24-Aug-23 07:00 AM 28-Aug-23 04:00 PM 5d 0d Task Dependent HAULING OUT

IP 43.5 START OF HAND OVER 29-Aug-23 07:00 AM 07-Sep-23 04:00 PM 10d 0d 07-Sep-23 04:00 PM, IP 43.5 START OF HAND OV

HO1000 HAND OVER 29-Aug-23 07:00 AM 07-Sep-23 04:00 PM 10d 0d Task Dependent HAND OVER

IP 43.8 PROJECT COMPLETION 08-Sep-23 07:00 AM 08-Sep-23 04:00 PM 1d 0d 08-Sep-23 04:00 PM, IP 43.8 PROJECT COMPLE

PC1000 PROJECT COMPLETION 08-Sep-23 07:00 AM 08-Sep-23 04:00 PM 1d 0d Task Dependent PROJECT COMPLETION

Remaining Work
Critical Remaining Work MASTER PROJECT CONSTRUCTION
Milestone
summary SCHEDULE
PLANNING STAGE - REV 03