PROJECT : CONSTRUCTION OF RESEARCH BUILDING

SUBJECT : MANPOWER SCHEDULE

TRADE UNIT QTY DURATION APRIL 2018 MAY 2018 JUNE 2018 JULY 2018 AUGUST 2018 SEPTEMBER 2018 OCTOBER 2018 NOVEMBER 2018
ROMBLON STATE UNIVERSITY 1-Apr 8-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov
1.00000 2.00000 3.00000 4.00000 5.00000 6.00000 7.00000 8.00000 9.00000 10.00000 11.00000 12.00000 13.00000 14.00000 15.00000 16.00000 17.00000 18.00000 19.00000 20.00000 21.00000 22.00000 23.00000 24.00000 25.00000 26.00000 27.00000 28.00000 29.00000 30.00000 31.00000 32.00000 33.00000 34.00000 35.00000
CONSTRUCTION OF EXTENSION & TRAINING CENTER

BACK HOE EXCAVATOR UNIT 1.00 35 days # # # # # # #

# # # # # # #
DUMP TRUCK UNIT 1.00 28 days

1 BAGGER CEMENT MIXER UNIT 1.00 96 days

VIBRATOR UNIT 2.00 96 days

PREPARED BY:

ENGR. JAKE F. CORTEZ

PMG HEAD -CIVIL