JADWAL WAKTU PELAKSANAAN

GABUNGAN SEMUA LINGKUP PEKERJAAN


PPK : 2.4 Kambang - Bts Bengkulu, Tapan - Bts. Jambi
Nama Paket : Preservasi Rekonstruksi Jalan Tapan - Bts. Bengkulu (SBSN) / PN
Lokasi : Kab. Pesisir Selatan
Prop / Kab / Kodya : Sumatera Barat/Kab.Pesisir Selatan

JANGKA WAKTU PELAKSANAAN 246 HARI KALENDER


KET.
NO. MATA
URAIAN SAT. PERKIRAAN BOBOT 30-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec 30-Dec
PEMB.
KUANTITAS (%) 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec 31-Dec
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36
Div. 1 UMUM 100
1.2 Mobilisasi LS 1,00 0,318 0,032 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,032 0,032
1.8.(1) Manajemen dan keselamatan lalu lintas LS 1,00 0,035 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001
1.17 Pengamanan Lingkungan Hidup LS 1,00 0,026 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001
1.21 Manajemen Mutu LS 1,00 0,140 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005
Div. 2 DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 18.110,00 0,439 0,037 0,037 0,037 0,037 0,037 0,037 0,037 0,037 0,037 0,037 0,037 0,037
2.2.(1) Pasangan Batu dengan Mortar M3 8.800,00 2,498 0,208 0,208 0,208 0,208 0,208 0,208 0,208 0,208 0,208 0,208 0,208 0,208
90
2.3.(11) Saluran Berbentuk U type DS 3 M' 23.440,00 ##### 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649 0,649
2.3.(12) Beton K250 (fc'20) untuk struktur drainase beton minor M3 1.604,54 1,142 0,127 0,127 0,127 0,127 0,127 0,127 0,127 0,127 0,127
2.3.(13) Baja Tulangan untuk Struktur Drainase Beton Minor Kg 157.245,90 1,134 0,126 0,126 0,126 0,126 0,126 0,126 0,126 0,126 0,126
2.4.(1) Bahan Porous atau Bahan Penyaring (Filter) M3 1.055,20 0,067 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003
2.4 (2) Anyaman Filter Plastik M2 659,50 0,009 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000
Skh-1.7.26.(1).a Pengadaan Struktur Box Beton Pracetak (1,5x1,5x1.0 m) Bh 5,00 0,012 - 0,006 0,006
Skh-1.7.26.(3).a Pemasangan Struktur Box Beton Pracetak (1,5x1,5x1.0 m) Bh 5,00 0,001 0,001
Div. 3 PEKERJAAN TANAH 80
3.1.(1a) Galian Biasa M3 24.040,00 0,565 0,047 0,047 0,047 0,047 0,047 0,047 0,047 0,047 0,047 0,047 0,047 0,047
3.1 (6) Galian Perkerasan Beraspal dengan Cold Milling Machine M3 411,57 0,104 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013
3.1.(7) Galian Perkerasan Beraspal tanpa Cold Milling Machine M3 411,57 0,085 0,011 0,011 0,011 0,011 0,011 0,011 0,011 0,011
3.2 (2a) Timbunan Pilihan dari Sumber Galian M3 9.616,00 1,449 0,121 0,121 0,121 0,121 0,121 0,121 0,121 0,121 0,121 0,121 0,121 0,121
Div. 4 PELEBARAN PERKERASAN DAN BAHU JALAN
4.2 (1) Lapis Pondasi Agregat Kelas A M3 9.616,00 2,509 0,209 0,209 0,209 0,209 0,209 0,209 0,209 0,209 0,209 0,209 0,209 0,209
4.2 (7) Lapis Resap Pengikat Liter 18.336,00 0,111 0,019 0,019 0,019 0,019 0,019 0,019 70
4.2.(12) Laston Lapis Pondasi Modifikasi (AC-Base Mod) Ton 3.514,40 2,297 0,383 0,383 0,383 0,383 0,383 0,383
4.2.(13) Bahan Anti Pengelupasan Kg 421,73 0,012 0,002 0,002 0,002 0,002 0,002 0,002
4.2 (14) Perkerasan Beton Semen M3 22.605,05 ##### 1,432 1,432 1,432 1,432 1,432 1,432 1,432 1,432 1,432 1,432 1,432 1,432
Div. 6 PERKERASAN ASPAL
6.1 (2a) Lapis Perekat - Aspal Cair Liter 79.233,90 0,515 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,023 0,02
6.3.(5b) Laston Lapis Aus Modifikasi (AC-WC Mod) Ton 23.600,06 ##### 2,368 2,368 2,368 2,368 2,368 2,368 2,37 60
6.3.(6b) Laston Lapis Antara Modifikasi (AC-BC Mod) Ton 31.255,61 ##### 2,561 2,561 2,561 2,561 2,561 2,561 2,561 2,561
6.3.(6d) Laston Lapis Antara Modifikasi Perata (AC-BC)(L) (Mod) LevellingTon 21.161,90 ##### 2,012 2,012 2,012 2,012 2,012 2,012 2,012
6.3.(8) Bahan Anti Pengelupasan Kg 9.199,73 0,260 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012
Div. 7 STRUKTUR
7.1 (7) a Beton Mutu Sedang fc'20 Mpa M3 25,20 0,016 0,008 0,008
7.1 (10) Beton Mutu Rendah fc'10 Mpa M3 374,10 0,167 0,167
7.3 (1) Baja Tulangan U24 Polos Kg 4.813,74 0,035 0,017 0,017
7.9.(1) Pasangan Batu M3 1.550,00 0,445 0,148 0,148 0,148 50
7.10 (3) a Bronjong dengan kawat yang dilapisi Galvanis M3 100,00 0,028 0,014 0,014
Div. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
8.1 (1) Lapis Pondasi Agregat Kelas A utk Pekerjaan Minor M3 643,59 0,261 0,033 0,033 0,033 0,033 0,033 0,033 0,033 0,033
8.1 (5) Campuran Aspal Panas untuk Pekerjaan Minor M3 643,32 0,909 0,114 0,114 0,114 0,114 0,114 0,114 0,114 0,114
8.3.(3) Pohon Jenis Mahoni Buah 160,00 0,023 0,011 0,011
8.4.(1) Marka Jalan Termoplastik M2 11.954,00 0,849 0,170 0,170 0,170 0,170 0,170
40
8.4.(5) Patok Pengarah Buah 370,00 0,022 0,022
8.4.(6a) Patok Kilometer Buah 17,00 0,004 0,004
8.4.(7) Rel Pengaman Buah 2.026,00 0,861 0,287 0,287 0,287
Div. 9 PEKERJAAN HARIAN
9.1.(1) Mandor Jam 600,00 0,004 0,001 0,001 0,001
9.1.(2) Pekerja Biasa Jam 1.000,00 0,005 0,002 0,002 0,002
9.1.(3) Tukang Kayu, Tukang Batu, dsb Jam 600,00 0,004 0,001 0,001 0,001 30
9.1.(4) a Dump Truck, kapasitas 3-4 m³ Jam 500,00 0,073 0,024 0,024 0,024
9.1.(9) Loader Roda Karet 1.0 - 1.6 M3 Jam 390,00 0,074 0,025 0,025 0,025
9.1.(11) Alat Penggali (Excavator) 80 - 140 PK Jam 390,00 0,115 0,038 0,038 0,038
Div. 10.a PEMELIHARAAN KINERJA JALAN
Skh.2.10.a(4) Lapis pondasi aggregat kelas A M3 400,00 0,106 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004
Skh.2.10.a(10) Campuran Aspal Panas M3 300,00 0,410 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 0,015 20
Skh.2.10.a(18) Pengendalian Tanaman M2 480.884,00 0,105 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004
Skh.2.10.a(19) Pembersihan Drainase M2 56.400,00 0,130 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005
Skh.2.10.a(20a) Pembersihan dan Perbaikan Rel Pengaman M' 5.100,00 0,096 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004 0,004
Skh.2.10.a(20b) Pembersihan dan Perbaikan Patok/Rambu Buah 750,00 0,044 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002
Div. 10.b PEMELIHARAAN KINERJA JEMBATAN
Skh.2.10.b(1) Pembersihan Jembatan M2 345,88 0,002 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000
Skh.2.10.b(2) Perbaikan retak / kerusakan beton non struktural M2 230,00 0,013 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 10

