BULAN 1 BULAN 2

1 28-Jul-2022 31-Jul-2022 7-Aug-2022 14-Aug-2022 21-Aug-2022 28-Aug-2022 4-Sep-2022


2 29-Jul-2022 1-Aug-2022 8-Aug-2022 15-Aug-2022 22-Aug-2022 29-Aug-2022 5-Sep-2022
3 30-Jul-2022 2-Aug-2022 9-Aug-2022 16-Aug-2022 23-Aug-2022 30-Aug-2022 6-Sep-2022
4 3-Aug-2022 10-Aug-2022 17-Aug-2022 24-Aug-2022 31-Aug-2022 7-Sep-2022
5 4-Aug-2022 11-Aug-2022 18-Aug-2022 25-Aug-2022 1-Sep-2022 8-Sep-2022
6 5-Aug-2022 12-Aug-2022 19-Aug-2022 26-Aug-2022 2-Sep-2022 9-Sep-2022
7 6-Aug-2022 13-Aug-2022 20-Aug-2022 27-Aug-2022 3-Sep-2022 10-Sep-2022
Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7

7.00 7.00 7.00 7.00 7.00 7.00 7.00


2 BULAN 3 BULAN 4
11-Sep-2022 18-Sep-2022 25-Sep-2022 2-Oct-2022 9-Oct-2022 16-Oct-2022 23-Oct-2022
12-Sep-2022 19-Sep-2022 26-Sep-2022 3-Oct-2022 10-Oct-2022 17-Oct-2022 24-Oct-2022
13-Sep-2022 20-Sep-2022 27-Sep-2022 4-Oct-2022 11-Oct-2022 18-Oct-2022 25-Oct-2022
14-Sep-2022 21-Sep-2022 28-Sep-2022 5-Oct-2022 12-Oct-2022 19-Oct-2022 26-Oct-2022
15-Sep-2022 22-Sep-2022 29-Sep-2022 6-Oct-2022 13-Oct-2022 20-Oct-2022 27-Oct-2022
16-Sep-2022 23-Sep-2022 30-Sep-2022 7-Oct-2022 14-Oct-2022 21-Oct-2022 28-Oct-2022
17-Sep-2022 24-Sep-2022 1-Oct-2022 8-Oct-2022 15-Oct-2022 22-Oct-2022 29-Oct-2022
Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13 Minggu 14

7.00 7.00 7.00 7.00 7.00 7.00 7.00


BULAN 4 BULAN 5 BULA
30-Oct-2022 6-Nov-2022 13-Nov-2022 20-Nov-2022 27-Nov-2022 4-Dec-2022 11-Dec-2022
31-Oct-2022 7-Nov-2022 14-Nov-2022 21-Nov-2022 28-Nov-2022 5-Dec-2022 12-Dec-2022
1-Nov-2022 8-Nov-2022 15-Nov-2022 22-Nov-2022 29-Nov-2022 6-Dec-2022 13-Dec-2022
2-Nov-2022 9-Nov-2022 16-Nov-2022 23-Nov-2022 30-Nov-2022 7-Dec-2022 14-Dec-2022
3-Nov-2022 10-Nov-2022 17-Nov-2022 24-Nov-2022 1-Dec-2022 8-Dec-2022 15-Dec-2022
4-Nov-2022 11-Nov-2022 18-Nov-2022 25-Nov-2022 2-Dec-2022 9-Dec-2022 16-Dec-2022
5-Nov-2022 12-Nov-2022 19-Nov-2022 26-Nov-2022 3-Dec-2022 10-Dec-2022 17-Dec-2022
Minggu 15 Minggu 16 Minggu 17 Minggu 18 Minggu 19 Minggu 20 Minggu 21

7.00 7.00 7.00 7.00 7.00 7.00 7.00

151.00
BULAN 6 BULAN 7 BULAN 8
18-Dec-2022 25-Dec-2022 1-Jan-2023 8-Jan-2023 15-Jan-2023 22-Jan-2023 29-Jan-2023 5-Feb-2023
19-Dec-2022 26-Dec-2022 2-Jan-2023 9-Jan-2023 16-Jan-2023 23-Jan-2023 30-Jan-2023 6-Feb-2023
20-Dec-2022 27-Dec-2022 3-Jan-2023 10-Jan-2023 17-Jan-2023 24-Jan-2023 31-Jan-2023 7-Feb-2023
21-Dec-2022 28-Dec-2022 4-Jan-2023 11-Jan-2023 18-Jan-2023 25-Jan-2023 1-Feb-2023 8-Feb-2023
22-Dec-2022 29-Dec-2022 5-Jan-2023 12-Jan-2023 19-Jan-2023 26-Jan-2023 2-Feb-2023 9-Feb-2023
23-Dec-2022 30-Dec-2022 6-Jan-2023 13-Jan-2023 20-Jan-2023 27-Jan-2023 3-Feb-2023 10-Feb-2023
24-Dec-2022 31-Dec-2022 7-Jan-2023 14-Jan-2023 21-Jan-2023 28-Jan-2023 4-Feb-2023 11-Feb-2023
Minggu 22 Minggu 23 Minggu 24 Minggu 25 Minggu 26 Minggu 27 Minggu 28 Minggu 29

4.00 7.00 7.00 7.00 7.00 7.00 7.00 4.00

50.00
BULAN 8 BULAN 9 BULAN 1
12-Feb-2023 19-Feb-2023 26-Feb-2023 5-Mar-2023 12-Mar-2023 19-Mar-2023 26-Mar-2023 2-Apr-2023
13-Feb-2023 20-Feb-2023 27-Feb-2023 6-Mar-2023 13-Mar-2023 20-Mar-2023 27-Mar-2023 3-Apr-2023
14-Feb-2023 21-Feb-2023 28-Feb-2023 7-Mar-2023 14-Mar-2023 21-Mar-2023 28-Mar-2023 4-Apr-2023
15-Feb-2023 22-Feb-2023 1-Mar-2023 8-Mar-2023 15-Mar-2023 22-Mar-2023 29-Mar-2023 5-Apr-2023
16-Feb-2023 23-Feb-2023 2-Mar-2023 9-Mar-2023 16-Mar-2023 23-Mar-2023 30-Mar-2023 6-Apr-2023
17-Feb-2023 24-Feb-2023 3-Mar-2023 10-Mar-2023 17-Mar-2023 24-Mar-2023 31-Mar-2023 7-Apr-2023
18-Feb-2023 25-Feb-2023 4-Mar-2023 11-Mar-2023 18-Mar-2023 25-Mar-2023 1-Apr-2023 8-Apr-2023
Minggu 30 Minggu 31 Minggu 32 Minggu 33 Minggu 34 Minggu 35 Minggu 36 Minggu 37

7.00 7.00 3.00

214
BULAN 10 BULAN 11 BULAN 1
9-Apr-2023 16-Apr-2023 23-Apr-2023 30-Apr-2023 7-May-2023 14-May-2023 21-May-2023 28-May-2023
10-Apr-2023 17-Apr-2023 24-Apr-2023 1-May-2023 8-May-2023 15-May-2023 22-May-2023 29-May-2023
11-Apr-2023 18-Apr-2023 25-Apr-2023 2-May-2023 9-May-2023 16-May-2023 23-May-2023 30-May-2023
12-Apr-2023 19-Apr-2023 26-Apr-2023 3-May-2023 10-May-2023 17-May-2023 24-May-2023 31-May-2023
13-Apr-2023 20-Apr-2023 27-Apr-2023 4-May-2023 11-May-2023 18-May-2023 25-May-2023 1-Jun-2023
14-Apr-2023 21-Apr-2023 28-Apr-2023 5-May-2023 12-May-2023 19-May-2023 26-May-2023 2-Jun-2023
15-Apr-2023 22-Apr-2023 29-Apr-2023 6-May-2023 13-May-2023 20-May-2023 27-May-2023 3-Jun-2023
Minggu 38 Minggu 39 Minggu 40 Minggu 41 Minggu 42 Minggu 43 Minggu 44 Minggu 45
BULAN 12
4-Jun-2023 11-Jun-2023 18-Jun-2023
5-Jun-2023 12-Jun-2023 19-Jun-2023
6-Jun-2023 13-Jun-2023 20-Jun-2023
7-Jun-2023 14-Jun-2023 21-Jun-2023
8-Jun-2023 15-Jun-2023 22-Jun-2023
9-Jun-2023 16-Jun-2023 23-Jun-2023
10-Jun-2023 17-Jun-2023 24-Jun-2023
Minggu 46 Minggu 47 Minggu 48
CONTRACT CHANGE ORDER (CCO-01)
PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN
LOKASI
: PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
: KOTA TERNATE-MALUKU UTARA
CCO-01
TAHUN ANGGARAN : 2022

CONTRACT CHANGE ORDER (CCO-01) CONTRACT CHANGE ORDER (CCO-01)


PEKERJAAN KURANG PEKERJAAN TAMBAH PEKERJAAN TAMBAH KURANG/CCO
NO URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT KET
VOLUME SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
VOLUME VOLUME VOLUME
( Rp ) ( Rp ) % Rp % Rp % Rp %
A PEKERJAAN PERSIAPAN
1 Mobilisasi Dan Demobilisasi Peralatan Dan Pekerja 1.00 LS 5,000,000.00 5,000,000.00 0.65 0.00 - 0.00 0.00 - 0.00 1.00 5,000,000.00 0.65 Tetap
2 Pembuatan Direksi Keet 1.00 LS 5,000,000.00 5,000,000.00 0.65 0.00 - 0.00 0.00 - 0.00 1.00 5,000,000.00 0.65 Tetap
3 Air Kerja dan Penerangan 1.00 LS 4,000,000.00 4,000,000.00 0.52 0.00 - 0.00 0.00 - 0.00 1.00 4,000,000.00 0.52 Tetap
4 Kesehatan dan Keselamatan Kerja (K3) 1.00 LS 10,000,000.00 10,000,000.00 1.31 0.00 - 0.00 0.00 - 0.00 1.00 10,000,000.00 1.31 Tetap
5 Papan Nama Proyek 1.00 LS 500,000.00 500,000.00 0.07 0.00 - 0.00 0.00 - 0.00 1.00 500,000.00 0.07 Tetap
6 Shop Drawing dan Asbuilt Drawing 1.00 LS 7,000,000.00 7,000,000.00 0.91 0.00 - 0.00 0.00 - 0.00 1.00 7,000,000.00 0.91 Tetap
7 Laporan, Back Up Data, Dokumentasi 1.00 LS 7,000,000.00 7,000,000.00 0.91 0.00 - 0.00 0.00 - 0.00 1.00 7,000,000.00 0.91 Tetap
8 Pembersihan Akhir 1.00 LS 6,968,282.80 6,968,282.80 0.91 0.00 - 0.00 0.00 - 0.00 1.00 6,968,282.80 0.91 Tetap
JUMLAH PEKERJAAN A 45,468,282.80 5.94 - 0.00 - 0.00 45,468,282.80 5.94
B PEKERJAAN LANTAI I
B.1 PEKERJAAN TANAH DAN PASIR
1 Galian Tanah Pondasi Telapak 30.86 M3 109,480.00 3,378,552.80 0.44 0.00 - 0.00 6.59 721,166.66 0.09 37.45 4,099,719.46 0.54 Tambah
2 Galian Tanah Pondasi Menerus 57.19 M3 109,480.00 6,261,161.20 0.82 0.00 - 0.00 10.43 1,142,364.16 0.15 67.62 7,403,525.36 0.97 Tambah
3 Urugan Kembali Pondasi Telapak 7.71 M3 36,413.60 280,748.86 0.04 0.00 - 0.00 4.77 173,780.26 0.02 12.48 454,529.12 0.06 Tambah
4 Urugan Kembali Pondasi Menerus 14.30 M3 36,413.60 520,714.48 0.07 0.00 - 0.00 8.24 300,102.14 0.04 22.54 820,816.62 0.11 Tambah
5 Urugan Pilihan Dibawah Lantai Bangunan 48.49 M3 179,860.00 8,721,411.40 1.14 0.00 - 0.00 44.81 8,059,256.09 1.05 93.30 16,780,667.49 2.19 Tambah
6 Urugan Pasir Dibawah Pondasi 2.12 M3 263,212.00 558,009.44 0.07 0.00 - 0.00 2.58 679,072.75 0.09 4.70 1,237,082.19 0.16 Tambah
7 Urugan Pasir Dibawah Pondasi Telapak 0.00 M3 263,212.00 - 0.00 0.00 - 0.00 1.47 386,132.00 0.05 1.47 386,132.00 0.05 Tambah
JUMLAH PEKERJAAN B.1 19,720,598.18 2.58 - 0.00 11,461,874.06 1.50 31,182,472.23 4.07
B.2 PEKERJAAN PASANGAN BATU
1 Pek. Pasangan Batu Kosong 11.33 M3 457,777.05 5,186,613.98 0.68 0.00 - 0.00 5.81 2,661,515.77 0.35 17.14 7,848,129.75 1.03 Tambah
2 Pek. Pasangan Batu Belah Camp. 1 : 4 35.41 M3 1,067,185.63 37,789,042.98 4.94 0.00 - 0.00 123.91 132,240,158.52 17.28 159.32 170,029,201.50 22.22 Tambah
JUMLAH PEKERJAAN B.2 42,975,656.96 5.62 - 0.00 134,901,674.28 17.63 177,877,331.24 23.24
B.3 PEKERJAAN BETON
1 Pek. Lantai Kerja Beton 1 : 3 : 5 1.03 M3 847,799.76 873,233.75 0.11 0.00 - 0.00 2.88 2,441,663.30 0.32 3.91 3,314,897.04 0.43 Tambah
2 Pek. Lantai Rabbat Beton 1 : 3 : 5 8.98 M3 847,799.76 7,613,241.80 0.99 0.00 - 0.00 0.00 - 0.00 8.98 7,613,241.80 0.99 Tetap
3 Pek. Pondasi Telapak
Beton K-275 6.80 M3 1,914,622.37 13,019,432.10 1.70 0.00 - 0.00 6.71 12,839,457.60 1.68 13.51 25,858,889.70 3.38 Tambah
Bekesting 27.20 M2 270,491.50 7,357,368.80 0.96 0.00 - 0.00 4.03 1,090,080.75 0.14 31.23 8,447,449.55 1.10 Tambah
Besi Beton 977.70 Kg 33,034.02 32,297,365.02 4.22 0.00 - 0.00 1537.13 50,777,613.56 6.64 2514.83 83,074,978.58 10.86 Tambah
4 Pek. Kolom Pedestal
Beton K-275 2.52 M3 1,914,622.37 4,824,848.37 0.63 0.00 - 0.00 10.99 21,040,551.05 2.75 13.51 25,865,399.42 3.38 Tambah
Bekesting 33.66 M2 333,997.95 11,242,371.00 1.47 0.00 - 0.00 101.63 33,945,347.25 4.44 135.29 45,187,718.25 5.90 Tambah
Besi Beton 626.64 Kg 33,034.02 20,700,440.64 2.70 0.00 - 0.00 1159.03 38,287,387.30 5.00 1785.67 58,987,827.94 7.71 Tambah
5 Pek. Sloof
Beton K-275 2.49 M3 1,914,622.37 4,767,409.70 0.62 0.00 - 0.00 11.34 21,706,837.72 2.84 13.83 26,474,247.41 3.46 Tambah
Bekesting 33.20 M2 270,491.50 8,980,317.80 1.17 0.00 - 0.00 63.42 17,155,360.77 2.24 96.62 26,135,678.57 3.42 Tambah
Besi Beton 823.24 Kg 33,034.02 27,194,929.71 3.55 0.00 - 0.00 900.30 29,740,593.02 3.89 1723.54 56,935,522.73 7.44 Tambah
6 Pek. Kolom Utama
Beton K-275 6.24 M3 1,914,622.37 11,947,243.58 1.56 0.00 - 0.00 8.24 15,784,146.80 2.06 14.48 27,731,390.38 3.62 Tambah
Bekesting 103.66 M2 333,997.95 34,622,227.50 4.52 0.00 - 0.00 46.28 15,455,955.54 2.02 149.94 50,078,183.03 6.54 Tambah
CONTRACT CHANGE ORDER (CCO-01) CONTRACT CHANGE ORDER (CCO-01)
PEKERJAAN KURANG PEKERJAAN TAMBAH PEKERJAAN TAMBAH KURANG/CCO
NO URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT KET
VOLUME SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
VOLUME VOLUME VOLUME
( Rp ) ( Rp ) % Rp % Rp % Rp %
Besi Beton 1452.11 Kg 33,034.02 47,969,036.23 6.27 0.00 - 0.00 516.66 17,067,453.11 2.23 1968.77 65,036,489.34 8.50 Tambah
CONTRACT CHANGE ORDER (CCO-01) CONTRACT CHANGE ORDER (CCO-01)
PEKERJAAN KURANG PEKERJAAN TAMBAH PEKERJAAN TAMBAH KURANG/CCO
NO URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT KET
VOLUME SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
VOLUME VOLUME VOLUME
( Rp ) ( Rp ) % Rp % Rp % Rp %
7 Pek. Kolom Praktis KP 20/20
Beton K-275 0.66 M3 1,914,622.37 1,263,650.76 0.17 0.66 1,263,650.76 0.17 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Bekesting 17.52 M2 333,997.95 5,851,644.08 0.76 17.52 5,851,644.08 0.76 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Besi Beton 117.50 Kg 33,034.02 3,881,497.79 0.51 117.50 3,881,497.79 0.51 0.00 - 0.00 0.00 - 0.00 Dihilangkan
JUMLAH PEKERJAAN B.3 244,406,258.62 31.94 10,996,792.64 1.44 277,332,447.74 36.24 510,741,913.73 66.74
B.4 PEKERJAAN LANTAI DAN DINDING
1 Pek. Pasangan Dinding Bata Tela Press 1 : 4 115.09 M2 192,695.44 22,177,317.90 2.90 115.09 22,177,317.90 2.90 0.00 - 0.00 0.00 - 0.00 Dihilangkan
2 Pek. Plesteran Dinding 1 : 4 115.09 M2 100,519.20 11,568,754.73 1.51 115.09 11,568,754.73 1.51 0.00 - 0.00 0.00 - 0.00 Dihilangkan
3 Pek. Acian 115.09 M2 57,740.42 6,645,345.15 0.87 115.09 6,645,345.15 0.87 0.00 - 0.00 0.00 - 0.00 Dihilangkan
4 Pek. Keramik Lantai 60 x 60 cm 150.20 M2 435,429.10 65,401,450.82 8.55 150.20 65,401,450.82 8.55 0.00 - 0.00 0.00 - 0.00 Dihilangkan
JUMLAH PEKERJAAN B.4 105,792,868.60 13.82 105,792,868.60 13.82 - 0.00 - 0.00
B.5 PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Alluminium 37.08 M' 256,921.00 9,526,630.68 1.24 37.08 9,526,630.68 1.24 0.00 - 0.00 0.00 - 0.00 Dihilangkan
2 Pek. Kusen Jendela Alluminium 75.76 M' 256,921.00 19,464,334.96 2.54 75.76 19,464,334.96 2.54 0.00 - 0.00 0.00 - 0.00 Dihilangkan
3 Pek. Kusen Ventilasi Alluminium 2.72 M' 256,921.00 698,825.12 0.09 2.72 698,825.12 0.09 0.00 - 0.00 0.00 - 0.00 Dihilangkan
JUMLAH PEKERJAAN B.5 29,689,790.76 3.88 29,689,790.76 3.88 - 0.00 - 0.00
B.6 PEKERJAAN INSTALASI LISTRIK
1 Pek. MCB 16A 2.00 BH 152,225.50 304,451.00 0.04 2.00 304,451.00 0.04 0.00 - 0.00 0.00 - 0.00 Dihilangkan
2 Pek. Instalasi Kabel NYM 3x2,5mm 100.00 M' 34,925.50 3,492,550.00 0.46 100.00 3,492,550.00 0.46 0.00 - 0.00 0.00 - 0.00 Dihilangkan
3 Pek. Instalasi Kabel NYM 2x2,5mm 100.00 M' 34,695.50 3,469,550.00 0.45 100.00 3,469,550.00 0.45 0.00 - 0.00 0.00 - 0.00 Dihilangkan
4 Pek. Saklar Seri Panasonic 30.00 BH 74,370.50 2,231,115.00 0.29 30.00 2,231,115.00 0.29 0.00 - 0.00 0.00 - 0.00 Dihilangkan
5 Pek. Saklar Tunggal Panasonic 6.00 BH 70,891.75 425,350.50 0.06 6.00 425,350.50 0.06 0.00 - 0.00 0.00 - 0.00 Dihilangkan
6 Pek. Stop Kontak Tanam Panasonic 20.00 BH 81,328.00 1,626,560.00 0.21 20.00 1,626,560.00 0.21 0.00 - 0.00 0.00 - 0.00 Dihilangkan
7 Stop Kontak Tanam AC Panasonic 10.00 BH 60,225.50 602,255.00 0.08 10.00 602,255.00 0.08 0.00 - 0.00 0.00 - 0.00 Dihilangkan
8 Lampu Balon Philips LED 11 Watt 15.00 BH 88,975.50 1,334,632.50 0.17 15.00 1,334,632.50 0.17 0.00 - 0.00 0.00 - 0.00 Dihilangkan
9 Lampu Balon Philips LED 25 Watt 20.00 BH 123,475.50 2,469,510.00 0.32 20.00 2,469,510.00 0.32 0.00 - 0.00 0.00 - 0.00 Dihilangkan
JUMLAH PEKERJAAN B.6 15,955,974.00 2.09 15,955,974.00 2.09 - 0.00 - 0.00
B.7 PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding 115.09 M2 33,711.91 3,879,903.15 0.51 115.09 3,879,903.15 0.51 0.00 - 0.00 0.00 - 0.00 Dihilangkan
JUMLAH PEKERJAAN B.7 3,879,903.15 0.51 3,879,903.15 0.51 - 0.00 - 0.00
C PEKERJAAN LANTAI II
C.1 PEKERJAAN BETON
1 Pek. Balok B1 25/40
Beton K-275 9.95 M3 1,914,622.37 19,050,492.56 2.49 9.95 19,050,492.56 2.49 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Bekesting 104.48 M2 342,277.95 35,761,200.22 4.67 104.48 35,761,200.22 4.67 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Besi Beton 1319.37 Kg 33,034.02 43,584,099.92 5.70 1319.37 43,584,099.92 5.70 0.00 - 0.00 0.00 - 0.00 Dihilangkan
2 Pek. Balok B2 20/35
Beton K-275 4.55 M3 1,914,622.37 8,711,531.77 1.14 4.55 8,711,531.77 1.14 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Bekesting 58.50 M2 342,277.95 20,023,260.08 2.62 58.50 20,023,260.08 2.62 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Besi Beton 712.40 Kg 33,034.02 23,533,438.52 3.08 712.40 23,533,438.52 3.08 0.00 - 0.00 0.00 - 0.00 Dihilangkan
3 Pek. Balok Anak Ba 15/25
Beton K-275 2.25 M3 1,914,622.37 4,307,900.33 0.56 2.25 4,307,900.33 0.56 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Bekesting 39.00 M2 342,277.95 13,348,840.05 1.74 39.00 13,348,840.05 1.74 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Besi Beton 577.92 Kg 33,034.02 19,091,023.01 2.49 577.92 19,091,023.01 2.49 0.00 - 0.00 0.00 - 0.00 Dihilangkan
CONTRACT CHANGE ORDER (CCO-01) CONTRACT CHANGE ORDER (CCO-01)
PEKERJAAN KURANG PEKERJAAN TAMBAH PEKERJAAN TAMBAH KURANG/CCO
NO URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT KET
VOLUME SAT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
VOLUME VOLUME VOLUME
( Rp ) ( Rp ) % Rp % Rp % Rp %
4 Pek. Pelat Lantai
Beton K-275 22.71 M3 1,914,622.37 43,481,073.97 5.68 22.71 43,481,073.97 5.68 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Bekesting 41.63 M2 342,277.95 14,249,031.06 1.86 41.63 14,249,031.06 1.86 0.00 - 0.00 0.00 - 0.00 Dihilangkan
Besi Beton 370.49 Kg 33,034.02 12,238,775.46 1.60 370.49 12,238,775.46 1.60 0.00 - 0.00 0.00 - 0.00 Dihilangkan
JUMLAH PEKERJAAN C.1 257,380,666.93 33.63 257,380,666.93 33.63 - 0.00 - 0.00
JUMLAH TOTAL 765,270,000.00 100.00 423,695,996.08 55.37 423,695,996.08 55.37 765,270,000.00 100.00
A JUMLAH HARGA 765,270,000.00 423,695,996.08 423,695,996.08 765,270,000.00
B PPN 11% 84,179,700.00 46,606,559.57 46,606,559.57 84,179,700.00
100.00 55.37 55.37 100.00
C TOTAL 849,449,700.00 470,302,555.65 470,302,555.65 849,449,700.00
D TOTAL PEMBULATAN 849,449,700.00 470,302,500.00 470,302,500.00 849,449,700.00
-
-
Disetujui Oleh : Dibuat oleh :
Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
RENCANA JADWAL PELAKSANAAN
PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE

KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

WAKTU PELAKSANAAN PEKERJAAN


HARGA SATUAN JUMLAH HARGA BOBOT BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5
NO URAIAN PEKERJAAN VOLOME SATUAN ( Rp ) ( Rp ) ( % ) M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 KET
28-Jul-22 4-Aug-22 11-Aug-22 18-Aug-22 25-Aug-22 1-Sep-22 8-Sep-22 15-Sep-22 22-Sep-22 29-Sep-22 6-Oct-22 13-Oct-22 20-Oct-22 27-Oct-22 3-Nov-22 10-Nov-22 17-Nov-22 25-Nov-22
3-Aug-22 10-Aug-22 17-Aug-22 24-Aug-22 31-Aug-22 7-Sep-22 14-Sep-22 21-Sep-22 28-Sep-22 5-Oct-22 12-Oct-22 19-Oct-22 26-Oct-22 2-Nov-22 9-Nov-22 16-Nov-22 24-Nov-22 28-Nov-22
A PEKERJAAN PERSIAPAN
1 Mobilisasi Dan Demobilisasi Peralatan Dan Pekerja 1.00 LS 5,000,000.00 5,000,000.00 0.65 0.13 0.13 0.13 0.13 0.13 100%
2 Pembuatan Direksi Keet 1.00 LS 5,000,000.00 5,000,000.00 0.65 0.65
3 Air Kerja dan Penerangan 1.00 LS 4,000,000.00 4,000,000.00 0.52 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
4 Kesehatan dan Keselamatan Kerja (K3) 1.00 LS 10,000,000.00 10,000,000.00 1.31 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
5 Papan Nama Proyek 1.00 LS 500,000.00 500,000.00 0.07 0.07
6 Shop Drawing dan Asbuilt Drawing 1.00 LS 7,000,000.00 7,000,000.00 0.91 0.46 0.46
7 Laporan, Back Up Data, Dokumentasi 1.00 LS 7,000,000.00 7,000,000.00 0.91 0.23 0.23 0.23 0.23
8 Pembersihan Akhir 1.00 LS 6,968,282.80 6,968,282.80 0.91 0.91
JUMLAH PEKERJAAN A 45,468,282.80 5.94
B PEKERJAAN LANTAI I
B.1 PEKERJAAN TANAH DAN PASIR
1 Galian Tanah Pondasi Telapak 30.86 M3 109,480.00 3,378,552.80 0.44 0.44
2 Galian Tanah Pondasi Menerus 57.19 M3 109,480.00 6,261,161.20 0.82 0.27 0.27 0.27
3 Urugan Kembali Pondasi Telapak 7.71 M3 36,413.60 280,748.86 0.04 0.04
4 Urugan Kembali Pondasi Menerus 14.30 M3 36,413.60 520,714.48 0.07 0.07
5 Urugan Pilihan Dibawah Lantai Bangunan 48.49 M3 179,860.00 8,721,411.40 1.14 0.38 0.38 0.38
6 Urugan Pasir Dibawah Pondasi 2.12 M3 263,212.00 558,009.44 0.07 0.07
7 Urugan Pasir Dibawah Pondasi Telapak 0.00 M3 263,212.00 - 0.00
JUMLAH PEKERJAAN B.1 19,720,598.18 2.58
B.2 PEKERJAAN PASANGAN BATU
1 Pek. Pasangan Batu Kosong 11.33 M3 457,777.05 5,186,613.98 0.68 0.68
2 Pek. Pasangan Batu Belah Camp. 1 : 4 35.41 M3 1,067,185.63 37,789,042.98 4.94 2.47 2.47
JUMLAH PEKERJAAN B.2 42,975,656.96 5.62
75%
B.3 PEKERJAAN BETON
1 Pek. Lantai Kerja Beton 1 : 3 : 5 1.03 M3 847,799.76 873,233.75 0.11 0.11
2 Pek. Lantai Rabbat Beton 1 : 3 : 5 8.98 M3 847,799.76 7,613,241.80 0.99 0.50 0.50
3 Pek. Pondasi Telapak
Beton K-275 6.80 M3 1,914,622.37 13,019,432.10 1.70 1.70
Bekesting 27.20 M2 270,491.50 7,357,368.80 0.96 0.96
Besi Beton 977.70 Kg 33,034.02 32,297,365.02 4.22 4.22
4 Pek. Kolom Pedestal
Beton K-275 2.52 M3 1,914,622.37 4,824,848.37 0.63 0.63
Bekesting 33.66 M2 333,997.95 11,242,371.00 1.47 1.47
Besi Beton 626.64 Kg 33,034.02 20,700,440.64 2.70 2.70
5 Pek. Sloof
Beton K-275 2.49 M3 1,914,622.37 4,767,409.70 0.62 0.62
Bekesting 33.20 M2 270,491.50 8,980,317.80 1.17 1.17
Besi Beton 823.24 Kg 33,034.02 27,194,929.71 3.55 3.55
6 Pek. Kolom Utama
Beton K-275 6.24 M3 1,914,622.37 11,947,243.58 1.56 1.56
Bekesting 103.66 M2 333,997.95 34,622,227.50 4.52 4.52
Besi Beton 1452.11 Kg 33,034.02 47,969,036.23 6.27 6.27
7 Pek. Kolom Praktis KP 20/20
Beton K-275 0.66 M3 1,914,622.37 1,263,650.76 0.17 0.06 0.06 0.06
Bekesting 17.52 M2 333,997.95 5,851,644.08 0.76 0.25 0.25 0.25
Besi Beton 117.50 Kg 33,034.02 3,881,497.79 0.51 0.17 0.17 0.17
50%
JUMLAH PEKERJAAN B.3 244,406,258.62 31.94
B.4 PEKERJAAN LANTAI DAN DINDING
1 Pek. Pasangan Dinding Bata Tela Press 1 : 4 115.09 M2 192,695.44 22,177,317.90 2.90 0.97 0.97 0.97
2 Pek. Plesteran Dinding 1 : 4 115.09 M2 100,519.20 11,568,754.73 1.51 0.50 0.50 0.50
3 Pek. Acian 115.09 M2 57,740.42 6,645,345.15 0.87 0.29 0.29 0.29
4 Pek. Keramik Lantai 60 x 60 cm 150.20 M2 435,429.10 65,401,450.82 8.55 4.27 4.27
JUMLAH PEKERJAAN B.4 105,792,868.60 13.82
B.5 PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Alluminium 37.08 M' 256,921.00 9,526,630.68 1.24 0.41 0.41 0.41
2 Pek. Kusen Jendela Alluminium 75.76 M' 256,921.00 19,464,334.96 2.54 0.85 0.85 0.85
3 Pek. Kusen Ventilasi Alluminium 2.72 M' 256,921.00 698,825.12 0.09 0.09
JUMLAH PEKERJAAN B.5 29,689,790.76 3.88
B.6 PEKERJAAN INSTALASI LISTRIK
1 Pek. MCB 16A 2.00 BH 152,225.50 304,451.00 0.04 0.04
2 Pek. Instalasi Kabel NYM 3x2,5mm 100.00 M' 34,925.50 3,492,550.00 0.46 0.46
3 Pek. Instalasi Kabel NYM 2x2,5mm 100.00 M' 34,695.50 3,469,550.00 0.45 0.45
4 Pek. Saklar Seri Panasonic 30.00 BH 74,370.50 2,231,115.00 0.29 0.29
5 Pek. Saklar Tunggal Panasonic 6.00 BH 70,891.75 425,350.50 0.06 0.06
6 Pek. Stop Kontak Tanam Panasonic 20.00 BH 81,328.00 1,626,560.00 0.21 0.21
7 Stop Kontak Tanam AC Panasonic 10.00 BH 60,225.50 602,255.00 0.08 0.08
8 Lampu Balon Philips LED 11 Watt 15.00 BH 88,975.50 1,334,632.50 0.17 0.17
9 Lampu Balon Philips LED 25 Watt 20.00 BH 123,475.50 2,469,510.00 0.32 0.32
JUMLAH PEKERJAAN B.6 15,955,974.00 2.09 25%
B.7 PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding 115.09 M2 33,711.91 3,879,903.15 0.51 0.25 0.25
JUMLAH PEKERJAAN B.7 3,879,903.15 0.51
C PEKERJAAN LANTAI II
C.1 PEKERJAAN BETON
1 Pek. Balok B1 25/40
Beton K-275 9.95 M3 1,914,622.37 19,050,492.56 2.49 2.49
Bekesting 104.48 M2 342,277.95 35,761,200.22 4.67 2.34 2.34
Besi Beton 1319.37 Kg 33,034.02 43,584,099.92 5.70 5.70
2 Pek. Balok B2 20/35
Beton K-275 4.55 M3 1,914,622.37 8,711,531.77 1.14 1.14
Bekesting 58.50 M2 342,277.95 20,023,260.08 2.62 1.31 1.31
Besi Beton 712.40 Kg 33,034.02 23,533,438.52 3.08 3.08
3 Pek. Balok Anak Ba 15/25
Beton K-275 2.25 M3 1,914,622.37 4,307,900.33 0.56 0.56
Bekesting 39.00 M2 342,277.95 13,348,840.05 1.74 1.74
Besi Beton 577.92 Kg 33,034.02 19,091,023.01 2.49 2.49
4 Pek. Pelat Lantai
Beton K-275 22.71 M3 1,914,622.37 43,481,073.97 5.68 5.68
Bekesting 41.63 M2 342,277.95 14,249,031.06 1.86 0.93 0.93
Besi Beton 370.49 Kg 33,034.02 12,238,775.46 1.60 1.60
JUMLAH PEKERJAAN C.1 257,380,666.93 33.63 0%
A JUMLAH TOTAL 765,270,000.00 100.00

