TIME SCHEDULE

PEKERJAAN : Pelapisan Runway, Taxiway dan Apron Serta Perbaikan Runway Termasuk Marking
LOKASI : Unit Penyelenggara Bandar Udara Yuvai Semaring Long Bawan
SUMBER DANA : APBN
TAHUN ANGGARAN : 2023

BULAN - I BULAN - II BULAN - III BULAN - IV BULAN - V BULAN - VI BULAN - VII BULAN - VIII BULAN - IX
2-Mar 29-Mar 30-Mar 3-May 4-May 31-May 1-Jun 28-Jun 29-Jun 2-Aug 3-Aug 30-Aug 31-Aug 4-Oct 5-Oct 1-Nov 2-Nov 26-Nov KET
Bobot
NO URAIAN PEKERJAAN JUMLAH HARGA ( Rp ) M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37 M38 M39
(%) 9-Mar 16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May 18-May 25-May 1-Jun 8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov
2-Mar
8-Mar 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr 3-May 10-May 17-May 24-May 31-May 7-Jun 14-Jun 21-Jun 28-Jun 5-Jul 12-Jul 19-Jul 26-Jul 2-Aug 9-Aug 16-Aug 23-Aug 30-Aug 6-Sep 13-Sep 20-Sep 27-Sep 4-Oct 11-Oct 18-Oct 25-Oct 1-Nov 8-Nov 15-Nov 22-Nov 26-Nov

I PEKERJAAN PERSIAPAN
1 Pekerjaan pembuatan direksi keet Rp 75.600.000,00 0,35% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04%
2 Pekerjaan pembuatan papan nama proyek Rp 826.250,22 0,004% 0,004%
3 Pek. Mobilisasi dan Demobilisasi Rp 411.000.000,00 1,91% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14%
4 Penyelenggaraan Pelaksanaan K3 Rp 36.650.000,00 0,17% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005% 0,005%
5 Pengukuran awal dan akhir, termasuk pembuatan as built drawing Rp 123.000.000,00 0,57% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05%
II REKONSTRUKSI LANDASAN PACU PANJANG 300 M
1 Galian Perkerasan Rp 837.273.320,43 3,89% 1,30% 1,30% 1,30%
2 Timbunan Tanah Konstruksi Rp 226.076.769,19 1,05% 0,52% 0,52%
3 Pek. Perataan dan Pemadatan Rp 238.450.311,71 1,11% 0,55% 0,55%
4 Pekerjaan Lapisan Subbase Course Rp 1.928.685.105,20 8,95% 2,24% 2,24% 2,24% 2,24%

LIBUR HARI RAYA IDUL FITRI


5 Pekerjaan Lapisan Base Course Rp 2.013.144.407,86 9,34% 2,34% 2,34% 2,34% 2,34%
6 Pekerjaan Prime Coating AC 60/70, 1.5 Kg/m Rp 721.075.016,64 3,35% 1,12% 1,12% 1,12%
7 Pekerjaan Lapisan Aspalt Concrete - Binder Course (AC-BC) Rp 4.664.226.361,33 21,65% 3,09% 3,09% 3,09% 3,09% 3,09% 3,09% 3,09%
8 Pekerjaan Tack Coating AC 60/70, 1Kg/m2 Rp 464.789.223,86 2,16% 1,08% 1,08%
9 Pekerjaan Lapisan Aspalt Concrete - Wearing Course (AC-WC) Rp 3.305.933.340,90 15,35% 3,07% 3,07% 3,07% 3,07% 3,07%
III. RUNWAY, APRON DAN TAXIWAY
A. PELAPISAN RUNWAY
1 Pekerjan Cold Milling Rp 18.152.568,55 0,08% 0,08%
2 Pekerjaan Tack Coating AC 60/70, 1Kg/m2 Rp 123.943.793,03 0,58% 0,58%
3 Pekerjaan Lapisan Aspalt Concrete - Wearing Course (AC-WC) Rp 881.582.224,24 4,09% 2,05% 2,05%
B. PELAPISAN TAXIWAY A DAN B
1 Pekerjan Cold Milling Rp 30.708.095,12 0,14% 0,14%
2 Pekerjaan Tack Coating AC 60/70, 1Kg/m2 Rp 209.671.583,21 0,97% 0,97%
3 Pekerjaan Lapisan Aspalt Concrete - Wearing Course (AC-WC) Rp 1.491.329.953,76 6,92% 2,307% 2,307% 2,307%
C. PELAPISAN APRON
1 Pekerjan Cold Milling Rp 52.944.991,59 0,25% 0,25%
2 Pekerjaan Tack Coating AC 60/70, 1Kg/m2 Rp 361.502.729,67 1,68% 1,68%
3 Pekerjaan Lapisan Aspalt Concrete - Wearing Course (AC-WC) Rp 2.571.281.487,37 11,94% 3,98% 3,98% 3,98%
IV. PEKERJAAN TANAH
1 Pekerjaan Tapering Tanah Rp 51.145.709,39 0,24% 0,24%
V. PEKERJAAN MARKING
1 Marking Rp 704.250.000,00 3,27% 1,09% 1,09% 1,09%
Jumlah Harga Pekerjaan 21.543.243.243,24 100,00%

RENCANA KEMAJUAN FISIK / MINGGUAN 0,004% 0,18% 0,24% 0,24% 1,53% 1,53% 2,06% 1,31% 3,03% 2,38% 2,38% 4,72% 2,48% 3,46% 3,46% 4,21% 3,10% 3,10% 3,10% 3,10% 3,10% 4,18% 4,15% 3,07% 3,07% 3,40% 3,65% 2,19% 3,02% 2,31% 2,56% 3,99% 3,98% 4,04% 4,04% 1,15% 1,28% 1,23%
RENCANA KOMULATIF KEMAJUAN FISIK / MINGGUAN 0,004% 0,19% 0,43% 0,66% 2,19% 3,73% 5,78% 7,10% 10,13% 12,51% 14,89% 14,89% 19,60% 22,08% 25,53% 28,99% 33,20% 36,30% 39,40% 42,50% 45,59% 48,69% 52,87% 57,02% 60,10% 63,17% 66,56% 70,21% 72,41% 75,43% 77,74% 80,30% 84,29% 88,27% 92,31% 96,35% 97,49% 98,77% 100,00%
RENCANA KOMULATIF KEMAJUAN FISIK / BULAN 0,66% 7,10% 28,99% 42,50% 60,10% 75,43% 98,77%
, ,
REALISASI KEMAJUAN FISIK / MINGGUAN
REALISASI KOMULATIF KEMAJUAN FISIK / MINGGUAN
REALISASI KOMULATIF KEMAJUAN FISIK / BULAN

DEVIASI +/-

Diketahui Oleh, Diperiksa Oleh, Dibuat Oleh,


Pejabat Pembuat Komitmen Konsultan Pengawas Kontraktor Pelaksana
UNIT PENYELENGGARA BANDAR UDARA CV. GRACONA PT. TARUM JAYA MANDIRI
KELAS III YUVAI SEMARING LONG BAWAN

ROBBY FAJAR SURYANEGARA MUHAMAD ANDAR NURJIANTO, ST WARSID, ST


NIP . 19840401 200712 1 002 Team Leader Manager Proyek