You are on page 1of 6

ADRA Turkey

E
R
TASKS :
Alexander S. Balint
PROJECT PLANNING
Prof. Dr. Gülay Altay
PROJECT PREPARATION
1. Project Negotiation
2. Terms of Reference Preparat.
3. Engineering Awards
4. Geotechnical Engineering
Prof. Dr. Gülay Altay
STRUCTURAL ENGINEERING
14/08
1. SITE INVESTIG. & MATERIAL TESTS

2. AS-BUILT DRAWINGS

3. STRUCTURAL ASSESSMENT OF
EXISTING STRUCTURE

4. STRENGHTENING PROJECT PREPAR.

5. FINAL DRAWINGS PREPARATION

6. BILL OF QUANTITIES

TENDERING PHASE

1. TENDER DOCUMENTS PREPARATION

2. TENDERING PERIOD

3. CONTRACT NEGOTIATION AND


CONTRACTOR SELECTION

REHABILITATION PHASE

1. PLACING OF CONSTRUCTION CONTRACTS

2. START OF REHABILITATION
WORK-IZZET BAYSAL DORM

3. START OF REHABILITATION
WORK-ATATÜRK SCHOOL

FINISHING & EVALUATION

INAUGURATION

PROJECT PROGRESS

26 25 24 23 22 21
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6

AUG. 1, 2000 08/08 15/08 22/08 29/08 05/09 12/09


ECHO PROJECT Nº 01 - GANTT PLANNING DIAGRAM
REHABILITATION OF 2 SCHOOL BUILDINGS IN BOLU, TURKEY

80

70

60
DATE BUDGET ACTUAL MAXIM. RESERVE

EUROS
01/08/00 0 0 630,650 699,314 50
01/09/00 67,925 42,925 630,650 699,314
01/10/00 126,150 150,000 630,650 699,314
01/11/00 257,185 200,000 630,650 699,314 40
01/12/00 421,085 400,000 630,650 699,314
01/01/01 630,650 600,000 630,650 699,314
31/01/01 630,650 695,715 699,314 30

20

Prof. Dr. Gülay Altay & ADRA Turkey


10

Contractors Mob

20 19 18 17 16 15 14 13 12 11 10
WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15 WEEK 16 WEEK 17

12/09 19/09 26/09 03/10 10/10 17/10 24/10 31/10 07/11 14/11 21/11
M September 3, 2020

Y
PROJECT EXPENDITURE DIAGRAM
800,000

700,000 699,314 699,314 699,314 699,314 699,314 699,314 699,314


695,715
Reserve
Maximum Expenditure Excluding Reserve
630,650 630,650 630,650 630,650 630,650 630,650 630,650
600,000 600,000
EUROS

500,000

421,085
400,000 400,000

300,000 Budget
Actual
257,185
Maxim.
200,000 200,000 Reserve

150,000
126,150
100,000
67,925
42,925
0 0
01/08/00 01/09/00 01/10/00 01/11/00 01/12/00 01/01/01 31/01/01

Building Contractors Supervised by Prof. Dr. Gülay Altay

Contractors Mobilisation

10 9 8 7 6 5 4 3 2 1
WEEK 17 WEEK 18 WEEK 19 WEEK 20 WEEK 21 WEEK 22 WEEK 23 WEEK 24 WEEK 25 WEEK 26

28/11 05/12 12/12 19/12 26/12 02/01 09/01 16/01 23/01 30/01

Design & Execution: Alexander S. Balint, Project Manager-ADRA Turkey

You might also like