RENCANA PROGRESS PEKERJAAN PERMINGGU (%) 0.30 1.57 5.08 6.42 8.50 4.68 7.05 6.57 19.87 8.37 11.10 3.71 6.46 5.97 1.45 0.58 1.19 1.14
KUMULATIF RENCANA PROGRESS PEKERJAAN PERMINGGU (%) 0.00 0.30 1.87 6.95 13.37 21.87 26.54 33.59 40.16 60.03 68.40 79.49 83.21 89.67 95.64 97.09 97.67 98.86 100.00
REALISASI PROGRESS PEKERJAAN PERMINGGU (%) 0.76 1.35
KUMULATIF REALISASI PROGRESS PEKERJAAN PERMINGGU (%) 0.00 0.76 2.11
DEVIASI PERMINGGU (%) 0.46 0.24

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
RENCANA JADWAL PELAKSANAAN (KURVA' S ADD-01)
PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE

KEGIATAN 0 PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN 0 PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI 0 KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN 0 2022

WAKTU PELAKSANAAN PEKERJAAN


HARGA SATUAN JUMLAH HARGA BOBOT BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5
NO URAIAN PEKERJAAN VOLOME SATUAN ( Rp ) ( Rp ) ( % ) M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 KET
28-Jul-22 1-Aug-22 8-Aug-22 15-Aug-22 22-Aug-22 29-Aug-22 5-Sep-22 12-Sep-22 19-Sep-22 26-Sep-22 3-Oct-22 10-Oct-22 17-Oct-22 24-Oct-22 31-Oct-22 7-Nov-22 14-Nov-22 21-Nov-22
31-Jul-22 7-Aug-22 14-Aug-22 21-Aug-22 28-Aug-22 4-Sep-22 11-Sep-22 18-Sep-22 25-Sep-22 2-Oct-22 9-Oct-22 16-Oct-22 23-Oct-22 30-Oct-22 6-Nov-22 13-Nov-22 20-Nov-22 24-Nov-22
A PEKERJAAN PERSIAPAN
1 Mobilisasi Dan Demobilisasi Peralatan Dan Pekerja 1.00 LS 5,000,000.00 5,000,000.00 0.65 0.13 0.13 0.13 0.13 0.13 100%
2 Pembuatan Direksi Keet 1.00 LS 5,000,000.00 5,000,000.00 0.65 0.65
3 Air Kerja dan Penerangan 1.00 LS 4,000,000.00 4,000,000.00 0.52 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
4 Kesehatan dan Keselamatan Kerja (K3) 1.00 LS 10,000,000.00 10,000,000.00 1.31 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
5 Papan Nama Proyek 1.00 LS 500,000.00 500,000.00 0.07 0.07
6 Shop Drawing dan Asbuilt Drawing 1.00 LS 7,000,000.00 7,000,000.00 0.91 0.46 0.46
7 Laporan, Back Up Data, Dokumentasi 1.00 LS 7,000,000.00 7,000,000.00 0.91 0.23 0.23 0.23 0.23
8 Pembersihan Akhir 1.00 LS 6,968,282.80 6,968,282.80 0.91 0.91
JUMLAH PEKERJAAN A 45,468,282.80 5.94
B PEKERJAAN LANTAI I
B.1 PEKERJAAN TANAH DAN PASIR
1 Galian Tanah Pondasi Telapak 37.45 M3 109,480.00 4,099,719.46 0.54 0.54
2 Galian Tanah Pondasi Menerus 67.62 M3 109,480.00 7,403,525.36 0.97 0.32 0.32 0.32
3 Urugan Kembali Pondasi Telapak 12.48 M3 36,413.60 454,529.12 0.06 0.06
4 Urugan Kembali Pondasi Menerus 22.54 M3 36,413.60 820,816.62 0.11 0.11
5 Urugan Pilihan Dibawah Lantai Bangunan 93.30 M3 179,860.00 16,780,667.49 2.19 0.73 0.73 0.73
6 Urugan Pasir Dibawah Pondasi 4.70 M3 263,212.00 1,237,082.19 0.16 0.16
7 Urugan Pasir Dibawah Pondasi Telapak 1.47 M3 263,212.00 386,132.00 0.05 0.05 SCHEDULE RENCANA
AWAL
JUMLAH PEKERJAAN B.1 31,182,472.23 4.07
B.2 PEKERJAAN PASANGAN BATU
1 Pek. Pasangan Batu Kosong 17.14 M3 457,777.05 7,848,129.75 1.03 1.03
2 Pek. Pasangan Batu Belah Camp. 1 : 4 159.32 M3 1,067,185.63 170,029,201.50 22.22 3.70 3.70 3.70 3.70 3.70 3.70
JUMLAH PEKERJAAN B.2 177,877,331.24 23.24
75%
B.3 PEKERJAAN BETON
1 Pek. Lantai Kerja Beton 1 : 3 : 5 3.91 M3 847,799.76 3,314,897.04 0.43 0.43
2 Pek. Lantai Rabbat Beton 1 : 3 : 5 8.98 M3 847,799.76 7,613,241.80 0.99 0.33 0.33 0.33
3 Pek. Pondasi Telapak
Beton K-275 13.51 M3 1,914,622.37 25,858,889.70 3.38 SCHEDULE
3.38
RENCANA ADD-01
Bekesting 31.23 M2 270,491.50 8,447,449.55 1.10 1.10
Besi Beton 2514.83 Kg 33,034.02 83,074,978.58 10.86 10.86
4 Pek. Kolom Pedestal
Beton K-275 13.51 M3 1,914,622.37 25,865,399.42 3.38 3.38
Bekesting 135.29 M2 333,997.95 45,187,718.25 5.90 5.90
Besi Beton 1785.67 Kg 33,034.02 58,987,827.94 7.71 7.71
5 Pek. Sloof
Beton K-275 13.83 M3 1,914,622.37 26,474,247.41 3.46 1.73 1.73
Bekesting 96.62 M2 270,491.50 26,135,678.57 3.42 3.42
Besi Beton 1723.54 Kg 33,034.02 56,935,522.73 7.44 7.44
6 Pek. Kolom Utama
Beton K-275 14.48 M3 1,914,622.37 27,731,390.38 3.62 3.62
Bekesting 149.94 M2 333,997.95 50,078,183.03 6.54 6.54
Besi Beton 1968.77 Kg 33,034.02 65,036,489.34 8.50 8.50
7 Pek. Kolom Praktis KP 20/20
Beton K-275 0.00 M3 1,914,622.37 - 0.00
Bekesting 0.00 M2 333,997.95 - 0.00
Besi Beton 0.00 Kg 33,034.02 - 0.00
50%
JUMLAH PEKERJAAN B.3 510,741,913.73 66.74
B.4 PEKERJAAN LANTAI DAN DINDING
1 Pek. Pasangan Dinding Bata Tela Press 1 : 4 0.00 M2 192,695.44 - 0.00
2 Pek. Plesteran Dinding 1 : 4 0.00 M2 100,519.20 - 0.00
SCHEDULE REALISASI
3 Pek. Acian 0.00 M2 57,740.42 - 0.00 ADD-01
4 Pek. Keramik Lantai 60 x 60 cm 0.00 M2 435,429.10 - 0.00
JUMLAH PEKERJAAN B.4 - 0.00
B.5 PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Alluminium 0.00 M' 256,921.00 - 0.00
2 Pek. Kusen Jendela Alluminium 0.00 M' 256,921.00 - 0.00
3 Pek. Kusen Ventilasi Alluminium 0.00 M' 256,921.00 - 0.00
JUMLAH PEKERJAAN B.5 - 0.00
B.6 PEKERJAAN INSTALASI LISTRIK
1 Pek. MCB 16A 0.00 BH 152,225.50 - 0.00
2 Pek. Instalasi Kabel NYM 3x2,5mm 0.00 M' 34,925.50 - 0.00
3 Pek. Instalasi Kabel NYM 2x2,5mm 0.00 M' 34,695.50 - 0.00
4 Pek. Saklar Seri Panasonic 0.00 BH 74,370.50 - 0.00
5 Pek. Saklar Tunggal Panasonic 0.00 BH 70,891.75 - 0.00
6 Pek. Stop Kontak Tanam Panasonic 0.00 BH 81,328.00 - 0.00
7 Stop Kontak Tanam AC Panasonic 0.00 BH 60,225.50 - 0.00
8 Lampu Balon Philips LED 11 Watt 0.00 BH 88,975.50 - 0.00
9 Lampu Balon Philips LED 25 Watt 0.00 BH 123,475.50 - 0.00
JUMLAH PEKERJAAN B.6 - 0.00 25%
B.7 PEKERJAAN PENGECATAN SCHEDULE REALISASI
1 Pek. Pengecatan Dinding 0.00 M2 33,711.91 - 0.00 RENCANA KONTRAK
AWAL
JUMLAH PEKERJAAN B.7 - 0.00
C PEKERJAAN LANTAI II
C.1 PEKERJAAN BETON
1 Pek. Balok B1 25/40
Beton K-275 0.00 M3 1,914,622.37 - 0.00
Bekesting 0.00 M2 342,277.95 - 0.00
Besi Beton 0.00 Kg 33,034.02 - 0.00
2 Pek. Balok B2 20/35
Beton K-275 0.00 M3 1,914,622.37 - 0.00
Bekesting 0.00 M2 342,277.95 - 0.00
Besi Beton 0.00 Kg 33,034.02 - 0.00
3 Pek. Balok Anak Ba 15/25
Beton K-275 0.00 M3 1,914,622.37 - 0.00
Bekesting 0.00 M2 342,277.95 - 0.00
Besi Beton 0.00 Kg 33,034.02 - 0.00
4 Pek. Pelat Lantai
Beton K-275 0.00 M3 1,914,622.37 - 0.00
Bekesting 0.00 M2 342,277.95 - 0.00
Besi Beton 0.00 Kg 33,034.02 - 0.00
JUMLAH PEKERJAAN C.1 - 0.00 0%
A JUMLAH TOTAL 765,270,000.00 100.00

RENCANA PROGRESS PEKERJAAN PERMINGGU (%) 0.30 1.57 5.08 6.42 8.50 4.68 7.05 6.57 19.87 8.37 11.10 3.71 6.46 5.97 1.45 0.58 1.19 1.14
KUMULATIF RENCANA PROGRESS PEKERJAAN PERMINGGU (%) 0.00 0.30 1.87 6.95 13.37 21.87 26.54 33.59 40.16 60.03 68.40 79.49 83.21 89.67 95.64 97.09 97.67 98.86 100.00
REALISASI PROGRESS PEKERJAAN PERMINGGU (%) 0.76 1.35
KUMULATIF REALISASI PROGRESS PEKERJAAN PERMINGGU (%) 0.00 0.76 2.11
RENCANA PROGRESS PEKERJAAN PERMINGGU CCO-01 (%) 0.93 0.47 1.45 4.13 4.47 22.37 17.63 4.64 4.76 16.77 11.79 5.46 0.43 0.66 1.02 1.14
KUMULATIF RENCANA PROGRESS PEKERJAAN PERMINGGU CCO-01 (%) 1.87 2.80 3.27 4.72 8.85 13.32 35.69 53.32 57.96 62.72 79.50 91.29 96.74 97.17 97.84 98.86 100.00
REALISASI PROGRESS PEKERJAAN PERMINGGU CCO-01 (%) 0.24 0.34 0.11 1.61 12.50 12.03 5.45 20.44 12.20 12.20
KUMULATIF REALISASI PROGRESS PEKERJAAN PERMINGGU CCO-01 (%) 0.00 2.11 2.34 2.68 2.79 4.40 16.89 28.93 34.38 54.82 67.01 79.21
DEVIASI PERMINGGU CCO-01 (%) -0.46 -0.59 -1.94 -4.45 3.58 -6.76 -18.94 -3.14 4.29 -0.29

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.1 PEKERJAAN TANAH DAN PASIR
Lembar 1

SKETSA GAMBAR

Galian Tanah Pondasi Telapak


BETON K-275

Ø12-200
Ø8-200

Slof S1 300x400
40

Ø12-200
Ø8-150
485

415

40
Ø8-150

Ø12-200 230

160

Ø12-150
30

30

Ø12-150
30
30

Rabat Beton T 10 cm
Urugan Pasir T 5 cm
40 (B)40 40 40 (B)40 40

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1 0.10 0.00
2 0.35 0.00 0.00 0.00
3 0.35 -0.55 (0.20) 0.00
-0.20
4 1.05 -0.55 (0.20) -0.58
5 1.05 0.00 0.00 -0.58
-0.40
6 1.30 0.00 0.00 0.00
-0.55 -0.55 -0.55 -0.55
7 1.30 -1.55 (2.02) 0.00
-0.60 8 0.10 -1.55 (2.02) -0.16
Y(EL)

9 0.10 0.00 0.00 -0.16


-0.80 1 0.10 0.00

-1.00

-1.20

TOTAL (4.42) -1.48


-1.40 TOTAL AREA (M2) 1.471

-1.55 -1.55 -1.55 -1.55


-1.60

-1.80
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40

X(DIST)

JUMLAH TOTAL AREA (M2) 1.471

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.1 PEKERJAAN TANAH DAN PASIR
Lembar 2

REKAP VOLUME

NO PANJANG (M') LEBAR (M') TINGGI (M') JUMLAH AREA (M2) VOLUME (M3) KET

1 1.20 18.00 1.47 31.77 GALIAN TANAH K1

2 10.59 URUGAN KEMBALI K1

3 1.20 1.20 0.05 18.00 0.06 1.30 URUGAN PASIR K1

4 1.20 1.00 4.73 5.67 GALIAN TANAH K2

5 1.89 URUGAN KEMBALI K2

6 2.85 1.20 0.05 1.00 0.06 0.17 URUGAN PASIR K2

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.1 PEKERJAAN TANAH DAN PASIR
Lembar 3

SKETSA GAMBAR

PONDASI TALUD

+5.00
50 110

375

Tanah Timbunan
500

Pas Batu Kali


125

Pas Batu Kali


75

Urugan Pasir T:5 cm

160

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.90
2 0.00 0.80 0.00 0.00
3 1.60 0.42 0.00 1.28
0.80 0.80
4 1.60 0.00 0.00 0.68
5 0.00 0.00 0.00 0.00
0.70
1 0.00 0.00

0.60
Y(EL)

0.50

0.42
0.40

0.30

0.20
TOTAL 0.00 1.96
TOTAL AREA (M2) 0.979
0.10

0.00 0.00 0.00


0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80

X(DIST)

JUMLAH TOTAL AREA (M2) 0.979

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.1 PEKERJAAN TANAH DAN PASIR
Lembar 4

SKETSA GAMBAR

Galian Tanah Pondasi Menerus

K5 200x200

S1 300x400
20

50

Tanah Timbunan
Elev.Eksisting
100

30

Pas Batu Kali


Pas Batu Kosong/Anstaping
20

Urugan Pasir T:5 cm


30
60
70

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.60
2 0.00 0.55 0.00 0.00
0.55 0.55 3 0.90 0.55 0.00 0.49
4 0.90 0.00 0.00 0.49
0.50
5 0.00 0.00 0.00 0.00
1 0.00 0.00

0.40
Y(EL)

0.30

0.20

TOTAL 0.00 0.98


0.10
TOTAL AREA (M2) 0.492

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00

X(DIST)

JUMLAH TOTAL AREA (M2) 0.492

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.1 PEKERJAAN TANAH DAN PASIR
Lembar 4

REKAP VOLUME

NO PANJANG (M') LEBAR (M') TINGGI (M') JUMLAH AREA (M2) VOLUME (M3) KET

1 15.50 0.98 15.17 PONDASI TALUD

2 5.06 URUGAN KEMBALI

3 15.50 1.25 0.05 0.06 0.97 URUGAN PASIR

4 106.61 0.49 52.45 PONDASI MENERUS

5 17.48 URUGAN KEMBALI

6 106.61 0.70 0.05 0.04 3.73 URUGAN PASIR

0.64 32.94 21.08 TIMBUNAN


0.64 18.97 12.14
0.64 10.58 6.77
0.64 15.92 10.19
0.64 10.62 6.80
0.64 14.88 9.52
0.64 5.87 3.76
0.64 8.66 5.54
0.64 7.93 5.07
0.64 4.41 2.82
0.64 5.49 3.51
0.64 3.18 2.04
0.64 6.34 4.06
93.30

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.1 PEKERJAAN TANAH DAN PASIR
Lembar 2

SKETSA GAMBAR

Galian Tanah Pondasi Telapak

BETON K-275

Ø12-200
Ø8-200

Slof S1 300x400
40

40
Ø12-200
Ø8-150

485
485

415

415

40
Ø8-150

Ø12-200

230

160
Ø12-150
30

30

30
Ø12-150

30

30
Rabat Beton T 10 cm
Urugan Pasir T 5 cm
40 (B)40 40

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
0.00 0.00 0.00 1 0.00 0.00
2 3.05 0.00 0.00 0.00
-0.20 3 3.05 -1.55 (4.73) 0.00
4 0.00 -1.55 (4.73) 0.00
-0.40
5 0.00 0.00 0.00 0.00
1 0.00 0.00
-0.60
Y(EL)

-0.80

-1.00

-1.20

-1.40

-1.55 -1.55
-1.60
TOTAL (9.46) 0.00
-1.80 TOTAL AREA (M2) 4.728
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50

X(DIST)

JUMLAH TOTAL AREA (M2) 4.728

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 1

SKETSA GAMBAR

Pek. Pasangan Batu Kosong

K5 200x200

S1 300x400
20

50

Tanah Timbunan
Elev.Eksisting
100

30

Pas Batu Kali


Pas Batu Kosong/Anstaping
20

Urugan Pasir T:5 cm


30
60
70

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
0.25
1 0.05 0.00
2 0.05 0.20 0.01 0.00
3 0.85 0.20 0.01 0.17
4 0.85 0.00 0.00 0.17
0.20 0.20 0.20
5 0.05 0.00 0.00 0.00
1 0.05 0.00

0.15
Y(EL)

0.10

0.05

TOTAL 0.02 0.34


TOTAL AREA (M2) 0.160
0.00 0.00 0.00

-0.05
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90

X(DIST)

JUMLAH TOTAL AREA (M2) 0.160

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 2

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+3.75
K1 350x400
40

S1 300x400

Tanah Timbunan
345
395

Pas Batu Kali

Elev.Eksisting
20 30

Pas Batu Kosong/Anstaping


Urugan Pasir T:5 cm

70
80
90

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
4.00 1 0.26 3.75
2 0.56 3.75 0.97 2.09
3.75 3.75
3 0.75 0.00 0.00 2.81
3.50
4 0.05 0.00 0.00 0.00
5 0.26 3.75 0.19 0.00
3.00 1 0.26 3.75

2.50
Y(EL)

2.00

1.50

1.00 TOTAL 1.15 4.90


TOTAL AREA (M2) 1.875
0.50

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80

X(DIST)

JUMLAH TOTAL AREA (M2) 1.875

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 3

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+2.75
K1 350x400
40

S1 300x400

Tanah Timbunan
24 5

Pas Batu Kali


29 5

Elev.Eksisting
30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm

70
80
90

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.26 2.75
3.00
2 0.56 2.75 0.71 1.53
2.75 2.75 3 0.75 0.00 0.00 2.06
4 0.05 0.00 0.00 0.00
2.50
5 0.26 2.75 0.14 0.00
1 0.26 2.75

2.00
Y(EL)

1.50

1.00

TOTAL 0.85 3.60


TOTAL AREA (M2) 1.375
0.50

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80

X(DIST)

JUMLAH TOTAL AREA (M2) 1.375

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 4

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+2.50
K1 350x400
40

S1 300x400

Tanah Timbunan
220
270

Pas Batu Kali

Elev.Eksisting
30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm

70
80
90

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.05 0.00
3.00
2 0.25 2.50 0.13 0.00
3 0.55 2.50 0.63 1.38
4 0.75 0.00 0.00 1.88
2.50 2.50 2.50 5 0.05 0.00 0.00 0.00
1 0.05 0.00

2.00
Y(EL)

1.50

1.00

TOTAL 0.75 3.25


TOTAL AREA (M2) 1.250
0.50

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80

X(DIST)

JUMLAH TOTAL AREA (M2) 1.250

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 5

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+2.35
K1 350x400
40

S1 300x400

Tanah Timbunan
205
255

Pas Batu Kali

Elev.Eksisting
30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm

70
80
90

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.05 0.00
2.50
2 0.25 2.35 0.12 0.00
2.35 2.35 3 0.55 2.35 0.59 1.29
4 0.75 0.00 0.00 1.76
5 0.05 0.00 0.00 0.00
2.00
1 0.05 0.00
Y(EL)

1.50

1.00

TOTAL 0.71 3.06


0.50 TOTAL AREA (M2) 1.176

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80

X(DIST)

JUMLAH TOTAL AREA (M2) 1.176

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 6

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+2.25

K1 350x400

S1 300x400
40

Tanah Timbunan
195
245

Pas Batu Kali

Elev.Eksisting
30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm

70
80
90

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.05 0.00
2.50
2 0.25 2.25 0.11 0.00
3 0.55 2.25 0.56 1.24
2.25 2.25
4 0.75 0.00 0.00 1.69
5 0.05 0.00 0.00 0.00
2.00
1 0.05 0.00
Y(EL)

1.50

1.00

TOTAL 0.68 2.93


0.50 TOTAL AREA (M2) 1.125

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80

X(DIST)

JUMLAH TOTAL AREA (M2) 1.125

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 7

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+1.75

K1 350x400
40

S1 300x400

Tanah Timbunan
145
195

Pas Batu Kali

Elev.Eksisting
30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm


70
80
90

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.05 0.00
2.00
2 0.25 1.75 0.09 0.00
3 0.55 1.75 0.44 0.96
1.80
1.75 1.75 4 0.75 0.00 0.00 1.31
5 0.05 0.00 0.00 0.00
1.60
1 0.05 0.00
1.40
Y(EL)

1.20

1.00

0.80

0.60
TOTAL 0.53 2.28
0.40 TOTAL AREA (M2) 0.875

0.20

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80

X(DIST)

JUMLAH TOTAL AREA (M2) 0.875

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 8

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+1.05

K1 350x400
40

S1 300x400

Tanah Timbunan
75

Pas Batu Kali


125

Elev.Eksisting
30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm


30
60
70

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
1.20
2 0.10 1.05 0.00 0.00
3 0.40 1.05 0.11 0.42
1.05 1.05 4 0.50 0.00 0.00 0.53
1.00 5 0.00 0.00 0.00 0.00
1 0.00 0.00

0.80
Y(EL)

0.60

0.40

TOTAL 0.11 0.95


TOTAL AREA (M2) 0.421
0.20

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60

X(DIST)

JUMLAH TOTAL AREA (M2) 0.421

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 9

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+0.70

K1 350x400

S1 300x400
40

Tanah Timbunan
40

Pas Batu Kali


Elev.Eksisting
90

30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm


30
60
70

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.80
2 0.10 0.70 0.00 0.00
3 0.40 0.70 0.07 0.28
0.70 0.70 0.70 4 0.50 0.00 0.00 0.35
5 0.00 0.00 0.00 0.00
1 0.00 0.00
0.60

0.50
Y(EL)

0.40

0.30

0.20 TOTAL 0.07 0.63


TOTAL AREA (M2) 0.281

0.10

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60

X(DIST)

JUMLAH TOTAL AREA (M2) 0.281

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 10

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+0.60

K1 350x400

S1 300x400
40

Tanah Timbunan
30

Pas Batu Kali


Elev.Eksisting
80

30

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm


30
60
70

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.70
2 0.10 0.60 0.00 0.00
3 0.40 0.60 0.06 0.24
4 0.50 0.00 0.00 0.30
0.60 0.60 0.60
5 0.00 0.00 0.00 0.00
1 0.00 0.00
0.50
Y(EL)

0.40

0.30

0.20
TOTAL 0.06 0.54
TOTAL AREA (M2) 0.241
0.10

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60

X(DIST)

JUMLAH TOTAL AREA (M2) 0.241

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 11

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+0.50

K5 200x200

S1 300x400
40

Tanah Timbunan
20

Pas Batu Kali


Elev.Eksisting
40
80

Pas Batu Kosong/Anstaping


20

Urugan Pasir T:5 cm


30
60
70

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.60
2 0.10 0.50 0.00 0.00
3 0.40 0.50 0.05 0.20
4 0.50 0.00 0.00 0.25
0.50 0.50 0.50 5 0.00 0.00 0.00 0.00
1 0.00 0.00

0.40
Y(EL)

0.30

0.20

TOTAL 0.05 0.45


TOTAL AREA (M2) 0.201
0.10

0.00 0.00 0.00


0.00 0.10 0.20 0.30 0.40 0.50 0.60

X(DIST)

JUMLAH TOTAL AREA (M2) 0.201

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 12

SKETSA GAMBAR

Pek. Pasangan Batu Belah Camp. 1 : 4

+5.00
50

475
600

Tanah Timbunan

Pas Batu Kali


125

Pas Batu Kali

Urugan Pasir T:5 cm

125

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 -6.00
0.00 0.00 0.00
2 0.00 0.00 0.00 0.00
3 0.50 0.00 0.00 0.00
4 1.25 -4.75 (2.38) 0.00
-1.00 5 1.25 -6.00 (7.50) -5.94
6 0.00 -6.00 (7.50) 0.00
1 0.00 -6.00
-2.00
Y(EL)

-3.00

-4.00

TOTAL (17.38) -5.94


-4.75 TOTAL AREA (M2) 5.719
-5.00

-6.00 -6.00 -6.00

-7.00
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40

X(DIST)

JUMLAH TOTAL AREA (M2) 5.719

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.2 PEKERJAAN PASANGAN BATU
Lembar 13

REKAP VOLUME

NO PANJANG (M') LEBAR (M') TINGGI (M') JUMLAH AREA (M2) VOLUME (M3) KET

1 107.15 0.16 17.14 BATU KOSONG

2 6.50 1.88 12.19 PAS BATU

3 8.00 1.38 11.00

4 7.70 1.25 9.63

5 9.00 1.18 10.58

6 7.50 1.13 8.44

7 13.00 0.88 11.38

8 8.00 0.42 3.37

9 5.70 0.28 1.60

10 26.50 0.24 6.39

11 15.25 0.20 3.07

12 14.28 5.72 81.69

159.32

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 1

SKETSA GAMBAR

BETON K-275 Pek. Pondasi Telapak

Ø12-200
Ø8-200 40

Slof S1 300x400

Ø12-200
Ø8-150
485

415

40
Ø8-150

Ø12-200

230

160
Ø12-150

30
30

Ø12-150
30

30
Rabat Beton T 10 cm
Urugan Pasir T 5 cm
40 (B)40 40 40 (B)40 40

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 -0.40
2 0.00 0.00 0.00 0.00
0.10
0.05 0.05
3 0.40 0.05 0.00 0.00
0.00 0.00 0.00 4 0.80 0.05 0.02 0.04
-0.10
5 1.20 0.00 0.00 0.06
-0.20
6 1.20 -0.40 (0.48) 0.00
Y(EL)

-0.30
7 0.00 -0.40 (0.48) 0.00
-0.40 -0.40 -0.40
1 0.00 -0.40
-0.50
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40

X(DIST)

TOTAL (0.94) 0.10


TOTAL AREA (M2) 0.520

JUMLAH TOTAL AREA (M2) 0.520

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 2

SKETSA GAMBAR

Pek. Pondasi Telapak

BETON K-275

Ø12-200
Ø8-200

285
Slof S1 300x400
40

40
43 200 43

48
Ø12-200

120
25
Ø8-150

48
485

485
415

415

40
Ø8-150

Ø12-200

230

160
Ø12-150
30

30

30
Ø12-150
30

30
Rabat Beton T 10 cm
Urugan Pasir T 5 cm
40 (B)40 40 40 (B)40 40

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.10 0.00
0.35
2 0.10 0.30 0.03 0.00
0.30 0.30 0.30
3 2.95 0.30 0.03 0.89
0.25
4 2.95 0.00 0.00 0.89
0.20
5 0.10 0.00 0.00 0.00
Y(EL)

0.15
0.10
1 0.10 0.00
0.05
0.00 0.00 0.00
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50

X(DIST)

TOTAL 0.06 1.77


TOTAL AREA (M2) 0.855

JUMLAH TOTAL AREA (M2) 0.855

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 3

SKETSA GAMBAR

Pek. Kolom Pedestal

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
0.50
1 0.00 0.00
2 0.49 0.42 0.00 0.00
0.42
0.40 3 0.92 -0.07 (0.04) 0.39
0.30
4 0.73 -0.23 (0.21) -0.05
5 0.47 0.07 0.05 -0.11
0.20 6 0.16 -0.19 (0.09) 0.01
Y(EL)

7 0.00 0.00 0.00 0.00


0.10
0.07 1 0.00 0.00
0.00 0.00

-0.07
-0.10

-0.20 -0.19
-0.23

-0.30
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00

X(DIST)
TOTAL (0.29) 0.24
TOTAL AREA (M2) 0.263

JUMLAH TOTAL AREA (M2) 0.263

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 4

SKETSA GAMBAR

Pek. Kolom Pedestal

56
30

43

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.40
2 0.00 0.30 0.00 0.00
0.30 0.30 0.30 3 0.56 0.30 0.00 0.17
0.20
4 0.93 -0.13 (0.07) 0.28
5 0.71 -0.32 (0.30) -0.09
0.10 6 0.43 0.00 0.00 -0.14
Y(EL)

0.00 0.00 0.00 7 0.00 0.00 0.00 0.00


1 0.00 0.00
-0.10
-0.13

-0.20

-0.30
-0.32

-0.40
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00

X(DIST)
TOTAL (0.38) 0.22
TOTAL AREA (M2) 0.298

JUMLAH TOTAL AREA (M2) 0.298

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 5

SKETSA GAMBAR

Pek. Kolom Pedestal

40

35

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.40 0.40
0.90
2 0.40 0.80 0.32 0.16
0.80 0.80 0.80 3 0.75 0.80 0.32 0.60
4 0.75 0.40 0.30 0.60
0.70 5 0.40 0.40 0.30 0.16
1 0.40 0.40
0.60
Y(EL)

0.50

0.40 0.40 0.40

0.30

0.20

0.10

TOTAL 1.24 1.52


0.00
0.35 0.40 0.45 0.50 0.55 0.60 0.65 0.70 0.75 0.80 TOTAL AREA (M2) 0.140

X(DIST)

JUMLAH TOTAL AREA (M2) 0.140

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 6

SKETSA GAMBAR

Pek. Kolom Pedestal

285
43 200 43

Ø10-150
Ø10-150

48
Ø10-150

120
25
Ø10-150

48
GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.43 0.48
0.80
2 0.43 0.73 0.31 0.20
0.73 0.73
0.70
3 2.43 0.73 0.31 1.76
0.60 4 2.43 0.48 1.15 1.76
5 0.43 0.48 1.15 0.20
0.50
0.48 0.48
1 0.43 0.48
Y(EL)

0.40

0.30

0.20

0.10

0.00
0.00 0.50 1.00 1.50 2.00 2.50 3.00

X(DIST)

TOTAL 2.92 3.92


TOTAL AREA (M2) 0.500

JUMLAH TOTAL AREA (M2) 0.500

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 7

SKETSA GAMBAR

Pek. Sloof

SLOF S2

20 15

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.25
2 0.00 0.20 0.00 0.00
3 0.15 0.20 0.00 0.03
0.20 0.20 0.20 4 0.15 0.00 0.00 0.03
5 0.00 0.00 0.00 0.00
0.15 1 0.00 0.00
Y(EL)

0.10

0.05

0.00 0.00 0.00


0.00 0.02 0.04 0.06 0.08 0.10 0.12 0.14 0.16

X(DIST)
TOTAL 0.00 0.06
TOTAL AREA (M2) 0.030

JUMLAH TOTAL AREA (M2) 0.030

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 8

SKETSA GAMBAR

Pek. Sloof Beton 30/40

SLOOF SI

40

30

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.45
2 0.00 0.40 0.00 0.00
0.40 0.40 0.40
3 0.30 0.40 0.00 0.12
0.35 4 0.30 0.00 0.00 0.12
0.30 5 0.00 0.00 0.00 0.00
1 0.00 0.00
Y(EL)

0.25

0.20

0.15

0.10

0.05

0.00 0.00 0.00


0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35

X(DIST)
TOTAL 0.00 0.24
TOTAL AREA (M2) 0.120

JUMLAH TOTAL AREA (M2) 0.120

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 9

SKETSA GAMBAR

Pek. Kolom Utama

KOLOM K1

40

35

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.45
2 0.00 0.40 0.00 0.00
0.40 0.40 0.40
3 0.35 0.40 0.00 0.14
0.35 4 0.35 0.00 0.00 0.14
0.30 5 0.00 0.00 0.00 0.00
1 0.00 0.00
Y(EL)