Skh.2.10.b(7) Penggantian Baut Buah 742,00 0,004 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000
Skh.2.10.b(8) Perbaikan Pasangan Batu M3 183,90 0,059 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002
Skh.2.10.b(9a) Perbaikan Pipa Cucuran dan Drainase Buah 120,00 0,004 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000
Skh.2.10.b(10) Perbaikan Sambungan Siar Suar M' 100,00 0,048 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002
Skh.2.10.b(11) Perbaikan Sandaran M' 300,00 0,012 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000
Skh.2.10.b(5) Pengecatan Sederhana/Elemen Beton M2 1.200,00 0,020 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0
Total Bobot #####
Progres Rencana Mingguan (%) 0,036 0,036 0,036 0,036 0,036 - - 0,036 0,451 0,498 0,654 2,885 2,977 3,538 3,538 3,538 3,368 3,786 4,588 4,722 4,569 4,430 5,599 4,986 4,982 5,147 4,813 4,560 4,534 4,534 4,556 4,995 4,991 1,935 0,351 0,259
Komulatif Rencana Mingguan (%) 0,036 0,072 0,108 0,144 0,180 0,180 0,180 0,216 0,667 1,164 1,818 4,703 7,680 ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### #####
Progres Realisasi Mingguan (%) 0,017 0,017 0,018 0,124 0,132 0,014 0,014
Komulatif Realisasi Mingguan (%) 0,017 0,034 0,052 0,176 0,308 0,322 0,336
Deviasi (%) (0,019) (0,037) (0,055) 0,033 0,129 0,143 0,157