0.25

0.20

0.15

0.10

0.05

0.00 0.00 0.00


0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40

X(DIST)

TOTAL 0.00 0.28


TOTAL AREA (M2) 0.140

JUMLAH TOTAL AREA (M2) 0.140

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 10

SKETSA GAMBAR

Pek. Kolom Praktis KP 20/20

KOLOM K2

20
20

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 0.00 0.00
0.25
2 0.00 0.20 0.00 0.00
0.20 0.20 0.20 3 0.20 0.20 0.00 0.04
4 0.20 0.00 0.00 0.04
0.15
5 0.00 0.00 0.00 0.00
Y(EL)

0.10 1 0.00 0.00

0.05

0.00 0.00 0.00


0.00 0.05 0.10 0.15 0.20 0.25

X(DIST)

TOTAL 0.00 0.08


TOTAL AREA (M2) 0.040

JUMLAH TOTAL AREA (M2) 0.040

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 11

SKETSA GAMBAR

Pek. Kolom K3

KOLOM K3

56
30

43

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
0.40
1 0.00 0.00
2 0.00 0.30 0.00 0.00
0.30 0.30 0.30
3 0.56 0.30 0.00 0.17
0.20 4 0.93 -0.13 (0.07) 0.28
0.10 5 0.71 -0.32 (0.30) -0.09
6 0.43 0.00 0.00 -0.14
Y(EL)

0.00 0.00 0.00


7 0.00 0.00 0.00 0.00
-0.10 1 0.00 0.00
-0.13
-0.20

-0.30
-0.32
-0.40
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00

X(DIST)

TOTAL (0.38) 0.22


TOTAL AREA (M2) 0.298

JUMLAH TOTAL AREA (M2) 0.298

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 12

SKETSA GAMBAR

Pek. Kolom K4

KOLOM K4

GRAFIK PERHITUNGAN
No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
0.50
1 0.00 0.00
2 0.49 0.42 0.00 0.00
0.42
0.40 3 0.92 -0.07 (0.04) 0.39
0.30 4 0.73 -0.23 (0.21) -0.05
5 0.47 0.07 0.05 -0.11
0.20
6 0.16 -0.19 (0.09) 0.01
Y(EL)

0.10 7 0.00 0.00 0.00 0.00


0.07
1 0.00 0.00
0.00 0.00
-0.07
-0.10

-0.20 -0.19
-0.23
-0.30
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00

X(DIST)

TOTAL (0.29) 0.24


TOTAL AREA (M2) 0.263

JUMLAH TOTAL AREA (M2) 0.263

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 13

REKAP VOLUME

NO PANJANG (M') LEBAR (M') TINGGI (M') JUMLAH AREA (M2) VOLUME (M3) KET

PEK. PONDASI TELAPAK


1 1.20 20 0.52 12.48 Beton K-275
1.20 0.10 1.44 2.88 Lantai Kerja
4.80 0.30 20 28.80 Bekesting

SHAARE WALL
2 1.20 1 0.86 1.03 Beton K-275
2.85 0.10 3.42 0.34 Lantai Kerja
8.10 0.30 1 2.43 Bekesting

PEK.KOLOM PEDESTAL
3 3.00 1 0.26 0.79 Beton K-275 (K4)
2.60 3.00 1 7.80 Bekesting

4 6.00 1 0.30 1.79 Beton K-275 (K3)


2.58 6.00 1 15.50 Bekesting

5 6.00 4 0.14 3.36 Beton K-275 (K1)


1.50 6.00 4 36.00 Bekesting

6 4.33 2 0.14 1.21 Beton K-275 (K1)


1.50 4.33 2 12.99 Bekesting

7 3.00 8 0.14 3.36 Beton K-275 (K1)


1.50 3.00 8 36.00 Bekesting

8 6.00 1 0.50 3.00 Beton K-275 (K2)


4.50 6.00 1 27.00 Bekesting

PEK. SLOOF
9 22.20 1 0.03 0.67 Beton K-275 (S2)
0.40 1 8.88 Bekesting

10 84.88 1 0.12 10.19 Beton K-275 (S1)


0.80 1 67.90 Bekesting
24.80 1 0.12 2.98 Beton K-275 (S1)
0.80 1 19.84 Bekesting

PEK. KOLOM UTAMA


11 4.00 18 0.14 10.08 Beton K-275 (K1)
1.50 4.00 18 108.00 Bekesting

12 4.00 1 0.04 0.16 Beton K-275 (K2)


0.80 4.00 1 3.20 Bekesting

13 4.00 1 0.30 1.19 Beton K-275 (K3)


2.58 4.00 1 10.34 Bekesting

14 4.00 1 0.26 1.05 Beton K-275 (K4)


2.60 4.00 1 10.40 Bekesting

15 4.00 1 0.50 2.00 Beton K-275 (K5)


4.50 4.00 1 18.00 Bekesting

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 1

SKETSA GAMBAR

Pek. Pondasi Telapak

P.TELAPAK P.TELAPAK SHEAR WALL


5

Ø12-100 Ø12-150
Ø12-150
35
30
20

Ø12-100
110 Rabat Beton T 10 cm
Urugan Pasir T 5 cm
120

120 285
Ø12-100 43 200 43
Ø12-100

Ø10-150
Ø10-150

48
Ø 12-100
Ø 12-100

Ø10-150
120

120
25
Ø10-150

48
Dia Jarak Panjang Besi Jumlah Total Unit Berat Jumlah Volume
No. Item Pekerjaan Ket
mm m1 A (m1) B (m1) C (m1) D (m1) Kait Batang Panjang (m1) Kg/m1 Bidang Kg

1 P.TELAPAK 16 0.100 0.300 1.100 0.300 1.10 0.14 12 35.28 1.578 20 1113.61 TULANGAN Z
16 0.100 0.300 1.100 0.300 1.10 0.14 12 35.28 1.578 20 1113.61 TULANGAN X

2 P.TELAPAK SHEAR WALL 16 0.150 0.200 2.750 0.200 2.750 0.14 15 90.60 1.578 1 142.99 TULANGAN Z
16 0.150 0.200 2.100 0.200 2.100 0.14 19 91.64 1.578 1 144.63 TULANGAN X

Jumlah Volume Lembar Ini 2514.8


Jumlah Volume Lembar Sebelumnya 0.00
Jumlah Volume Sampai Lembar Ini 2514.8

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 2

SKETSA GAMBAR

Pek. Kolom Pedestal

KOLOM PEDESTAL

(A ) VA R IA S I
40

35
6-D16

30
8-Ø12

Ø8-150 40 (B)40 40

Dia Jarak Panjang Besi Jumlah Total Unit Berat Jumlah Volume
No. Item Pekerjaan Ket
mm m1 A (m1) B (m1) C (m1) D (m1) Kait Batang Panjang (m1) Kg/m1 Bidang Kg

1 KOLOM PEDESTAL (K1) 16 6.000 0.150 0.260 0.14 6 39.30 1.578 4 248.10 TUL. POKOK
12 6.000 0.14 8 49.12 0.888 4 174.43
8 0.150 0.170 0.320 0.170 0.32 0.10 41 44.28 0.395 4 69.88 TUL. BEGEL

2 KOLOM PEDESTAL (K1) 16 4.330 0.150 0.260 0.14 6 29.28 1.578 2 92.42 TUL. POKOK
12 4.330 0.14 8 35.76 0.888 2 63.49
8 0.150 0.170 0.320 0.170 0.32 0.10 30 32.26 0.395 2 25.45 TUL. BEGEL

3 KOLOM PEDESTAL (K1) 16 3.000 0.150 0.260 0.14 6 21.30 1.578 8 268.93 TUL. POKOK
12 3.000 0.14 8 25.12 0.888 8 178.40
8 0.150 0.170 0.320 0.170 0.32 0.10 21 22.68 0.395 8 71.59 TUL. BEGEL

4 KOLOM PEDESTAL (K2) 16 6.000 0.150 0.260 0.14 6 39.30 1.578 1 62.02 TUL. POKOK
12 6.000 0.14 8 49.12 0.888 1 43.61
8 0.150 0.170 0.320 0.170 0.32 0.10 41 44.28 0.395 1 17.47 TUL. BEGEL

5 KOLOM PEDESTAL (K4) 16 3.000 0.150 0.260 0.14 6 21.30 1.578 1 33.62 TUL. POKOK
12 3.000 0.14 8 25.12 0.888 1 22.30
8 0.150 0.170 0.320 0.170 0.32 0.10 21 22.68 0.395 1 8.95 TUL. BEGEL

Jumlah Volume Lembar Ini 1380.67


Jumlah Volume Lembar Sebelumnya 0.00
Jumlah Volume Sampai Lembar Ini 1380.67

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 3

SKETSA GAMBAR

Pek. Kolom Pedestal

KOLOM K3

56

30
KOLOM K2 (SHEAR WALL)
43

28-Ø12
25

Ø8-150

200 KOLOM K4

20-Ø12
Ø8-150

28-Ø12
Ø8-150

Dia Jarak Panjang Besi Jumlah Total Unit Berat Jumlah Volume
No. Item Pekerjaan Ket
mm m1 A (m1) B (m1) C (m1) D (m1) Kait Batang Panjang (m1) Kg/m1 Bidang Kg

1 K2 SHEAR WALL 12 3.000 0.150 0.260 0.14 20 71.00 0.888 1 63.03 TUL. POKOK
8 0.150 1.900 0.150 1.900 0.150 0.10 21 88.20 0.395 1 34.80 TUL. BEGEL

2 PEDESTAL K3 12 6.000 0.150 0.260 0.14 28 183.40 0.888 1 162.82 TUL. POKOK
8 0.150 0.800 0.200 0.980 0.200 0.10 41 93.48 0.395 1 36.88 TUL. BEGEL

3 PEDESTAL K4 12 3.000 0.150 0.260 0.14 28 99.40 0.888 1 88.24 TUL. POKOK
8 0.150 1.100 0.150 0.820 0.150 0.10 21 48.72 0.395 1 19.22 TUL. BEGEL

Jumlah Volume Lembar Ini 405.00


Jumlah Volume Lembar Sebelumnya 1380.67
Jumlah Volume Sampai Lembar Ini 1785.67

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 4

SKETSA GAMBAR

Pek. Sloof Pek. Sloof Beton 30/40

SLOF S2
SLOOF BAWAH SI SLOOF SI
20

40

40
15

30 30
8-Ø12
12-Ø12 12-Ø12
Ø6-150
Ø8-150 Ø8-150

Dia Jarak Panjang Besi Jumlah Total Unit Berat Jumlah Volume
No. Item Pekerjaan Ket
mm m1 A (m1) B (m1) C (m1) D (m1) Kait Batang Panjang (m1) Kg/m1 Bidang Kg

1 SLOF S1 12 22.20 0.16 8 178.89 0.888 1 158.81 TUL. POKOK


8 0.150 0.120 0.170 0.120 0.170 0.10 149 101.33 0.395 1 39.98 TUL. BEGEL

2 SLOF S1 12 84.88 0.16 12 1020.46 0.888 1 905.92 TUL. POKOK


8 0.150 0.230 0.330 0.230 0.330 0.10 567 691.56 0.395 1 272.86 TUL. BEGEL
12 24.80 0.16 12 299.52 0.888 1 265.90 TUL. POKOK
8 0.150 0.230 0.330 0.230 0.330 0.10 166 202.93 0.395 1 80.07 TUL. BEGEL

Jumlah Volume Lembar Ini 1723.54


Jumlah Volume Lembar Sebelumnya 1785.67
Jumlah Volume Sampai Lembar Ini 3509.21

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 5

SKETSA GAMBAR

Pek. Kolom Utama Pek. Kolom Praktis KP 20/20

KOLOM K1 KOLOM K2
40

20
20
35
6-D16

8-Ø12 8-Ø12

Ø8-150 Ø6-150

Dia Jarak Panjang Besi Jumlah Total Unit Berat Jumlah Volume
No. Item Pekerjaan Ket
mm m1 A (m1) B (m1) C (m1) D (m1) Kait Batang Panjang (m1) Kg/m1 Bidang Kg

1 KOLOM K1 16 4.250 0.14 6 26.34 1.578 18 748.28 TUL. POKOK


12 4.250 0.14 8 35.12 0.888 18 561.21
8 0.150 0.170 0.320 0.170 0.32 0.10 29 31.68 0.395 18 224.99 TUL. BEGEL

1 KOLOM K2 12 4.250 0.14 8 35.12 0.888 1 31.18 TUL. POKOK


6 0.150 0.170 0.170 0.170 0.17 0.10 29 22.88 0.222 1 5.08 TUL. BEGEL

Jumlah Volume Lembar Ini 1570.73


Jumlah Volume Lembar Sebelumnya 0.00
Jumlah Volume Sampai Lembar Ini 1570.73

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 6

SKETSA GAMBAR

KOLOM K3

56

30
KOLOM K2 (SHEAR WALL)
43

28-Ø12
25

Ø8-150

200 KOLOM K4

20-Ø12
Ø8-150

28-Ø12
Ø8-150

Dia Jarak Panjang Besi Jumlah Total Unit Berat Jumlah Volume
No. Item Pekerjaan Ket
mm m1 A (m1) B (m1) C (m1) D (m1) Kait Batang Panjang (m1) Kg/m1 Bidang Kg

1 KOLOM K2 SHEAR WALL 12 4.250 0.14 20 87.80 0.888 1 77.95 TUL. POKOK
8 0.150 1.900 0.150 1.900 0.150 0.10 29 123.20 0.395 1 48.61 TUL. BEGEL

2 KOLOM K3 12 4.250 0.14 28 122.92 0.888 1 109.12 TUL. POKOK


8 0.150 0.800 0.200 0.980 0.200 0.10 29 66.88 0.395 1 26.39 TUL. BEGEL

3 KOLOM K4 12 4.250 0.14 28 122.92 0.888 1 109.12 TUL. POKOK


8 0.150 1.100 0.150 0.820 0.150 0.10 29 68.05 0.395 1 26.85 TUL. BEGEL

Jumlah Volume Lembar Ini 398.04


Jumlah Volume Lembar Sebelumnya 1570.73
Jumlah Volume Sampai Lembar Ini 1968.77

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA MC-0
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : B.3 PEKERJAAN BETON
Lembar 1

SKETSA GAMBAR

RING BALOK B1 RING BALOK B2 RING BALOK B3

25
40

35
15
25 20
4-Ø16 4-Ø16

11-Ø12 9-Ø12 12-Ø10

Ø8-150 Ø8-150 Ø6-150

Dia Jarak Panjang Besi Jumlah Total Unit Berat Jumlah Volume
No. Item Pekerjaan Ket
mm m1 A (m1) B (m1) C (m1) D (m1) Kait Batang Panjang (m1) Kg/m1 Bidang Kg

1 BALOK B1 16 4.250 0.14 4 17.56 1.578 18 498.85 TUL. POKOK


12 4.250 0.14 11 48.29 0.888 18 771.66
8 0.150 0.170 0.320 0.170 0.32 0.10 29 31.68 0.395 18 224.99 TUL. BEGEL

Jumlah Volume Lembar Ini 1495.50


Jumlah Volume Lembar Sebelumnya 1968.77
Jumlah Volume Sampai Lembar Ini 3464.28

Disetujui Oleh : Dibuat oleh :


Pejabat Penandatangan Kontrak Penyedia Jasa,
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV.ZHAFIRAH PERSADA
PROVINSI MALUKU UTARA

RIMDANI ALI,ST HASBI HAMISI


NIP: 19800804 200803 1 001 Direktur
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN TULANGAN KOLOM PEDESTAL

Sketsa

KOLOM PEDESTAL

(A) VARIASI
40

35
6-D16
30

8-Ø12

Ø8-150 40 (B)40 40

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
2.00 0.15 13.33 1.10 14.67 17.00 249.33 0.3944 8 98.34

2.00 0.30 2.30 6.00 13.80 7.00 96.60 1.5776 16 152.40

2.00 0.30 2.30 8.00 18.40 7.00 128.80 0.8874 12 114.30

2.55 0.15 17.00 1.10 18.70 5.00 93.50 0.3944 8 36.88

2.55 0.30 2.85 6.00 17.10 5.00 85.50 1.5776 16 134.88

2.55 0.30 2.85 8.00 22.80 5.00 114.00 0.8874 12 101.16

3.25 0.15 21.67 1.10 23.83 1.00 23.83 0.3944 8 9.40

3.25 0.30 3.55 6.00 21.30 1.00 21.30 1.5776 16 33.60

3.25 0.30 3.55 8.00 28.40 1.00 28.40 0.8874 12 25.20

3.75 0.15 25.00 1.10 27.50 1.00 27.50 0.3944 8 10.85

3.75 0.30 4.05 6.00 24.30 1.00 24.30 1.5776 16 38.34

3.75 0.30 4.05 8.00 32.40 1.00 32.40 0.8874 12 28.75

4.75 0.15 31.67 1.10 34.83 3.00 104.50 0.3944 8 41.21

4.75 0.30 5.05 6.00 30.30 3.00 90.90 1.5776 16 143.40

4.75 0.30 5.05 8.00 40.40 3.00 121.20 0.8874 12 107.55


Total Berat 1076.27 Kg
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN KOLOM PEDESTAL

Sketsa

KOLOM PEDESTAL
40

25
35 415
Ø12-200
Ø8-200
470

Ø12-200

6-D16 Ø8-200

8-Ø12
Ø12-150
30

Ø12-150
Rabat Beton T 10 cm

Ø8-150
Urugan Pasir T 5 cm

Volume Total
Panjang Lebar Sisi Tinggi Jumlah KPD Area Keterangan
BH Volume
a b c d e f=(e/c) g = (exf) h
0.40 0.35 2.00 7.00 0.14 0.28 1.96 Beton K-275

1.50 2.00 7.00 3.00 21.00 Bekisting KOLOM PEDESTAL

0.40 0.35 4.70 5.00 0.14 0.66 3.29 Beton K-275

1.50 4.70 5.00 7.05 35.25 Bekisting KOLOM PEDESTAL

0.40 0.35 4.00 1.00 0.14 0.56 0.56 Beton K-275

1.50 4.00 1.00 6.00 6.00 Bekisting KOLOM PEDESTAL

0.40 0.35 3.75 1.00 0.14 0.53 0.53 Beton K-275

1.50 3.75 1.00 5.63 5.63 Bekisting KOLOM PEDESTAL

0.40 0.35 4.75 3.00 0.14 0.67 2.00 Beton K-275

1.50 4.75 3.00 7.13 21.38 Bekisting KOLOM PEDESTAL

2.00 0.20 4.75 3.00 0.40 1.90 5.70 Beton K-275

4.40 4.75 3.00 20.90 62.70 Bekisting KOLOM PEDESTAL

TOTAL VOLUME KOLOM PEDESTAL 7.77 Beton K-275


TOTAL VOLUME KOLOM PEDESTAL 151.95 Bekisting KOLOM PEDESTAL
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN GALIAN PASANGAN BATU

Sketsa

75

155
70

120

Volume Total
Panjang Lebar Sisi Tinggi Jumlah KPD Jumlah Keterangan
BH Volume
a b c d e f=(e/c) g = (exf) h
85.69 0.70 0.80 47.99 GALIAN PONDASI MENERUS

16.00 URUGAN TANAH KEMBALI

URUGAN PASIR PONDASI


85.69 0.70 0.05 3.00
MENERUS

1.20 1.20 1.55 17.00 37.94 GALIAN PONDASI TELAPAK

12.65 URUGAN TANAH KEMBALI

1.20 1.20 0.05 17.00 1.22 URUGAN PASIR PONDASI TELAPAK


BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN PASANGAN BATU

Sketsa

Volume Total
Panjang A B Tinggi AREA Jumlah Keterangan
BH Volume
a b c d e f=(e/c) g = (exf) h
21.98 0.30 0.60 1.55 0.45 0.70 15.33 15.33

33.63 0.30 0.60 0.60 0.45 0.27 9.08 9.08

21.58 0.30 0.60 1.68 0.45 0.75 16.27 16.27

18.00 0.50 1.20 5.00 0.85 4.25 76.50 76.50

15.33 0.30 0.60 4.50 0.45 2.03 31.04 31.04

92.52 0.60 0.20 11.10

18.00 1.20 1.20 25.92

18.00 1.20 0.20 4.32

TOTAL VOLUME PASANGAN BATU 174.14


TOTAL VOLUME PASANGAN BATU kosong 15.42
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN GALIAN PONDASI MENERUS

Sketsa

75
70
Volume Total
Panjang Lebar Sisi Tinggi Panjang Area Keterangan
BH Volume
a b c d e f=(e/c) g = (exf) h
135.00 0.70 0.70 66.15 GALIAN PONDASI

TOTAL VOLUME KOLOM PEDESTAL 66.15 GALIAN PONDASI


BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN TULANGAN PONDASI FOOT PLATE

Sketsa
5
35
30

120 Ø12-150
Ø12-150
120 Rabat Beton T 10 cm
Urugan Pasir T 5 cm
Ø12-100 285
Ø12-100
43 200 43

Ø10-150
Ø10-150
Ø12-100

48
Ø12-100

Ø10-150
120

120
25
Ø10-150

48
Jarak Panjang Total
Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
1.20 0.10 0.20 1.40 12.00 16.80 2.00 33.60 0.8874 12 29.82

1.20 0.10 0.20 1.40 12.00 16.80 2.00 33.60 0.8874 12 29.82

2.00 0.15 0.20 2.20 13.33 29.33 2.00 58.67 0.8874 12 52.06

1.20 0.15 0.20 1.40 8.00 11.20 2.00 22.40 0.8874 12 19.88

2.00 0.15 0.20 2.20 13.33 29.33 2.00 58.67 0.8874 12 104.12

1.20 0.15 0.20 1.40 8.00 11.20 2.00 22.40 0.8874 12 39.76

Total Pondasi Footplate 18.00 Bh


Total Berat 1289.21 Kg
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN TULANGAN SLOOF

Sketsa

SLOOF SI

40

30

12-Ø12

Ø8-150

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
135.00 0.15 0.06 1.20 900.00 1080.00 0.3944 8 425.95 SENGKANG

14.00 105.62 1478.68 0.8874 12 1312.18 TUL POKOK


Total Berat 1738.13 Kg
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN TULANGAN KOLOM

Sketsa

KOLOM K1

40

35
6-D16

8-Ø12

Ø8-150

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
4.00 0.15 0.06 1.20 26.67 32.00 0.3944 8 227.17 SENGKANG

8.00 72.00 576.00 0.8874 12 511.14 TUL POKOK


6.00 76.00 456.00 1.5776 16 719.39 TUL POKOK

4.00 0.15 0.06 4.40 26.67 117.33 0.8874 12 208.24 SENGKANG

4.00 0.15 0.06 4.40 26.67 117.33 0.3944 8 46.28 SENGKANG


Total Berat 1712.22 Kg
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN KOLOM SLOOF

Sketsa

Panjang Volume Total


Panjang Lebar Sisi Tinggi Area Keterangan
Sloof BH Volume
a b c d e f=(e/c) g = (exf) h
0.40 0.30 135.00 0.12 16.20 16.20 Beton K-275

0.80 135.00 108.00 108.00 Bekisting SLOOF S1

TOTAL VOLUME KOLOM PEDESTAL 16.20 Beton K-275


TOTAL VOLUME KOLOM PEDESTAL 108.00 Bekisting KOLOM PEDESTAL
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN TULANGAN KOLOM K1 350X400

Sketsa

KOLOM PEDESTAL

40

35
6-D16

8-Ø12

Ø8-150

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
4.00 0.15 26.67 1.10 29.33 17.00 498.67 0.3944 8 196.67

4.00 0.30 4.30 6.00 25.80 17.00 438.60 1.5776 16 691.94

4.00 0.30 4.30 8.00 34.40 17.00 584.80 0.8874 12 518.95


Total Berat 1407.56 Kg
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN KOLOM K1 350X400

Sketsa

KOLOM K1
40

35
6-D16

8-Ø12

Ø8-150

Volume Total
Panjang Lebar Sisi Tinggi Jumlah KPD Area Keterangan
BH Volume
a b c d e f=(e/c) g = (exf) h
0.40 0.35 4.00 15.00 0.14 0.56 8.40 Beton K-275

1.50 4.00 15.00 6.00 90.00 Bekisting KOLOM K1 350X400

4.00 1.00 0.28 1.12 1.12 Beton K-275

3.00 4.00 1.00 12.00 12.00 Bekisting KOLOM K1 350X400

2.00 0.35 4.00 1.00 0.70 2.80 2.80 Beton K-275

4.70 4.00 1.00 18.80 18.80 Bekisting KOLOM K1 350X400

4.00 1.00 0.27 1.08 1.08 Beton K-275

2.80 4.00 1.00 11.20 11.20 Bekisting KOLOM K1 350X400

TOTAL VOLUME KOLOM PEDESTAL 13.40 Beton K-275


TOTAL VOLUME KOLOM PEDESTAL 132.00 Bekisting KOLOM K1 350X400
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : TULANGAN PLAT LANTAI

Sketsa

SEG M EN 3B
144

121

121
201

SEG M EN 2A

421
SEGM EN 4

SEGM EN 3
V O ID
575

854

SEG M EN 1A

442
SEGMEN 2

1782
822
344

SEGMEN 1

798
504

520

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
7.98 0.15 0.04 8.02 53.20 426.66 2.00 853.33 0.61625 10 525.86 Segmen 1

5.20 0.15 0.04 5.24 34.67 181.65 2.00 363.31 0.61625 10 223.89 Segmen 1

4.40 0.15 0.04 4.44 29.33 130.24 1.00 130.24 0.61625 10 80.26 Segmen 1A

5.20 0.15 0.04 5.24 34.67 181.65 1.00 181.65 0.61625 10 111.94 Segmen 1A

8.22 0.15 0.04 8.26 54.80 452.65 2.00 905.30 0.61625 10 557.89 Segmen 2

5.04 0.15 0.04 5.08 33.60 170.69 2.00 341.38 0.61625 10 210.37 Segmen 2

4.21 0.15 0.04 4.25 28.07 119.28 1.00 119.28 0.61625 10 73.51 Segmen 2A

5.04 0.15 0.04 5.08 33.60 170.69 1.00 170.69 0.61625 10 105.19 Segmen 2A

8.54 0.15 0.04 8.58 56.93 488.49 2.00 976.98 0.61625 10 602.06 Segmen 3

3.44 0.15 0.04 3.48 22.93 79.81 2.00 159.62 0.61625 10 98.36 Segmen 3

1.44 0.15 0.04 1.48 9.60 14.21 1.00 14.21 0.61625 10 8.76 Segmen 3A

1.21 0.15 0.04 1.25 8.07 10.08 1.00 10.08 0.61625 10 6.21 Segmen 3A
5.75 0.15 0.04 5.79 38.33 221.95 2.00 443.90 0.61625 10 273.55 Segmen 4

2.01 0.15 0.04 2.05 13.40 27.47 2.00 54.94 0.61625 10 33.86 Segmen 4

7.70 0.15 0.04 7.74 51.33 397.32 2.00 794.64 0.61625 10 489.70 Segmen 5

1.28 0.15 0.04 1.32 8.53 11.26 2.00 22.53 0.61625 10 13.88 Segmen 5

4.60 0.15 0.04 4.64 30.67 142.29 1.00 142.29 0.61625 10 87.69 Segmen 6

3.68 0.15 0.04 3.72 24.53 91.26 1.00 91.26 0.61625 10 56.24 Segmen 6

2.01 0.15 0.04 2.05 13.40 27.47 1.00 27.47 0.61625 10 16.93 Segmen 7

3.11 0.15 0.04 3.15 20.73 65.31 1.00 65.31 0.61625 10 40.25 Segmen 7
Total Berat 3616.40 Kg
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : TULANGAN KOLOM PEDESTAL SLOOF KOLOM

Sketsa

KOLOM K1

40
25

Ø12-200
Ø8-200

35
415
470

Ø12-200
Ø8-200

6-D16

Ø12-150
8-Ø12
30

Ø12-150
Rabat Beton T 10 cm
Urugan Pasir T 5 cm

Ø8-150

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m

Total Berat 0.00 Kg


BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN RING BALOK BI

Sketsa

RING BALOK B1

40

25

12-Ø12

Ø8-150

Volume Total
Panjang Lebar Sisi Tinggi Panjang Area Keterangan
BH Volume
a b c d e f=(e/c) g = (exf) h
0.40 0.25 125.22 0.10 12.52 12.52 Beton K-275

1.30 125.22 162.79 162.79 Bekisting BALOK

TOTAL VOLUME KOLOM PEDESTAL 12.52 Beton K-275


TOTAL VOLUME KOLOM PEDESTAL 162.79 Bekisting KOLOM PEDESTAL
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN TULANGAN RING BALOK BI

Sketsa

RING BALOK B1

40 25

12-Ø12

Ø8-150

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
125.22 0.15 0.06 1.40 834.80 1168.72 0.3944 8 460.94 SENGKANG

15.00 125.22 1878.30 0.8874 12 1666.80 TUL POKOK


Total Berat 2127.75 Kg
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN
INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN RING BALOK B2

Sketsa

RING BALOK B2
35

20

12-Ø12

Ø8-150

Volume Total
Panjang Lebar Sisi Tinggi Panjang Area Keterangan
BH Volume
a b c d e f=(e/c) g = (exf) h
0.40 0.25 125.22 0.10 12.52 12.52 Beton K-275

1.30 125.22 162.79 162.79 Bekisting BALOK

TOTAL VOLUME KOLOM PEDESTAL 12.52 Beton K-275


TOTAL VOLUME KOLOM PEDESTAL 162.79 Bekisting KOLOM PEDESTAL
BACK UP DATA
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
ITEM PEKERJAAN : PEKRJAAN TULANGAN RING BALOK B2

Sketsa

Jarak Panjang Total


Panjang Lebar Kait Besi Jumlah Panjang Lapisan Bj Dia Total Berat Keterangan
Tulangan Besi Panjang
a b c d e = (a+d) f=(e/c) g = (exf) h I =(gxh) j k l=(ixj) m
125.22 0.15 0.06 1.40 834.80 1168.72 0.3944 8 460.94 SENGKANG

15.00 125.22 1878.30 0.8874 12 1666.80 TUL POKOK


Total Berat 2127.75 Kg
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
Lembar 1

BAC UP DATA
SKET GAMBAR

175.3990

GRAFIK PERHITUNGAN
1. PELAT LANTAI No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 17.90 0.00
20.00
2 17.90 4.18 74.84 0.00
18.00 17.82 17.82
17.82 17.82 3 12.86 4.18 74.84 53.77
16.00 4 12.86 8.07 103.78 53.77
14.00 5 7.88 8.07 103.78 63.58
12.00 11.94 11.94 6 7.88 9.71 76.57 63.58
Y(EL)

10.00 9.71 9.71


9.71 9.71
7 5.85 9.71 76.57 56.83
8.00 8.07 8.07 8.07 8.07 7.98 7.98 8 2.90 11.94 69.87 28.16
6.00
9 7.87 17.82 51.66 94.04
4.18 4.18 4.18 4.18
10 11.48 17.82 140.34 204.52
4.00
11 23.11 7.98 91.58 411.92
2.00
12 23.11 0.00 0.00 184.44
0.00 0.00 0.00 0.00 0.00
0.00 5.00 10.00 15.00 20.00 25.00
13 17.90 0.00 0.00 0.00
1 17.90 0.00
X(DIST)
TOTAL 863.82 1214.62
TOTAL AREA (M2) 0.000

2. VOID No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1


1 1.00 -9.45
0.00 0.00 0.00 2 1.00 0.00 0.00 -9.45
-1.00 3 2.40 0.00 0.00 0.00
-2.00
4 2.40 -9.45 (22.68) 0.00
5 1.00 -9.45 (22.68) -9.45
-3.00
1 1.00 -9.45
-4.00
Y(EL)

-5.00
-6.00
-7.00
-8.00
-9.00
-9.45 -9.45
-10.00
0.80 1.00 1.20 1.40 1.60 1.80 2.00 2.20 2.40 2.60

X(DIST)
TOTAL (45.36) -18.90
TOTAL AREA (M2) 0.000

JUMLAH TOTAL AREA (M2) 0.000


Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
KEGIATAN Direksi: Lapangan Konsultan
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR Supervisi
KAWASAN Kontraktor
PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSIPelaksana
PEKERJAAN : PEMBANGUNAN
PPK 1.4 Provinsi MASJID ALI AKBAR TABONAPT.
Maluku Utara TRIBINA MATRA KARYA
TERNATE PT. BULI BANGUN
LOKASI : KOTA TERNATE-MALUKU UTARA CIPTA,PT.MEGACOTAMA LINO
TAHUN ANGGARAN : 2022 RAYA,PT.ARISTA CIPTA Kso.
Lembar 2

Ode Saimin PERHITUNGAN VOLUME


Munajat Tilli,ST Mohammad Wan Halik,ST
NIP: 198203152008011016 Quantity Engineer Managger Pelaksana
NO PANJANG (M') LEBAR (M') TINGGI (M') AREA (M2) VOLUME (M3) KET

1 0.12 0.00 0.00 PELAT LANTAI

JUMLAH TOTAL VOLUME 0.000


KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
Lembar 1

BAC UP DATA
SKET GAMBAR

175.3990

GRAFIK PERHITUNGAN
1. PELAT LANTAI No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 17.90 0.00
20.00
2 17.90 4.18 74.84 0.00
18.00 17.82 17.82
17.82 17.82 3 12.86 4.18 74.84 53.77
16.00 4 12.86 8.07 103.78 53.77
14.00 5 7.88 8.07 103.78 63.58
12.00 11.94 11.94 6 7.88 9.71 76.57 63.58
Y(EL)

10.00 9.71 9.71


9.71 9.71
7 5.85 9.71 76.57 56.83
8.00 8.07 8.07 8.07 8.07 7.98 7.98 8 2.90 11.94 69.87 28.16
6.00
9 7.87 17.82 51.66 94.04
4.18 4.18 4.18 4.18
10 11.48 17.82 140.34 204.52
4.00
11 23.11 7.98 91.58 411.92
2.00
12 23.11 0.00 0.00 184.44
0.00 0.00 0.00 0.00 0.00
0.00 5.00 10.00 15.00 20.00 25.00
13 17.90 0.00 0.00 0.00
1 17.90 0.00
X(DIST)
TOTAL 863.82 1214.62
TOTAL AREA (M2) 0.000

JUMLAH TOTAL AREA (M2) 0.000


Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
KEGIATAN Direksi: Lapangan Konsultan
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR Supervisi
KAWASAN Kontraktor
PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSIPelaksana
PEKERJAAN : PEMBANGUNAN
PPK 1.4 Provinsi MASJID ALI AKBAR TABONAPT.
Maluku Utara TRIBINA MATRA KARYA
TERNATE PT. BULI BANGUN
LOKASI : KOTA TERNATE-MALUKU UTARA CIPTA,PT.MEGACOTAMA LINO
TAHUN ANGGARAN : 2022 RAYA,PT.ARISTA CIPTA Kso.
Lembar 2

Ode Saimin PERHITUNGAN VOLUME


Munajat Tilli,ST Mohammad Wan Halik,ST
NIP: 198203152008011016 Quantity Engineer Managger Pelaksana
NO PANJANG (M') LEBAR (M') TINGGI (M') AREA (M2) VOLUME (M3) KET

1 0.05 0.00 0.00 RABAT BETON

JUMLAH TOTAL VOLUME 0.000


KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
Lembar 1

BAC UP DATA
SKET GAMBAR

175.3990

GRAFIK PERHITUNGAN
1. PELAT LANTAI No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 17.90 0.00
20.00
2 17.90 4.18 74.84 0.00
18.00 17.82 17.82
17.82 17.82 3 12.86 4.18 74.84 53.77
16.00 4 12.86 8.07 103.78 53.77
14.00 5 7.88 8.07 103.78 63.58
12.00 11.94 11.94 6 7.88 9.71 76.57 63.58
Y(EL)

10.00 9.71 9.71


9.71 9.71
7 5.85 9.71 76.57 56.83
8.00 8.07 8.07 8.07 8.07 7.98 7.98 8 2.90 11.94 69.87 28.16
6.00
9 7.87 17.82 51.66 94.04
4.18 4.18 4.18 4.18
10 11.48 17.82 140.34 204.52
4.00
11 23.11 7.98 91.58 411.92
2.00
12 23.11 0.00 0.00 184.44
0.00 0.00 0.00 0.00 0.00
0.00 5.00 10.00 15.00 20.00 25.00
13 17.90 0.00 0.00 0.00
1 17.90 0.00
X(DIST)
TOTAL 863.82 1214.62
TOTAL AREA (M2) 0.000

JUMLAH TOTAL AREA (M2) 0.000


Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :
KEGIATAN Direksi: Lapangan Konsultan
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR Supervisi
KAWASAN Kontraktor
PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSIPelaksana
PEKERJAAN : PEMBANGUNAN
PPK 1.4 Provinsi MASJID ALI AKBAR TABONAPT.
Maluku Utara TRIBINA MATRA KARYA
TERNATE PT. BULI BANGUN
LOKASI : KOTA TERNATE-MALUKU UTARA CIPTA,PT.MEGACOTAMA LINO
TAHUN ANGGARAN : 2022 RAYA,PT.ARISTA CIPTA Kso.
Lembar 2

Ode Saimin PERHITUNGAN VOLUME


Munajat Tilli,ST Mohammad Wan Halik,ST
NIP: 198203152008011016 Quantity Engineer Managger Pelaksana
NO PANJANG (M') LEBAR (M') TINGGI (M') AREA (M2) VOLUME (M3) KET

1 1.59 0.00 0.00 URUGAN PASIR

0.1 0.00 0.00

JUMLAH TOTAL VOLUME 0.000


KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
Lembar 1

BAC UP DATA
SKET GAMBAR

175.3990

GRAFIK PERHITUNGAN
1. PELAT LANTAI No X(DIST) Y(EL) Xn*Yn+1 Yn*Xn-1 VOLUME (M2)
1 17.90 0.00
20.00
2 17.90 4.18 74.84 0.00
18.00 17.82 17.82
17.82 17.82 3 12.86 4.18 74.84 53.77
16.00 4 12.86 8.07 103.78 53.77
14.00 5 7.88 8.07 103.78 63.58
12.00 11.94 11.94 6 7.88 9.71 76.57 63.58
Y(EL)

10.00 9.71 9.71


9.71 9.71
7 5.85 9.71 76.57 56.83
8.00 8.07 8.07 8.07 8.07 7.98 7.98 8 2.90 11.94 69.87 28.16
6.00
9 7.87 17.82 51.66 94.04
4.18 4.18 4.18 4.18
10 11.48 17.82 140.34 204.52
4.00
11 23.11 7.98 91.58 411.92
2.00
12 23.11 0.00 0.00 184.44
0.00 0.00 0.00 0.00 0.00
0.00 5.00 10.00 15.00 20.00 25.00
13 17.90 0.00 0.00 0.00
1 17.90 0.00
X(DIST)
TOTAL 863.82 1214.62
TOTAL AREA (M2) 0.000

JUMLAH TOTAL AREA lenclering (M2) 0.000


BACK UP DATA
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

STA DIMENSI/LEBAR TINGGI PANJANG LUAS UNIT VOLUME


NO URAIAN PEKERJAAN
(M) ATAS BAWAH RERATA (M) (M) (M2) (BH) (M3/M2)

1 Pek. Pondasi Telapak 1 0.4 1.00 1.00 17.00 6.80


Bekesting 1 0.4 1.00 1.60 17.00 27.20
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot x 17 Volume
Arah memanjang Dia.16 2.6 7 18.2 1.58 28.756 488.852 977.704
Arah melintang Dia.16 2.6 7 18.2 1.58 28.756 488.852
2 Pek. Kolom Pedestal 0.3 1.65 0.3 0.1485 17 2.5245
Bekesting 0.3 1.65 0.3 1.98 17 33.66
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot x 17 Volume
Arah memanjang Dia.16 1.65 12 19.8 1.58 31.284 531.828 626.637
Beugel Dia.8 1.3 11 14.3 0.39 5.577 94.809
3 Pek. Kolom Praktis 0.15 3.65 0.15 0.082125 8 0.657
Bekesting 0.15 3.65 0.15 2.19 8 17.52
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot x8 Volume
Arah memanjang Dia.10 3.65 4 14.6 0.616 8.9936 71.9488 117.5008
Beugel Dia.8 0.6 24.333333 14.6 0.39 5.694 45.552

4 Kusen Pintu Alluminium Tinggi Lebar Total P Total L Unit 37.08


PJ1 3 5.64 15 11.28 1 26.28
P2 2.2 1 4.4 1 1 5.4
P3 2.2 1 4.4 1 1 5.4

5 Kusen Jendela Alluminium Tinggi Lebar Total P Total L Unit 75.76


J1 3 4.64 12 13.92 2 51.84
J2 1 5.5 2 11 1 13
J3 1 3.46 4 6.92 1 10.92

6 Kusen Ventilasi Alluminium Tinggi Lebar Total P Total L Unit 2.72


V1 0.76 0.6 1.52 1.2 1 2.72

7 Pintu Kaca Tempered Tinggi Lebar Luas Unit M2


3 5.64 16.92 1 16.92
8 Jendela Kaca Tinggi Lebar Luas Unit M2
J1 3 4.64 13.92 2 27.84
9 Ventilasi Kaca Tinggi Lebar Luas Unit M2
V1 0.76 0.6 0.456 1 0.456

10 Dinding Bata Tela Press 3.55 32.42 115.091

11 Keramik 60/60 Dimensi Luas(m2) Tinggi Volume Unit Tot Vol


7.97 4.82 38.4154 150.19865
5.1 3.89 19.839
9.67 5 48.35
10.15 8.59 43.59425
Total = 150.19865
B LANTAI II
1 Balok B1 25/40 Panjang Lebar Tinggi Luas Volume
Beton K-275 99.5 0.25 0.4 24.875 9.95
Bekesting 99.5 1.05 104.475 104.475
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot Volume
Dia.14 99.5 4 398 1.58 628.84 1319.37
Dia.12 99.5 4 398 0.89 354.22
Dia.8 1.3 663.33333 862.33333 0.39 336.31
2 Balok B2 20/35 Panjang Lebar Tinggi Luas Volume
Beton K-275 65 0.2 0.35 13 4.55
Bekesting 65 0.9 58.5 58.5
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot Volume
Dia.14 65 4 260 1.58 410.8 712.4
Dia.12 65 2 130 0.89 115.7
Dia.8 1.1 433.33333 476.66667 0.39 185.9
3 Balok Anak 15/25 Panjang Lebar Tinggi Luas Volume
Beton K-275 60 0.15 0.25 9 2.25
Bekesting 60 0.65 39 39
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot Volume
Dia.14 60 4 240 1.58 379.2 577.92
Dia.10 60 2 120 0.616 73.92
Dia.8 0.8 400 320 0.39 124.8

4 Kolom Utama K1 30/30 Dimensi Luas(m2) Tinggi Volume Unit Tot Vol
Beton K-275 0.3 0.3 0.09 3.65 0.3285 17 5.5845
Bekesting 0.3 0.3 1.2 3.65 4.38 17 74.46
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot Volume
Dia.14 3.65 6 21.9 1.58 34.602
Dia.12 3.65 2 7.3 0.89 6.497
Dia.8 1.2 24.333333 29.2 0.39 11.388
Total = 52.487 17 892.279
5 Kolom Praktis 15/15 Dimensi Luas(m2) Tinggi Volume Unit Tot Vol
Beton K-275 0.15 0.15 0.0225 3.65 0.082125 8 0.657
Bekesting 0.15 0.15 0.6 3.65 2.19 8 17.52
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot Volume
Dia. 10 3.65 4 14.6 0.616 8.9936
Dia. 8 0.6 24.333333 14.6 0.39 5.694
Total = 14.6876 8 117.5008
6 Pelat Lantai Dimensi Luas(m2) Tinggi Volume Unit Tot Vol
Beton K-275 7.99 5.21 0.12 4.995348 22.710924
5.05 3.89 0.12 2.35734
9.85 5 0.12 5.91
a t b Luas(m2) Tebal Plat
1.31 7.71 7.59 34.3095 0.12 4.11714
Segitiga 10.26 8.66 0.12 44.4258 5.331096
Bekesting 7.99 5.21 41.6279
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot Volume
Memanjang Dia.12 15.85 64.333333 1019.6833 0.89 1815.04
Melintang Dia.12 9.65 105.66667 1019.6833 0.89 1815.04
Total = 3630.072667 3630.0727
7 Pelat Atap Dimensi Luas(m2) Tinggi Volume Unit Tot Vol
Beton K-275 7.97 4.82 0.12 38.4154 4.609848 18.023838
5.1 3.89 0.12 19.839 2.38068
9.67 5 0.12 48.35 5.802
Segitiga 10.15 8.59 0.12 43.59425 5.23131
Total = 18.023838
Bekesting 150.19865
Besi Beton Panjang Jum.Tul P.Tot Berat/m Berat Tot Volume
Memanjang Dia. 12 21 38.55 809.55 0.89 720.4995
Melintang Dia.12 7.71 105 809.55 0.89 720.4995
Total = 1440.999 1440.999

8 Kusen Pintu Alluminium Tinggi Lebar Total P Total L Unit 81.16

P2 2.2 1 4.4 1 1 5.4


9 Kusen Jendela Alluminium Tinggi Lebar Total P Total L Unit 75.76
J1 3 4.64 12 13.92 2 51.84
J2 1 5.5 2 11 1 13
J3 1 3.46 4 6.92 1 10.92
10 Kusen Ventilasi Alluminium Tinggi Lebar Total P Total L Unit 2.72
V1 0.76 0.6 1.52 1.2 1 2.72
11 Jendela Kaca Tinggi Lebar Luas Unit M2
J1 3 4.64 13.92 2 27.84
J2 1 5.5 5.5 1 5.5
J3 1 3.46 3.46 1 3.46
Total = 36.8
12 Ventilasi Kaca Tinggi Lebar Luas Unit M2
V1 0.76 0.6 0.456 1 0.456
13 Plafond Lt 2 Dimensi Luas(m2) Tinggi Volume Unit Tot Vol
Rangka Plafond Hollow 7.97 4.82 38.4154 150.19865
5.1 3.89 19.839
9.67 5 48.35
10.15 8.59 43.59425
Total = 150.19865
List Plafond Gypsum 32.89 22.3 110.38
SKETSA/GAMBAR KERJA
REKAPITULASI

PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI


KEGIATAN :
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

JUMLAH HARGA
NO URAIAN PEKERJAAN
(Rp)
1 2 3

A PEKERJAAN PERSIAPAN 45,468,282.80

B PEKERJAAN LANTAI I 462,421,050.27


B.1 PEKERJAAN TANAH DAN PASIR 19,720,598.18

B.2 PEKERJAAN PASANGAN BATU 42,975,656.96

B.3 PEKERJAAN BETON 244,406,258.62

B.4 PEKERJAAN LANTAI DAN DINDING 105,792,868.60

B.5 PEKERJAAN PINTU DAN JENDELA 29,689,790.76

B.6 PEKERJAAN INSTALASI LISTRIK 15,955,974.00

B.7 PEKERJAAN PENGECATAN 3,879,903.15

C PEKERJAAN LANTAI II 257,380,666.93


C.1 PEKERJAAN BETON 257,380,666.93

JUMLAH TOTAL 765,270,000.00


PPN 11% 84,179,700.00
JUMLAH 849,449,700.00
PEMBULATAN 849,449,700.00

Terbilang : Delapan Ratus Empat Puluh Sembilan Juta Empat Ratus Empat Puluh Sembilan Ribu Tuju Ratus Rupiah
###
###
###

Ternate,07 Juli 2022 ###


Penawar : ###
CV.ZHAFIRAH PERSADA

TTD ###

HASBI HAMISI
Direktur
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

VOLUME SATUAN HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN
(Rp) (Rp)
1 2 3 4 5 6
A PEKERJAAN PERSIAPAN
1 Mobilisasi Dan Demobilisasi Peralatan Dan Pekerja 1.00 LS 5,000,000.00 5,000,000.00
2 Pembuatan Direksi Keet 1.00 LS 5,000,000.00 5,000,000.00
3 Air Kerja dan Penerangan 1.00 LS 4,000,000.00 4,000,000.00
4 Kesehatan dan Keselamatan Kerja (K3) 1.00 LS 10,000,000.00 10,000,000.00
5 Papan Nama Proyek 1.00 LS 500,000.00 500,000.00
6 Shop Drawing dan Asbuilt Drawing 1.00 LS 7,000,000.00 7,000,000.00
7 Laporan, Back Up Data, Dokumentasi 1.00 LS 7,000,000.00 7,000,000.00
8 Pembersihan Akhir 1.00 LS 6,968,282.80 6,968,282.80
JUMLAH PEKERJAAN A 45,468,282.80
B PEKERJAAN LANTAI I
B.1 PEKERJAAN TANAH DAN PASIR
1 Galian Tanah Pondasi Telapak 30.86 M3 109,480.00 3,378,552.80
2 Galian Tanah Pondasi Menerus 57.19 M3 109,480.00 6,261,161.20
3 Urugan Kembali Pondasi Telapak 7.71 M3 36,413.60 280,748.86
4 Urugan Kembali Pondasi Menerus 14.30 M3 36,413.60 520,714.48
5 Urugan Pilihan Dibawah Lantai Bangunan 48.49 M3 179,860.00 8,721,411.40
6 Urugan Pasir Dibawah Pondasi 2.12 M3 263,212.00 558,009.44
JUMLAH PEKERJAAN B.1 19,720,598.18
B.2 PEKERJAAN PASANGAN BATU
1 Pek. Pasangan Batu Kosong 11.33 M3 457,777.05 5,186,613.98
2 Pek. Pasangan Batu Belah Camp. 1 : 4 35.41 M3 1,067,185.63 37,789,042.98
JUMLAH PEKERJAAN B.2 42,975,656.96
B.3 PEKERJAAN BETON
1 Pek. Lantai Kerja Beton 1 : 3 : 5 1.03 M3 847,799.76 873,233.75
2 Pek. Lantai Rabbat Beton 1 : 3 : 5 8.98 M3 847,799.76 7,613,241.80
3 Pek. Pondasi Telapak
Beton K-275 6.80 M3 1,914,622.37 13,019,432.10
Bekesting 27.20 M2 270,491.50 7,357,368.80
Besi Beton 977.70 Kg 33,034.02 32,297,365.02
4 Pek. Kolom Pedestal
Beton K-275 2.52 M3 1,914,622.37 4,824,848.37
Bekesting 33.66 M2 333,997.95 11,242,371.00
Besi Beton 626.64 Kg 33,034.02 20,700,440.64
5 Pek. Sloof
Beton K-275 2.49 M3 1,914,622.37 4,767,409.70
Bekesting 33.20 M2 270,491.50 8,980,317.80
Besi Beton 823.24 Kg 33,034.02 27,194,929.71
6 Pek. Kolom Utama
Beton K-275 6.24 M3 1,914,622.37 11,947,243.58
Bekesting 103.66 M2 333,997.95 34,622,227.50
Besi Beton 1,452.11 Kg 33,034.02 47,969,036.23
7 Pek. Kolom Praktis KP 20/20
Beton K-275 0.66 M3 1,914,622.37 1,263,650.76
Bekesting 17.52 M2 333,997.95 5,851,644.08
Besi Beton 117.50 Kg 33,034.02 3,881,497.79
JUMLAH PEKERJAAN B.3 244,406,258.62
B.4 PEKERJAAN LANTAI DAN DINDING
1 Pek. Pasangan Dinding Bata Tela Press 1 : 4 115.09 M2 192,695.44 22,177,317.90
2 Pek. Plesteran Dinding 1 : 4 115.09 M2 100,519.20 11,568,754.73
3 Pek. Acian 115.09 M2 57,740.42 6,645,345.15
4 Pek. Keramik Lantai 60 x 60 cm 150.20 M2 435,429.10 65,401,450.82
JUMLAH PEKERJAAN B.4 105,792,868.60
B.5 PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Alluminium 37.08 M' 256,921.00 9,526,630.68
2 Pek. Kusen Jendela Alluminium 75.76 M' 256,921.00 19,464,334.96
3 Pek. Kusen Ventilasi Alluminium 2.72 M' 256,921.00 698,825.12
JUMLAH PEKERJAAN B.5 29,689,790.76
B.6 PEKERJAAN INSTALASI LISTRIK
1 Pek. MCB 16A 2.00 BH 152,225.50 304,451.00
2 Pek. Instalasi Kabel NYM 3x2,5mm 100.00 M' 34,925.50 3,492,550.00
3 Pek. Instalasi Kabel NYM 2x2,5mm 100.00 M' 34,695.50 3,469,550.00
4 Pek. Saklar Seri Panasonic 30.00 BH 74,370.50 2,231,115.00
5 Pek. Saklar Tunggal Panasonic 6.00 BH 70,891.75 425,350.50
6 Pek. Stop Kontak Tanam Panasonic 20.00 BH 81,328.00 1,626,560.00
7 Stop Kontak Tanam AC Panasonic 10.00 BH 60,225.50 602,255.00
8 Lampu Balon Philips LED 11 Watt 15.00 BH 88,975.50 1,334,632.50
9 Lampu Balon Philips LED 25 Watt 20.00 BH 123,475.50 2,469,510.00
JUMLAH PEKERJAAN B.6 15,955,974.00
B.7 PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding 115.09 M2 33,711.91 3,879,903.15
JUMLAH PEKERJAAN B.7 3,879,903.15
C PEKERJAAN LANTAI II
C.1 PEKERJAAN BETON
1 Pek. Balok B1 25/40
Beton K-275 9.95 M3 1,914,622.37 19,050,492.56
Bekesting 104.48 M2 342,277.95 35,761,200.22
Besi Beton 1,319.37 Kg 33,034.02 43,584,099.92
2 Pek. Balok B2 20/35
Beton K-275 4.55 M3 1,914,622.37 8,711,531.77
Bekesting 58.50 M2 342,277.95 20,023,260.08
Besi Beton 712.40 Kg 33,034.02 23,533,438.52
3 Pek. Balok Anak Ba 15/25
Beton K-275 2.25 M3 1,914,622.37 4,307,900.33
Bekesting 39.00 M2 342,277.95 13,348,840.05
Besi Beton 577.92 Kg 33,034.02 19,091,023.01
4 Pek. Pelat Lantai
Beton K-275 22.71 M3 1,914,622.37 43,481,073.97
Bekesting 41.63 M2 342,277.95 14,249,031.06
Besi Beton 370.49 Kg 33,034.02 12,238,775.46
JUMLAH PEKERJAAN C.1 257,380,666.93
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN
KEGIATAN :
STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6
A PEKERJAAN PERSIAPAN
1 Mobilisasi Dan Demobilisasi Peralatan Dan Pekerja 1.00 LS 5,000,000.00 5,000,000.00
2 Pembuatan Direksi Keet 1.00 LS 5,000,000.00 5,000,000.00
3 Air Kerja dan Penerangan 1.00 LS 4,000,000.00 4,000,000.00
4 Kesehatan dan Keselamatan Kerja (K3) 1.00 LS 10,000,000.00 10,000,000.00
5 Papan Nama Proyek 1.00 LS 500,000.00 500,000.00
6 Shop Drawing dan Asbuilt Drawing 1.00 LS 7,000,000.00 7,000,000.00
7 Laporan, Back Up Data, Dokumentasi 1.00 LS 7,000,000.00 7,000,000.00
8 Pembersihan Akhir 1.00 LS 6,968,282.80 6,968,282.80
JUMLAH PEKERJAAN A 45,468,282.80
B PEKERJAAN LANTAI I
B.1 PEKERJAAN TANAH DAN PASIR
1 Galian Tanah Pondasi Telapak 30.86 M3 109,480.00 3,378,552.80
2 Galian Tanah Pondasi Menerus 57.19 M3 109,480.00 6,261,161.20
3 Urugan Kembali Pondasi Telapak 7.71 M3 36,413.60 280,748.86
4 Urugan Kembali Pondasi Menerus 14.30 M3 36,413.60 520,714.48
5 Urugan Pilihan Dibawah Lantai Bangunan 48.49 M3 179,860.00 8,721,411.40
6 Urugan Pasir Dibawah Pondasi 2.12 M3 263,212.00 558,009.44
JUMLAH PEKERJAAN B.1 19,720,598.18
B.2 PEKERJAAN PASANGAN BATU
1 Pek. Pasangan Batu Kosong 11.33 M3 457,777.05 5,186,613.98
2 Pek. Pasangan Batu Belah Camp. 1 : 4 35.41 M3 1,067,185.63 37,789,042.98
JUMLAH PEKERJAAN B.2 42,975,656.96
B.3 PEKERJAAN BETON
1 Pek. Lantai Kerja Beton 1 : 3 : 5 1.03 M3 847,799.76 873,233.75
2 Pek. Lantai Rabbat Beton 1 : 3 : 5 8.98 M3 847,799.76 7,613,241.80
3 Pek. Pondasi Telapak
Beton K-275 6.80 M3 1,914,622.37 13,019,432.10
Bekesting 27.20 M2 270,491.50 7,357,368.80
Besi Beton 977.70 Kg 33,034.02 32,297,365.02
4 Pek. Kolom Pedestal
Beton K-275 2.52 M3 1,914,622.37 4,824,848.37
Bekesting 33.66 M2 333,997.95 11,242,371.00
Besi Beton 626.64 Kg 33,034.02 20,700,440.64
5 Pek. Sloof Beton 15/25
Beton K-275 2.49 M3 1,914,622.37 4,767,409.70
Bekesting 33.20 M2 270,491.50 8,980,317.80
Besi Beton 823.24 Kg 33,034.02 27,194,929.71
6 Pek. Kolom Utama K1 30/30
Beton K-275 6.24 M3 1,914,622.37 11,947,243.58
Bekesting 103.66 M2 333,997.95 34,622,227.50
Besi Beton 1,452.11 Kg 33,034.02 47,969,036.23
7 Pek. Kolom Praktis KP 15/15
Beton K-275 0.66 M3 1,914,622.37 1,263,650.76
Bekesting 17.52 M2 333,997.95 5,851,644.08
Besi Beton 117.50 Kg 33,034.02 3,881,497.79
JUMLAH PEKERJAAN B.3 244,406,258.62
B.4 PEKERJAAN LANTAI DAN DINDING
1 Pek. Pasangan Dinding Bata Tela Press 1 : 4 115.09 M2 192,695.44 22,177,317.90
2 Pek. Plesteran Dinding 1 : 4 115.09 M2 100,519.20 11,568,754.73
3 Pek. Acian 115.09 M2 57,740.42 6,645,345.15
4 Pek. Keramik Lantai 60 x 60 cm 150.20 M2 435,429.10 65,401,450.82
JUMLAH PEKERJAAN B.4 105,792,868.60
B.5 PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Alluminium 37.08 M' 256,921.00 9,526,630.68
2 Pek. Kusen Jendela Alluminium 75.76 M' 256,921.00 19,464,334.96
3 Pek. Kusen Ventilasi Alluminium 2.72 M' 256,921.00 698,825.12
JUMLAH PEKERJAAN B.5 29,689,790.76
B.6 PEKERJAAN INSTALASI LISTRIK
1 Pek. MCB 16A 2.00 BH 152,225.50 304,451.00
2 Pek. Instalasi Kabel NYM 3x2,5mm 100.00 M' 34,925.50 3,492,550.00
3 Pek. Instalasi Kabel NYM 2x2,5mm 100.00 M' 34,695.50 3,469,550.00
4 Pek. Saklar Seri Panasonic 30.00 BH 74,370.50 2,231,115.00
5 Pek. Saklar Tunggal Panasonic 6.00 BH 70,891.75 425,350.50
6 Pek. Stop Kontak Tanam Panasonic 20.00 BH 81,328.00 1,626,560.00
7 Stop Kontak Tanam AC Panasonic 10.00 BH 60,225.50 602,255.00
8 Lampu Balon Philips LED 11 Watt 15.00 BH 88,975.50 1,334,632.50
9 Lampu Balon Philips LED 25 Watt 20.00 BH 123,475.50 2,469,510.00
JUMLAH PEKERJAAN B.6 15,955,974.00
B.7 PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding 115.09 M2 33,711.91 3,879,903.15

JUMLAH PEKERJAAN B.7 3,879,903.15


C PEKERJAAN LANTAI II
C.1 PEKERJAAN BETON
1 Pek. Balok B1 25/40
Beton K-275 9.95 M3 1,914,622.37 19,050,492.56
Bekesting 104.48 M2 342,277.95 35,761,200.22
Besi Beton 1,319.37 Kg 33,034.02 43,584,099.92
2 Pek. Balok B2 20/35
Beton K-275 4.55 M3 1,914,622.37 8,711,531.77
Bekesting 58.50 M2 342,277.95 20,023,260.08
Besi Beton 712.40 Kg 33,034.02 23,533,438.52
3 Pek. Balok Anak Ba 15/25
Beton K-275 2.25 M3 1,914,622.37 4,307,900.33
Bekesting 39.00 M2 342,277.95 13,348,840.05
Besi Beton 577.92 Kg 33,034.02 19,091,023.01
4 Pek. Pelat Lantai
Beton K-275 22.71 M3 1,914,622.37 43,481,073.97
Bekesting 41.63 M2 342,277.95 14,249,031.06
Besi Beton 370.49 Kg 33,034.02 12,238,775.46

JUMLAH PEKERJAAN C.1 257,380,666.93


ANALISA HARGA SATUAN

KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 GALIAN TANAH BIASA (M3)


A. UPAH
1 Pekerja 0.7500 Oh Rp 120,000.00 Rp 90,000.00
2 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 95,200.00

2 URUG KEMBALI TANAH GALIAN (M3)


A. UPAH
1 Pekerja 0.2500 Oh Rp 120,000.00 Rp 30,000.00
2 Mandor 0.0080 Oh Rp 208,000.00 Rp 1,664.00
JUMLAH Rp 31,664.00

3 URUGAN PASIR URUG BAWAH PONDASI DAN LANTAI (M3)


A. BAHAN
1 Pasir Urug 1.2000 M3 Rp 159,000.00 Rp 190,800.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 228,880.00

URUGAN AGGREGAT KLS C (SIRTU/KALI) (M3)


A. BAHAN
1 Aggregat Kls C (Sirtu/Kali) 1.2000 M3 Rp - Rp -
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 38,080.00

4 PASANGAN BATU KOSONG (M3)


A. BAHAN
1 Batu Kali/Gunung 1.2000 M3 Rp 144,000.00 Rp 172,800.00
2 Pasir Urug 0.3000 M3 Rp 159,000.00 Rp 47,700.00
B. UPAH
1 Pekerja 0.7800 Oh Rp 120,000.00 Rp 93,600.00
2 Kapala Tukang 0.0390 Oh Rp 208,000.00 Rp 8,112.00
3 Mandor 0.0390 Oh Rp 208,000.00 Rp 8,112.00
4 Tukang Batu 0.3900 Oh Rp 173,700.00 Rp 67,743.00
JUMLAH Rp 398,067.00
5 PEK. PASANGAN BATU KALI 1 : 4 (M3)
A. BAHAN
1 Batu Kali/Gunung 1.2000 M3 Rp 144,000.00 Rp 172,800.00
2 Semen Portland 3.2600 Zak Rp 71,875.00 Rp 234,312.50
3 Pasir Pasang 0.5200 M3 Rp 345,000.00 Rp 179,400.00
B. UPAH
1 Pekerja 1.5000 Oh Rp 120,000.00 Rp 180,000.00
2 Tukang Batu 0.7500 Oh Rp 173,700.00 Rp 130,275.00
3 Kepala Tukang 0.0750 Oh Rp 208,000.00 Rp 15,600.00
4 Mandor 0.0750 Oh Rp 208,000.00 Rp 15,600.00
JUMLAH Rp 927,987.50

6 TIMBUNAN TANAH DI BAWAH LANTAI (M3)


A. BAHAN
1 Timbunan Tanah 1.2000 M3 Rp 101,000.00 Rp 121,200.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 159,280.00

7 LANTAI KERJA BETON TUMBUK 1 : 3 : 5 ; T. 5 CM (M3)


A. BAHAN
1 Semen Portland 4.3600 Zak Rp 71,875.00 Rp 313,375.00
2 Pasir Beton 0.0260 M3 Rp 345,000.00 Rp 8,970.00
3 Batu Pecah 2/3 0.0435 M3 Rp 403,000.00 Rp 17,530.50
B. UPAH
1 Pekerja 0.0825 Oh Rp 120,000.00 Rp 9,900.00
2 Tukang Batu 0.0125 Oh Rp 173,700.00 Rp 2,171.25
3 Kepala Tukang 0.0013 Oh Rp 208,000.00 Rp 260.00
4 Mandor 0.0040 Oh Rp 208,000.00 Rp 832.00
JUMLAH Rp 353,038.75

8 PEKERJAAN RABAT BAWAH LANTAI (M3)


A. BAHAN
1 Semen Portland 4.3600 Zak Rp 71,875.00 Rp 313,375.00
2 Pasir Beton 0.0260 M3 Rp 345,000.00 Rp 8,970.00
3 Batu Pecah 2/3 0.0435 M3 Rp 403,000.00 Rp 17,530.50
B. UPAH
1 Pekerja 0.0825 Oh Rp 120,000.00 Rp 9,900.00
2 Tukang Batu 0.0125 Oh Rp 173,700.00 Rp 2,171.25
3 Kepala Tukang 0.0013 Oh Rp 208,000.00 Rp 260.00
4 Mandor 0.0040 Oh Rp 208,000.00 Rp 832.00
JUMLAH Rp 353,038.75
9 PEKERJAAN LANTAI FLOOR HARDENER (Konsumsi 4 Kg/m2)
A. BAHAN
1 Floor Hardener 4.0000 Kg #NAME? #NAME?
2 Alat Bantu 1.0000 Ls Rp 5,000.00 Rp 5,000.00
B. UPAH
1 Pekerja 0.1200 Oh Rp 120,000.00 Rp 14,400.00
2 Tukang Batu 0.1200 Oh Rp 173,700.00 Rp 20,844.00
3 Kepala Tukang 0.0120 Oh Rp 208,000.00 Rp 2,496.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH #NAME?

10 BETON K-250 (M3)


A. BAHAN
1 Semen Portland 8.2600 Zak Rp 71,875.00 Rp 593,687.50
2 Pasir Beton 0.4864 M3 Rp 345,000.00 Rp 167,808.00
3 Batu Pecah 2/3 0.5672 M3 Rp 403,000.00 Rp 228,581.60
4 Air Bersih 215.0000 Ltr Rp 1,500.00 Rp 322,500.00

B. UPAH
1 Pekerja 1.6500 Oh Rp 120,000.00 Rp 198,000.00
2 Tukang Batu 0.2750 Oh Rp 173,700.00 Rp 47,767.50
3 Kepala Tukang 0.0280 Oh Rp 208,000.00 Rp 5,824.00
4 Mandor 0.0830 Oh Rp 208,000.00 Rp 17,264.00
JUMLAH Rp 1,581,432.60

11 BETON K-175 (M3)


A. BAHAN
1 Semen Portland 6.5200 Zak Rp 71,875.00 Rp 468,625.00
2 Pasir Beton 0.6379 M3 Rp 345,000.00 Rp 220,075.50
3 Batu Pecah 2/3 0.7607 M3 Rp 403,000.00 Rp 306,562.10
4 Air Bersih 200.0000 Ltr Rp 1,500.00 Rp 300,000.00
B. UPAH
1 Pekerja 1.2000 Oh Rp 120,000.00 Rp 144,000.00
2 Tukang Batu 0.2000 Oh Rp 173,700.00 Rp 34,740.00
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0600 Oh Rp 208,000.00 Rp 12,480.00
JUMLAH Rp 1,490,642.60

11 BEKISTING PONDASI (M2)


A. BAHAN
1 Paku Campur 0.3000 Kg #NAME? #NAME?
2 Minyak Bekisting 0.1000 Ltr #NAME? #NAME?
3 Kayu Kls III 0.0400 M3 #NAME? #NAME?
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Kayu 0.2600 Oh Rp 173,700.00 Rp 45,162.00
3 Kepala Tukang 0.0260 Oh Rp 208,000.00 Rp 5,408.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH #NAME?
12 BEKISTING KOLOM (M2)
A. BAHAN
1 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Paku Campur 0.4000 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.2000 Ltr Rp 33,000.00 Rp 6,600.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Kayu 0.3300 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.0330 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 254,433.00

13 BEKISTING SLOOF (M2)


A. BAHAN
1 Paku Campur 0.3000 Kg Rp 21,000.00 Rp 6,300.00
2 Minyak Bekisting 0.1000 Ltr Rp 33,000.00 Rp 3,300.00
3 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Kayu 0.2600 Oh Rp 173,700.00 Rp 45,162.00
3 Kepala Tukang 0.0260 Oh Rp 208,000.00 Rp 5,408.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 235,210.00

14 BEKISTING BALOK (M2)


A. BAHAN
1 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Paku Campur 0.4000 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.2000 Ltr Rp 33,000.00 Rp 6,600.00
B. UPAH
1 Pekerja 0.3200 Oh Rp 120,000.00 Rp 38,400.00
2 Tukang Kayu 0.3300 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.0330 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 256,833.00
14 BEKISTING TANGGA (M2)
A. BAHAN
1 Kayu Kls II 0.0300 M3 Rp 3,450,000.00 Rp 103,500.00
2 Paku Campur 0.4000 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.1500 Ltr Rp 33,000.00 Rp 4,950.00

B. UPAH
1 Pekerja 0.3200 Oh Rp 120,000.00 Rp 38,400.00
2 Tukang Kayu 0.3300 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.0330 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 220,683.00

15 BEKISTING LANTAI (M2)


A. BAHAN
1 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Paku Campur 0.4000 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.2000 Ltr Rp 33,000.00 Rp 6,600.00
B. UPAH
1 Pekerja 0.3200 Oh Rp 120,000.00 Rp 38,400.00
2 Tukang Kayu 0.3300 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.0330 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 256,833.00

16 BESI BETON (KG)


A. BAHAN
1 Besi Beton 1.0500 Kg Rp 316,000.00 Rp 331,800.00
2 Kawat Ikat Beton 0.0150 Kg Rp 52,675.00 Rp 790.13
B. UPAH
1 Pekerja 0.0070 Oh Rp 120,000.00 Rp 840.00
2 Tukang Besi Beton 0.0070 Oh Rp 173,700.00 Rp 1,215.90
3 Kepala Tukang 0.0007 Oh Rp 208,000.00 Rp 145.60
4 Mandor 0.0004 Oh Rp 208,000.00 Rp 83.20
JUMLAH Rp 334,874.83
17 BESI BAJA WF (KG)
A. BAHAN
1 Besi Baja WF 1.1500 Kg Rp - Rp -
2 Kawat Las 0.0400 Kg Rp 52,675.00 Rp 2,107.00
3 Solar 0.0300 Ltr #NAME? #NAME?
4 Minyak Pelumas 0.0040 Ltr #NAME? #NAME?
5 Sewa Alat 0.0170 Jam Rp 100,000.00 Rp 1,700.00

B. UPAH
1 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
2 Tukang Las Konstruksi 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH #NAME?

18 BESI PROFIL KANAL C,CNP (KG)


A. BAHAN
1 Besi Profil Kanal C 125 1.1500 Kg Rp - Rp -
B. UPAH
1 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
2 Tukang Las Konstruksi 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH Rp 19,494.00

19 PAS. DINDING ROSTER BETON (M2)


A. BAHAN
1 Roster Beton 17.0000 Bh Rp 42,000.00 Rp 714,000.00
2 Semen Portland 0.1972 Zak Rp 71,875.00 Rp 14,173.75
3 Pasir Pasang 0.0450 M3 Rp 345,000.00 Rp 15,525.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0150 Oh Rp 208,000.00 Rp 3,120.00
JUMLAH Rp 802,268.75
20 PAS. DINDING BATU BATA 1 PC : 4 PS (M2)
A. BAHAN
1 Batu Bata 70.0000 Bh Rp 1,725.00 Rp 120,750.00
2 Semen Portland 0.2300 Zak Rp 71,875.00 Rp 16,531.25
3 Pasir Pasang 0.0430 M3 Rp 345,000.00 Rp 14,835.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0150 Oh Rp 208,000.00 Rp 3,120.00
JUMLAH Rp 210,686.25

21 PLESTERAN DINDING CAMP 1 PC : 5 PS (M2)


A. BAHAN
1 Pasir Pasang 0.0260 Bh #NAME? #NAME?
2 Semen Portland 0.1037 Zak Rp 71,875.00 Rp 7,452.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Batu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0150 Oh Rp 208,000.00 Rp 3,120.00
JUMLAH #NAME?

20 PLESTERAN DINDING CAMP 1 PC : 3 PS (M2)


A. BAHAN
1 Pasir Pasang 0.0230 Bh Rp 345,000.00 Rp 7,935.00
2 Semen Portland 0.1555 Zak Rp 71,875.00 Rp 11,178.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Batu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0150 Oh Rp 208,000.00 Rp 3,120.00
JUMLAH Rp 87,408.00

21 PEK. ACIAN DINDING (M2)


A. BAHAN
1 Semen Portland 0.0651 Zak Rp 71,875.00 Rp 4,679.06
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 50,209.06
22 PEK. PEMASANGAN KRAMIK LANTAI KASAR 40 x 40 (M2)
A. BAHAN
1 Keramik 40 x 40 Cm 6.0000 Bh #NAME? #NAME?
2 Semen Portland 0.1680 Zak Rp 71,875.00 Rp 12,075.00
3 Pasir Pasang 0.0420 M3 #NAME? #NAME?
4 Semen Warna 0.5000 Kg Rp 17,940.00 Rp 8,970.00
B. UPAH
1 Pekerja 0.6200 Oh Rp 120,000.00 Rp 74,400.00
2 Tukang Batu 0.3500 Oh Rp 173,700.00 Rp 60,795.00
3 Kepala Tukang 0.0350 Oh Rp 208,000.00 Rp 7,280.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH #NAME?

1 PEK. PEMASANGAN KERAMIK LANTAI GRANIT 60 x 60 (M2)


A. BAHAN
1 Keramik Granit 60 x 60 3.0000 Bh Rp 66,666.67 Rp 200,000.00
2 Semen Portland 0.1680 Zak Rp 71,875.00 Rp 12,075.00
3 Pasir Pasang 0.0420 M3 Rp 345,000.00 Rp 14,490.00
4 Semen Warna 0.5000 Kg Rp 17,940.00 Rp 8,970.00
B. UPAH
1 Pekerja 0.6200 Oh Rp 120,000.00 Rp 74,400.00
2 Tukang Batu 0.3500 Oh Rp 173,700.00 Rp 60,795.00
3 Kepala Tukang 0.0350 Oh Rp 208,000.00 Rp 7,280.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH Rp 378,634.00

23 PEK. PEMASANGAN KRAMIK TANGGA KASAR 40 x 40 (M2)


A. BAHAN
1 Keramik 40 x 40 Cm 12.0000 Bh #NAME? #NAME?
2 Semen Portland 0.1680 Zak Rp 71,875.00 Rp 12,075.00
3 Pasir Pasang 0.0420 M3 #NAME? #NAME?
4 Semen Warna 0.5000 Kg Rp 17,940.00 Rp 8,970.00
B. UPAH
1 Pekerja 0.6200 Oh Rp 120,000.00 Rp 74,400.00
2 Tukang Batu 0.3500 Oh Rp 173,700.00 Rp 60,795.00
3 Kepala Tukang 0.0350 Oh Rp 208,000.00 Rp 7,280.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH #NAME?

23 PEK. PEMASANGAN KERAMIK LICIN MENGKILAP 40 x 40 (M2)


A. BAHAN
1 Keramik 40 x 40 Cm Licin Mengkilap 12.0000 Bh #NAME? #NAME?
2 Semen Portland 0.1680 Zak Rp 71,875.00 Rp 12,075.00
3 Pasir Pasang 0.0420 M3 #NAME? #NAME?
4 Semen Warna 0.5000 Kg Rp 17,940.00 Rp 8,970.00
B. UPAH
1 Pekerja 0.6200 Oh Rp 120,000.00 Rp 74,400.00
2 Tukang Batu 0.3500 Oh Rp 173,700.00 Rp 60,795.00
3 Kepala Tukang 0.0350 Oh Rp 208,000.00 Rp 7,280.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH #NAME?

24 PEK. PEMASANGAN KRAMIK KASAR 20 x 50 (M2)


A. BAHAN
1 Keramik 20 x 25 Cm 20.0000 Bh Rp 7,000.00 Rp 140,000.00
2 Semen Portland 0.1638 Zak Rp 71,875.00 Rp 11,773.13
3 Pasir Pasang 0.0450 M3 Rp 345,000.00 Rp 15,525.00
4 Semen Warna 1.6200 Kg Rp 17,940.00 Rp 29,062.80
B. UPAH
1 Pekerja 0.6200 Oh Rp 120,000.00 Rp 74,400.00
2 Tukang Batu 0.3500 Oh Rp 173,700.00 Rp 60,795.00
3 Kepala Tukang 0.0350 Oh Rp 208,000.00 Rp 7,280.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH Rp 339,459.93
25 PAS. KUSEN PINTU/JENDELA ALUMUNIUM WARNA 4"(M')
A. BAHAN
1 Aluminium Profil Warna 4" 1.1000 M' Rp 50,000.00 Rp 55,000.00
2 Sekrup Fixer 2.0000 Bh Rp 15,360.00 Rp 30,720.00
3 Sealent 4.0000 Tube Rp 25,000.00 Rp 100,000.00
B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Aluminium 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0220 Oh Rp 208,000.00 Rp 4,576.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 256,921.00

26 PAS. BINGKAI JENDELA ALLUMUNIUM KACA 5 MM (M2)


A. BAHAN
1 Aluminium Profil Warna 4" 4.1000 M' Rp 50,000.00 Rp 205,000.00
2 Kaca 5 mm 1.1000 M2 Rp 480,000.00 Rp 528,000.00
3 Sealent 0.2700 Tube Rp 25,000.00 Rp 6,750.00
B. UPAH
1 Pekerja 0.0850 Oh Rp 120,000.00 Rp 10,200.00
2 Tukang Aluminium 0.0850 Oh Rp 173,700.00 Rp 14,764.50
3 Kepala Tukang 0.0090 Oh Rp 208,000.00 Rp 1,872.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 767,626.50

27 PAS. PINTU ROLLING DOOR (M2)


A. BAHAN
1 Rolling Door Alluminium 1.0000 M2 Rp 480,000.00 Rp 480,000.00
B. UPAH
1 Pekerja 1.0500 Oh Rp 120,000.00 Rp 126,000.00
2 Tukang Aluminium 1.5000 Oh Rp 173,700.00 Rp 260,550.00
3 Kepala Tukang 0.1050 Oh Rp 208,000.00 Rp 21,840.00
4 Mandor 0.0052 Oh Rp 208,000.00 Rp 1,081.60
JUMLAH Rp 889,471.60

PAS.PINTU KACA TEMPERED (M2)


A. BAHAN
1 List Alluminium U 4.4000 M' Rp 70,000.00 Rp 308,000.00
2 Kaca Tempered 12 mm 1.1000 M2 Rp 670,000.00 Rp 737,000.00
3 Floor Hinges 2.0000 Set Rp 900,000.00 Rp 1,800,000.00
4 Over Panel 2.0000 Set Rp 950,000.00 Rp 1,900,000.00
5 Top Patch Fitting 2.0000 Set Rp 650,000.00 Rp 1,300,000.00
6 Bottom Patch Fitting 2.0000 Set Rp 650,000.00 Rp 1,300,000.00
7 Bottom Patch Lock+Cylinder 2.0000 Set Rp 950,000.00 Rp 1,900,000.00
8 Pull Handle 2.0000 Set Rp 1,300,000.00 Rp 2,600,000.00
B. UPAH
1 Pekerja 0.0850 Oh Rp 120,000.00 Rp 10,200.00
2 Tukang Aluminium 0.0850 Oh Rp 173,700.00 Rp 14,764.50
3 Kepala Tukang 0.0090 Oh Rp 208,000.00 Rp 1,872.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 11,872,876.50

28 PEKERJAAN RANGKA PLAFOND BESI HOLLOW (M2)


A. BAHAN
1 Besi Hollow 3.6000 M' Rp 40,000.00 Rp 144,000.00
2 Kawat 0.1500 Kg Rp 52,675.00 Rp 7,901.25
3 Ramset 4.0000 Bh Rp 8,000.00 Rp 32,000.00
B. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Tukang Aluminium 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 346,351.25

29 PASANG PLAFOND GYPSUM BOARD, uk. 1.200 x 2.400 x 9 mm


A. BAHAN
1 Gypsum Board 0.4600 Lbr Rp 70,000.00 Rp 32,200.00
2 Tepung Gypsum 0.4400 Kg Rp 40,000.00 Rp 17,600.00
3 tape Textile 1.5000 M' Rp 20,000.00 Rp 30,000.00
4 Paku Sekrup 0.1100 Kg Rp 15,000.00 Rp 1,650.00
B. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Tukang 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 243,900.00
30 PASANG LIST PLAFOND GYPSUM (M')
A. BAHAN
1 List Gypsum Profil 1.0500 M' Rp 30,000.00 Rp 31,500.00
2 Tepung Gypsum 0.1500 Kg Rp 40,000.00 Rp 6,000.00
B. UPAH
1 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
2 Tukang 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH Rp 56,994.00

27 PEKERJAAN RANGKA ALLUMUNIUM (M')


A. BAHAN
1 Aluminium Profil Warna 4" 1.0500 M' Rp 15,360.00 Rp 16,128.00
2 Sekrup Fixer 1.0000 Bh #NAME? #NAME?
3 Sealent 4.0000 Tube #NAME? #NAME?
B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Aluminium 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0220 Oh Rp 208,000.00 Rp 4,576.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH #NAME?

28 PAS. DINDING KACA 5 MM (M2)


A. BAHAN
1 Kaca t = 5 MM 1.0500 M2 #NAME? #NAME?
B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Aluminium 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0220 Oh Rp 208,000.00 Rp 4,576.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH #NAME?

29 PEK. KOSEN PINTU DAN JENDELA KAYU KLS 1 (M3)


A. BAHAN
1 Kayu Kls I 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Paku Campur 1.2500 Kg Rp 21,000.00 Rp 26,250.00
3 Lem Kayu 1.0000 Kg Rp 40,000.00 Rp 40,000.00
B. UPAH
1 Pekerja 7.0000 Oh Rp 120,000.00 Rp 840,000.00
2 Tukang Kayu 13.0000 Oh Rp 173,700.00 Rp 2,258,100.00
3 Kepala Tukang 2.1000 Oh Rp 208,000.00 Rp 436,800.00
4 Mandor 0.3500 Oh Rp 208,000.00 Rp 72,800.00
JUMLAH Rp 11,896,450.00

30 DAUN PINTU PANIL KLS 1 (M2)


A. BAHAN
1 Kayu Kls I 0.0400 M3 Rp 7,125,000.00 Rp 285,000.00
2 Lem Kayu 0.5000 Kg Rp 40,000.00 Rp 20,000.00
B. UPAH
1 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
2 Tukang Kayu 3.0000 Oh Rp 173,700.00 Rp 521,100.00
3 Kepala Tukang 0.3000 Oh Rp 208,000.00 Rp 62,400.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 1,018,900.00
31 DAUN PINTU,BINGKAI JENDELA, VENTILASI KACA, KAYU KLS 2 (M2)
A. BAHAN
1 Kayu Kls II 0.0240 M3 Rp 3,450,000.00 Rp 82,800.00
2 Kaca Polos/Riben 3 mm 1.1000 M2 Rp 205,000.00 Rp 225,500.00
3 Lem Kayu 0.3000 Kg Rp 40,000.00 Rp 12,000.00
B. UPAH
1 Pekerja 0.8000 Oh Rp 120,000.00 Rp 96,000.00
2 Tukang Kayu 2.4000 Oh Rp 173,700.00 Rp 416,880.00
3 Kepala Tukang 0.2400 Oh Rp 208,000.00 Rp 49,920.00
4 Mandor 0.0400 Oh Rp 208,000.00 Rp 8,320.00
JUMLAH Rp 891,420.00

32 PEMASANGAN KACA 3 MM (M2)


A. BAHAN
1 Kaca 3 Mm 1.1000 M2 Rp 205,000.00 Rp 225,500.00
2 Sealant 0.0500 Tube Rp 25,000.00 Rp 1,250.00
B. UPAH
1 Pekerja 0.0150 Oh Rp 120,000.00 Rp 1,800.00
2 Tukang Kayu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0008 Oh Rp 208,000.00 Rp 166.40
JUMLAH Rp 257,891.40

31 ENGSEL PINTU (BH)


A. BAHAN
1 Engsel Pintu 1.0000 Bh Rp 130,000.00 Rp 130,000.00
B. UPAH
1 Pekerja 0.0150 Oh Rp 120,000.00 Rp 1,800.00
2 Tukang Kayu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0008 Oh Rp 208,000.00 Rp 166.40
JUMLAH Rp 161,141.40

32 ENGSEL JENDELA (BH)


A. BAHAN
1 Engsel Jendela 1.0000 Bh Rp 120,000.00 Rp 120,000.00
B. UPAH
1 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0005 Oh Rp 208,000.00 Rp 104.00
JUMLAH Rp 140,754.00

33 KAIT ANGIN (BH)


A. BAHAN
1 Kait Angin 1.0000 Bh #NAME? #NAME?
B. UPAH
1 Pekerja 0.0150 Oh Rp 120,000.00 Rp 1,800.00
2 Tukang Kayu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0080 Oh Rp 208,000.00 Rp 1,664.00
JUMLAH #NAME?
34 GRENDEL PINTU (BH)
A. BAHAN
1 Grendel Pintu 1.0000 Bh Rp 100,000.00 Rp 100,000.00
B. UPAH
1 Tukang Kayu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
2 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
3 Mandor 0.0008 Oh Rp 208,000.00 Rp 166.40
4 Pekerja 0.0150 Oh Rp 120,000.00 Rp 1,800.00
JUMLAH Rp 131,141.40

35 GRENDEL JENDELA (BH)


A. BAHAN
1 Grendel Jendela 1.0000 Bh Rp 90,000.00 Rp 90,000.00
B. UPAH
1 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
2 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
3 Mandor 0.0005 Oh Rp 208,000.00 Rp 104.00
4 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
JUMLAH Rp 110,754.00

36 KUNCI PINTU 2 SLAG (BH)


A. BAHAN
1 Kunci Pintu 2 Slaag 1.0000 Bh #NAME? #NAME?
B. UPAH
1 Tukang Kayu 0.6000 Oh Rp 173,700.00 Rp 104,220.00
2 Kepala Tukang 0.0600 Oh Rp 208,000.00 Rp 12,480.00
3 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
4 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
JUMLAH #NAME?

37 KUNCI PINTU SILINDER (BH)


A. BAHAN
1 Kunci Pintu Silinder 1.0000 Bh Rp 600,000.00 Rp 600,000.00
B. UPAH
1 Tukang Kayu 0.5000 Oh Rp 173,700.00 Rp 86,850.00
2 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
3 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
4 Pekerja 0.0050 Oh Rp 120,000.00 Rp 600.00
JUMLAH Rp 698,474.00

38 PEGANGAN PINTU (BH)


A. BAHAN
1 Handle Pintu 1.0000 Bh Rp 98,000.00 Rp 98,000.00
B. UPAH
1 Tukang Kayu 0.5000 Oh Rp 173,700.00 Rp 86,850.00
2 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
3 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
4 Pekerja 0.0050 Oh Rp 120,000.00 Rp 600.00
JUMLAH Rp 196,474.00
38 PEK. PENGECATAN TEMBOK BARU 2 LAPIS (M2)
A. BAHAN
1 Cat Dasar 0.1000 Kg Rp 633,000.00 Rp 63,300.00
2 Cat Penutup 2 x 0.2600 Kg Rp 633,000.00 Rp 164,580.00
B. UPAH
1 Tukang Cat 0.0630 Oh Rp 173,700.00 Rp 10,943.10
2 Kepala Tukang 0.0063 Oh Rp 208,000.00 Rp 1,310.40
3 Mandor 0.0025 Oh Rp 208,000.00 Rp 520.00
4 Pekerja 0.0200 Oh Rp 120,000.00 Rp 2,400.00
JUMLAH Rp 243,053.50

39 PENGECETAN PLAFON (M2)


A. BAHAN

1 Cat Dasar 0.1000 Kg Rp 70,000.00 Rp 7,000.00


2 Cat Penutup 2 x 0.2600 Kg Rp 70,000.00 Rp 18,200.00
B. UPAH
1 Tukang Cat 0.0630 Oh Rp 173,700.00 Rp 10,943.10
2 Kepala Tukang 0.0063 Oh Rp 208,000.00 Rp 1,310.40
3 Mandor 0.0025 Oh Rp 208,000.00 Rp 520.00
4 Pekerja 0.0200 Oh Rp 120,000.00 Rp 2,400.00
JUMLAH Rp 40,373.50

40 MCB (BH)
A. BAHAN
1 MCB 16 A 1.0000 Bh Rp 115,000.00 Rp 115,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

40 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 4 x 6 mm 1.0000 M' Rp 30,000.00 Rp 30,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

40 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 4 x 3,5 mm 1.0000 M' Rp 27,000.00 Rp 27,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

40 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 3 x 2,5 mm 1.0000 M' Rp 13,000.00 Rp 13,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

40 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 2 x 2,5 mm 1.0000 M' Rp 12,800.00 Rp 12,800.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

40 SAKLAR SERI PANASONIC (BH)


A. BAHAN
1 Saklar Seri Panasonic 1.0000 Bh Rp 47,300.00 Rp 47,300.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

41 SAKLAR TUNGGAL PANASONIC (BH)


A. BAHAN
1 Saklar Tunggal Panasonic 1.0000 Bh Rp 44,275.00 Rp 44,275.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

42 STOP KONTAK TANAM PANASONIC (BH)


A. BAHAN
1 Stop Kontak Tanam Panasonic 1.0000 Bh Rp 53,350.00 Rp 53,350.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

43 STOP KONTAK TANAM AC PANASONIC (BH)


A. BAHAN
1 Stop Kontak Tanam AC Panasonic 1.0000 Bh Rp 35,000.00 Rp 35,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

43 DOWN LIGTH 5 INCHI (BH)


A. BAHAN
1 Down Ligth 5 Inchi 1.0000 Bh Rp 50,000.00 Rp 50,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

44 BALON PHILIPS LED 7 WATT (BH)


A. BAHAN
1 Balon Philips LED 7 Watt 1.0000 Bh Rp 35,000.00 Rp 35,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

44 BALON PHILIPS LED 9 WATT (BH)


A. BAHAN
1 Balon Philips LED 9 Watt 1.0000 Bh Rp 40,000.00 Rp 40,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

45 BALON PHILIPS LED 12 WATT (BH)


A. BAHAN
1 Balon Philips LED 12 Watt 1.0000 Bh Rp 70,000.00 Rp 70,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh #NAME? #NAME?
JUMLAH #NAME?

1 PEMASANGAN PIPA PVC 10 INC (M')


A. BAHAN
1 Pipa PVC Dia. 10" 1.2000 M' Rp 32,500.00 Rp 39,000.00
2 Accessories 1.0000 Ls Rp 5,850.00 Rp 5,850.00
B. UPAH
1 Pekerja 0.0350 Oh Rp 120,000.00 Rp 4,200.00
2 Tukang Batu 0.0120 Oh Rp 173,700.00 Rp 2,084.40
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 56,334.40

46 PEMASANGAN PIPA PVC 4 INC (M')


A. BAHAN
1 Pipa PVC Dia. 4" 1.2000 M' Rp 27,500.00 Rp 33,000.00
2 Accessories 1.0000 Ls Rp 4,950.00 Rp 4,950.00
B. UPAH
1 Pekerja 0.0350 Oh Rp 120,000.00 Rp 4,200.00
2 Tukang Batu 0.0120 Oh Rp 173,700.00 Rp 2,084.40
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 49,434.40

47 PEMASANGAN PIPA PVC 2 INC (M')


A. BAHAN
1 Pipa PVC Dia. 2" 1.2000 M' Rp 25,000.00 Rp 30,000.00
2 Accessories 1.0000 Ls Rp 4,500.00 Rp 4,500.00
B. UPAH
1 Pekerja 0.0810 Oh Rp 120,000.00 Rp 9,720.00
2 Tukang Batu 0.0140 Oh Rp 173,700.00 Rp 2,431.80
3 Kepala Tukang 0.0140 Oh Rp 208,000.00 Rp 2,912.00
4 Mandor 0.0040 Oh Rp 208,000.00 Rp 832.00
JUMLAH Rp 50,395.80

48 PEMASANGAN PIPA PVC 1/2 INC (M')


A. BAHAN
1 Pipa PVC Dia. 1/2" 1.2000 M' Rp 25,000.00 Rp 30,000.00
2 Accessories 1.0000 Ls Rp 4,500.00 Rp 4,500.00
B. UPAH
1 Pekerja 0.0260 Oh Rp 120,000.00 Rp 3,120.00
2 Tukang Batu 0.0400 Oh Rp 173,700.00 Rp 6,948.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0020 Oh Rp 208,000.00 Rp 416.00
JUMLAH Rp 46,232.00

49 PEMASANGAN KLOSET DUDUK (BH)


A. BAHAN
1 Kloset Duduk 1.0000 Bh Rp 1,750,000.00 Rp 1,750,000.00
2 Semen Portland 0.1200 Zak Rp 71,875.00 Rp 8,625.00
3 Pasir Pasang 0.0100 M3 Rp 345,000.00 Rp 3,450.00
B. UPAH
1 Tukang Batu 1.5000 Oh Rp 173,700.00 Rp 260,550.00
2 Kepala Tukang 1.5000 Oh Rp 208,000.00 Rp 312,000.00
3 Mandor 0.1600 Oh Rp 208,000.00 Rp 33,280.00
4 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
JUMLAH Rp 2,487,905.00

50 PEMASANGAN KRAN (BH)


A. BAHAN
1 Kran Air 1.0000 Bh Rp 25,000.00 Rp 25,000.00
2 Seal Tape 0.0250 Bh Rp 5,000.00 Rp 125.00
B. UPAH
1 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
2 Kepala Tukang 0.0050 Oh Rp 208,000.00 Rp 1,040.00
3 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
4 Pekerja 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 46,815.00
51 PEMASANGAN FLORDRAIN (BH)
A. BAHAN
1 Floor Drain 1.0000 Bh Rp 35,000.00 Rp 35,000.00
B. UPAH
1 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 56,690.00

52 PEMASANGAN WESTAFEL (BH)


A. BAHAN
1 Wastafel 1.0000 Bh Rp 1,000,000.00 Rp 1,000,000.00
2 Semen Portland 0.1200 Zak Rp 71,875.00 Rp 8,625.00
3 Pasir Pasang 0.0100 M3 Rp 345,000.00 Rp 3,450.00
4 Perlengkapan 1.0000 Ls Rp 50,000.00 Rp 50,000.00
B. UPAH
1 Pekerja 1.2000 Oh Rp 120,000.00 Rp 144,000.00
2 Tukang Batu 1.4500 Oh Rp 173,700.00 Rp 251,865.00
3 Kepala Tukang 0.1500 Oh Rp 208,000.00 Rp 31,200.00
4 Mandor 0.1600 Oh Rp 208,000.00 Rp 33,280.00
JUMLAH Rp 1,522,420.00

SEPTICKTANK 1.5 x 2 x 2 (M) (BH)


A. BAHAN
1 Septicktank 1.5 x 2 x 2 (M) 1.0000 Bh Rp 4,500,000.00 Rp 4,500,000.00
2 Perlengkapan 1.0000 Ls Rp 675,000.00 Rp 675,000.00
B. UPAH
1 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 5,196,690.00

54 PENUTUP ATAP SPANDEK 0,3 (M2)


A. BAHAN
1 Spandek 1.1000 M2 Rp 37,750.00 Rp 41,525.00
2 Bout Sekrup 0.0100 Kg Rp 15,000.00 Rp 150.00
B. UPAH
1 Pekerja 0.1000 Oh Rp 120,000.00 Rp 12,000.00
2 Tukang Batu 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 101,260.00

BUBUNGAN ATAP SPANDEK (M')


A. BAHAN
1 Nok Spandek 0.7000 Lbr Rp 54,900.00 Rp 38,430.00
2 Bout Sekrup 0.0200 Kg Rp 15,000.00 Rp 300.00
B. UPAH
1 Pekerja 0.1200 Oh Rp 120,000.00 Rp 14,400.00
2 Tukang Batu 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 66,048.00
56 RANGKA BAJA RINGAN (main truss C75-0,75)/Profil C (M2)
A. BAHAN
1 Main truss (C75-0,75) 2.0000 M' Rp 138,000.00 Rp 276,000.00
2 Reng U tipe 41 -33 3.0000 Bh Rp 11,000.00 Rp 33,000.00
3 Screw 12 - 14 x 20 9.0000 Pc Rp 11,000.00 Rp 99,000.00
4 Screw 10 - 16 x 16 11.0000 Pc Rp 13,000.00 Rp 143,000.00
5 Baut dinabolt 0.6000 Pc Rp 8,000.00 Rp 4,800.00
B. UPAH
1 Pekerja 0.1200 Oh Rp 120,000.00 Rp 14,400.00
2 Tukang Batu 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 583,118.00

PEKERJAAN RANGKA ATAP PIPA GALVANIS (M2)


A. BAHAN
1 Pipa Galvanis 1 - 2 " 4.6000 M' Rp 120,000.00 Rp 552,000.00
2 Accesories 1.0000 Ls Rp 165,600.00 Rp 165,600.00
3 Pengelasan 1.0000 Ls Rp 138,000.00 Rp 138,000.00
B. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Tukang Aluminium 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 1,018,050.00

PEKERJAAN COVERING ACP (M2)


A. BAHAN
1 Allumunium Composite 1.1000 M2 Rp 420,000.00 Rp 462,000.00
2 Besi Hollow Galvanis 4x4x1 mm 0.8000 Btg Rp 50,000.00 Rp 40,000.00
3 Braket Siku/Spigot/Stifner 0.2670 Btg Rp 60,000.00 Rp 16,020.00
4 Paku Sekrup Beton 0.0800 Kg Rp 21,000.00 Rp 1,680.00
5 Paku Sekrup 0.1100 Kg Rp 21,000.00 Rp 2,310.00
6 Sealant 0.2500 Tube Rp 25,000.00 Rp 6,250.00
B. PERALATAN
1 Sewa Stager(2 set) 0.0200 Set Rp 150,000.00 Rp 3,000.00
2 Listrik Kerja 1.0000 Ls Rp 10,000.00 Rp 10,000.00
3 Alat Bantu Lainnya 1.0000 Ls Rp 10,000.00 Rp 10,000.00
C. UPAH
1 Pekerja 0.3900 Oh Rp 120,000.00 Rp 46,800.00
2 Tukang Besi/Las 0.7000 Oh Rp 173,700.00 Rp 121,590.00
3 Kepala Tukang 0.0700 Oh Rp 208,000.00 Rp 14,560.00
4 Mandor 0.0070 Oh Rp 208,000.00 Rp 1,456.00
JUMLAH Rp 735,666.00

57 PAVING BLOCK NATURAL TEBAL 6 CM (M2)


A. BAHAN
1 Paving Block tebal 6 cm 50.0000 BH Rp 2,000.00 Rp 100,000.00
2 Pasir Urug (pasir alas) 0.0500 M3 Rp 159,000.00 Rp 7,950.00
B. UPAH
1 Pekerja 0.2500 Oh Rp 120,000.00 Rp 30,000.00
2 Tukang Batu 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0010 Oh Rp 208,000.00 Rp 208.00
JUMLAH Rp 235,408.00

58 Membuat dan Memasang 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I.
A. BAHAN
1 Balok Kayu 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Paku 10 cm 1.2500 Kg Rp 21,000.00 Rp 26,250.00
3 Lem Kayu 1.0000 Kg Rp 40,000.00 Rp 40,000.00
B. UPAH
1 Pekerja 7.0000 Oh Rp 120,000.00 Rp 840,000.00
2 Tukang Kayu 21.0000 Oh Rp 173,700.00 Rp 3,647,700.00
3 Kepala Tukang 2.1000 Oh Rp 208,000.00 Rp 436,800.00
4 Mandor 0.3500 Oh Rp 208,000.00 Rp 72,800.00
JUMLAH Rp 13,286,050.00

59 Membuat dan Memasang 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas II.
A. BAHAN
1 Balok Kayu 1.2000 M3 Rp 7,475,000.00 Rp 8,970,000.00
2 Paku 10 cm 1.2500 Kg Rp 21,000.00 Rp 26,250.00
3 Lem Kayu 1.0000 Kg Rp 40,000.00 Rp 40,000.00
B. UPAH
1 Pekerja 6.0000 Oh Rp 120,000.00 Rp 720,000.00
2 Tukang Kayu 18.0000 Oh Rp 173,700.00 Rp 3,126,600.00
3 Kepala Tukang 1.8000 Oh Rp 208,000.00 Rp 374,400.00
4 Mandor 0.3000 Oh Rp 208,000.00 Rp 62,400.00
JUMLAH Rp 13,319,650.00
60 Membuat dan Memasang 1 m2 Daun Pintu Panel, Kayu Kelas II A
A. BAHAN
1 Papan Kayu 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Lem Kayu 0.5000 Kg Rp 40,000.00 Rp 20,000.00
B. UPAH
1 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
2 Tukang Kayu 3.0000 Oh Rp 173,700.00 Rp 521,100.00
3 Kepala Tukang 0.3000 Oh Rp 208,000.00 Rp 62,400.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 871,900.00

61 Membuat dan Memasang 1 m2 Pintu dan Jendela Kaca, Kayu Kelas II.
A. BAHAN
1 Papan Kayu 0.0240 M3 Rp 3,450,000.00 Rp 82,800.00
2 Lem Kayu 0.3000 Kg Rp 40,000.00 Rp 12,000.00
B. UPAH
1 Pekerja 0.8000 Oh Rp 120,000.00 Rp 96,000.00
2 Tukang Kayu 2.4000 Oh Rp 173,700.00 Rp 416,880.00
3 Kepala Tukang 0.2400 Oh Rp 208,000.00 Rp 49,920.00
4 Mandor 0.0400 Oh Rp 208,000.00 Rp 8,320.00
JUMLAH Rp 665,920.00

62 Membuat dan Memasang 1 m2 Pintu dan Jendela Jalusi, Kayu Kelas II.
A. BAHAN
1 Papan Kayu 0.0640 M3 Rp 3,450,000.00 Rp 220,800.00
2 Lem Kayu 0.5000 Kg Rp 40,000.00 Rp 20,000.00
B. UPAH
1 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
2 Tukang Kayu 3.0000 Oh Rp 173,700.00 Rp 521,100.00
3 Kepala Tukang 0.3000 Oh Rp 208,000.00 Rp 62,400.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 954,700.00

63 Membuat dan Memasang 1 m2 Daun Bingkai Jendela, Kayu Kls. II


A. BAHAN
1 Papan Kayu 0.0350 M3 Rp 3,450,000.00 Rp 120,750.00

B. UPAH
1 Pekerja 0.8000 Oh Rp 120,000.00 Rp 96,000.00
2 Tukang Kayu 2.0000 Oh Rp 173,700.00 Rp 347,400.00
3 Kepala Tukang 0.2000 Oh Rp 208,000.00 Rp 41,600.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 616,150.00

64 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA, KAYU KLS I.


A. BAHAN
1 Balok Kayu Kls I 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 23,500.00 Rp 352,500.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 13,475,730.00

MEMASANG 1 M3 BALOK BUBUNGAN KAYU KLS I.


A. BAHAN
1 Balok Kayu Kls I 1.1000 M3 Rp 25,000.00 Rp 27,500.00
2 Paku 12 cm 5.6000 Kg Rp 650,000.00 Rp 3,640,000.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 8,450,630.00
MEMASANG 1 M3 KONSTRUKSI GORDENG KAYU KLS II.
A. BAHAN
1 Balok Kayu Kls I 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 23,500.00 Rp 352,500.00
3 Paku 12 cm 3.0000 Kg Rp 21,000.00 Rp 63,000.00
B. UPAH
1 Pekerja 2.4000 Oh Rp 120,000.00 Rp 288,000.00
2 Tukang Kayu 7.2000 Oh Rp 173,700.00 Rp 1,250,640.00
3 Kepala Tukang 0.7200 Oh Rp 208,000.00 Rp 149,760.00
4 Mandor 0.1200 Oh Rp 208,000.00 Rp 24,960.00
JUMLAH Rp 10,351,360.00

66 Memasang 1 m2 Rangka Langit - Langit 60x60 cm, Kayu Kelas II


A. BAHAN
1 Kaso - Kaso (5 x 7) cm 0.0163 M3 Rp 3,450,000.00 Rp 56,235.00
2 Paku 7 cm - 10 cm 0.2500 Kg Rp 21,000.00 Rp 5,250.00

B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu 0.3000 Oh Rp 173,700.00 Rp 52,110.00
3 Kepala Tukang 0.0300 Oh Rp 208,000.00 Rp 6,240.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 145,915.00

67 MEMASANG 1 M1 LISTPLANK KAYU KLS I.


A. BAHAN
1 Papan Kayu 0.0108 M3 Rp 3,450,000.00 Rp 37,260.00
2 Paku 5 cm dan 7 cm 0.1000 Kg Rp 21,000.00 Rp 2,100.00

B. UPAH
1 Pekerja 0.1000 Oh Rp 120,000.00 Rp 12,000.00
2 Tukang Kayu 0.2000 Oh Rp 173,700.00 Rp 34,740.00
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 91,300.00

67 MEMASANG 1 M2 LABRIZIRING DARI PAPAN KAYU KLS I


A. BAHAN
1 Papan Kayu 0.0070 M3 Rp 7,125,000.00 Rp 49,875.00
2 Paku 5 cm - 10 cm 0.1000 Kg Rp 21,000.00 Rp 2,100.00
3 Paku Sekrup 10 cm 0.1500 Kg Rp 21,000.00 Rp 3,150.00
B. UPAH
1 Pekerja 0.6000 Oh Rp 120,000.00 Rp 72,000.00
2 Tukang Kayu 1.8000 Oh Rp 173,700.00 Rp 312,660.00
3 Kepala Tukang 0.1800 Oh Rp 208,000.00 Rp 37,440.00
4 Mandor 0.0300 Oh Rp 208,000.00 Rp 6,240.00
JUMLAH Rp 483,465.00

64 MEMASANG 1 M3 KONSTRUKSI KAYU KLS I (8/12)


A. BAHAN
1 Balok Kayu Kls I (8/12) 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 14,773,230.00

64 MEMASANG 1 M3 KONSTRUKSI KAYU KLS I (5/10)


A. BAHAN
1 Balok Kayu Kls I (5/10) 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 14,773,230.00

64 MEMASANG 1 M3 KONSTRUKSI KAYU KLS I (5/5)


A. BAHAN
1 Balok Kayu Kls I (5/5) 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 14,773,230.00

68 Pemasangan 1 m2 Atap Seng Gelombang BJLS 0.30 mm


A. BAHAN
1 Seng Gelombang 0.9000 Lbr Rp 83,400.00 Rp 75,060.00
2 Paku Seng' 0.0200 Kg Rp 40,000.00 Rp 800.00

B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Kayu 0.2000 Oh Rp 173,700.00 Rp 34,740.00
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0800 Oh Rp 208,000.00 Rp 16,640.00
JUMLAH Rp 149,400.00

69 Pemasangan 1 m2 Atap Seng Gelombang Alluminium Warna


A. BAHAN
1 Seng Gelombang Alluminium 0.9000 Lbr Rp 78,000.00 Rp 70,200.00
2 Paku Seng' 0.0200 Kg Rp 40,000.00 Rp 800.00

B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Kayu 0.2000 Oh Rp 173,700.00 Rp 34,740.00
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0800 Oh Rp 208,000.00 Rp 16,640.00
JUMLAH Rp 144,540.00
70 Pemasangan 1 m1 Atap Nok Seng BJLS 0.30 mm
A. BAHAN
1 Seng Plat BJLS 30 0.8900 Lbr Rp 95,650.00 Rp 85,128.50
2 Paku Seng' 0.0600 Kg Rp 40,000.00 Rp 2,400.00
B. UPAH
1 Pekerja 0.1250 Oh Rp 120,000.00 Rp 15,000.00
2 Tukang Kayu 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0250 Oh Rp 208,000.00 Rp 5,200.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 152,401.50

71 Mengerjakan 1 m2 Atap Genteng Metal Multiroof


A. BAHAN
1 Genteng Metal Multi Roof 1.0200 Lbr Rp 130,000.00 Rp 132,600.00
2 Paku Genteng 0.0300 Kg Rp - Rp -
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 178,130.00

72 Pemasangan 1 m1 Nok Genteng Metal Multiroof


A. BAHAN
1 Nok Genteng 1.1000 Bh Rp 70,000.00 Rp 77,000.00
2 Paku Genteng 0.0500 Kg Rp - Rp -
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 122,530.00

73 Mengerjakan 1 m2 Atap Genteng Sakuraroof


A. BAHAN
1 Genteng Sakuraroof 1.0200 Lbr Rp 130,000.00 Rp 132,600.00
2 Paku Genteng 0.0300 Kg Rp - Rp -
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 178,130.00

74 Mengerjakan 1 m1 Nok Genteng Sakuraroof


A. BAHAN
1 Nok Genteng Sakuraroof 1.0000 Bh Rp 70,000.00 Rp 70,000.00
2 Paku Genteng 0.0500 Kg Rp - Rp -
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 115,530.00
75 Mengerjakan 1 M2 Kasau dan Reng Genteng Metal Rangka Kayu Kelas II.
A. BAHAN
1 Kayu Kls II 0.0140 M3 Rp 3,450,000.00 Rp 48,300.00
2 Paku Genteng 0.1500 Kg Rp 21,000.00 Rp 3,150.00
B. UPAH
1 Pekerja 0.1000 Oh Rp 120,000.00 Rp 12,000.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 93,300.00

76 Mengerjakan 1 M2 Plafond Tripleks


A. BAHAN
1 Tripleks 3 mm 0.5000 Lbr Rp 75,000.00 Rp 37,500.00
2 Paku Campur 0.0500 Kg Rp 21,000.00 Rp 1,050.00
B. UPAH
1 Pekerja 0.0250 Oh Rp 120,000.00 Rp 3,000.00
2 Tukang Kayu 0.0750 Oh Rp 173,700.00 Rp 13,027.50
3 Kepala Tukang 0.0080 Oh Rp 208,000.00 Rp 1,664.00
4 Mandor 0.0010 Oh Rp 208,000.00 Rp 208.00
JUMLAH Rp 56,449.50
DAFTAR HARGA SATUAN UPAH
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI
KEGIATAN :
KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022
HARGA SATUAN
TERPAKAI
NO PERSONIL SATUAN

( Rp )

1 Kepala Tukang Oh 208,000.00


2 Operator Terlatih Oh 208,000.00
3 Mandor Oh 208,000.00
4 Pekerja Oh 120,000.00
5 Penjaga Malam Oh 100,000.00
6 Tukang Besi Beton Oh 173,700.00
7 Tukang Kayu Oh 173,700.00
8 Tukang Cat Oh 173,700.00
9 Tukang Aluminium Oh 173,700.00
10 Tukang Batu Oh 173,700.00
11 Tukang Las Oh 173,700.00
12 Tukang Besi Konstruksi Oh 173,700.00
13 Tukang Listrik Oh 173,700.00
14 Sopir Truck Oh 160,000.00
DAFTAR HARGA SATUAN MATERIAL
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN
KEGIATAN :
STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022 HARGA SATUAN
TERPAKAI
HARGA SATUAN
NO MATERIAL SATUAN
DASAR (Rp)

( Rp ) ###
BAHAN BANGUNAN (Material Batu)
1 Air Bersih Ltr 1,500.00 1,500.00
2 Paving Blok tebal 6 cm BH 2,000.00 2,000.00
3 Batu Kali/Gunung (dia. 30-50) M3 144,000.00 144,000.00
4 Batu Kali/Gunung (dia. 20/20, 15/20, 10/15, 10/10) M3 144,000.00 144,000.00
5 Batu Kali/Gunung Pecah (dia. 20/20, 15/20, 10/15, 10/10) M3 144,000.00 144,000.00
6 Batu Pecah 3/5 M3 345,000.00 345,000.00
7 Batu Pecah 2/3 (Koral) M3 403,000.00 403,000.00
8 Batu Pecah 1/2 M3 403,000.00 403,000.00
9 Split/Abu Batu (0,01 - 0,02 mm) M3 345,000.00 345,000.00
10 Kerikl Beton/Koral Beton M3 403,000.00 403,000.00
11 Batu Tempel Hitam M3 - 0.00
12 Batu Bata Tela Press BH 1,725.00 1,725.00
13 Roster Beton BH 42,000.00 42,000.00
14 Agregat Halus M3 295,000.00 295,000.00
15 Agregat Kasar M3 235,000.00 235,000.00
16 Agregat Base Kls A M3 - ###
17 Agregat Base Kls B M3 - ###
18 Agregat Base Kls C (sirtu) M3 - ###
BAHAN BANGUNAN (Material Pasir dan Tanah)
1 Pasir Beton Halus (Hotmix) / Pasir Gali / Pasir Kali M3 345,000.00 345,000.00
2 Pasir Pasangan ( Pasir Kali/Pantai) M3 345,000.00 345,000.00
3 Pasir Urug (Timbunan) M3 159,000.00 159,000.00
4 Tanah Urug Pilihan (Timbunan) M3 101,000.00 101,000.00
5 Pasir Urug (pasir Alas) M3 159,000.00 159,000.00
6 Pasir Halus M3 345,000.00 345,000.00
7 Agregat Kls C (Sirtu/Kali) M3 0.00 ###
BAHAN BANGUNAN (Material Kayu)
1 Perancah Kayu M3 2,000,000.00 2,000,000.00
2 Kayu Kls I M3 7,475,000.00 7,475,000.00
3 Kayu Kls II M3 3,450,000.00 3,450,000.00
4 Papan Kayu Kls I M3 7,125,000.00 7,125,000.00
5 Papan Kayu Kls II M3 3,450,000.00 3,450,000.00
6 Balok Kayu Kls I (8/12) M3 7,475,000.00 7,475,000.00
7 Balok Kayu Kls I (5/10) M3 7,475,000.00 7,475,000.00
8 Balok Kayu Kls I (5/5) M3 7,475,000.00 7,475,000.00
9 Dolken Kayu Galam (Kaso) M3 0.00 ###
10 Multipleks/Playwood 9 mm Lbr 0.00 ###
Material Pabrik
Bahan Besi dan Kaca
1 Paku Campur 5 - 15 centi KG 21,000.00 21,000.00
2 Paku 10 centi 21,000.00 21,000.00
3 Paku Beton KG 22,000.00 22,000.00
4 Paku Tripleks KG 28,500.00 28,500.00
5 Paku Seng KG 40,000.00 40,000.00
6 Paku Genteng KG 0.00 0.00
7 Sekrup Fixer DOS 15,360.00 15,360.00
8 Paku Sekrup Beton KG 21,000.00 21,000.00
9 Paku Sekrup KG 21,000.00 21,000.00
10 Reng U tipe 41 -33 BH 11,000.00 11,000.00
11 Screw 12 - 14 x 20 Pc 11,000.00 11,000.00
12 Screw 10 - 16 x 16 Pc 13,000.00 13,000.00
13 Sealent Tube 25,000.00 25,000.00
14 Kaca Bening 3 mm M2 205,000.00 205,000.00
15 Kaca Polos/Riben 5 mm M2 480,000.00 480,000.00
16 Kaca Tempered Clear 5 mm M2 120,000.00 120,000.00
17 Kaca Tempered Clear 12 mm M2 670,000.00 670,000.00
18 Floor Hinges Set 900,000.00 900,000.00
19 Over Panel Set 950,000.00 950,000.00
20 Top Patch Fitting Set 650,000.00 650,000.00
21 Bottom Patch Fitting Set 650,000.00 650,000.00
22 Bottom Patch Lock+Cylinder Set 950,000.00 950,000.00
23 Pull Handle Set 1,300,000.00 1,300,000.00
24 Besi Hollow 2/4 Btg 40,000.00 40,000.00
25 Besi Hollow Galvanis 4x4x1 mm Btg 50,000.00 50,000.00
26 Besi Hollow Galvanis 4x4x2x6 Btg 303,700.00 303,700.00
27 Besi Pipa Galvanis M' 120,000.00 120,000.00
28 List Alluminium U M' 70,000.00 70,000.00
29 Aluminium Profil Warna 4" M' 50,000.00 50,000.00
30 Allumunium Composite M2 420,000.00 420,000.00
31 Braket Siku/Spigot/Stifner Btg 60,000.00 60,000.00
32 Besi Strip Tbl 5 mm Kg 110,000.00 110,000.00
33 Baja Ringan; Main truss (C75-0,75) Staf 138,000.00 138,000.00
34 Kawat Ikat/Bendrat Kg 52,675.00 52,675.00
35 Ramset/ Dinabolt Bh 8,000.00 8,000.00
36 Keramik Granit 60 x 60 DOS 200,000.00 200,000.00
37 Keramik Tegel 40 x 40 DOS 180,000.00 180,000.00
38 Keramik Tegel 20 x 25 DOS 140,000.00 140,000.00
39 Keramik Tegel 25 x 25 DOS 144,000.00 144,000.00
40 Keramik Tegel 25 x 50 DOS 160,000.00 160,000.00
41 Keramik tegel 30 x 30 DOS 100,000.00 100,000.00
42 Tripleks 3 mm Lbr 75,000.00 75,000.00
43 Tripleks 4 mm Lbr 85,000.00 85,000.00
44 Tripleks 5 mm Lbr 95,000.00 95,000.00
45 Tripleks 6 mm Lbr 100,000.00 100,000.00
46 Tripleks 7 mm Lbr 105,000.00 105,000.00
47 Tripleks 8 mm Lbr 110,000.00 110,000.00
48 Gypsum Lbr 70,000.00 70,000.00
49 List Gypsum Profil M' 30,000.00 30,000.00
50 List Profil Plafond Kayu Kls II M' 45,000.00 45,000.00
51 Tepung Gypsum Kg 40,000.00 40,000.00
52 tape Textile M' 20,000.00 20,000.00
53 Paku Gypsum Kg 15,000.00 15,000.00
54 Baut dinabolt Pc - ###
55 Besi Beton dia. 8 Staf 51,750.00 51,750.00
56 Besi Beton Dia. 10 Staf 82,225.00 82,225.00
57 Besi Beton Dia. 12 Staf 118,500.00 118,500.00
58 Besi Beton Dia. 16 Staf 316,000.00 316,000.00
59 Besi Beton Polos/Ulir Kg 23,500.00 23,500.00
60 Besi Baja WF 300x150x6,5x9 Staf - ###
61 Besi Profil Kanal C 125 Staf - ###
62 Busbar Fasa Bh - ###
63 Minyak Bekesting Liter 33,000.00 33,000.00
64 Balon Philips LED 7 Watt Bh 35,000.00 35,000.00
65 Balon Philips LED 9 Watt Bh 40,000.00 40,000.00
66 Balon Philips LED 10 Watt Bh 50,000.00 50,000.00
67 Balon Philips LED 11 Watt Bh 60,000.00 60,000.00
68 Balon Philips LED 12 Watt Bh 70,000.00 70,000.00
69 Balon Philips LED 16 Watt Bh 90,000.00 90,000.00
70 Balon Philips LED 25 Watt BH 50,000.00 50,000.00
71 Lampu Downlight LED Philips 12 watt BH 200,000.00 200,000.00
72 Lampu Downlight LED Philips 25 watt BH 220,000.00 220,000.00
73 Lampu Kristal Besar BH 10,000,000.00 10,000,000.00
74 Lampu Hias BH 3,000,000.00 3,000,000.00
75 Lampu Hias Tempel BH 550,000.00 550,000.00
76 Lampu Sorot 100 watt BH 350,000.00 350,000.00
77 Stop Kontak Bh 53,350.00 53,350.00
78 Saklar Tunggal Bh 44,275.00 44,275.00
79 Saklar Ganda Bh 47,300.00 47,300.00
80 Stop Kontak AC Bh 35,000.00 35,000.00
81 Mangko Tanam Panasonic BH 25,000.00 25,000.00
82 T. Dos BH 25,000.00 25,000.00
83 MCB 16 A BH 115,000.00 115,000.00
84 Stick Arde Tembaga BH 250,000.00 250,000.00
85 Klem no. 10 DOS 15,000.00 15,000.00
86 Klem no. 14 DOS 25,000.00 25,000.00
87 Kabel NYM 4 x 6 mm M' 30,000.00 30,000.00
88 Kabel NYM 4 x 3,5 mm M' 27,000.00 27,000.00
89 Kabel NYM 3 x 1,5 mm M' 25,300.00 25,300.00
90 Kabel NYM 2 x 1,5 mm M' 25,300.00 25,300.00
91 Kabel NYY 4 x 10 mm M' 85,000.00 85,000.00
92 Kabel NYY 3 x 4 mm Rol 1,250,000.00 1,250,000.00
93 Kabel NYY 3 x 2,5 mm Rol 650,000.00 650,000.00
94 Kabel NYM 3 x 2,5 mm Rol 650,000.00 650,000.00
95 Kabel NYM 2 x 2,5 mm Rol 640,000.00 640,000.00
96 Pipa Listrik pvc Clipsal Staf 25,000.00 25,000.00
97 Box Pendingin (cooler box) kap.120 L Bh - ###
98 Conveyor L=3 m Unit - ###
99 Cat Tembok Fres 25 Kg 633,000.00 633,000.00
100 Cat Tembok Catylac Interior 25 Kg 803,000.00 803,000.00
101 Cat Tembok Komilex 20 Kg 259,000.00 259,000.00
102 Cat Tembok Matex 20 Kg 384,000.00 384,000.00
103 Cat Tembok No-Drop 20 Kg 917,000.00 917,000.00
104 Cat Tembok Aries 20 Kg 158,000.00 158,000.00
105 Cat Dasar/Alkali Lenkote 20 Kg 1,091,000.00 1,091,000.00
106 Cat Dasar/Alkali Nipon 3 in 1 20 L 830,000.00 830,000.00
107 Cat Dasar/Alkali Dulux Alkali 20 L 953,000.00 953,000.00
108 Cat Dasar/Alkali Mowilex Alakli 20 L 1,077,000.00 1,077,000.00
109 Cat Kayu/Besi Avian 1L 70,000.00 70,000.00
110 Cat Kayu/Besi V-Gloss 1L 58,900.00 58,900.00
111 Cat Kayu/Besi Glotex 1L 59,000.00 59,000.00
112 Cat Meni Kg 65,000.00 65,000.00
113 Dempul Kg 45,000.00 45,000.00
114 Lem Kayu Kg 40,000.00 40,000.00
115 Dolken Btg - ###
116 Down Ligth 5 Inchi Bh 50,000.00 50,000.00
117 Engsel Jendela Bh 120,000.00 120,000.00
118 Engsel Pintu Bh 130,000.00 130,000.00
119 Grendel Jendela Bh 90,000.00 90,000.00
120 Grendel Pintu Bh 100,000.00 100,000.00
121 Kait Angin Bh 90,000.00 90,000.00
122 Floor Drain Bh 35,000.00 35,000.00
123 Semen Portland Tonasa Zak 71,875.00 71,875.00
124 Semen PC Bosowa Zak 87,850.00 87,850.00
125 Semen Conch Zak 65,560.00 65,560.00
126 Semen Putih Kg 17,940.00 17,940.00
127 Semen Warna Kg 17,940.00 17,940.00
128 Kunci Pintu Biasa SET 600,000.00 600,000.00
129 Kunci Pintu Antik SET 700,000.00 700,000.00
130 Kunci Pintu KM/WC SET 445,000.00 445,000.00
131 Handle Pintu BH 98,000.00 98,000.00
132 Engsel Pintu BH 78,000.00 78,000.00
133 Engsel Jendela BH 59,900.00 59,900.00
134 Pipa PVC 10 " M 32,500.00 32,500.00
135 Pipa PVC 4 ' M 30,000.00 30,000.00
136 Pipa PVC 3 ' M 27,500.00 27,500.00
137 Pipa PVC 2 ' M 25,000.00 25,000.00
138 Pipa PVC 3/4 ' M 25,000.00 25,000.00
139 Pipa PVC 1 " M 27,500.00 27,500.00
140 Pipa PVC 1/2 " M 22,500.00 22,500.00
141 Kran Air BH 25,000.00 25,000.00
142 Wastafel BH 1,000,000.00 1,000,000.00
143 Septictank 1,5 m x 2 m x 2 m BH 4,500,000.00 4,500,000.00
144 Seal Tape BH 5,000.00 5,000.00
145 Klosed Duduk BH 1,750,000.00 1,750,000.00
146 Closed Jongkok BH 451,000.00 451,000.00
Bahan Atap
1 Atap Enamel (bahan + Pasang) M2 2,490,000.00 2,490,000.00
2 Seng Gelombang 0.20 Lbr 60,000.00 60,000.00
3 Seng Gelombang 0.25 Lbr 78,000.00 78,000.00
4 Seng Gelombang 0.3 Lbr 83,400.00 83,400.00
5 Seng Plat BJLS 30 Lbr 95,650.00 95,650.00
6 Spandek M2 37,750.00 37,750.00
7 Nok Atap Spandek Lbr 54,900.00 54,900.00
8 Genteng Metal Multiroof Lbr 130,000.00 130,000.00
9 Nok Genteng Metal Multiroof Lbr 70,000.00 70,000.00
10 Atap Rumbia/Daun Kirai/Daun Sagu Lbr - ###
11 Atap Onduline Lbr - ###
12 Nok Onduline Lbr - ###
13 Ornamen Dinding GRC (Cetak + Pemasangan) M2 - ###
DAFTAR HARGA SATUAN ALAT

KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

HARGA SATUAN
NO ALAT SATUAN
( Rp )

1 Dump Truck Hari 1,750,000.00


Jam 250,000.00
2 Concrete Mixer Hari 350,000.00
Jam 50,000.00
3 Alat Pemadatan (Stamper) Hari 1,820,000.00
Jam 260,000.00
4 Water Pump Hari 315,000.00
Jam 45,000.00
5 Excavator Hari 2,100,000.00
Jam 300,000.00
6 Generator Dan Alat Penerangan Hari 600,000.00
Jam 100,000.00
BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Beton Bertulang

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Balok Beton Bertulang B1 25/50 K-225 101.1 0.25 0.5 1 M3 12.6375 M3

Bekesting 101.1 126.375 M2

Besi Beton panjang Berat/m Berat 1848.108 Kg


Tul.dia. 16 (6 bh) 101.1 1.583 960.2478
tul.dia.14 ( 4 bh) 101.1 1.208 488.5152
Tul.segkang dia.8 1011 0.395 399.345

SKETSA/GAMBAR KERJA
BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Beton Bertulang

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Balok Beton Bertulang B2 20/30 K-225 44.8 0.2 0.3 1 M3 2.688

Bekesting 44.8 0.7 31.36 M2

Besi Beton panjang Berat/m Berat 384.54827 Kg


Tul.dia. 12 (5 bh) 44.8 0.891 199.584
tul.dia.10 ( 2 bh) 44.8 0.616 55.1936
Tul.segkang dia.8 328.53333 0.395 129.77067

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Beton Bertulang

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Balok Beton Bertulang B3 15/20 K-250 71.6 0.15 0.2 1 M3 2.148

Bekesting 71.6 0.55 39.38 M2

Besi Beton panjang Berat/m Berat 327.25973 Kg

tul.dia.10 ( 4 bh) 71.6 0.616 176.4224


Tul.segkang dia.8 381.86667 0.395 150.83733

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Beton Bertulang

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Ring Balok Beton Bertulang RB2 20/30 K-250 142.1 0.2 0.3 1 M3 8.526

Bekesting 142.1 0.8 113.68 M2

Besi Beton panjang Berat/m Berat 1219.739 Kg


Tul.dia. 12 (5 bh) 142.1 0.891 633.0555
tul.dia.10 ( 2 bh) 142.1 0.616 175.0672
Tul.segkang dia.8 1042.0667 0.395 411.61633

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Beton Bertulang

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Ring Balok Beton Bertulang RB3 15/20 K-250 28.87 0.15 0.2 1 M3 0.8661

Bekesting 28.87 0.55 15.8785 M2

Besi Beton panjang Berat/m Berat 131.95515 Kg


tul.dia.10 ( 4 bh) 28.87 0.616 71.13568
Tul.segkang dia.8 153.97333 0.395 60.819467

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Beton Bertulang
PANJANG LEBAR TINGGI
NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Plat Lantai Beton Bertulang K-250 Luas Total = 31.5 6.8 0.12 = 214.2 m2
Luas Bukaan = 0 18 = 0 m2
Luas Lantai = 214.2 - 0 = 214.2 m2
Volume = 214.2 x 0.12 = 25.704 M3 25.704
Bekesting 31.5 6.8 214.2 M2

Besi Beton Panjang Jum.Tul P.Total 2 x Berat/m Berat Total 7634.088 Kg


Tul. Memanjang ( dia. 12) 31.5 68 4284 0.891 3817.044

Tul. Melintang (dia.12) 6.8 315 4284 0.891 3817.044

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Beton Bertulang
PANJANG LEBAR TINGGI
NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
M3 6.59
1 Pek. Kolom Beton Bertulang
Beton Kolom K2 25/25 0.25 0.25 3.55 7 M3 1.553125
Beton Kolom Kp 12/12 0.12 0.12 3.55 11 M3 0.56232
Beton Kolom K1 30/30 0.3 0.3 3.55 14 M3 4.473
Bekseting K1 3.55 1.2 14 59.64
K2 3.55 1 7 24.85
total 84.49 M2
Besi Beton panjang berat/m Berat jum.kolom Berat tot 317.89777 Kg
K2 Tul.dia. 16 (4 bh) 3.55 1.583 22.4786 7 157.3502
tul.dia.12 ( 4 bh) 3.55 0.891 12.6522 7 88.5654
Tul.segkang dia.8 26.033333 0.395 10.283167 7 71.982167
panjang berat/m Berat jum.kolom Berat tot 661.97087 Kg
K1 Tul.dia. 16 (4 bh) 3.55 1.583 22.4786 14 314.7004
tul.dia.12 ( 4 bh) 3.55 0.891 12.6522 14 177.1308
Tul.segkang dia.8 30.766667 0.395 12.152833 14 170.13967
Total 979.8686 Kg

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Lantai dan Dinding

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
1 Pek. Pasangan Dinding Bata 1 : 4 M2 551.12

Dinding Bata 1 : 4 190 3.55 1 123.3793 551.1207

PJ1 2.48 2.74 5 33.976


P1 1.14 2.74 4 12.4944
P2 1.04 2.74 2 5.6992
P3 1.04 2.17 8 18.0544
PJ3 3.18 2.74 3 26.1396
J1 2.95 1.75 5 25.8125
V1 0.94 0.64 2 1.2032

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Lantai dan Dinding

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Plesteran Dinding Vol. Plesteran = 2 x Vol. Pas Dinding 2 x 551.12 = 1102.2414 M2

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Lantai dan Dinding

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
1 Pek. Acian Dinding Vol. Acian = Vol. Plesteran 1102.2414 M2

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Lantai dan Dinding

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
1 Pek. Lantai Keramik 60/60 744.9 M2
R. 5 x 5 5 5 6 150
R. 4,10 x 5 4.1 5 2 41
R. 6,25 x 5 6.25 5 2 62.5
R. 5 x 3 5 3 3 45
R. 21 x 15 21 15 1 315
R. Selasar 73 1.8 1 131.4

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Lantai dan Dinding

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Lantai Keramik 30 x 30


R. KM/WC 5 3 2 30 M2

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Lantai dan Dinding

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Dinding Keramik 30/30


R. KM/WC 26 2 2 104 M2
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
3.61 M3
1 Pek. Kusen Pintu, Jendela dan Ventilasi PxLxT
PJ1 P = panjang kayu balok 15.29 0.08 0.12 5 0.73392
PJ2 L = lebar kayu balok 15.29 0.08 0.12 5 0.73392
PJ3 T = tebal kayu balok 15.98 0.08 0.12 3 0.460224
P1 7.36 0.08 0.12 4 0.282624
P2 7.16 0.08 0.12 2 0.137472
P3 5.18 0.08 0.12 8 0.397824
J1 17 0.08 0.12 5 0.816
V1 2.76 0.08 0.12 2 0.052992

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
114.59 M2
1 Pek. Daun Pintu, Jendela, Ventilasi Kaca PxL
PJ1 2.48 1.75 5 21.7
PJ2 2.48 1.75 5 21.7
PJ3 3.18 1.75 3 16.695
P1 2.74 0.94 4 10.3024
P2 2.74 0.84 2 4.6032
P3 2.17 0.84 8 14.5824
J1 2.75 1.75 5 24.0625
V1 0.74 0.64 2 0.9472

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

JUMLAH
NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
ENGSEL
a b c d
90.00 BH
1 Pas. Engsel Pintu axd
PJ1 3 5 15
PJ2 3 5 15
PJ3 6 3 18
P1 3 4 12
P2 3 2 6
P3 3 8 24

SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

JUMLAH
NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
ENGSEL
a b c d
1 Pas. Engsel Jendela 220.00 BH
PJ1 10 5 50
PJ2 10 5 50
PJ3 12 3 36
J1 16 5 80
V1 2 2 4
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME

a b c d
220.00 BH
1 Pas. Kait Angin
PJ1 10 5 50
PJ2 10 5 50
PJ3 12 3 36
J1 16 5 80
V1 2 2 4
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME

a b c d
30.00 BH
1 Pas. Grendel Pintu
PJ1 1 5 5
PJ2 1 5 5
PJ3 2 3 6
P1 1 4 4
P2 1 2 2
P3 1 8 8
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME

a b c d
110.00 BH
1 Pas. Grendel Jendela
PJ1 5 5 25
PJ2 5 5 25
PJ3 6 3 18
J1 8 5 40
V1 1 2 2
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pintu Jendela Ventilasi

NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME

a b c d

1 Pas. Kunci Pintu 27 BH

PJ1 1 5 5
PJ2 1 5 5
PJ3 1 3 3
P1 1 4 4
P2 1 2 2
P3 1 8 8
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Plafond

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pas. Rangka Plafond Kayu PxL 681.5 M2


R. 5 x 5 5 5 6 150
R. 5 x 4.10 5 4.1 2 41
R. 5 x 3,5 5 3.5 3 52.5
R. 20 x 15 20 15 1 300
R. KM/WC 5 3 2 30
R. Selasar 30 1.8 2 108
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Plafond

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pas. Langit-Langit Plafond Tripleks vol. plafond = vol. rangka plafond 681.5 M2
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Plafond

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pas. List Profil Plafond 436.6 M'


R. 5 x 5 5 5 6 120
R. 5 x 4.10 5 4.1 2 36.4
R. 5 x 3,5 5 3.5 3 51
R. 20 x 15 20 15 1 70
R. KM/WC 5 3 2 32
R. Selasar 30 1.8 2 127.2

SKETSA/GAMBAR KERJA
SKETSA/GAMBAR KERJA

BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Instalasi Sanitasi Air

PANJANG LEBAR TINGGI VOLUME


NO URAIAN PEKERJAAN RUMUS UNIT SAT
(M) (M) (M) MC-0
a b c d
1 Pek. Pas. Closed Jongkok 8.00 BH

Sayap Kanan 4
Sayap Kiri 4

SKETSA/GAMBAR KERJA
BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Instalasi Sanitasi Air

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
1 Pek. Pas. Floor Drain 8.00 BH

Sayap Kanan 4
Sayap Kiri 4

2 Pas. Instalasi pipa 4 inch 10 M

3 Pas. Instalasi Pipa 1/2 inch 20 M

4 Pas. Kran air 8 BH

SKETSA/GAMBAR KERJA
BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Instalasi Listrik

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Kabel Listrik NYM 3 x 2,5 100 M

2 Kabel Listrik NYM 2 x 2,5 150 M

3 MCB 16 A 2 BH
4 Saklar Ganda Tanam 18 BH
5 Saklar Tunggal 2 BH
6 Stop Kontak 31 BH
7 Sto Kontak AC 10 BH
8 Lampu TL 8 watt 10 BH
9 Lampu TL 18 watt 88 BH

SKETSA/GAMBAR KERJA
BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Pengecatan

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pengecatan Dinding 1102.2414 M2

2 Pengecatan Plafond 681.5 M2

SKETSA/GAMBAR KERJA
BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI II
ITEM PEKERJAAN : Pekerjaan Kuda-Kuda dan Atap

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d

1 Pek. Rangka Atap Baja Ringan 276.22975 M2


Sayap Kanan (tiris luar) 30 3.6 108
Sayap Kanan (tiris dalam) 30 5.25 157.5
Sayap kanan (tiris depan) 4.75 + 8.1 / 2 x 1.67 10.72975

2 Pek. Atap Genteng Multi Roof 276.22975 M2

3 Pek. Nok Genteng Multi Roof 34.75 34.75 M1

SKETSA/GAMBAR KERJA
BACK UP DATA
JENIS PEKERJAAN : PEKERJAAN LANTAI I
ITEM PEKERJAAN : Pekerjaan Tangga Beton

PANJANG LEBAR TINGGI


NO URAIAN PEKERJAAN RUMUS UNIT SAT VOLUME
(M) (M) (M)
a b c d
1 Pek. Tangga Beton Bertulang M3 2.48
Lebar AT Tinggi AT LEBAR T.
Anak Tangga I Rumus Segitiga 0.3 0.2 1.32 9 0.3564
Bordes I Rumus persegi 2.45 2.75 0.12 1 0.8085
Anak Tangga II Rumus Segitiga 0.3 0.2 1.32 8 0.3168

PANJANG Tebal plat LEBAR T.


Plat Tangga I Rumus persegi 3.36 0.12 1.32 1 0.532224
Plat Tangga II Rumus persegi 2.94 0.12 1.32 1 0.465696

Bekseting Panjang Lebar 8.316 M2


3.36 1.32 4.4352
2.94 1.32 3.8808
Besi Beton Dia Jarak Panjang Jum.Tul Jum anak 407.7535 Kg
Plat I Memanjang 12 0.1 3.36 13.2 39.47328
Plat II Memanjang 12 0.1 2.94 13.2 34.53912
Plat Bordes Memanjang 12 0.1 2.75 24.5 59.96375
Plat I Melintang 12 0.1 1.32 33.6 39.47328
Plat II Melintang 12 0.1 1.32 29.4 34.53912
Plat Bordes Melintang 12 0.1 2.45 27.5 59.96375
Kait anak tangga 12 0.1 0.7 13.2 17 139.8012
(Clearing & Striping)
A. PERALATAN
1 Cat Menie 0.0470 Jam Rp 850,000.00 Rp 39,950.00

B. UPAH
1 Tukang Cat
2 Kepala Tukang
3 Mandor 0.0175 Oh Rp 208,000.00 Rp 3,640.00
4 Pekerja 0.0180 Oh Rp 120,000.00 Rp 2,160.00
Jumlah Rp 45,750.00
Overhead & Profit Rp 6,862.50
JUMLAH Rp 52,612.50
ANALISA HARGA SATUAN

KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI

PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE


LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 PEMASANGAN PIPA PVC 10 INC (M')


A. BAHAN
1 Pipa PVC Dia. 10" 1.2000 M' Rp 32,500.00 Rp 39,000.00
2 Accessories 1.0000 Ls Rp 5,850.00 Rp 5,850.00
B. UPAH
1 Pekerja 0.0350 Oh Rp 120,000.00 Rp 4,200.00
2 Tukang Batu 0.0120 Oh Rp 173,700.00 Rp 2,084.40
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 56,334.40

1 PEMASANGAN PIPA PVC 4 INC (M')


A. BAHAN
1 Pipa PVC Dia. 4" 1.2000 M' Rp 30,000.00 Rp 36,000.00
2 Accessories 1.0000 Ls Rp 5,400.00 Rp 5,400.00
B. UPAH
1 Pekerja 0.0350 Oh Rp 120,000.00 Rp 4,200.00
2 Tukang Batu 0.0120 Oh Rp 173,700.00 Rp 2,084.40
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
Jumlah Rp 52,884.40
Overhead & Profit Rp 7,932.66
JUMLAH Rp 60,817.06

3 PEMASANGAN PIPA PVC 3 INC (M')


A. BAHAN
1 Pipa PVC Dia. 3" 1.2000 M' Rp 27,500.00 Rp 33,000.00
2 Accessories 1.0000 Ls Rp 4,950.00 Rp 4,950.00
B. UPAH
1 Pekerja 0.0350 Oh Rp 120,000.00 Rp 4,200.00
2 Tukang Batu 0.0120 Oh Rp 173,700.00 Rp 2,084.40
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
Jumlah Rp 49,434.40
Overhead & Profit Rp 7,415.16
JUMLAH Rp 56,849.56

PEMASANGAN PIPA PVC 2 INC (M')


A. BAHAN
1 Pipa PVC Dia. 2" 1.2000 M' Rp 25,000.00 Rp 30,000.00
2 Accessories 1.0000 Ls Rp 4,500.00 Rp 4,500.00
B. UPAH
1 Pekerja 0.0810 Oh Rp 120,000.00 Rp 9,720.00
2 Tukang Batu 0.0140 Oh Rp 173,700.00 Rp 2,431.80
3 Kepala Tukang 0.0140 Oh Rp 208,000.00 Rp 2,912.00
4 Mandor 0.0040 Oh Rp 208,000.00 Rp 832.00
Jumlah Rp 50,395.80
Overhead & Profit Rp 7,559.37
JUMLAH Rp 57,955.17

PEMASANGAN PIPA PVC 3/4 INC (M')


A. BAHAN
1 Pipa PVC Dia. 3/4" 1.2000 M' Rp 25,000.00 Rp 30,000.00
2 Accessories 1.0000 Ls Rp 4,500.00 Rp 4,500.00
B. UPAH
1 Pekerja 0.0810 Oh Rp 120,000.00 Rp 9,720.00
2 Tukang Batu 0.0140 Oh Rp 173,700.00 Rp 2,431.80
3 Kepala Tukang 0.0140 Oh Rp 208,000.00 Rp 2,912.00
4 Mandor 0.0040 Oh Rp 208,000.00 Rp 832.00
Jumlah Rp 50,395.80
Overhead & Profit Rp 7,559.37
JUMLAH Rp 57,955.17

3 PEMASANGAN PIPA PVC 1/2 INC (M')


A. BAHAN
1 Pipa PVC Dia. 1/2" 1.2000 M' Rp 22,500.00 Rp 27,000.00
2 Accessories 1.0000 Ls Rp 4,050.00 Rp 4,050.00
B. UPAH
1 Pekerja 0.0260 Oh Rp 120,000.00 Rp 3,120.00
2 Tukang Batu 0.0400 Oh Rp 173,700.00 Rp 6,948.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0020 Oh Rp 208,000.00 Rp 416.00
Jumlah Rp 42,782.00
Overhead & Profit Rp 6,417.30
JUMLAH Rp 49,199.30

7 PEMASANGAN KLOSET DUDUK (BH)


A. BAHAN
1 Kloset Duduk 1.0000 Bh Rp 1,750,000.00 Rp 1,750,000.00
2 Semen Portland 0.1200 Zak Rp 71,875.00 Rp 8,625.00
3 Pasir Pasang 0.0100 M3 Rp 345,000.00 Rp 3,450.00
B. UPAH
1 Tukang Batu 1.5000 Oh Rp 173,700.00 Rp 260,550.00
2 Kepala Tukang 1.5000 Oh Rp 208,000.00 Rp 312,000.00
3 Mandor 0.1600 Oh Rp 208,000.00 Rp 33,280.00
4 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
Rp 2,487,905.00
Rp 373,185.75
JUMLAH Rp 2,861,090.75

4 PEMASANGAN KLOSET JONGKOK (BH)


A. BAHAN
1 Kloset Jongkok 1.0000 Bh Rp 451,000.00 Rp 451,000.00
2 Semen Portland 0.1200 Zak Rp 71,875.00 Rp 8,625.00
3 Pasir Pasang 0.0100 M3 Rp 345,000.00 Rp 3,450.00
B. UPAH
1 Tukang Batu 1.5000 Oh Rp 173,700.00 Rp 260,550.00
2 Kepala Tukang 1.5000 Oh Rp 208,000.00 Rp 312,000.00
3 Mandor 0.1600 Oh Rp 208,000.00 Rp 33,280.00
4 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
Jumlah Rp 1,188,905.00
Overhead & Profit Rp 178,335.75
JUMLAH Rp 1,367,240.75
5 PEMASANGAN KRAN (BH)
A. BAHAN
1 Kran Air 1/2" 1.0000 Bh Rp 25,000.00 Rp 25,000.00
2 Seal Tape 0.0250 Bh Rp 5,000.00 Rp 125.00
B. UPAH
1 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
2 Kepala Tukang 0.0050 Oh Rp 208,000.00 Rp 1,040.00
3 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
Jumlah Rp 46,815.00
Overhead & Profit Rp 7,022.25
JUMLAH Rp 53,837.25

6 PEMASANGAN FLORDRAIN (BH)


A. BAHAN
1 Floor Drain 1.0000 Bh Rp 35,000.00 Rp 35,000.00
B. UPAH
1 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
Jumlah Rp 56,690.00
Overhead & Profit Rp 8,503.50
JUMLAH Rp 65,193.50
ANALISA HARGA SATUAN

PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS


KEGIATAN :
DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 MCB (BH)
A. BAHAN
1 MCB 16 A 1.0000 Bh Rp 115,000.00 Rp 115,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 132,370.00
Overhead & Profit Rp 19,855.50
JUMLAH Rp 152,225.50

2 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 4 x 6 mm 1.0000 M' Rp 30,000.00 Rp 30,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp -
JUMLAH Rp 30,000.00

3 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 4 x 3,5 mm 1.0000 M' Rp 27,000.00 Rp 27,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp -
JUMLAH Rp 27,000.00

2 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 3 x 2,5 mm 1.0000 M' Rp 13,000.00 Rp 13,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 30,370.00
Overhead & Profit Rp 4,555.50
JUMLAH Rp 34,925.50

3 INSTALASI KABEL NYM (M')


A. BAHAN
1 Kabel NYM 2 x 2,5 mm 1.0000 M' Rp 12,800.00 Rp 12,800.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 30,170.00
Overhead & Profit Rp 4,525.50
JUMLAH Rp 34,695.50

4 SAKLAR SERI PANASONIC (BH)


A. BAHAN
1 Saklar Seri Panasonic 1.0000 Bh Rp 47,300.00 Rp 47,300.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 64,670.00
Overhead & Profit Rp 9,700.50
JUMLAH Rp 74,370.50

5 SAKLAR TUNGGAL PANASONIC (BH)


A. BAHAN
1 Saklar Tunggal Panasonic 1.0000 Bh Rp 44,275.00 Rp 44,275.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 61,645.00
Overhead & Profit Rp 9,246.75
JUMLAH Rp 70,891.75

6 STOP KONTAK TANAM PANASONIC (BH)


A. BAHAN
1 Stop Kontak Tanam Panasonic 1.0000 Bh Rp 53,350.00 Rp 53,350.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 70,720.00
Overhead & Profit Rp 10,608.00
JUMLAH Rp 81,328.00

7 STOP KONTAK TANAM AC PANASONIC (BH)


A. BAHAN
1 Stop Kontak Tanam AC Panasonic 1.0000 Bh Rp 35,000.00 Rp 35,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 52,370.00
Overhead & Profit Rp 7,855.50
JUMLAH Rp 60,225.50

10 DOWN LIGTH 5 INCHI (BH)


A. BAHAN
1 Down Ligth 5 Inchi 1.0000 Bh Rp 50,000.00 Rp 50,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp -
JUMLAH Rp 50,000.00

11 BALON PHILIPS LED 7 WATT (BH)


A. BAHAN
1 Balon Philips LED 7 Watt 1.0000 Bh Rp 35,000.00 Rp 35,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp -
JUMLAH Rp 35,000.00

8 BALON PHILIPS LED 25 WATT (BH)


A. BAHAN
1 Balon Philips LED 25 Watt 1.0000 Bh Rp 90,000.00 Rp 90,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 107,370.00
Overhead & Profit Rp 16,105.50
JUMLAH Rp 123,475.50

9 BALON PHILIPS LED 11 WATT (BH)


A. BAHAN
1 Balon Philips LED 11 Watt 1.0000 Bh Rp 60,000.00 Rp 60,000.00
B. UPAH
1 Upah Pasang 0.1000 Oh Rp 173,700.00 Rp 17,370.00
Jumlah Rp 77,370.00
Overhead & Profit Rp 11,605.50
JUMLAH Rp 88,975.50
ANALISA HARGA SATUAN
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH
KEGIATAN :
PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 BESI BETON (KG)


A. BAHAN
1 Besi Beton 1.0500 Kg Rp 316,000.00 Rp 331,800.00
2 Kawat Ikat Beton 0.0150 Kg Rp 52,675.00 Rp 790.13
B. UPAH
1 Pekerja 0.0070 Oh Rp 120,000.00 Rp 840.00
2 Tukang Besi Beton 0.0070 Oh Rp 173,700.00 Rp 1,215.90
3 Kepala Tukang 0.0007 Oh Rp 208,000.00 Rp 145.60
4 Mandor 0.0004 Oh Rp 208,000.00 Rp 83.20
JUMLAH Rp 334,874.83

17 BESI BAJA WF (KG)


A. BAHAN
1 Besi Baja WF 1.1500 Kg Rp - Rp -
2 Kawat Las 0.0400 Kg Rp 52,675.00 Rp 2,107.00
3 Solar 0.0300 Ltr Rp - Rp -
4 Minyak Pelumas 0.0040 Ltr Rp - Rp -
5 Sewa Alat 0.0170 Jam Rp 100,000.00 Rp 1,700.00

B. UPAH
1 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
2 Tukang Las Konstruksi 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH Rp 23,301.00

18 BESI PROFIL KANAL C,CNP (KG)


A. BAHAN
1 Besi Profil Kanal C 125 1.1500 Kg Rp - Rp -
B. UPAH
1 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
2 Tukang Las Konstruksi 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
JUMLAH Rp 19,494.00

PAS. KUSEN PINTU/JENDELA ALUMUNIUM WARNA 4"(M')


A. BAHAN
1 Aluminium Profil Warna 4" 1.1000 M' Rp 50,000.00 Rp 55,000.00
2 Sekrup Fixer 2.0000 Bh Rp 15,360.00 Rp 30,720.00
3 Sealent 4.0000 Tube Rp 25,000.00 Rp 100,000.00
B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Aluminium 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0220 Oh Rp 208,000.00 Rp 4,576.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 256,921.00

1 PAS. BINGKAI JENDELA ALLUMUNIUM KACA 5 MM (M2)


A. BAHAN
1 Aluminium Profil Warna 4" 4.1000 M' Rp 50,000.00 Rp 205,000.00
2 Kaca 5 mm 1.1000 M2 Rp 480,000.00 Rp 528,000.00
3 Sealent 0.2700 Tube Rp 25,000.00 Rp 6,750.00
B. UPAH
1 Pekerja 0.0850 Oh Rp 120,000.00 Rp 10,200.00
2 Tukang Aluminium 0.0850 Oh Rp 173,700.00 Rp 14,764.50
3 Kepala Tukang 0.0090 Oh Rp 208,000.00 Rp 1,872.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 767,626.50

27 PAS. PINTU ROLLING DOOR (M2)


A. BAHAN
1 Rolling Door Alluminium 1.0000 M2 Rp 480,000.00 Rp 480,000.00
B. UPAH
1 Pekerja 1.0500 Oh Rp 120,000.00 Rp 126,000.00
2 Tukang Aluminium 1.5000 Oh Rp 173,700.00 Rp 260,550.00
3 Kepala Tukang 0.1050 Oh Rp 208,000.00 Rp 21,840.00
4 Mandor 0.0052 Oh Rp 208,000.00 Rp 1,081.60
JUMLAH Rp 889,471.60

PAS.PINTU KACA TEMPERED (M2)


A. BAHAN
1 List Alluminium U 4.4000 M' Rp 70,000.00 Rp 308,000.00
2 Kaca Tempered 12 mm 1.1000 M2 Rp 670,000.00 Rp 737,000.00
3 Floor Hinges 2.0000 Set Rp 900,000.00 Rp 1,800,000.00
4 Over Panel 2.0000 Set Rp 950,000.00 Rp 1,900,000.00
5 Top Patch Fitting 2.0000 Set Rp 650,000.00 Rp 1,300,000.00
6 Bottom Patch Fitting 2.0000 Set Rp 650,000.00 Rp 1,300,000.00
7 Bottom Patch Lock+Cylinder 2.0000 Set Rp 950,000.00 Rp 1,900,000.00
8 Pull Handle 2.0000 Set Rp 1,300,000.00 Rp 2,600,000.00
B. UPAH
1 Pekerja 0.0850 Oh Rp 120,000.00 Rp 10,200.00
2 Tukang Aluminium 0.0850 Oh Rp 173,700.00 Rp 14,764.50
3 Kepala Tukang 0.0090 Oh Rp 208,000.00 Rp 1,872.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 11,872,876.50

1 PEKERJAAN RANGKA PLAFOND BESI HOLLOW (M2)


A. BAHAN
1 Besi Hollow 40x40x2 0.4150 Btg Rp 303,700.00 Rp 126,035.50
2 Hollow 2/4 0.1500 Btg Rp 52,675.00 Rp 7,901.25
3 Ramset/Dinabolt 4.0000 Bh Rp 8,000.00 Rp 32,000.00
B. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Tukang 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
Jumlah Rp 328,386.75
Overhead & Profit Rp 49,258.01
JUMLAH Rp 377,644.76

PEKERJAAN RANGKA PLAFOND BESI HOLLOW (M2)


A. BAHAN
1 Besi Hollow 40x40x2 0.4150 Btg Rp 303,700.00 Rp 126,035.50
2 Alat Bantu 1.0000 Ls Rp 30,000.00 Rp 30,000.00
B. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Tukang 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
Jumlah Rp 318,485.50
Overhead & Profit Rp 47,772.83
JUMLAH Rp 366,258.33

2 PASANG PLAFOND GYPSUM BOARD (M2)


A. BAHAN
1 Gypsum Board 0.4600 Lbr Rp 70,000.00 Rp 32,200.00
2 Tepung Gypsum 0.4400 Kg Rp 40,000.00 Rp 17,600.00
3 Tape Textile 1.5000 M' Rp 20,000.00 Rp 30,000.00
4 Paku Gypsum 0.1100 Kg Rp 15,000.00 Rp 1,650.00
B. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Tukang 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
Jumlah Rp 243,900.00
Overhead & Profit Rp 36,585.00
JUMLAH Rp 280,485.00

3 PASANG LIST PLAFOND GYPSUM BOARD (M')


A. BAHAN
1 List Gypsum profil 1.0500 M' Rp 30,000.00 Rp 31,500.00
2 Tepung Gypsum 0.4400 Kg Rp 40,000.00 Rp 17,600.00
B. UPAH
1 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
2 Tukang 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
Jumlah Rp 68,594.00
Overhead & Profit Rp 10,289.10
JUMLAH Rp 78,883.10

2 PEKERJAAN RANGKA ALLUMUNIUM (M')


A. BAHAN
1 Aluminium Profil Warna 4" 1.0500 M' Rp 15,360.00 Rp 16,128.00
2 Sekrup Fixer 1.0000 Bh Rp -
3 Sealent 4.0000 Tube Rp -
B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Aluminium 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0220 Oh Rp 208,000.00 Rp 4,576.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 87,329.00

54 PENUTUP ATAP SPANDEK 0,3 (M2)


A. BAHAN
1 Spandek 1.1000 M2 Rp 37,750.00 Rp 41,525.00
2 Bout Sekrup 0.0100 Kg Rp 15,000.00 Rp 150.00
B. UPAH
1 Pekerja 0.1000 Oh Rp 120,000.00 Rp 12,000.00
2 Tukang Batu 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 101,260.00

BUBUNGAN ATAP SPANDEK (M')


A. BAHAN
1 Nok Spandek 0.7000 Lbr Rp 54,900.00 Rp 38,430.00
2 Bout Sekrup 0.0200 Kg Rp 15,000.00 Rp 300.00
B. UPAH
1 Pekerja 0.1200 Oh Rp 120,000.00 Rp 14,400.00
2 Tukang Batu 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
JUMLAH Rp 66,048.00

4 RANGKA BAJA RINGAN (main truss C75-0,75)/Profil C (M2)


A. BAHAN
1 Main truss (C75-0,75) 2.0000 M' Rp 23,000.00 Rp 46,000.00
2 Reng U tipe 41 -33 3.0000 Bh Rp 11,000.00 Rp 33,000.00
3 Screw 12 - 14 x 20 9.0000 Pc Rp 11,000.00 Rp 99,000.00
4 Screw 10 - 16 x 16 11.0000 Pc Rp 13,000.00 Rp 143,000.00
5 Baut dinabolt 0.6000 Pc Rp 8,000.00 Rp 4,800.00
B. UPAH
1 Pekerja 0.1200 Oh Rp 120,000.00 Rp 14,400.00
2 Tukang Batu 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
Jumlah Rp 353,118.00
Overhead & Profit Rp 52,967.70
JUMLAH Rp 406,085.70

PEKERJAAN RANGKA ATAP PIPA GALVANIS (M2)


A. BAHAN
1 Pipa Galvanis 1 - 2 " 4.6000 M' Rp 120,000.00 Rp 552,000.00
2 Accesories 1.0000 Ls Rp 165,600.00 Rp 165,600.00
3 Pengelasan 1.0000 Ls Rp 138,000.00 Rp 138,000.00
B. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Tukang Aluminium 0.5000 Oh Rp 173,700.00 Rp 86,850.00
3 Kepala Tukang 0.0500 Oh Rp 208,000.00 Rp 10,400.00
4 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 1,018,050.00

PEKERJAAN COVERING ACP (M2)


A. BAHAN
1 Allumunium Composite 1.1000 M2 Rp 420,000.00 Rp 462,000.00
2 Besi Hollow Galvanis 4x4x1 mm 0.8000 Btg Rp 50,000.00 Rp 40,000.00
3 Braket Siku/Spigot/Stifner 0.2670 Btg Rp 60,000.00 Rp 16,020.00
4 Paku Sekrup Beton 0.0800 Kg Rp 21,000.00 Rp 1,680.00
5 Paku Sekrup 0.1100 Kg Rp 21,000.00 Rp 2,310.00
6 Sealant 0.2500 Tube Rp 25,000.00 Rp 6,250.00
B. PERALATAN
1 Sewa Stager(2 set) 0.0200 Set Rp 150,000.00 Rp 3,000.00
2 Listrik Kerja 1.0000 Ls Rp 10,000.00 Rp 10,000.00
3 Alat Bantu Lainnya 1.0000 Ls Rp 10,000.00 Rp 10,000.00
C. UPAH
1 Pekerja 0.3900 Oh Rp 120,000.00 Rp 46,800.00
2 Tukang Besi/Las 0.7000 Oh Rp 173,700.00 Rp 121,590.00
3 Kepala Tukang 0.0700 Oh Rp 208,000.00 Rp 14,560.00
4 Mandor 0.0070 Oh Rp 208,000.00 Rp 1,456.00
JUMLAH Rp 735,666.00
ANALISA HARGA SATUAN
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH
KEGIATAN :
PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 GALIAN TANAH BIASA SEDALAM 1 M (M3)


A. UPAH
1 Pekerja 0.7500 Oh Rp 120,000.00 Rp 90,000.00
2 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
Jumlah Rp 95,200.00
Overhead & Profit Rp 14,280.00
JUMLAH Rp 109,480.00

2 GALIAN TANAH BIASA SEDALAM 2 M (M3)


A. UPAH
1 Pekerja 0.9000 Oh Rp 120,000.00 Rp 108,000.00
2 Mandor 0.0450 Oh Rp 208,000.00 Rp 9,360.00
JUMLAH Rp 117,360.00

3 GALIAN TANAH BIASA SEDALAM 3 M (M3)


A. UPAH
1 Pekerja 1.0500 Oh Rp 120,000.00 Rp 126,000.00
2 Mandor 0.0670 Oh Rp 208,000.00 Rp 13,936.00
JUMLAH Rp 139,936.00

4 GALIAN TANAH KERAS SEDALAM 1 M (M3)


A. UPAH
1 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
2 Mandor 0.3200 Oh Rp 208,000.00 Rp 66,560.00
JUMLAH Rp 186,560.00

5 GALIAN TANAH CADAS SEDALAM 1 M (M3)


A. UPAH
1 Pekerja 1.5000 Oh Rp 120,000.00 Rp 180,000.00
2 Mandor 0.0600 Oh Rp 208,000.00 Rp 12,480.00
JUMLAH Rp 192,480.00

6 GALIAN TANAH LUMPUR SEDALAM 1 M (M3)


A. UPAH
1 Pekerja 1.2000 Oh Rp 120,000.00 Rp 144,000.00
2 Mandor 0.0450 Oh Rp 208,000.00 Rp 9,360.00
JUMLAH Rp 153,360.00

7 STRIPPING TEBING SETINGGI 1 M (M2)


A. UPAH
1 Pekerja 0.0500 Oh Rp 120,000.00 Rp 6,000.00
2 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 7,040.00

8 MEMBUANG TANAH SEJAUH 15 METER (M3)


A. UPAH
1 Pekerja 0.3300 Oh Rp 120,000.00 Rp 39,600.00
2 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 41,680.00

9 MEMADATKAN TANAH PER 20 cm (M3)


A. UPAH
1 Pekerja 0.5000 Oh Rp 120,000.00 Rp 60,000.00
2 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 70,400.00

2 URUG KEMBALI TANAH GALIAN (M3)


A. UPAH
1 Pekerja 0.2500 Oh Rp 120,000.00 Rp 30,000.00
2 Mandor 0.0080 Oh Rp 208,000.00 Rp 1,664.00
Jumlah Rp 31,664.00
Overhead & Profit Rp 4,749.60
JUMLAH Rp 36,413.60

11 URUG KEMBALI TANAH HUMUS (M3)


A. UPAH
1 Pekerja 0.2500 Oh Rp 120,000.00 Rp 30,000.00
2 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
JUMLAH Rp 35,200.00

1 URUGAN PASIR URUG (M3)


A. BAHAN
1 Pasir Urug (Sirtu) 1.2000 M3 Rp 159,000.00 Rp 190,800.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
Jumlah Rp 228,880.00
Overhead & Profit Rp 34,332.00
JUMLAH Rp 263,212.00

2 URUGAN TANAH PILIHAN (M3)


A. BAHAN
1 Tanah Urug Pilihan 1.2000 M3 Rp 101,000.00 Rp 121,200.00
B. UPAH
1 Pekerja 0.2500 Oh Rp 120,000.00 Rp 30,000.00
2 Mandor 0.0250 Oh Rp 208,000.00 Rp 5,200.00
Jumlah Rp 156,400.00
Overhead & Profit Rp 23,460.00
JUMLAH Rp 179,860.00
ANALISA HARGA SATUAN
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN
KEGIATAN :
STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

PAS. DINDING ROSTER BETON (M2)


A. BAHAN
1 Roster Beton 17.0000 Bh Rp 42,000.00 Rp 714,000.00
2 Semen Portland 0.1972 Zak Rp 71,875.00 Rp 14,173.75
3 Pasir Pasang 0.0450 M3 Rp 345,000.00 Rp 15,525.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0150 Oh Rp 208,000.00 Rp 3,120.00
JUMLAH Rp 802,268.75

PAS. DINDING BATU BATA TELA PRESS 1 PC : 4 PS (M2)


A. BAHAN
1 Batu Bata Tela 45.0000 Bh Rp 1,725.00 Rp 77,625.00
2 Semen Portland 0.2300 Zak Rp 71,875.00 Rp 16,531.25
3 Pasir Pasang/Halus 0.0430 M3 Rp 345,000.00 Rp 14,835.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0150 Oh Rp 208,000.00 Rp 3,120.00
Jumlah Rp 167,561.25
Overhead & Profit Rp 25,134.19
JUMLAH Rp 192,695.44

PLESTERAN DINDING CAMP 1 PC : 4 PS (M2)


A. BAHAN
1 Pasir Pasang/Halus 0.0230 m3 Rp 345,000.00 Rp 7,935.00
2 Semen Portland 0.1555 Zak Rp 71,875.00 Rp 11,178.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Batu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0150 Oh Rp 208,000.00 Rp 3,120.00
Jumlah Rp 87,408.00
Overhead & Profit Rp 13,111.20
JUMLAH Rp 100,519.20

PEK. ACIAN DINDING (M2)


A. BAHAN
1 Semen Portland 0.0651 Zak Rp 71,875.00 Rp 4,679.06
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Batu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
Jumlah Rp 50,209.06
Overhead & Profit Rp 7,531.36
JUMLAH Rp 57,740.42
PEK. PEMASANGAN KERAMIK LANTAI GRANIT 60 x 60 (M2)
A. BAHAN
1 Keramik Granit 60 x 60 3.0000 Bh Rp 66,666.67 Rp 200,000.00
2 Semen Portland 0.1680 Zak Rp 71,875.00 Rp 12,075.00
3 Pasir Pasang 0.0420 M3 Rp 345,000.00 Rp 14,490.00
4 Semen Warna 0.5000 Kg Rp 17,940.00 Rp 8,970.00
B. UPAH
1 Pekerja 0.6200 Oh Rp 120,000.00 Rp 74,400.00
2 Tukang Batu 0.3500 Oh Rp 173,700.00 Rp 60,795.00
3 Kepala Tukang 0.0350 Oh Rp 208,000.00 Rp 7,280.00
4 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
Jumlah Rp 378,634.00
Overhead & Profit Rp 56,795.10
JUMLAH Rp 435,429.10
ANALISA HARGA SATUAN
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH
KEGIATAN :
PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 PASANGAN BATU KOSONG (M3)


A. BAHAN
1 Batu Kali/Gunung 1.2000 M3 Rp 144,000.00 Rp 172,800.00
2 Pasir Urug 0.3000 M3 Rp 159,000.00 Rp 47,700.00
B. UPAH
1 Pekerja 0.7800 Oh Rp 120,000.00 Rp 93,600.00
2 Kapala Tukang 0.0390 Oh Rp 208,000.00 Rp 8,112.00
3 Mandor 0.0390 Oh Rp 208,000.00 Rp 8,112.00
4 Tukang Batu 0.3900 Oh Rp 173,700.00 Rp 67,743.00
Jumlah Rp 398,067.00
Overhead & Profit Rp 59,710.05
JUMLAH Rp 457,777.05

2 PEK. PASANGAN BATU KALI 1 : 4 (M3)


A. BAHAN
1 Batu Kali/Gunung 1.2000 M3 Rp 144,000.00 Rp 172,800.00
2 Semen Portland 3.2600 Zak Rp 71,875.00 Rp 234,312.50
3 Pasir Pasang 0.5200 M3 Rp 345,000.00 Rp 179,400.00
B. UPAH
1 Pekerja 1.5000 Oh Rp 120,000.00 Rp 180,000.00
2 Tukang Batu 0.7500 Oh Rp 173,700.00 Rp 130,275.00
3 Kepala Tukang 0.0750 Oh Rp 208,000.00 Rp 15,600.00
4 Mandor 0.0750 Oh Rp 208,000.00 Rp 15,600.00
Jumlah Rp 927,987.50
Overhead & Profit Rp 139,198.13
JUMLAH Rp 1,067,185.63

3 PEK. PASANGAN BATU KALI 1 : 3 (M3)


A. BAHAN
1 Batu Kali/Gunung 1.2000 M3 Rp 144,000.00 Rp 172,800.00
2 Semen Portland 4.0400 Zak Rp 71,875.00 Rp 290,375.00
3 Pasir Pasang 0.4850 M3 Rp 345,000.00 Rp 167,325.00
B. UPAH
1 Pekerja 1.5000 Oh Rp 120,000.00 Rp 180,000.00
2 Tukang Batu 0.7500 Oh Rp 173,700.00 Rp 130,275.00
3 Kepala Tukang 0.0750 Oh Rp 208,000.00 Rp 15,600.00
4 Mandor 0.0750 Oh Rp 208,000.00 Rp 15,600.00
JUMLAH Rp 971,975.00

4 PEK. PASANGAN BATU KALI 1 : 5 (M3)


A. BAHAN
1 Batu Kali/Gunung 1.2000 M3 Rp 144,000.00 Rp 172,800.00
2 Semen Portland 2.7200 Zak Rp 71,875.00 Rp 195,500.00
3 Pasir Pasang 0.5440 M3 Rp 345,000.00 Rp 187,680.00
B. UPAH
1 Pekerja 1.5000 Oh Rp 120,000.00 Rp 180,000.00
2 Tukang Batu 0.7500 Oh Rp 173,700.00 Rp 130,275.00
3 Kepala Tukang 0.0750 Oh Rp 208,000.00 Rp 15,600.00
4 Mandor 0.0750 Oh Rp 208,000.00 Rp 15,600.00
JUMLAH Rp 897,455.00

5 PEK. PASANGAN BATU KALI 1 : 6 (M3)


A. BAHAN
1 Batu Kali/Gunung 1.2000 M3 Rp 144,000.00 Rp 172,800.00
2 Semen Portland 2.3400 Zak Rp 71,875.00 Rp 168,187.50
3 Pasir Pasang 0.5610 M3 Rp 345,000.00 Rp 193,545.00
B. UPAH
1 Pekerja 1.5000 Oh Rp 120,000.00 Rp 180,000.00
2 Tukang Batu 0.7500 Oh Rp 173,700.00 Rp 130,275.00
3 Kepala Tukang 0.0750 Oh Rp 208,000.00 Rp 15,600.00
4 Mandor 0.0750 Oh Rp 208,000.00 Rp 15,600.00
JUMLAH Rp 876,007.50
ANALISA HARGA SATUAN

KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI

PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE


LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

LANTAI KERJA BETON 1 : 3 : 5 ; T. 5 CM (M3)


A. BAHAN
1 Semen Portland 4.9400 Zak Rp 71,875.00 Rp 355,062.50
2 Pasir Beton 0.6207 M3 Rp 345,000.00 Rp 214,146.43
3 Batu Pecah 2/3 0.3842 M3 Rp 403,000.00 Rp 154,845.00
B. UPAH
1 Pekerja 0.0825 Oh Rp 120,000.00 Rp 9,900.00
2 Tukang Batu 0.0125 Oh Rp 173,700.00 Rp 2,171.25
3 Kepala Tukang 0.0013 Oh Rp 208,000.00 Rp 260.00
4 Mandor 0.0040 Oh Rp 208,000.00 Rp 832.00
Jumlah Rp 737,217.18
Overhead & Profit Rp 110,582.58
JUMLAH Rp 847,799.76

BETON K-275 (M3)


A. BAHAN
1 Semen Portland 8.12 Zak Rp 71,875.00 Rp 583,625.00
2 Pasir Beton 684.00 Kg Rp 224.03 Rp 153,233.77
3 Batu Pecah 2/3 1,026.00 Kg Rp 230.29 Rp 236,273.14
4 Air Bersih 215.00 Ltr Rp 1,500.00 Rp 322,500.00
5 Concrete Mixer 0.4016 Jam Rp 250,000.00 Rp 100,401.61
B. UPAH
1 Pekerja 1.6500 Oh Rp 120,000.00 Rp 198,000.00
2 Tukang Batu 0.2750 Oh Rp 173,700.00 Rp 47,767.50
3 Kepala Tukang 0.0280 Oh Rp 208,000.00 Rp 5,824.00
4 Mandor 0.0830 Oh Rp 208,000.00 Rp 17,264.00
Jumlah Rp 1,664,889.02
OverHead & Profit Rp 249,733.35
Harga Satuan Pekerjaan Rp 1,914,622.37

BETON K-250 (M3)


A. BAHAN
1 Semen Portland 8.26 Zak Rp 71,875.00 Rp 593,687.50
2 Pasir Beton 0.49 M3 Rp 345,000.00 Rp 167,808.00
3 Batu Pecah 2/3 0.57 M3 Rp 403,000.00 Rp 228,581.60
4 Air Bersih 215.00 Ltr Rp 1,500.00 Rp 322,500.00

B. UPAH
1 Pekerja 1.6500 Oh Rp 120,000.00 Rp 198,000.00
2 Tukang Batu 0.2750 Oh Rp 173,700.00 Rp 47,767.50
3 Kepala Tukang 0.0280 Oh Rp 208,000.00 Rp 5,824.00
4 Mandor 0.0830 Oh Rp 208,000.00 Rp 17,264.00
JUMLAH Rp 1,581,432.60

3 BEKISTING PONDASI (M2)


A. BAHAN
1 Paku Campur 0.30 Kg Rp 21,000.00 Rp 6,300.00
2 Minyak Bekisting 0.10 Ltr Rp 33,000.00 Rp 3,300.00
3 Kayu Kls III 0.04 M3 Rp 3,450,000.00 Rp 138,000.00
B. UPAH
1 Pekerja 0.30 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Kayu 0.26 Oh Rp 173,700.00 Rp 45,162.00
3 Kepala Tukang 0.03 Oh Rp 208,000.00 Rp 5,408.00
4 Mandor 0.01 Oh Rp 208,000.00 Rp 1,040.00
Jumlah Rp 235,210.00
Overhead & Profit Rp 35,281.50
JUMLAH Rp 270,491.50
4 BEKISTING KOLOM (M2)
A. BAHAN
1 Kayu Kls II 0.04 M3 Rp 3,450,000.00 Rp 138,000.00
2 Paku Campur 0.40 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.20 Ltr Rp 33,000.00 Rp 6,600.00
B. UPAH
1 Pekerja 0.60 Oh Rp 120,000.00 Rp 72,000.00
2 Tukang Kayu 0.33 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.03 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.01 Oh Rp 208,000.00 Rp 1,248.00
Jumlah Rp 290,433.00
Overhead & Profit Rp 43,564.95
JUMLAH Rp 333,997.95

5 BEKISTING SLOOF (M2)


A. BAHAN
1 Paku Campur 0.3000 Kg Rp 21,000.00 Rp 6,300.00
2 Minyak Bekisting 0.1000 Ltr Rp 33,000.00 Rp 3,300.00
3 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
B. UPAH
1 Pekerja 0.3000 Oh Rp 120,000.00 Rp 36,000.00
2 Tukang Kayu 0.2600 Oh Rp 173,700.00 Rp 45,162.00
3 Kepala Tukang 0.0260 Oh Rp 208,000.00 Rp 5,408.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
Jumlah Rp 235,210.00
Overhead & Profit Rp 35,281.50
JUMLAH Rp 270,491.50

6 BEKISTING BALOK (M2)


A. BAHAN
1 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Paku Campur 0.4000 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.2000 Ltr Rp 33,000.00 Rp 6,600.00
B. UPAH
1 Pekerja 0.6600 Oh Rp 120,000.00 Rp 79,200.00
2 Tukang Kayu 0.3300 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.0330 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
Jumlah Rp 297,633.00
Overhead & Profit Rp 44,644.95
JUMLAH Rp 342,277.95

7 BEKISTING TANGGA (M2)


A. BAHAN
1 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Paku Campur 0.4000 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.1500 Ltr Rp 33,000.00 Rp 4,950.00

B. UPAH
1 Pekerja 0.6600 Oh Rp 120,000.00 Rp 79,200.00
2 Tukang Kayu 0.3300 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.0330 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
Jumlah Rp 295,983.00
Overhead & Profit Rp 44,397.45
JUMLAH Rp 340,380.45

3 BEKISTING LANTAI (M2)


A. BAHAN
1 Kayu Kls II 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Paku Campur 0.4000 Kg Rp 21,000.00 Rp 8,400.00
3 Minyak Bekisting 0.2000 Ltr Rp 33,000.00 Rp 6,600.00
B. UPAH
1 Pekerja 0.6600 Oh Rp 120,000.00 Rp 79,200.00
2 Tukang Kayu 0.3300 Oh Rp 173,700.00 Rp 57,321.00
3 Kepala Tukang 0.0330 Oh Rp 208,000.00 Rp 6,864.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
Jumlah Rp 297,633.00
Overhead & Profit Rp 44,644.95
JUMLAH Rp 342,277.95

9 160 KG BESI BETON PER 1 M3 BETON


A. BAHAN
1 Besi Beton Polos/Ulir 160.0000 Kg Rp 26,333.33 Rp 4,213,333.33
2 Kawat Ikat Beton 3.0000 Kg Rp 480,000.00 Rp 1,440,000.00
B. UPAH
1 Pekerja 0.0070 Oh Rp 120,000.00 Rp 840.00
2 Tukang Besi Beton 0.0070 Oh Rp 173,700.00 Rp 1,215.90
3 Kepala Tukang 0.0007 Oh Rp 208,000.00 Rp 145.60
4 Mandor 0.0004 Oh Rp 208,000.00 Rp 83.20
JUMLAH Rp 5,655,618.03

10 130 KG BESI BETON PER 1 M3 BETON


A. BAHAN
1 Besi Beton Polos/Ulir 130.0000 Kg Rp 26,333.33 Rp 3,423,333.33
2 Kawat Ikat Beton 3.0000 Kg Rp 52,675.00 Rp 158,025.00
B. UPAH
1 Pekerja 0.0070 Oh Rp 120,000.00 Rp 840.00
2 Tukang Besi Beton 0.0070 Oh Rp 173,700.00 Rp 1,215.90
3 Kepala Tukang 0.0007 Oh Rp 208,000.00 Rp 145.60
4 Mandor 0.0004 Oh Rp 208,000.00 Rp 83.20
JUMLAH Rp 3,583,643.03

11 115 KG BESI BETON PER 1 M3 BETON


A. BAHAN
1 Besi Beton Polos/Ulir 115.0000 Kg Rp 26,333.33 Rp 3,028,333.33
2 Kawat Ikat Beton 0.0150 Kg Rp 52,675.00 Rp 790.13
B. UPAH
1 Pekerja 0.0070 Oh Rp 120,000.00 Rp 840.00
2 Tukang Besi Beton 0.0070 Oh Rp 173,700.00 Rp 1,215.90
3 Kepala Tukang 0.0007 Oh Rp 208,000.00 Rp 145.60
4 Mandor 0.0004 Oh Rp 208,000.00 Rp 83.20
JUMLAH Rp 3,031,408.16

3 PEMBESIAN 100 KG BESI DENGAN BESI POLOS ATAU ULIR


A. BAHAN
1 Besi Beton Polos/Ulir 105.0000 Kg Rp 23,500.00 Rp 2,467,500.00
2 Kawat Ikat Beton 2.1000 Kg Rp 52,675.00 Rp 110,617.50
B. UPAH
1 Pekerja 2.1000 Oh Rp 120,000.00 Rp 252,000.00
2 Tukang Besi Beton 1.4000 Oh Rp 173,700.00 Rp 243,180.00
3 Kepala Tukang 0.1400 Oh Rp 208,000.00 Rp 29,120.00
4 Mandor 0.2100 Oh Rp 208,000.00 Rp 43,680.00
Jumlah Rp 3,146,097.50
Overhead & Profit Rp 157,304.88
JUMLAH 100 KG Rp 3,303,402.38
JUMLAH 1 KG Rp 33,034.02
ANALISA HARGA SATUAN
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH
KEGIATAN :
PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 PEK. KUSEN PINTU DAN JENDELA KAYU KLS 1 (M3)


A. BAHAN
1 Kayu Kls I 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Paku Campur 1.2500 Kg Rp 21,000.00 Rp 26,250.00
3 Lem Kayu 1.0000 Kg Rp 40,000.00 Rp 40,000.00
B. UPAH
1 Pekerja 7.0000 Oh Rp 120,000.00 Rp 840,000.00
2 Tukang Kayu 13.0000 Oh Rp 173,700.00 Rp 2,258,100.00
3 Kepala Tukang 2.1000 Oh Rp 208,000.00 Rp 436,800.00
4 Mandor 0.3500 Oh Rp 208,000.00 Rp 72,800.00
Jumlah Rp 11,896,450.00
Overhead & Profit Rp 1,784,467.50
JUMLAH Rp 13,680,917.50

2 DAUN PINTU PANIL KLS 1 (M2)


A. BAHAN
1 Kayu Kls I 0.0400 M3 Rp 7,125,000.00 Rp 285,000.00
2 Lem Kayu 0.5000 Kg Rp 40,000.00 Rp 20,000.00
B. UPAH
1 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
2 Tukang Kayu 3.0000 Oh Rp 173,700.00 Rp 521,100.00
3 Kepala Tukang 0.3000 Oh Rp 208,000.00 Rp 62,400.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 1,018,900.00

1 DAUN PINTU,BINGKAI JENDELA, VENTILASI KACA, KAYU KLS 2 (M2)


A. BAHAN
1 Kayu Kls II 0.0240 M3 Rp 3,450,000.00 Rp 82,800.00
2 Kaca Polos/Riben 3 mm 1.1000 M2 Rp 205,000.00 Rp 225,500.00
3 Lem Kayu 0.3000 Kg Rp 40,000.00 Rp 12,000.00
B. UPAH
1 Pekerja 0.8000 Oh Rp 120,000.00 Rp 96,000.00
2 Tukang Kayu 2.4000 Oh Rp 173,700.00 Rp 416,880.00
3 Kepala Tukang 0.2400 Oh Rp 208,000.00 Rp 49,920.00
4 Mandor 0.0400 Oh Rp 208,000.00 Rp 8,320.00
Jumlah Rp 891,420.00
Overhead & Profit Rp 133,713.00
JUMLAH Rp 1,025,133.00

59 Membuat dan Memasang 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas II.
A. BAHAN
1 Balok Kayu 1.2000 M3 Rp 3,450,000.00 Rp 4,140,000.00
2 Paku 10 cm 1.2500 Kg Rp 21,000.00 Rp 26,250.00
3 Lem Kayu 1.0000 Kg Rp 40,000.00 Rp 40,000.00
B. UPAH
1 Pekerja 6.0000 Oh Rp 120,000.00 Rp 720,000.00
2 Tukang Kayu 18.0000 Oh Rp 173,700.00 Rp 3,126,600.00
3 Kepala Tukang 1.8000 Oh Rp 208,000.00 Rp 374,400.00
4 Mandor 0.3000 Oh Rp 208,000.00 Rp 62,400.00
JUMLAH Rp 8,489,650.00

60 Membuat dan Memasang 1 m2 Daun Pintu Panel, Kayu Kelas II A


A. BAHAN
1 Papan Kayu 0.0400 M3 Rp 3,450,000.00 Rp 138,000.00
2 Lem Kayu 0.5000 Kg Rp 40,000.00 Rp 20,000.00
B. UPAH
1 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
2 Tukang Kayu 3.0000 Oh Rp 173,700.00 Rp 521,100.00
3 Kepala Tukang 0.3000 Oh Rp 208,000.00 Rp 62,400.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 871,900.00

61 Membuat dan Memasang 1 m2 Pintu dan Jendela Kaca, Kayu Kelas II.
A. BAHAN
1 Papan Kayu 0.0240 M3 Rp 3,450,000.00 Rp 82,800.00
2 Lem Kayu 0.3000 Kg Rp 40,000.00 Rp 12,000.00
B. UPAH
1 Pekerja 0.8000 Oh Rp 120,000.00 Rp 96,000.00
2 Tukang Kayu 2.4000 Oh Rp 173,700.00 Rp 416,880.00
3 Kepala Tukang 0.2400 Oh Rp 208,000.00 Rp 49,920.00
4 Mandor 0.0400 Oh Rp 208,000.00 Rp 8,320.00
JUMLAH Rp 665,920.00

62 Membuat dan Memasang 1 m2 Pintu dan Jendela Jalusi, Kayu Kelas II.
A. BAHAN
1 Papan Kayu 0.0640 M3 Rp 3,450,000.00 Rp 220,800.00
2 Lem Kayu 0.5000 Kg Rp 40,000.00 Rp 20,000.00
B. UPAH
1 Pekerja 1.0000 Oh Rp 120,000.00 Rp 120,000.00
2 Tukang Kayu 3.0000 Oh Rp 173,700.00 Rp 521,100.00
3 Kepala Tukang 0.3000 Oh Rp 208,000.00 Rp 62,400.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 954,700.00

63 Membuat dan Memasang 1 m2 Daun Bingkai Jendela, Kayu Kls. II


A. BAHAN
1 Papan Kayu 0.0350 M3 Rp 3,450,000.00 Rp 120,750.00

B. UPAH
1 Pekerja 0.8000 Oh Rp 120,000.00 Rp 96,000.00
2 Tukang Kayu 2.0000 Oh Rp 173,700.00 Rp 347,400.00
3 Kepala Tukang 0.2000 Oh Rp 208,000.00 Rp 41,600.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 616,150.00

3 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA, KAYU KLS I.


A. BAHAN
1 Balok Kayu Kls I, 8/12 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 14,773,230.00

4 MEMASANG 1 M3 BALOK/KOLOM KAYU KLS I, 8/12.


A. BAHAN
1 Balok Kayu Kls I, 8/12 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 13,123,230.00

5 MEMASANG 1 M3 BALOK/KOLOM KAYU KLS I, 5/10.


A. BAHAN
1 Balok Kayu Kls I, 5/10 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 13,123,230.00

6 MEMASANG 1 M3 BALOK/KOLOM KAYU KLS I, 5/5.


A. BAHAN
1 Balok Kayu Kls I, 5/5 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 13,123,230.00

4 MEMASANG 1 M3 KONSTRUKSI GORDENG KAYU KLS I.


A. BAHAN
1 Balok Kayu Kls I 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 3.0000 Kg Rp 21,000.00 Rp 63,000.00
B. UPAH
1 Pekerja 2.4000 Oh Rp 120,000.00 Rp 288,000.00
2 Tukang Kayu 7.2000 Oh Rp 173,700.00 Rp 1,250,640.00
3 Kepala Tukang 0.7200 Oh Rp 208,000.00 Rp 149,760.00
4 Mandor 0.1200 Oh Rp 208,000.00 Rp 24,960.00
JUMLAH Rp 11,648,860.00

3 Memasang 1 m2 Rangka Langit - Langit 60x60 cm, Kayu Kelas II


A. BAHAN
1 Kaso - Kaso (5 x 7) cm 0.0163 M3 Rp 3,450,000.00 Rp 56,235.00
2 Paku 7 cm - 10 cm 0.2500 Kg Rp 21,000.00 Rp 5,250.00

B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu 0.3000 Oh Rp 173,700.00 Rp 52,110.00
3 Kepala Tukang 0.0300 Oh Rp 208,000.00 Rp 6,240.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
JUMLAH Rp 145,915.00

9 MEMASANG 1 M1 LISTPLANK KAYU KLS I.


A. BAHAN
1 Papan Kayu 0.0108 M3 Rp 3,450,000.00 Rp 37,260.00
2 Paku 5 cm dan 7 cm 0.1000 Kg Rp 21,000.00 Rp 2,100.00

B. UPAH
1 Pekerja 0.1000 Oh Rp 120,000.00 Rp 12,000.00
2 Tukang Kayu 0.2000 Oh Rp 173,700.00 Rp 34,740.00
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0050 Oh Rp 208,000.00 Rp 1,040.00
JUMLAH Rp 91,300.00

10 MEMASANG 1 M2 LABRIZIRING DARI PAPAN KAYU KLS I


A. BAHAN
1 Papan Kayu 0.0070 M3 Rp 7,125,000.00 Rp 49,875.00
2 Paku 5 cm - 10 cm 0.1000 Kg Rp 21,000.00 Rp 2,100.00
3 Paku Sekrup 10 cm 0.1500 Kg Rp 21,000.00 Rp 3,150.00
B. UPAH
1 Pekerja 0.6000 Oh Rp 120,000.00 Rp 72,000.00
2 Tukang Kayu 1.8000 Oh Rp 173,700.00 Rp 312,660.00
3 Kepala Tukang 0.1800 Oh Rp 208,000.00 Rp 37,440.00
4 Mandor 0.0300 Oh Rp 208,000.00 Rp 6,240.00
JUMLAH Rp 483,465.00

64 MEMASANG 1 M3 KONSTRUKSI KAYU KLS I (8/12)


A. BAHAN
1 Balok Kayu Kls I (8/12) 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 14,773,230.00

64 MEMASANG 1 M3 KONSTRUKSI KAYU KLS I (5/10)


A. BAHAN
1 Balok Kayu Kls I (5/10) 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 14,773,230.00

64 MEMASANG 1 M3 KONSTRUKSI KAYU KLS I (5/5)


A. BAHAN
1 Balok Kayu Kls I (5/5) 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
2 Besi Strip Tbl 5 mm 15.0000 Kg Rp 110,000.00 Rp 1,650,000.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 14,773,230.00
11 MEMASANG 1 M3 KONSTRUKSI PAGAR KAYU
A. BAHAN
1 Balok Kayu Kls I (5/5) 1.1000 M3 Rp 7,475,000.00 Rp 8,222,500.00
3 Paku 12 cm 5.6000 Kg Rp 21,000.00 Rp 117,600.00
B. UPAH
1 Pekerja 6.7000 Oh Rp 120,000.00 Rp 804,000.00
2 Tukang Kayu 20.1000 Oh Rp 173,700.00 Rp 3,491,370.00
3 Kepala Tukang 2.0100 Oh Rp 208,000.00 Rp 418,080.00
4 Mandor 0.3350 Oh Rp 208,000.00 Rp 69,680.00
JUMLAH Rp 13,123,230.00

12 Mengerjakan 1 M2 Kasau dan Reng Genteng Metal Rangka Kayu Kelas II.
A. BAHAN
1 Kayu Kls II 0.0140 M3 Rp 3,450,000.00 Rp 48,300.00
2 Paku Genteng 0.1500 Kg Rp 21,000.00 Rp 3,150.00
B. UPAH
1 Pekerja 0.1000 Oh Rp 120,000.00 Rp 12,000.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0500 Oh Rp 208,000.00 Rp 10,400.00
JUMLAH Rp 93,300.00

4 Mengerjakan 1 M2 Plafond Tripleks


A. BAHAN
1 Tripleks 5 mm 0.5000 Lbr Rp 95,000.00 Rp 47,500.00
2 Paku Tripleks 0.0500 Kg Rp 28,500.00 Rp 1,425.00
B. UPAH
1 Pekerja 0.0250 Oh Rp 120,000.00 Rp 3,000.00
2 Tukang Kayu 0.0750 Oh Rp 173,700.00 Rp 13,027.50
3 Kepala Tukang 0.0080 Oh Rp 208,000.00 Rp 1,664.00
4 Mandor 0.0010 Oh Rp 208,000.00 Rp 208.00
JUMLAH Rp 66,824.50

5 Membuat Pagar Sementara Seng Gelombang Tinggi 2 M


A. BAHAN
1 Seng Gelombnag BJLS 0,3 1.2000 Lbr Rp 83,400.00 Rp 100,080.00
2 Paku Biasa campur 0.0600 Kg Rp 21,000.00 Rp 1,260.00
3 Paku Seng 0.0400 Kg Rp 40,000.00 Rp 1,600.00
4 Kayu Blaok Kls II 0.0720 M3 Rp 3,450,000.00 Rp 248,400.00
B. UPAH
1 Pekerja 0.4000 Oh Rp 120,000.00 Rp 48,000.00
2 Tukang Kayu 0.2000 Oh Rp 173,700.00 Rp 34,740.00
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0200 Oh Rp 208,000.00 Rp 4,160.00
Jumlah Rp 442,400.00
Overhead & Profit Rp 66,360.00
JUMLAH Rp 508,760.00
ANALISA HARGA SATUAN

KEGIATAN : PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 PENUTUP ATAP SPANDEK 0,3 (M2)


A. BAHAN
1 Spandek 1.1000 M2 Rp 37,750.00 Rp 41,525.00
2 Bout Sekrup 0.0100 Kg Rp 15,000.00 Rp 150.00
B. UPAH
1 Pekerja 0.1000 Oh Rp 120,000.00 Rp 12,000.00
2 Tukang 0.2500 Oh Rp 173,700.00 Rp 43,425.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
Jumlah Rp 101,260.00
Overhead & Profit Rp 15,189.00
JUMLAH Rp 116,449.00

2 BUBUNGAN ATAP SPANDEK (M')


A. BAHAN
1 Nok Spandek 0.7000 Lbr Rp 54,900.00 Rp 38,430.00
2 Bout Sekrup 0.0200 Kg Rp 15,000.00 Rp 300.00
B. UPAH
1 Pekerja 0.1200 Oh Rp 120,000.00 Rp 14,400.00
2 Tukang 0.0600 Oh Rp 173,700.00 Rp 10,422.00
3 Kepala Tukang 0.0060 Oh Rp 208,000.00 Rp 1,248.00
4 Mandor 0.0060 Oh Rp 208,000.00 Rp 1,248.00
Jumlah Rp 66,048.00
Overhead & Profit Rp 9,907.20
JUMLAH Rp 75,955.20

3 1 M2 PASANG ATAP ONDULINE


A. BAHAN
1 Atap Onduline 0.7400 Lbr Rp - Rp -
2 Paku Onduline 0.0300 Kg Rp 35,000.00 Rp 1,050.00
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu Trampil 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0010 Oh Rp 208,000.00 Rp 208.00
Jumlah Rp 44,708.00
Overhead & Profit Rp 6,706.20
JUMLAH Rp 51,414.20

4 1 M' PASANG NOK ONDULINE


A. BAHAN
1 Nok Onduline 1.3330 Lbr Rp - Rp -
2 Paku Onduline 0.0500 Kg Rp 44,275.00 Rp 2,213.75
B. UPAH
1 Pekerja 0.2500 Oh Rp 120,000.00 Rp 30,000.00
2 Tukang Kayu Trampil 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0100 Oh Rp 208,000.00 Rp 2,080.00
Jumlah Rp 63,468.75
Overhead & Profit Rp 9,520.31
JUMLAH Rp 72,989.06

1 1 M2 PEMASANGAN ATAP SENG GELOMBANG BJLS 0,30 MM


A. BAHAN
1 Seng Gelombang BJLS 0,30 0.9000 Lbr Rp 83,400.00 Rp 75,060.00
2 Paku Seng 0.0500 Kg Rp 40,000.00 Rp 2,000.00
B. UPAH
1 Pekerja 0.1500 Oh Rp 120,000.00 Rp 18,000.00
2 Tukang Kayu Trampil 0.2000 Oh Rp 173,700.00 Rp 34,740.00
3 Kepala Tukang 0.0200 Oh Rp 208,000.00 Rp 4,160.00
4 Mandor 0.0800 Oh Rp 208,000.00 Rp 16,640.00
Jumlah Rp 150,600.00
Overhead & Profit Rp 22,590.00
JUMLAH Rp 173,190.00

1 1 M2 PEMASANGAN ATAP GENTENG METAL MULTIROOF


A. BAHAN
1 Genteng Metal Multiroof 2.0000 Lbr Rp 130,000.00 Rp 260,000.00
2 Paku 0.2000 Kg Rp 40,000.00 Rp 8,000.00
B. UPAH
1 Pekerja 0.2000 Oh Rp 120,000.00 Rp 24,000.00
2 Tukang Kayu Trampil 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0010 Oh Rp 208,000.00 Rp 208.00
Jumlah Rp 311,658.00
Overhead & Profit Rp 46,748.70
JUMLAH Rp 358,406.70

2 1 M' PEMASANGAN NOK GENTENG METAL MULTIROOF


A. BAHAN
1 Nok Genteng 1.1000 Lbr Rp 70,000.00 Rp 77,000.00
2 Paku 0.0500 Kg Rp 40,000.00 Rp 2,000.00
B. UPAH
1 Pekerja 0.2500 Oh Rp 120,000.00 Rp 30,000.00
2 Tukang Kayu Trampil 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0130 Oh Rp 208,000.00 Rp 2,704.00
Jumlah Rp 140,879.00
Overhead & Profit Rp 21,131.85
JUMLAH Rp 162,010.85
ANALISA HARGA SATUAN
PEMBANGUNAN DAN PENGEMBANGAN INFRASTRUKTUR KAWASAN PERMUKIMAN DI KAWASAN STRATEGIS DAERAH
KEGIATAN :
PROVINSI
PEKERJAAN : PEMBANGUNAN MASJID ALI AKBAR TABONA TERNATE
LOKASI : KOTA TERNATE-MALUKU UTARA
TAHUN ANGGARAN : 2022

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 ENGSEL PINTU (BH)


A. BAHAN
1 Engsel Pintu 1.0000 Bh Rp 130,000.00 Rp 130,000.00
B. UPAH
1 Pekerja 0.0150 Oh Rp 120,000.00 Rp 1,800.00
2 Tukang Kayu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0008 Oh Rp 208,000.00 Rp 166.40
Jumlah Rp 161,141.40
Overhead & Profit Rp 24,171.21
JUMLAH Rp 185,312.61

2 ENGSEL JENDELA (BH)


A. BAHAN
1 Engsel Jendela 1.0000 Bh Rp 120,000.00 Rp 120,000.00
B. UPAH
1 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
2 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
3 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
4 Mandor 0.0005 Oh Rp 208,000.00 Rp 104.00
Jumlah Rp 140,754.00
Overhead & Profit Rp 21,113.10
JUMLAH Rp 161,867.10

3 KAIT ANGIN (BH)


A. BAHAN
1 Kait Angin 1.0000 Bh Rp 90,000.00 Rp 90,000.00
B. UPAH
1 Pekerja 0.0150 Oh Rp 120,000.00 Rp 1,800.00
2 Tukang Kayu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
3 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
4 Mandor 0.0080 Oh Rp 208,000.00 Rp 1,664.00
Jumlah Rp 122,639.00
Overhead & Profit Rp 18,395.85
JUMLAH Rp 141,034.85

4 GRENDEL PINTU (BH)


A. BAHAN
1 Grendel Pintu 1.0000 Bh Rp 100,000.00 Rp 100,000.00
B. UPAH
1 Tukang Kayu 0.1500 Oh Rp 173,700.00 Rp 26,055.00
2 Kepala Tukang 0.0150 Oh Rp 208,000.00 Rp 3,120.00
3 Mandor 0.0008 Oh Rp 208,000.00 Rp 166.40
4 Pekerja 0.0150 Oh Rp 120,000.00 Rp 1,800.00
Jumlah Rp 131,141.40
Overhead & Profit Rp 19,671.21
JUMLAH Rp 150,812.61

5 GRENDEL JENDELA (BH)


A. BAHAN
1 Grendel Jendela 1.0000 Bh Rp 90,000.00 Rp 90,000.00
B. UPAH
1 Tukang Kayu 0.1000 Oh Rp 173,700.00 Rp 17,370.00
2 Kepala Tukang 0.0100 Oh Rp 208,000.00 Rp 2,080.00
3 Mandor 0.0005 Oh Rp 208,000.00 Rp 104.00
4 Pekerja 0.0100 Oh Rp 120,000.00 Rp 1,200.00
Jumlah Rp 110,754.00
Overhead & Profit Rp 16,613.10
JUMLAH Rp 127,367.10

6 KUNCI PINTU 2 SLAG (BH)


A. BAHAN
1 Kunci Pintu 2 Slaag 1.0000 Set Rp 600,000.00 Rp 600,000.00
B. UPAH
1 Tukang Kayu 0.6000 Oh Rp 173,700.00 Rp 104,220.00
2 Kepala Tukang 0.0600 Oh Rp 208,000.00 Rp 12,480.00
3 Mandor 0.0030 Oh Rp 208,000.00 Rp 624.00
4 Pekerja 0.0600 Oh Rp 120,000.00 Rp 7,200.00
Jumlah Rp 724,524.00
Overhead & Profit Rp 108,678.60
JUMLAH Rp 833,202.60
PROPOSAL
RENCANA ANGGARAN BIAYA (RAB)
JASA PENGUKURAN /SURVEY PEMETAAN

HARGA SATUAN JUMLAH HARGA


NO URAIAN SATUAN VOLUME
(Rp) (Rp)
1 Pengukuran Luasan/Areal/Lahan M2 1.00 750.00 750.00
2 Pengukuran Jarak M' 1.00 3,000.00 3,000.00
a. Pengukuran Luasan/Areal/Lahan Ha 1.00 7,500,000.00 7,500,000.00
b. Pengukuran Jarak Km 1.00 3,000,000.00 3,000,000.00

Produk yang dihasilkan:


1 Data Ukur (untuk semua jenis pengukuran)
2 Gambar Peta Topografi (untuk pengukuran Luasan/Areal/Lahan)
3 Gambar Long section dan Cross section (untuk pengukuran Jarak/Jalan)
4 Hasil Perhitungan Volume Galian dan Timbunan (untul pengukuran Jarak/Jalan)

You might also like